P. Emma, et al. LCLS Operations Lectures

Size: px
Start display at page:

Download "P. Emma, et al. LCLS Operations Lectures"

Transcription

1 P. Emma, et al. LCLS Operations Lectures LCLS 1

2 LCLS Accelerator Schematic 6 MeV 135 MeV 250 MeV σ z 0.83 mm σ z 0.83 mm σ z 0.19 mm σ δ 0.05 % σ δ 0.10 % σ δ 1.6 % Linac-0 L =6 m rf gun L0-a,b Linac-1 L 9 9 m rf 25 ϕ rf Linac-X L =0.6 m rf = 160 ϕ rf Linac-2 L 330 m rf 41 ϕ rf 4.30 GeV σ z mm σ δ 0.71 % Linac-3 L 550 m rf 0 ϕ rf 13.6 GeV σ z mm σ δ 0.01 %...existing linac DL1 L 12 m R b,c,d X BC1 L 6 6 m mm R b 24-6d SLAC linac tunnel BC2 L 22 m mm R a 30-8c Commission in Jan Commission in Jan DL2 L =275 m 56 0 R 56 undulator L =130 m research yard 2

3 Complete & Detailed Optics (cathode to dump) dump cathode L2 BC2 L3 sec-21 sec-30 LTU undulator muon plug wall Full MAD files at: ssrl.slac.stanford.edu/lcls/linac/optics/ 3

4 LCLS Installation and Commissioning Time-Line Drive-Laser Commissioning Drive-Laser Install undulator LTU/und. First FEL hall ready Install Light linac/bc2 Install First Spont. Light MM J J A S O N D J F M A M J J A S O N D J F M A M J J June 2006 Gun/Inj./BC1 Install (8/21 1/5) Gun/Inj./BC1 Commissioning linac/bc2 Commissioning FEL Comm. LTU/undulator Commissioning 4

5 LONG BELLOWS ASSEMBLY SPOOLS FROMVALVE SEAL UHV ALL METAL GATE VALVES RF Gun TREATMENT CHAMBER PORCUPINE CATHODE HOLDER VACUUM PUMPS 6 MeV L0a RF section Injector Layout 62 MeV L0b RF section gun spectrometer 135 MeV Transverse RF deflector L1 RF section (21-1b) 1b) main SLAC Linac injector spectrometer sector 20 sector 21 5

6 LCLS Injector Commissioning Dates ( 06( - 07) July 24: Aug. 29: Dec. 18: Dec. 19: Dec. 20-Jan. 1: Jan. 2: Jan. 12: Jan. 12-Feb. 4: Sector-20 ready for laser installation Laser installation complete Virtual cathode fully characterized (ready to install gun) RF gun installation starts (10 days) + pre-beam checkout Holidays VVS s switched on (RF power available) First laser UV-light on cathode! Electrons in GTL and gun-spect spect.. (RF processing L0a,b, L1, LX) Feb. 5: Beam into L0a, L0b and down to 135-MeV spect. Feb. 20: ~June: Beam into main linac (to TD11 dump) Take beam down full linac (to BSY SL2 stopper) 6

7 OUT OF DATE Microsoft Project Commissioning Schedule DOWN 2007 DOWN

8 pass-1 OUT OF DATE pass-2 pass DOWN pass-1 pass DOWN 8

9 pass-1 pass DOWN OUT OF DATE pass DOWN 9

10 Commissioning Definition and Strategy All components have been installed, aligned, connected, and initially verified by the system engineer, then commissioning starts. Commissioning Sequence (1-4)( 1. Pre-Beam Checkout (tunnel and MCC) Controls/software testing, check cameras, snail hunt, etc Magnet polarities, cable connections, verify motion-control, etc 2. Beam-based Hardware and Software Checkout Establish beam transport, RF setup, MPS/BCS tests, etc Checkout of all wires, screens, BPMs, toroids, magnets, etc 3. First-Order Optics: Measurement and Correction Steering, transmission, oscillation data, feedback setup, etc Beta and dispersion matching, beam-base base align key quads, etc 4. Full Beam Characterization: Measurement and Correction Measure emittance, energy spread, distributions - correct Measure beam sensitivities, optimize tuning, beam experiments No (serious) emittance measurements until all hardware/software checked out! 10

11 Electron Commissioning Organization Project Director J. Galayda Commissioning Don P. Emma Alternating Weekly Run Coordinator One Lead Physicist per shift Shift Physicists Controls & System Engineers MCC & Laser Operators 11

12 LCLS Injector Commissioning Day 24-Hour Cycle (7 days/week, 1/2/07 to 9/1/07,, 32 total weeks) DAY DAY SHIFT SHIFT (8:00-16:00) 1 lead lead physicist, 1 physicist, 1 controls eng., eng., 1 sys. sys. engineer, 1 LCLS LCLS operator, 1 laser laser operator SWING SHIFT SHIFT (16:00-24:00) 1 lead lead physicist, 1 physicist, 1 LCLS LCLS operator, 1 laser laser operator OWL OWL SHIFT SHIFT (0:00-8:00) 1 LCLS LCLS operator, 1 laser laser operator? 12

13 Parameters Parameter RF rate Beam rate Drive-laser rate Bunch charge Drive-laser pulse length Gun gradient Value 30 Hz 30 Hz 120 Hz pc 10 ps fwhm 120 MV/m Comments 30 Hz in linac (possible short-term term 120-Hz rate in L0- BC1 for feedback tests, etc) Hz in gun for short time to verify full rate 30 Hz e beam as baseline possible short term 120- Hz tests in L0-BC1 for feedback tests, etc 120-Hz at all times shutters provide e rate as required above depends on QE and diagnostics some short spans at 10 pc later in 07 we explore 1-nC1 10-ps fwhm startup with possibility of 6-ps 6 at 0.2 nc later early laser tests may provide path to more convenient pulse-length length changes Set as goal, although 110 MV/m is adequate in 07 13

14 Issues Controls will be mixed (SLC & epics) and capabilities may be limited initially Most High-Level Applications (emittance, bunch length, feedback) must done through MATLAB as a temporary solution Most LCLS physicists not yet experienced in SLAC control room with SLC controls Help from operations group will be needed LCLS Lecture Series + Workshop in Oct.? 14

15 Q = 1 nc f = 120 Hz G = 120 MV/m γε x,y = 1 µm τ = 10 ps I = 100 A E = 6 MeV solenoid RF gun cathode RF Photo-Cathode Gun spec. dipole UV laser YAG screens e e 15

16 LONG BELLOWS ASSEMBLY SPOOLS FROMVALVE SEAL UHV ALL METAL GATE VALVES RF Gun YAG screen TREATMENT CHAMBER PORCUPINE CATHODE HOLDER VACUUM PUMPS YAG screen YAG screen YAG screen trajectory (BPMs) emittance (+ (+ slice) energy spread (+ (+ slice) bunch length (+ (+ dist.) charge (+ (+ dark dark current) gun spectrometer Injector Diagnostics YAG screen Transverse RF deflector OTR & wire OTR & wire OTR & wire main SLAC Linac injector spectrometer 16 YAG OTR & wire YAG & OTR

17 Injector Through BC1 Commissioning no laser-heater until 08 RF deflector γε x,y γε and slice σ E E 17

18 Injector Through BC1 Commissioning (2) BC1 relative bunch length monitors X-band RF σ E E slice γε y γε x,y stopper 18

19 Setup of Linac-1, X-band X RF Phases 20-µm m res. BC1 BPM 20-µm m res. BC1 BPM LX RF phase L1 RF phase Linac-1 1 RF phase scan (X-band off, BC1 bends at 295 MeV) Linac-X X RF phase scan (BC1 bends at 250 MeV) rf gun new new set phase to 25 ±0.5 set phase to 160 ±0.5 Linac b 1b 21-1d 1d X Turn on BC1 energy feedback Switch off BC2 chicane Use sec-25 RF-deflector to meas. bunch length ( (σ z1 ) Adjust S-band S RF phase (±0.5( 0.5 ) ) to set σ z1 195 ±10 µm 19

20 40-µm m res. BC2 BPM Setup of Linac-2 2 RF 5-µm m res. LTU BPM wake-loss scan L2 RF phase Linac-2 2 RF phase scan (BC2 bends at 5.9 GeV, or ) L2 phase Scan Linac-2 2 phase & use LTU BPM to find max. wake-induced energy loss across Linac-3 set phase to 41 ±0.5 L2 L3 Turn on BC2 energy feedback Use sec-25 RF-deflector to measure length ( (σ z2 ) Adjust L2 RF phase (±0.5( 0.5 ) ) to set σ z2 20 ± 2 µm Linac-3 3 phasing is trivial (±5 )( 20

21 Longitudinal Beam-Based Based Feedback gun V 0 δ 0 σ z1 σ z2 L0 L0 δ 1 δ 2 δ 3 ϕ 1 V 1 ϕ 2 V 2 V 3 L1 X L2 L3 DL1 BC1 BC2 DL2 21

22 Location of Main Linac Diagnostics 5+ energy spread meas. stations (optimized with small β) 5+ emittance meas. stations designed into optics ( ( ψ x,y ) BPMs at or near most quadrupoles and in each bend syst. RF deflectors for slice ε and σ E measurements (L0 & L3) rf gun L0 L0 T-cav. γε x,y γε x,y γε x,y T-cav. γε x,y...existing linac L1 X L2 L3 γε x,y σ E σ E σ E E E E σ E E σ E E 22

23 Slice-Emittance Measurement Simulation slice OTR 10 times RF-deflector at 1 MV σ y bunch length 135 MeV quad scanned 23

24 Slice-Emittance Measurement Simulation Injector (135 MeV) with S-band RF-deflector at 1 MV (same SLAC slice-ε code used at BNL/SDL) (slice-y-emittance emittance also simulated in BC1-center) = meas. sim. = calc. = y distribution = actual DL1 slice-emit emit on WS02 slice-5 24

25 y-slice-emittance Measurement in BC1 Q21201 scanned ±20% 3.9 mm 0.1 mm 25

26 weak quad setting Slice ε y Measurements at BNL undulators linac (off) linac dump dump 75 MeV 75 MeV 5 MeV medium quad setting strong quad setting 200 pc, 100 A, 75 MeV Data from DUVFEL at BNL: : W. Graves, et al. 26

27 vertical bends Linac-To To-Undulator (LTU) energy centroid & spread meas. (OTR) ( & 10 4 ) + collimation 4 ε-wires, wires, 6 collimators, 1 OTR vertical vertical bends bends horiz. horiz.. jog jog m energy energy diagnostics diagnostics emit. emit. diagnostics diagnostics collimators collimators branch branch points points for for future future undulators undulators 27

28 Slice Energy Spread Measurements in LTU σ E /E 10 4 LTU at 14 GeV with S-band S RF-deflector at 24 MV σ x 12 µm FEL goal 28

29 Summary Injector commissioning starts very soon (Laser:: Aug. 06, Electrons: : Jan. 07) Phase-II of commissioning comes in Jan. 08 LCLS group will need continual help from operations group LCLS is a 30-year machine this is just the start 29

Beam Losses During LCLS Injector Phase-1 1 Operation

Beam Losses During LCLS Injector Phase-1 1 Operation Beam Losses During LCLS Injector Phase-1 1 Operation & Paul Emma September 28, 2006 Radiation Safety Committee Review Scope of Phase 1 Operation Request for Three Operating Modes Operating Plan for Phase

More information

LCLS Injector Technical Review

LCLS Injector Technical Review LCLS Injector Technical Review Stanford Linear Accelerator Center November 3&4 2003 Review Committee Members: Prof. Patrick O Shea Chair University of Maryland Dr. E. Colby Stanford Linear Accelerator

More information

Requirements for the Beam Abort Magnet and Dump

Requirements for the Beam Abort Magnet and Dump Requirements for the Beam Abort Magnet and Dump A beam abort kicker (pulsed dipole magnet) and dump are required upbeam of the LCLS undulator in order to protect the undulator from mis-steered and poor

More information

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems LCLS RF Reference and Control R. Akre Last Update 5-19-04 Sector 0 RF and Timing Systems The reference system for the RF and timing starts at the 476MHz Master Oscillator, figure 1. Figure 1. Front end

More information

Week 0: PPS Certification and Processing. Mon Feb 11 Tue Feb 12 Wed Feb 13 Thu Feb 14 Fri Feb 15 Sat Feb 16 Sun Feb 17

Week 0: PPS Certification and Processing. Mon Feb 11 Tue Feb 12 Wed Feb 13 Thu Feb 14 Fri Feb 15 Sat Feb 16 Sun Feb 17 Week 0: PPS Certification and Processing Mon Feb 11 Tue Feb 12 Wed Feb 13 Thu Feb 14 Fri Feb 15 Sat Feb 16 Sun Feb 17 Work in tunnel Work in tunnel PPS Certification PPS Certification PPS Certification

More information

A Facility for Accelerator Physics and Test Beam Experiments

A Facility for Accelerator Physics and Test Beam Experiments A Facility for Accelerator Physics and Test Beam Experiments U.S. Department of Energy Review Roger Erickson for the FACET Design Team February 20, 2008 SLAC Overview with FACET FACET consists of four

More information

TWO BUNCHES WITH NS-SEPARATION WITH LCLS*

TWO BUNCHES WITH NS-SEPARATION WITH LCLS* TWO BUNCHES WITH NS-SEPARATION WITH LCLS* F.-J. Decker, S. Gilevich, Z. Huang, H. Loos, A. Marinelli, C.A. Stan, J.L. Turner, Z. van Hoover, S. Vetter, SLAC, Menlo Park, CA 94025, USA Abstract The Linac

More information

Summary of the 1 st Beam Line Review Meeting Injector ( )

Summary of the 1 st Beam Line Review Meeting Injector ( ) Summary of the 1 st Beam Line Review Meeting Injector (23.10.2006) 15.11.2006 Review the status of: beam dynamics understanding and simulations completeness of beam line description conceptual design of

More information

Beam Instrumentation for X-ray FELs

Beam Instrumentation for X-ray FELs Beam Instrumentation for X-ray FELs 05/16/2011 1 1 Outline X-ray FEL overview Diagnostics requirements for X-ray FELs Transverse Diagnostics Longitudinal Diagnostics Summary 2 2 X-ray FEL Overview 100

More information

Digital BPMs and Orbit Feedback Systems

Digital BPMs and Orbit Feedback Systems Digital BPMs and Orbit Feedback Systems, M. Böge, M. Dehler, B. Keil, P. Pollet, V. Schlott Outline stability requirements at SLS storage ring digital beam position monitors (DBPM) SLS global fast orbit

More information

SPEAR 3: Operations Update and Impact of Top-Off Injection

SPEAR 3: Operations Update and Impact of Top-Off Injection SPEAR 3: Operations Update and Impact of Top-Off Injection R. Hettel for the SSRL ASD 2005 SSRL Users Meeting October 18, 2005 SPEAR 3 Operations Update and Development Plans Highlights of 2005 SPEAR 3

More information

An Overview of Beam Diagnostic and Control Systems for AREAL Linac

An Overview of Beam Diagnostic and Control Systems for AREAL Linac An Overview of Beam Diagnostic and Control Systems for AREAL Linac Presenter G. Amatuni Ultrafast Beams and Applications 04-07 July 2017, CANDLE, Armenia Contents: 1. Current status of existing diagnostic

More information

Future Performance of the LCLS

Future Performance of the LCLS Future Performance of the LCLS J. Welch for many* SLAC National Accelerator Laboratory FLS 2010, ICFA Beam Dynamics Workshop on Future Light Sources, March 1-5, 2010. SLAC National Accelerator Laboratory,

More information

Hall-B Beamline Commissioning Plan for CLAS12

Hall-B Beamline Commissioning Plan for CLAS12 Hall-B Beamline Commissioning Plan for CLAS12 Version 1.5 S. Stepanyan December 19, 2017 1 Introduction The beamline for CLAS12 utilizes the existing Hall-B beamline setup with a few modifications and

More information

RF considerations for SwissFEL

RF considerations for SwissFEL RF considerations for H. Fitze in behalf of the PSI RF group Workshop on Compact X-Ray Free Electron Lasers 19.-21. July 2010, Shanghai Agenda Introduction RF-Gun Development C-band development Summary

More information

Linac-Beam Characterizations at 600 MeV Using Optical Transition Radiation Diagnostics *

Linac-Beam Characterizations at 600 MeV Using Optical Transition Radiation Diagnostics * Linac-Beam Characterizations at 6 MeV Using Optical Transition Radiation Diagnostics * A. H. Lumpkin, W. J. Berg, B. X. Yang, and M. White Advanced Photon Source, Argonne National Laboratory 97 South Cass

More information

Photoinjector Laser Operation and Cathode Performance

Photoinjector Laser Operation and Cathode Performance Photoinjector Laser Operation and Cathode Performance Daniele Sertore, INFN Milano LASA Siegfried Schreiber, DESY Laser operational experience Laser beam properties Cathode performances Outlook TTF and

More information

30 GHz Power Production / Beam Line

30 GHz Power Production / Beam Line 30 GHz Power Production / Beam Line Motivation & Requirements Layout Power mode operation vs. nominal parameters Beam optics Achieved performance Problems Beam phase switch for 30 GHz pulse compression

More information

Status of CTF3. G.Geschonke CERN, AB

Status of CTF3. G.Geschonke CERN, AB Status of CTF3 G.Geschonke CERN, AB CTF3 layout CTF3 - Test of Drive Beam Generation, Acceleration & RF Multiplication by a factor 10 Drive Beam Injector ~ 50 m 3.5 A - 2100 b of 2.33 nc 150 MeV - 1.4

More information

Design Studies For The LCLS 120 Hz RF Gun Injector

Design Studies For The LCLS 120 Hz RF Gun Injector BNL-67922 Informal Report LCLS-TN-01-3 Design Studies For The LCLS 120 Hz RF Gun Injector X.J. Wang, M. Babzien, I. Ben-Zvi, X.Y. Chang, S. Pjerov, and M. Woodle National Synchrotron Light Source Brookhaven

More information

4.4 Injector Linear Accelerator

4.4 Injector Linear Accelerator 4.4 Injector Linear Accelerator 100 MeV S-band linear accelerator based on the components already built for the S-Band Linear Collider Test Facility at DESY [1, 2] will be used as an injector for the CANDLE

More information

PEP II Design Outline

PEP II Design Outline PEP II Design Outline Balša Terzić Jefferson Lab Collider Review Retreat, February 24, 2010 Outline General Information Parameter list (and evolution), initial design, upgrades Collider Ring Layout, insertions,

More information

Linac 4 Instrumentation K.Hanke CERN

Linac 4 Instrumentation K.Hanke CERN Linac 4 Instrumentation K.Hanke CERN CERN Linac 4 PS2 (2016?) SPL (2015?) Linac4 (2012) Linac4 will first inject into the PSB and then can be the first element of a new LHC injector chain. It will increase

More information

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation Matthias Liepe Assistant Professor of Physics Cornell University Experience with the Cornell ERL Injector SRF

More information

SABER A Facility for Accelerator Physics and Test Beam Experiments Roger Erickson SABER Workshop March 15, 2006

SABER A Facility for Accelerator Physics and Test Beam Experiments Roger Erickson SABER Workshop March 15, 2006 SABER A Facility for Accelerator Physics and Test Beam Experiments Roger Erickson SABER Workshop March 15, 2006 FFTB will soon be gone! The Problem: On April 10, 2006, the Final Focus Test Beam (FFTB)

More information

TESLA FEL-Report

TESLA FEL-Report Determination of the Longitudinal Phase Space Distribution produced with the TTF Photo Injector M. Geitz a,s.schreiber a,g.von Walter b, D. Sertore a;1, M. Bernard c, B. Leblond c a Deutsches Elektronen-Synchrotron,

More information

TTF / VUV-FEL. Schedule 2005 and Project Management Issues. Schedule 2005 Project Organisation Budget & Controlling

TTF / VUV-FEL. Schedule 2005 and Project Management Issues. Schedule 2005 Project Organisation Budget & Controlling TTF / VUV-FEL Schedule 200 and Project Management Issues Schedule 200 Project Organisation Budget & Controlling Hans Weise / DESY DESY MAC Meeting November 9th, 2004 TTF Linac Start-up After Final Installation

More information

Current status of XFEL/SPring-8 project and SCSS test accelerator

Current status of XFEL/SPring-8 project and SCSS test accelerator Current status of XFEL/SPring-8 project and SCSS test accelerator Takahiro Inagaki for XFEL project in SPring-8 inagaki@spring8.or.jp Outline (1) Introduction (2) Key technology for compactness (3) Key

More information

Photo cathode RF gun -

Photo cathode RF gun - Photo cathode RF gun - *),,, ( 05 Nov. 2004 Spring8 UTNL Linac & Mg Photocathode RF Gun Mg photocathode NERL, 18 MeV Linac and the RF gun Electron Beam Mg photocathode Mg photocathode RF gun of SPring8

More information

Present Status and Future Upgrade of KEKB Injector Linac

Present Status and Future Upgrade of KEKB Injector Linac Present Status and Future Upgrade of KEKB Injector Linac Kazuro Furukawa, for e /e + Linac Group Present Status Upgrade in the Near Future R&D towards SuperKEKB 1 Machine Features Present Status and Future

More information

Simulations on Beam Monitor Systems for Longitudinal Feedback Schemes at FLASH.

Simulations on Beam Monitor Systems for Longitudinal Feedback Schemes at FLASH. Simulations on Beam Monitor Systems for Longitudinal Feedback Schemes at FLASH. Christopher Behrens for the FLASH team Deutsches Elektronen-Synchrotron (DESY) FLS-2010 Workshop at SLAC, 4. March 2010 C.

More information

Drive Laser Operations

Drive Laser Operations Drive-Laser Operations Drive Laser Thales laser Transport system Recent Laser Milestones Safety Technical Where do we stand today? Laser Acceptance Status Laser Commissioning UV on cathode Injector Commissioning

More information

The basic parameters of the pre-injector are listed in the Table below. 100 MeV

The basic parameters of the pre-injector are listed in the Table below. 100 MeV 3.3 The Pre-injector The high design brightness of the SLS requires very high phase space density of the stored electrons, leading to a comparatively short lifetime of the beam in the storage ring. This,

More information

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

Diamond RF Status (RF Activities at Daresbury) Mike Dykes Diamond RF Status (RF Activities at Daresbury) Mike Dykes ASTeC What is it? What does it do? Diamond Status Linac Booster RF Storage Ring RF Summary Content ASTeC ASTeC was formed in 2001 as a centre of

More information

Focus of efforts. ILC 2010, Mar/27/10 A. Seryi, BDS: 2

Focus of efforts. ILC 2010, Mar/27/10 A. Seryi, BDS: 2 Beam Delivery System Updates Andrei Seryi for BDS design and ATF2 commissioning teams LCWS 2010 / ILC 2010 March 28, 2010 Plan of the program at ILC2010 Focus of efforts Work on parameter set for a possible

More information

Screen investigations for low energetic electron beams at PITZ

Screen investigations for low energetic electron beams at PITZ 1 Screen investigations for low energetic electron beams at PITZ S. Rimjaem, J. Bähr, H.J. Grabosch, M. Groß Contents Review of PITZ setup Screens and beam profile monitors at PITZ Test results Summary

More information

LCLS-II Injector Tuning Procedures. F. Zhou (SLAC) & F. Sannibale (LBNL) 2/6/2017

LCLS-II Injector Tuning Procedures. F. Zhou (SLAC) & F. Sannibale (LBNL) 2/6/2017 LCLSII-TN-17-3 LCLS-II Injector Tuning Procedures F. Zhou (SLAC) & F. Sannibale (LBNL) /6/17 1. Introduction Figure 1 shows

More information

BUNCH-COMPRESSOR TRANSVERSE PROFILE MONITORS OF THE SwissFEL INJECTOR TEST FACILITY

BUNCH-COMPRESSOR TRANSVERSE PROFILE MONITORS OF THE SwissFEL INJECTOR TEST FACILITY Proceedings of IBIC, Tsukuba, Japan MOPB8 BUNCH-COMPRESSOR TRANSVERSE PROFILE MONITORS OF THE SwissFEL INJECTOR TEST FACILITY Gian Luca Orlandi, Masamitsu Aiba, Simona Bettoni, Bolko Beutner, Helge Brands,

More information

PEP II STATUS AND PLANS *

PEP II STATUS AND PLANS * PEP II STATUS AND PLANS * John T. Seeman + Stanford Linear Accelerator Center, Stanford University, Stanford, CA 94309 USA The PEP II B-Factory 1 project is an e + e - colliding beam storage ring complex

More information

TITLE PAGE. Title of paper: PUSH-PULL FEL, A NEW ERL CONCEPT Author: Andrew Hutton. Author Affiliation: Jefferson Lab. Requested Proceedings:

TITLE PAGE. Title of paper: PUSH-PULL FEL, A NEW ERL CONCEPT Author: Andrew Hutton. Author Affiliation: Jefferson Lab. Requested Proceedings: TITLE PAGE Title of paper: PUSH-PULL FEL, A NEW ERL CONCEPT Author: Andrew Hutton Author Affiliation: Jefferson Lab Requested Proceedings: Unique Session ID: Classification Codes: Keywords: Energy Recovery,

More information

Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi)

Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi) Commissioning of Accelerators Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi) www.europeanspallationsource.se 6 July, 2017 Contents General points Definition of Commissioning

More information

First Results and Future of the Photo Injector Test Facility at DESY Zeuthen PITZ. introduction first measurements future schedule

First Results and Future of the Photo Injector Test Facility at DESY Zeuthen PITZ. introduction first measurements future schedule First Results and Future of the Photo Injector Test Facility at DESY Zeuthen PITZ introduction first measurements future schedule Frank Stephan for the PITZ Collaboration, TTF Meeting Saclay, April 3 rd

More information

RUNNING EXPERIENCE OF FZD SRF PHOTOINJECTOR

RUNNING EXPERIENCE OF FZD SRF PHOTOINJECTOR RUNNING EXPERIENCE OF FZD SRF PHOTOINJECTOR Rong Xiang On behalf of the BESSY-DESY-FZD-MBI collaboration and the ELBE team FEL 2009, Liverpool, United Kingdom, August 23 ~ 28, 2009 Outline Introduction

More information

EUROFEL-Report-2007-DS EUROPEAN FEL Design Study

EUROFEL-Report-2007-DS EUROPEAN FEL Design Study EUROFEL-Report-2007-DS4-095 EUROPEAN FEL Design Study Deliverable N : D 4.3 Deliverable Title: Task: Authors: Generation of 3rd harmonic photons at 90 nm DS-4 see next page Contract N : 011935 Project

More information

Electron Bypass Line (EBL) Design Electrons to A-line bypassing LCLS T. Fieguth, R. Arnold

Electron Bypass Line (EBL) Design Electrons to A-line bypassing LCLS T. Fieguth, R. Arnold September 2007 SLAC-TN-08-001 Electron Bypass Line (EBL) Design Electrons to A-line bypassing LCLS T. Fieguth, R. Arnold Introduction Forty one years ago, September 20, 1966, the first beam entered End

More information

Report on the LCLS Injector Technical Review

Report on the LCLS Injector Technical Review Report on the LCLS Injector Technical Review Stanford Linear Accelerator Center November 3&4, 2003 Committee Members Prof. Patrick G. O Shea, Chair, University of Maryland Dr. Eric Colby, Stanford Linear

More information

AREAL- Phase 1. B. Grigoryan on behalf of AREAL team

AREAL- Phase 1. B. Grigoryan on behalf of AREAL team AREAL- Phase 1 Progress & Status B. Grigoryan on behalf of AREAL team Contents Machine Layout Building & Infrastructure Laser System RF System Vacuum System Cooling System Control System Beam Diagnostics

More information

Start to End Simulations

Start to End Simulations Start to End Simulations Motivation, Methods, and Examples Michael Borland Operations Analysis Group APS Operations Division March 20, 2005 A Laboratory Operated by The University of Chicago Motivation

More information

Summary of recent photocathode studies

Summary of recent photocathode studies Summary of recent photocathode studies S. Lederer, S. Schreiber DESY L. Monaco, D. Sertore INFN Milano LASA FLASH seminar November 17 th, 2009 Outlook Cs 2 Te photocathodes Pulsed QE measurements laser

More information

An Operational Diagnostic Complement for Positrons at CEBAF/JLab

An Operational Diagnostic Complement for Positrons at CEBAF/JLab An Operational Diagnostic Complement for Positrons at CEBAF/JLab Michael Tiefenback JLab, CASA International Workshop on Physics with Positrons at Jefferson Lab 12-15 September 2017 Operating CEBAF with

More information

Top-Up Experience at SPEAR3

Top-Up Experience at SPEAR3 Top-Up Experience at SPEAR3 Contents SPEAR 3 and the injector Top-up requirements Hardware systems and modifications Safety systems & injected beam tracking Interlocks & Diagnostics SPEAR3 Accelerator

More information

Suppression of Timing drift between laser and electron beam driven photo-cathode RF gun

Suppression of Timing drift between laser and electron beam driven photo-cathode RF gun Suppression of Timing drift between laser and electron beam driven photo-cathode RF gun A. Sakumi, M. Uesaka, Y. Muroya, T. Ueda Nuclear Professional School, University of Tokyo J. Urakawa, KEK, Japan

More information

LCLS Linac Technical Design Review Diagnostics and Controls

LCLS Linac Technical Design Review Diagnostics and Controls Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Linac Technical Design Review Diagnostics and Controls December 12, 12, 2003 Requirements for for beamline instrumentation Upgrades

More information

CLIC Feasibility Demonstration at CTF3

CLIC Feasibility Demonstration at CTF3 CLIC Feasibility Demonstration at CTF3 Roger Ruber Uppsala University, Sweden, for the CLIC/CTF3 Collaboration http://cern.ch/clic-study LINAC 10 MO303 13 Sep 2010 The Key to CLIC Efficiency NC Linac for

More information

High Rep Rate Guns: FZD Superconducting RF Photogun

High Rep Rate Guns: FZD Superconducting RF Photogun High Rep Rate Guns: FZD Superconducting RF Photogun J. Teichert, A. Arnold, H. Büttig, D. Janssen, M. Justus, U. Lehnert, P. Michel, K. Moeller, P. Murcek, Ch. Schneider, R. Schurig, G. Staats, F. Staufenbiel,

More information

Status of the X-ray FEL control system at SPring-8

Status of the X-ray FEL control system at SPring-8 Status of the X-ray FEL control system at SPring-8 T.Fukui 1, T.Hirono 2, N.Hosoda 1, M.Ishii 2, M.Kitamura 1 H.Maesaka 1,T.Masuda 2, T.Matsushita 2, T.Ohata 2, Y.Otake 1, K.Shirasawa 1,M.Takeuchi 2, R.Tanaka

More information

THE NEXT LINEAR COLLIDER TEST ACCELERATOR: STATUS AND RESULTS * Abstract

THE NEXT LINEAR COLLIDER TEST ACCELERATOR: STATUS AND RESULTS * Abstract SLAC PUB 7246 June 996 THE NEXT LINEAR COLLIDER TEST ACCELERATOR: STATUS AND RESULTS * Ronald D. Ruth, SLAC, Stanford, CA, USA Abstract At SLAC, we are pursuing the design of a Next Linear Collider (NLC)

More information

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR Proceedings of FEL213, New York, NY, USA STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR F. Loehl, J. Alex, H. Blumer, M. Bopp, H. Braun, A. Citterio, U. Ellenberger, H. Fitze, H. Joehri, T. Kleeb, L.

More information

Cathode Studies at FLASH: CW and Pulsed QE measurements

Cathode Studies at FLASH: CW and Pulsed QE measurements Cathode Studies at FLASH: CW and Pulsed QE measurements L. Monaco, D. Sertore, P. Michelato S. Lederer, S. Schreiber Work supported by the European Community (contract number RII3-CT-2004-506008) 1/27

More information

Next Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack

Next Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack The Four 50 MW XL4 X-band klystrons installed on the 8-Pack The Demonstrate an NLC power source Two Phases: 8-Pack Phase-1 (current): Multi-moded SLED II power compression Produce NLC baseline power: 475

More information

Detailed Design Report

Detailed Design Report Detailed Design Report Chapter 4 MAX IV Injector 4.6. Acceleration MAX IV Facility CHAPTER 4.6. ACCELERATION 1(10) 4.6. Acceleration 4.6. Acceleration...2 4.6.1. RF Units... 2 4.6.2. Accelerator Units...

More information

Status of Elettra, top-up and other upgrades

Status of Elettra, top-up and other upgrades Status of Elettra, top-up and other upgrades Emanuel Karantzoulis ELETTRA / Trieste, Italy / 2010 November 25-26 Past and Present Configurations 1994-2007 From 2008 No full energy injection Full energy

More information

Results of recent photocathode studies at FLASH. S. Lederer, S. Schreiber DESY. L. Monaco, D. Sertore, P. Michelato INFN Milano LASA

Results of recent photocathode studies at FLASH. S. Lederer, S. Schreiber DESY. L. Monaco, D. Sertore, P. Michelato INFN Milano LASA Results of recent photocathode studies at FLASH S. Lederer, S. Schreiber DESY L. Monaco, D. Sertore, P. Michelato INFN Milano LASA FLASH seminar October 21 st, 2008 Outlook Cs 2 Te photocathodes cw QE

More information

SLAC X-band Technology R&D. Tor Raubenheimer DOE Briefing June 11 th, 2010

SLAC X-band Technology R&D. Tor Raubenheimer DOE Briefing June 11 th, 2010 SLAC X-band Technology R&D Tor Raubenheimer DOE Briefing June 11 th, 2010 Introduction Overall ARD strategy ILC Program X-band program Compact XFEL and other applications Status and development needs Proposed

More information

A Cathode Development Cornell Cultera This scope includes all labor and purchases required produce photocathodes required by CBETA.

A Cathode Development Cornell Cultera This scope includes all labor and purchases required produce photocathodes required by CBETA. A1.01 PROJECT MANAGEMENT BNL/Cornell Michnoff A1.01.01 Milestones BNL/Cornell Michnoff This scope is a placeholder for all project high level milestones for NYSERDA. There is no cost or labor related to

More information

The Elettra Storage Ring and Top-Up Operation

The Elettra Storage Ring and Top-Up Operation The Elettra Storage Ring and Top-Up Operation Emanuel Karantzoulis Past and Present Configurations 1994-2007 From 2008 5000 hours /year to the users 2010: Operations transition year Decay mode, 2 GeV (340mA)

More information

Photocathodes FLASH: Quantum Efficiency (QE)

Photocathodes FLASH: Quantum Efficiency (QE) Photocathodes Studies @ FLASH: Quantum Efficiency (QE) L. Monaco, D. Sertore, P. Michelato J. H. Han, S. Schreiber Work supported by the European Community (contract number RII3-CT-4-568) /8 Main Topics

More information

LHC Beam Instrumentation Further Discussion

LHC Beam Instrumentation Further Discussion LHC Beam Instrumentation Further Discussion LHC Machine Advisory Committee 9 th December 2005 Rhodri Jones (CERN AB/BDI) Possible Discussion Topics Open Questions Tune measurement base band tune & 50Hz

More information

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline 3 cerl 3-1 cerl Overview As described before, the aim of the cerl in the R&D program includes the development of critical components for the ERL, as well as the construction of a test accelerator. The

More information

Undulator Protection for FLASH and for the European XFEL

Undulator Protection for FLASH and for the European XFEL Undulator Protection for FLASH and for the European FLASH sacrificial undulator: beam loss simulations FLASH BLM system plans FLASH sacrificial undulator FLASH Collimators BC2 scraper gun collimator (Ø

More information

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team Status of SOLARIS Paweł Borowiec On behalf of Solaris Team e-mail: pawel.borowiec@uj.edu.pl XX ESLS-RF Meeting, Villingen 16-17.11.2016 Outline 1. Timeline 2. Injector 3. Storage ring 16-17.11.2016 XX

More information

High QE Photocathodes lifetime and dark current investigation

High QE Photocathodes lifetime and dark current investigation High QE Photocathodes lifetime and dark current investigation Paolo Michelato INFN Milano - LASA Main Topics High QE photocathode lifetime QE vs. time (measurements on several cathodes, FLASH data) QE

More information

12GeV CEBAF Commissioning

12GeV CEBAF Commissioning 12GeV CEBAF Commissioning Operations Dept. Accelerator Division JLAB Outline 1 Process Integrated Process Overview Accelerator Readiness Review Process Internal Reviews/Process Process Recap 2 Beam Commissioning

More information

G0 Laser Status Parity Controls Injector Diagnostics

G0 Laser Status Parity Controls Injector Diagnostics G0 Laser Status Parity Controls Injector Diagnostics G0 Collaboration Mtg Jefferson Lab August 16, 2002 G0 Collaboration Mtg (August 16, 2002), 1 Installed new AOM homebuilt laser G0 Collaboration Mtg

More information

Beam Instrumentation for CTF3 and CLIC

Beam Instrumentation for CTF3 and CLIC Beam Instrumentation for CTF3 and CLIC Beam loss - Beam halo monitoring developments CLIC diagnostic Common developments with other projects Specific requirements for CLIC Beam Loss and Beam Halo measurement

More information

Accelerator Instrumentation RD. Monday, July 14, 2003 Marc Ross

Accelerator Instrumentation RD. Monday, July 14, 2003 Marc Ross Monday, Marc Ross Linear Collider RD Most RD funds address the most serious cost driver energy The most serious impact of the late technology choice is the failure to adequately address luminosity RD issues

More information

INSTALLATION STATUS OF THE ELECTRON BEAM PROFILER FOR THE FERMILAB MAIN INJECTOR*

INSTALLATION STATUS OF THE ELECTRON BEAM PROFILER FOR THE FERMILAB MAIN INJECTOR* TUPB77 INSTALLATION STATUS OF THE ELECTRON BEAM PROFILER FOR THE FERMILAB MAIN INJECTOR* R. Thurman-Keup #, M. Alvarez, J. Fitzgerald, C. Lundberg, P. Prieto, M. Roberts, J. Zagel, FNAL, Batavia, IL 651,

More information

Jefferson Lab Experience with Beam Halo, Beam Loss, etc.

Jefferson Lab Experience with Beam Halo, Beam Loss, etc. Jefferson Lab Experience with Beam Halo, Beam Loss, etc. Pavel Evtushenko with a lot of input from many experienced colleagues Steve Benson, Dave Douglas, Kevin Jordan, Carlos Hernandez-Garcia, Dan Sexton,

More information

The FLASH objective: SASE between 60 and 13 nm

The FLASH objective: SASE between 60 and 13 nm Injector beam control studies winter 2006/07 talk from E. Vogel on work performed by W. Cichalewski, C. Gerth, W. Jalmuzna,W. Koprek, F. Löhl, D. Noelle, P. Pucyk, H. Schlarb, T. Traber, E. Vogel, FLASH

More information

Upgrading LHC Luminosity

Upgrading LHC Luminosity 1 Upgrading LHC Luminosity 2 Luminosity (cm -2 s -1 ) Present (2011) ~2 x10 33 Beam intensity @ injection (*) Nominal (2015?) 1 x 10 34 1.1 x10 11 Upgraded (2021?) ~5 x10 34 ~2.4 x10 11 (*) protons per

More information

FEL TEST PLAN WORKSHEET

FEL TEST PLAN WORKSHEET FEL TEST PLAN WORKSHEET PROGRAM DEPUTY APPROVAL FEL Exp Coordinator Signoff: Date: PI Reviewer Signoff: Date: Expiration Date (max. 90 days from approval): Presentation Required? yes no COMPLETION INFORMATION

More information

Activities on FEL Development and Application at Kyoto University

Activities on FEL Development and Application at Kyoto University Activities on FEL Development and Application at Kyoto University China-Korea-Japan Joint Workshop on Electron / Photon Sources and Applications Dec. 2-3, 2010 @ SINAP, Shanghai Kai Masuda Inst. Advanced

More information

Summary report on synchronization, diagnostics and instrumentation

Summary report on synchronization, diagnostics and instrumentation Summary report on synchronization, diagnostics and instrumentation A.P. Freyberger and G.A. Krafft Jefferson Lab, 12000 Jefferson Avenue, Newport News, VA. 23606 Abstract The proceedings of Working Group

More information

Andrei Seryi, Toshiaki Tauchi. December 15-18, 2008

Andrei Seryi, Toshiaki Tauchi. December 15-18, 2008 ATF2 milestones for discussion Andrei Seryi, Toshiaki Tauchi December 15-18, 2008 7th ATF2 Project Meeting What are natural milestones for ATF2? ATF2 design: Nominal IP β y* =0.1 mm & L * =1 m this give

More information

5 Project Costs and Schedule

5 Project Costs and Schedule 93 5 Project Costs and Schedule 5.1 Overview The cost evaluation for the integrated version of the XFEL with 30 experiments and 35 GeV beam energy as described in the TDR-2001 yielded 673 million EUR for

More information

PEP-II Disassembly Technical Systems

PEP-II Disassembly Technical Systems PEP-II Disassembly Technical Systems PEP-II D&D Review 6-Aug-2007 S.DeBarger S.Ecklund, A.Hill, D.Kharakh, M.Zurawel Outline Project safety Disassembly of technical systems Shielding Vac/Mechanical Cable

More information

POLARIZED LIGHT SOURCES FOR PHOTOCATHODE ELECTRON GUNS AT SLAC?

POLARIZED LIGHT SOURCES FOR PHOTOCATHODE ELECTRON GUNS AT SLAC? SLAC-PUB-5965 December 1992 (4 POLARIZED LIGHT SOURCES FOR PHOTOCATHODE ELECTRON GUNS AT SLAC? M. Woods,O J. Frisch, K. Witte, M. Zolotorev Stanford Linear Accelerator Center Stanford University, Stanford,

More information

First Simultaneous Top-up Operation of Three Different Rings in KEK Injector Linac

First Simultaneous Top-up Operation of Three Different Rings in KEK Injector Linac First Simultaneous Top-up Operation of Three Different Rings in KEK Injector Linac Masanori Satoh (Acc. Lab., KEK) for the injector upgrade group 2010/9/16 1 Overview of Linac Beam Operation 2010/9/16

More information

The PEFP 20-MeV Proton Linear Accelerator

The PEFP 20-MeV Proton Linear Accelerator Journal of the Korean Physical Society, Vol. 52, No. 3, March 2008, pp. 721726 Review Articles The PEFP 20-MeV Proton Linear Accelerator Y. S. Cho, H. J. Kwon, J. H. Jang, H. S. Kim, K. T. Seol, D. I.

More information

CONSTRUCTION AND COMMISSIONING OF BEPCII

CONSTRUCTION AND COMMISSIONING OF BEPCII Abstract CONSTRUCTION AND COMMISSIONING OF BEPCII C. Zhang, J.Q. Wang, L. Ma and G.X.Pei for the BEPCII Team, IHEP, CAS P.O.Box 918, Beijing 100049, China BEPCII is the major upgrade of BEPC (Beijing Electron-

More information

Non-Invasive Energy Spread Monitoring for the JLAB Experimental Program via Synchrotron Light Interferometers

Non-Invasive Energy Spread Monitoring for the JLAB Experimental Program via Synchrotron Light Interferometers Non-Invasive for the JLAB Experimental Program via Synchrotron Light Interferometers P. Chevtsov, T. Day, A.P. Freyberger, R. Hicks Jefferson Lab J.-C. Denard Synchrotron SOLEIL 20th March 2005 1. Energy

More information

STATUS OF THE EUROPEAN XFEL

STATUS OF THE EUROPEAN XFEL STATUS OF THE EUROPEAN XFEL M. Hüning, DESY, Hamburg, Germany for the European XFEL Accelerator Construction Consortium * Abstract The European XFEL is one of the world's largest accelerators presently

More information

High Brightness Injector Development and ERL Planning at Cornell. Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics

High Brightness Injector Development and ERL Planning at Cornell. Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics High Brightness Injector Development and ERL Planning at Cornell Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics June 22, 2006 JLab CASA Seminar 2 Background During 2000-2001,

More information

November 5,1999. The NLC Injector UCRL-JC

November 5,1999. The NLC Injector UCRL-JC Preprint UCRL-JC-13-6450 The NLC Injector System V. Bharadwaj, J.E. Clendenin, P. Emma, J. Frisch, R.K. Jobe, T. Kotseroglou, P. Krejcik, A. V. Kulikov, Z. Li, T. Maruyama, K.K. Millage, B. McKee, G. Mulhollan,

More information

SLAC ILC Accelerator R&D Program

SLAC ILC Accelerator R&D Program SLAC ILC Accelerator R&D Program SLUO Meeting September 26 th, 2005 Tor Raubenheimer SLAC 2005 ILC Program NLC group was redirected towards ILC Developed a program aimed at the topics identified in the

More information

STATUS AND COMMISSIONING RESULTS OF THE R&D ERL AT BNL*

STATUS AND COMMISSIONING RESULTS OF THE R&D ERL AT BNL* STATUS AND COMMISSIONING RESULTS OF THE R&D ERL AT BNL* D. Kayran #,1,2, Z. Altinbas 1, D. Beavis 1, S. Belomestnykh 1,2, I. Ben-Zvi 1,2, S. Deonarine 1, D.M. Gassner 1, R. C. Gupta 1, H. Hahn 1,L.R. Hammons

More information

Production of quasi-monochromatic MeV photon in a synchrotron radiation facility

Production of quasi-monochromatic MeV photon in a synchrotron radiation facility Production of quasi-monochromatic MeV photon in a synchrotron radiation facility Presentation at University of Saskatchewan April 22-23, 2010 Yoshitaka Kawashima Brookhaven National Laboratory NSLS-II,

More information

STATUS OF THE SwissFEL C-BAND LINAC

STATUS OF THE SwissFEL C-BAND LINAC STATUS OF THE SwissFEL C-BAND LINAC F. Loehl, J. Alex, H. Blumer, M. Bopp, H. Braun, A. Citterio, U. Ellenberger, H. Fitze, H. Joehri, T. Kleeb, L. Paly, J.-Y. Raguin, L. Schulz, R. Zennaro, C. Zumbach,

More information

Jae-Young Choi On behalf of PLS-II Linac team

Jae-Young Choi On behalf of PLS-II Linac team PLS-II Linac 2015. 4. 8. Jae-Young Choi On behalf of PLS-II Linac team Accelerators in Pohang Accelerator Laboratory XFEL (under construction) 400 M$ Machines under installation PLS-II PAL : Chronology

More information

Status of the Jefferson Lab Polarized Beam Physics Program and Preparations for Upcoming Parity Experiments

Status of the Jefferson Lab Polarized Beam Physics Program and Preparations for Upcoming Parity Experiments Status of the Jefferson Lab Polarized Beam Physics Program and Preparations for Upcoming Parity Experiments P. Adderley, M. Baylac, J. Clark, A. Day, J. Grames, J. Hansknecht, M. Poelker, M. Stutzman PESP

More information