5 Project Costs and Schedule

Size: px
Start display at page:

Download "5 Project Costs and Schedule"

Transcription

1 93 5 Project Costs and Schedule 5.1 Overview The cost evaluation for the integrated version of the XFEL with 30 experiments and 35 GeV beam energy as described in the TDR-2001 yielded 673 million EUR for the complete project including manpower. In accord with the Stellungnahme by the German Science Council, the layout of the facility with separate linac presented in this report has been worked out such as to stay within this original cost frame. In order to achieve this goal in the case that the XFEL part of TESLA would be started earlier than the linear collider, thus loosing the cost benefit of large scale production, the energy of the linear accelerator has been reduced to 20 GeV at the nominal gradient of 23.5 MV/m, the number of FEL beamlines has been reduced from 5 to 3, the number of beamlines for short pulse spontaneous radiation from 5 to 2, and the number of experimental stations from 30 to 10. The goal was almost met with the estimated cost of 684 million EUR for the capital investment and manpower. However, additional funds of 25 million EUR are required for R&D (7 million EUR), spare components (12 million EUR) and pre-operation (6 million EUR). It should be mentioned that in case of a parallel construction of the XFEL and the linear collider with the benefit of large scale industrial production, the total cost for capital investment and personnel would be reduced by 145 million EUR. The technical specification of the facility includes a safety margin (e.g. rf power, cryogenic plant capacity, etc.), which is necessary to guarantee the envisaged performance and also contributes to the reliability of the cost figure above. However, to cover uncertainties in the cost estimates, unforeseen events and delays, which can not be completely ruled out, we estimate that a risk budget of 10% of the total cost quoted above would have to be foreseen for equipment and personnel (see below). The investment costs given include all components necessary for the construction of the decoupled linear accelerator for the XFEL and the XFEL laboratory. All numbers are quoted at year 2000 prices. The manpower required for the various stages of the project (i.e. preparation, procurement, testing, assembly and commissioning) is included in the total cost assuming 50 thousand EUR per person per year on average.

2 94 5 Project Costs and Schedule the costs for the linear accelerator part of the decoupled XFEL amount to 446 million EUR including 110 million EUR for personnel; the costs for the XFEL laboratory itself with experimental stations and beamlines are 238 million EUR including 30 million for personnel. The total cost is divided up into the major items as shown in Tables and (see also Fig ). To assure full competition in future bidding procedures, no further cost breakdown is given in this public report. In the following section we will describe the various procedures used for the cost evaluation of the major components. Distribution of 684 million EUR project cost 14% Accelerator modules 7% 3% 6% 5% 14% 7% 3% 7% RF system 3% Injector 6% Electron beam lines 20% Civil engineering 9% Infrastructure 20% 6% 20% Personnel 6% Undulators 9% 20% 3% Photon beam lines 7% Experiments 5% XFEL Laboratory Figure 5.1.1: Overview of the project cost distribution. 5.2 Cost Estimate Basis for the Linear Accelerator For the Technical Design Report of the TESLA project published in March 2001 the cost estimates for all major components were obtained from studies made by industry and are based on the large number of components needed for the LC. For the XFEL laboratory decoupled from the linear collider as described in this report these estimates are not valid any more, if the XFEL facility is constructed before or independent from the linear collider.

3 5.2 Cost Estimate Basis for the Linear Accelerator 95 Sub-system cost [M-EUR] components included Linear accelerator modules (78) cryostats, 936 cavities, input couplers, HOM couplers, tuning systems, quadrupoles, steering magnets and instrumentation for 78 modules RF system (26) 47 RF power supplies, modulators, HV pulse cables, transformers, klystrons, waveguide system, low level RF controls, interlocks, cables Injector 23 RF gun system, special accelerator modules and RF systems, beam transfer lines, bunch compressors, diagnostics Electron beam lines 38 beam transport lines, magnets, beam collimation, beam extraction and dump systems, vacuum systems, power supplies, feedback systems, diagnostics Civil engineering km tunnel for linear accelerator, surface buildings for cryogenics and RF components, connecting shafts, beam dump halls, civil construction for injector Infrastructure 59 tunnel infrastructure, cable trays, power distribution, main power connection, cryoplant and cryogenic distribution system, water and ventilation systems, safety systems, module and RF test facility, control systems, vacuum pump stations, cabling, interlocks, magnet supplies, miscellaneous Sum of investments accelerator 336 Personnel cost 110 Personnel for the accelerator part Costs for preoperation and spares 14 Electrical power and materials; spares accelerator modules and RF components Table 5.1.1: Cost overview for the major items of the linear accelerator. All numbers are given in million EUR at year 2000 prices. In this case the price reduction due to the production of large numbers cannot be obtained. For the completion of the present report new in-depth evaluations by industry could not be performed. However, industrial prices for small quantities are available from the TESLA Test Facility for all components needed for the accelerator. Using these prices directly for the components

4 96 5 Project Costs and Schedule Sub-system cost [M-EUR] components included Undulators undulator segments including magnetic and mechanical structures, and motion control; 119 intersection elements including magnets, phase shifter, beam-position-monitor and power supplies; vacuum system Photon Beamlines 20 5 beamlines including each a vacuum system, photon shutter and collimator, beamposition monitor, double-crystal monochromator, double-bounce mirror unit, optical enclosures Experiments experiments including all apparatus and preparatory laboratories XFEL Laboratory 34 infrastructure for the XFEL laboratory, special laboratories, site costs Ellerhoop and Borstel- Hohenraden Civil engineering 68 experimental hall and tunnels for photon and undulator installation, access shaft buildings and corresponding surface buildings, office building, central facility buildings Ellerhoop Sum of investments XFEL laboratory 208 Personnel cost 30 Personnel for the XFEL laboratory Costs for spares and R&D 11 Spare undulator segments; R&D for optical components and detectors Table 5.1.2: Cost overview for the major items of the XFEL laboratory. All numbers are given in million EUR at year 2000 prices. of the XFEL facility would lead to an overestimate of the cost in most cases. Therefore industrial scaling laws have been applied, where it seemed appropriate, to obtain a probable price for each component. The numbers from the TDR-2001 have been used to check the validity of the scaling. As scaling procedures only apply for large numbers and only give a trend of the cost evolution, an uncertainty of the cost for each component has been estimated, yielding part of the specific risk budget mentioned above.

5 5.2 Cost Estimate Basis for the Linear Accelerator Linear accelerator modules The cryomodules for the linear accelerator with the superconducting cavities are the largest cost item with 99 million EUR. The cost is dominated by the s.c. cavities, the cryostat and the assembly of the module. Niobium, cavity fabrication and treatment procedures each constitute a substantial part of the cavity costs. Superconducting cavities The cost of cavity fabrication for the TDR-2001 was estimated using industrial studies made by companies with expertise in niobium production, cavity fabrication, and the planning of mass production plants. For this report there are no studies of equivalent depth available. However, there is a quotation for the mechanical fabrication of 2000 cavities against which our scaling has been cross-checked. An industrial estimate of the cavity preparation and module assembly for 1000 cavities is available. Niobium production The amount of material needed for the cavities for the XFEL linear accelerator is about 20 tons of high purity (RRR 300) niobium. For the TDR-2001 there exist price quotations for 500 tons. The price for the TDR was in part based on savings on sheet cuts for re-melting and streamlining of facilities for continuous production. These savings will most probably not be applicable for 20 tons. This has been accounted for in the cost and its uncertainty used for this report. There is an additional uncertainty in the price of niobium as prices are quoted in US-$: the price used in the cost estimate is based on 1 US-$/EUR. Cavity fabrication For the TDR-2001 the TTF cavity production was analyzed in terms of cost driving and critical procedures in an industrial study (Babcock Noell Nuclear GmbH, Würzburg, Germany). In the fabrication of TTF cavities, electron beam welding has been identified as the dominant cost driving procedure. A new fabrication facility was planned with three vacuum chamber welding installations for the fabrication of cavities. The facility, together with the use of multiple welding tooling, substantially reduced the welding costs. The total facility costs were determined in detail (planning, investment, effort for ramping up and closing the facility, personnel, repair and maintenance, consumption, quality insurance) and were compiled in a report. The same study was also done for the fabrication of 2000 cavities only. It should be mentioned, that the use of special tooling and at least one three chamber welding machine will also be necessary for the production of the 936 cavities for the XFEL linear accelerator to allow for the production of the linac modules within two years. The price quotation for 2000 cavities and the price for the present small number production for TTF has been used to estimate the price for this report.

6 98 5 Project Costs and Schedule Cryomodules For the TDR-2001 two industrial studies were made for the mass production: the costs for the vacuum vessel and cold mass were taken from an industrial study by E. Zanon SpA, Schio, Italy; the costs for the cavity preparation and cryomodule assembly were derived from an industrial study by Babcock Noell Nuclear GmbH. The price for the cryostat from these studies and the present price for the small number production have been used to estimate the price for 78 cryostats. For the cost of cavity preparation and module assembly a study is being performed by Babcock Noell Nuclear GmbH. First results from this study have been used for the cost estimate in this report. Costs for other components were derived from the experience gained from the procurement of similar components for TTF using industrial scaling laws Main linac RF system The RF system is also a large cost item for the linear accelerator. The most relevant parts with respect to cost are: klystrons; modulators and pulse transformers; wave guide distribution system; interlock and controls; low level RF system; HV cables. Klystron The cost estimate assumes the production of the total number of 30 klystrons by one manufacturer. For the TDR-2001 a mass production study was made by the prototype manufacturer (Thomson Tubes Electroniques, Velizy, France). In this study special production facilities were set up, to allow for the projected number of about 80 klystrons per year. This investment will presumably not pay and will not be necessary for 30 klystrons only. Therefore prices for klystrons and for the auxiliary systems are based on present TTF costs with some cost reduction assumed. Modulator and pulse transformer The cost estimate is based on the production of the total number of 30 modulators (HV power supply, pulser, internal modulator interlock) and pulse transformers by one manufacturer. Again the actual numbers from TTF assuming some savings for the larger number have been used. Low level RF system, waveguide distribution system and cables The cost for the low level RF system is based on TTF experience assuming some cost reduction for the larger number. The cost estimate for the wave guide system is based on experience with the existing TTF system, adjusted for the production of a larger number. Different parts of the system will be supplied from different manufacturers. For the cable cost the actual price of such a cable has been taken.

7 5.2 Cost Estimate Basis for the Linear Accelerator Injection systems The costs for the injector have been taken from the TDR Electron beam lines and beam dump system The cost estimate for the magnets, powersupplies, cables, the vacuum system and the diagnostics is based on the original TDR-2001 numbers as many components are similar in layout. The difference in number has been compensated by an increased price per unit. The beam dump system has been modified with respect to the TDR-2001, where a water dump capable of handling 2 MW beams had been used, a system similar to the beam dumps for the linear collider. To save cost for this first stage of the project the average beam power of the facility has been reduced to 300 kw allowing the use of a simpler solid beam dump, where cost numbers are available from TTF. Costs for the kicker magnet and pulser system have been evaluated from the experience with the HERA beam dump system Civil engineering Civil engineering is a major cost item amounting to 70 million EUR. It includes all tunnels, shafts, underground and surface buildings for the linear accelerator and the beam distribution. The construction cost estimate for the linear accelerator tunnel, shafts, underground and surface buildings is taken from an actual cost estimate by an engineering team, which prepared the detailed layout of the facility for the plan approval procedure (Planfeststellungsverfahren). A certain percentage of the total construction cost has been taken into account for the services of architects and civil engineers according to HERA experience and public regulations Infrastructure The infrastructure costs amount to 59 million EUR. The major cost items are the cryogenic plants, distribution lines, and connection boxes. Additional items included are: the main power connection and distribution; water cooling and ventilation systems; safety installations; control systems and interlocks; test equipment for cryomodules and RF components. The cost evaluation of most components has been performed in an identical way as for the original TDR Some cost numbers for the infrastructure have been obtained by dividing the costs of the TDR-2001 by the number of service halls or tunnel length. Compared to the TDR-2001 the size of the test facility equipment has been reduced by a factor of three, adjusting to the reduced number of components to be tested. This will allow to test all components for the accelerator within one year and a half. The cost of the equipment has been taken as one third of the TDR-2001 cost. The cost for the accelerator control system and the linac external vacuum systems have been evaluated on the basis of HERA and TTF experience. Contrary to the TDR-2001 spare

8 100 5 Project Costs and Schedule linac modules are not included into this item but are quoted separately. 5.3 Investment Costs for the XFEL Laboratory The cost estimate for the XFEL laboratory is based on the TDR-2001 and has been scaled to the design presented in this report. This includes the infrastructure cost which in the TDR was subsummised in the infrastructure cost of the accelerator. The total investment costs for the XFEL laboratory, including civil engineering, the cost for the site in Ellerhoop and infrastructure is given in Table As in the cost estimation in the TDR-2001 a specific risk budget covers the uncertainties of the industrial price estimates for the undulators and additional cost for the X-ray optics due to extremely demanding specifications required for the XFEL radiation Undulator segments For the realization of undulator segments an industrial study has been done in 2000 by Vacuumschmelze, Hanau, Germany. The study assumes a production line delivering 6 undulator segments per month. It is assumed that the same production plant is used for production of about 40% of this original estimate. This assumption is well justified since the estimated total production time is two years. For each undulator segment a vacuum system with chamber and pumping, and an intersection element is needed including phase shifters, magnets, quadrupoles, beam-positionmonitors, as well as the required power supplies and front-end electronics. The required amount of components already leads to savings compared to small series quotations Photon beamlines and diagnostics The photon beamlines cover the entire handling of the X-ray beams and its guidance to the experimental hall. This includes a large vacuum system for the long drift distances, beam collimation and photon shutter. For this large system a cost reduction compared to small series is included. The photon beamlines further include the photon diagnostics station, monochromators and mirrors. Price estimates take current quotations for small series into account. The total number of devices is still small and additional requirements to the devices are expected to prohibit any further reduction. Cost for optical and experimental enclosures are based on recent quotations (e.g. for the ESRF, Grenoble, France) Experiments The cost estimate for experiments is based on detailed listings of components for a variety of different experiments as outlined in the TDR The costs are proportional to the number of experiments and have been scaled accordingly. In addition to the costs for experiments, the preparatory laboratories required for the experiments and the needs for laser and detector installations on site were considered.

9 5.4 Manpower Requirements XFEL laboratory The cost for the XFEL laboratory includes all infrastructure for the XFEL laboratory, special laboratories for installation and performance test of components, and the cost for the land at the sites in Ellerhoop and Borstel-Hohenraden. Cost estimates are based on current costs for equivalent components and laboratories installed at DESY. The costs for the land were estimated using present market prices XFEL civil engineering Civil engineering is a relatively large cost item that includes most of the switchyard building at Ellerhoop including the costs for the shaft and access buildings, and 50% of the cost for the tunnels. Furthermore, the experimental hall and other buildings for the user operation on the Ellerhoop site are included here. The construction cost estimate for the underground and surface buildings directly related to the XFEL radiation is taken from an actual cost estimate by an engineering team, which prepared the detailed layout of the facility for the plan approval procedure (Planfeststellungsverfahren). Cost estimates for other buildings are based on experience at DESY during recent years. 5.4 Manpower Requirements The manpower required for the different stages of the project (design, procurement, fabrication and assembly, testing, installation and commissioning) has been estimated mainly on the basis of the experiences gained at TTF, in large projects like HERA or the ESRF and from the considerations made for TDR A total of 2200 person years for the accelerator and 600 person years for the XFEL laboratory will be required. The equivalent costs of 140 Mio Euro are included in the total cost estimate. 5.5 Time Schedule The construction time of the XFEL is 6 years, counting from the start of civil construction to the beginning of commissioning the linear accelerator. The evaluation of the schedule has been done under similar assumptions as for the TDR Figure shows the construction schedule, indicating the major activities. 5.6 Pre-operating Costs and Spares For the commissioning phase electrical power and material consumption have been taken into account with 6 million EUR. For critical components (such as accelerator modules) a number of spares will be produced; these costs amount to 12 million EUR. Since pre-operation and the production of spares will be required in the construction phase of the project they are indicated as a separate item.

10 102 5 Project Costs and Schedule 5.7 Operating Costs A very preliminary estimate for the operating costs has been made. The total cost for operation has been estimated at 50 million EUR per year. This includes the electrical power consumption, the regular replacement or refurbishing of klystrons, the maintenance and refurbishing of optical components and detectors, and the helium losses. The numbers are determined assuming current prices and an annual operation time of 5,000 h. Costs for general maintenance and repair have been estimated assuming 2 % per year of the original total investment costs corresponding to the DESY experience. A total staff of 450 is included, distributed between accelerator and XFEL laboratory m 1200 m Source Super conductive LINAC Switch yard XrayLaboratory Task X-FELProject Civil construction Year Equipment fabrication Assembly & Tests Machine installation Commissioning Commissioning with beam Figure 5.7.1: Time schedule.

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline 3 cerl 3-1 cerl Overview As described before, the aim of the cerl in the R&D program includes the development of critical components for the ERL, as well as the construction of a test accelerator. The

More information

STATUS OF THE EUROPEAN XFEL

STATUS OF THE EUROPEAN XFEL STATUS OF THE EUROPEAN XFEL M. Hüning, DESY, Hamburg, Germany for the European XFEL Accelerator Construction Consortium * Abstract The European XFEL is one of the world's largest accelerators presently

More information

AREAL- Phase 1. B. Grigoryan on behalf of AREAL team

AREAL- Phase 1. B. Grigoryan on behalf of AREAL team AREAL- Phase 1 Progress & Status B. Grigoryan on behalf of AREAL team Contents Machine Layout Building & Infrastructure Laser System RF System Vacuum System Cooling System Control System Beam Diagnostics

More information

Nick Walker DESY MAC

Nick Walker DESY MAC Nick Walker DESY MAC 4.5.2006 XFEL X-Ray Free-Electron Laser DESY ILC Project Group Accelerator Experimentation Behnke, Elsen, Walker (chair) WP 15, 16 WP 4-7 Accelerator Physics and Design WP 6 High Gradient

More information

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala) 2 Work Package and Work Unit descriptions 2.8 WP8: RF Systems (R. Ruber, Uppsala) The RF systems work package (WP) addresses the design and development of the RF power generation, control and distribution

More information

STATUS OF THE EUROPEAN XFEL CONSTRUCTING THE 17.5 GEV SUPERCONDUCTING LINEAR ACCELERATOR

STATUS OF THE EUROPEAN XFEL CONSTRUCTING THE 17.5 GEV SUPERCONDUCTING LINEAR ACCELERATOR STATUS OF THE EUROPEAN XFEL CONSTRUCTING THE 17.5 GEV SUPERCONDUCTING LINEAR ACCELERATOR Winfried Decking, DESY for the European XFEL Accelerator Consortium Up to 17.5 GeV SC Linac, 27000 pulses per second

More information

Availability and Reliability Issues for the ILC

Availability and Reliability Issues for the ILC Availability and Reliability Issues for the ILC SLAC Presented at PAC07 26 June 07 Contents Introduction and purpose of studies The availability simulation What was modeled (important assumptions) Some

More information

SUMMARY OF THE ILC R&D AND DESIGN

SUMMARY OF THE ILC R&D AND DESIGN SUMMARY OF THE ILC R&D AND DESIGN B. C. Barish, California Institute of Technology, USA Abstract The International Linear Collider (ILC) is a linear electron-positron collider based on 1.3 GHz superconducting

More information

Technical Document 1 attached to the European XFEL Convention

Technical Document 1 attached to the European XFEL Convention May 30, 2007 Technical Document 1 attached to the European XFEL Convention Executive Summary of the Technical Design Report (Part A) and Scenario for the Rapid Start-up of the European XFEL Facility (Part

More information

ILC-LNF TECHNICAL NOTE

ILC-LNF TECHNICAL NOTE IL-LNF EHNIAL NOE Divisione Acceleratori Frascati, July 4, 2006 Note: IL-LNF-001 RF SYSEM FOR HE IL DAMPING RINGS R. Boni, INFN-LNF, Frascati, Italy G. avallari, ERN, Geneva, Switzerland Introduction For

More information

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR Proceedings of FEL213, New York, NY, USA STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR F. Loehl, J. Alex, H. Blumer, M. Bopp, H. Braun, A. Citterio, U. Ellenberger, H. Fitze, H. Joehri, T. Kleeb, L.

More information

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation Matthias Liepe Assistant Professor of Physics Cornell University Experience with the Cornell ERL Injector SRF

More information

STATUS OF THE INTERNATIONAL LINEAR COLLIDER

STATUS OF THE INTERNATIONAL LINEAR COLLIDER STATUS OF THE INTERNATIONAL LINEAR COLLIDER K. Yokoya, KEK, Tsukuba, Japan Abstract The International Linear Collider (ILC) is the nextgeneration electron-positron collider. Since the publication of the

More information

The X-Ray FEL at DESY

The X-Ray FEL at DESY The X-Ray FEL at DESY Hans Weise / DESY TESLA The Superconducting Electron- Positron Linear Collider with an Integrated X-Ray Laser Laboratory Technical Design Report March 2001 integrated into TESLA LC:

More information

STATUS OF THE SwissFEL C-BAND LINAC

STATUS OF THE SwissFEL C-BAND LINAC STATUS OF THE SwissFEL C-BAND LINAC F. Loehl, J. Alex, H. Blumer, M. Bopp, H. Braun, A. Citterio, U. Ellenberger, H. Fitze, H. Joehri, T. Kleeb, L. Paly, J.-Y. Raguin, L. Schulz, R. Zennaro, C. Zumbach,

More information

Detailed Design Report

Detailed Design Report Detailed Design Report Chapter 4 MAX IV Injector 4.6. Acceleration MAX IV Facility CHAPTER 4.6. ACCELERATION 1(10) 4.6. Acceleration 4.6. Acceleration...2 4.6.1. RF Units... 2 4.6.2. Accelerator Units...

More information

PEP-II Overview & Ramp Down Plan. J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007

PEP-II Overview & Ramp Down Plan. J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007 PEP-II Overview & Ramp Down Plan J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007 Topics Overview of the PEP-II Collider PEP-II turns off September 30, 2008. General list of components and buildings

More information

Present Status and Future Upgrade of KEKB Injector Linac

Present Status and Future Upgrade of KEKB Injector Linac Present Status and Future Upgrade of KEKB Injector Linac Kazuro Furukawa, for e /e + Linac Group Present Status Upgrade in the Near Future R&D towards SuperKEKB 1 Machine Features Present Status and Future

More information

Status of CTF3. G.Geschonke CERN, AB

Status of CTF3. G.Geschonke CERN, AB Status of CTF3 G.Geschonke CERN, AB CTF3 layout CTF3 - Test of Drive Beam Generation, Acceleration & RF Multiplication by a factor 10 Drive Beam Injector ~ 50 m 3.5 A - 2100 b of 2.33 nc 150 MeV - 1.4

More information

TITLE PAGE. Title of paper: PUSH-PULL FEL, A NEW ERL CONCEPT Author: Andrew Hutton. Author Affiliation: Jefferson Lab. Requested Proceedings:

TITLE PAGE. Title of paper: PUSH-PULL FEL, A NEW ERL CONCEPT Author: Andrew Hutton. Author Affiliation: Jefferson Lab. Requested Proceedings: TITLE PAGE Title of paper: PUSH-PULL FEL, A NEW ERL CONCEPT Author: Andrew Hutton Author Affiliation: Jefferson Lab Requested Proceedings: Unique Session ID: Classification Codes: Keywords: Energy Recovery,

More information

INFN School on Electron Accelerators. RF Power Sources and Distribution

INFN School on Electron Accelerators. RF Power Sources and Distribution INFN School on Electron Accelerators 12-14 September 2007, INFN Sezione di Pisa Lecture 7b RF Power Sources and Distribution Carlo Pagani University of Milano INFN Milano-LASA & GDE The ILC Double Tunnel

More information

Upgrading LHC Luminosity

Upgrading LHC Luminosity 1 Upgrading LHC Luminosity 2 Luminosity (cm -2 s -1 ) Present (2011) ~2 x10 33 Beam intensity @ injection (*) Nominal (2015?) 1 x 10 34 1.1 x10 11 Upgraded (2021?) ~5 x10 34 ~2.4 x10 11 (*) protons per

More information

TTF / VUV-FEL. Schedule 2005 and Project Management Issues. Schedule 2005 Project Organisation Budget & Controlling

TTF / VUV-FEL. Schedule 2005 and Project Management Issues. Schedule 2005 Project Organisation Budget & Controlling TTF / VUV-FEL Schedule 200 and Project Management Issues Schedule 200 Project Organisation Budget & Controlling Hans Weise / DESY DESY MAC Meeting November 9th, 2004 TTF Linac Start-up After Final Installation

More information

SLAC ILC Accelerator R&D Program

SLAC ILC Accelerator R&D Program SLAC ILC Accelerator R&D Program SLUO Meeting September 26 th, 2005 Tor Raubenheimer SLAC 2005 ILC Program NLC group was redirected towards ILC Developed a program aimed at the topics identified in the

More information

Status of JRA-SRF in CARE

Status of JRA-SRF in CARE Status of JRA-SRF in CARE Reminder JRA-SRF: Strategy, Partner, financial volume Where do we stand in JRA-SRF today Progress in work-packages, schedule Administrative & financial issues What is next First

More information

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting Status of BESSY II and berlinpro Wolfgang Anders Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting 16.-17.11.2016 at PSI Outline BESSY II Problems with circulators Landau cavity

More information

The ESS Accelerator. For Norwegian Industry and Research. Oslo, 24 Sept Håkan Danared Deputy Head Accelerator Division Group Leader Beam Physics

The ESS Accelerator. For Norwegian Industry and Research. Oslo, 24 Sept Håkan Danared Deputy Head Accelerator Division Group Leader Beam Physics The ESS Accelerator For Norwegian Industry and Research Oslo, 24 Sept 2013 Håkan Danared Deputy Head Accelerator Division Group Leader Beam Physics The Hadron Intensity Frontier Courtesy of M. Seidel (PSI)

More information

RF considerations for SwissFEL

RF considerations for SwissFEL RF considerations for H. Fitze in behalf of the PSI RF group Workshop on Compact X-Ray Free Electron Lasers 19.-21. July 2010, Shanghai Agenda Introduction RF-Gun Development C-band development Summary

More information

LLRF at SSRF. Yubin Zhao

LLRF at SSRF. Yubin Zhao LLRF at SSRF Yubin Zhao 2017.10.16 contents SSRF RF operation status Proton therapy LLRF Third harmonic cavity LLRF Three LINAC LLRF Hard X FEL LLRF (future project ) Trip statistics of RF system Trip

More information

ESS: The Machine. Bucharest, 24 April Håkan Danared Deputy Head Accelerator Division. H. Danared Industry & Partner Days Bucharest Page 1

ESS: The Machine. Bucharest, 24 April Håkan Danared Deputy Head Accelerator Division. H. Danared Industry & Partner Days Bucharest Page 1 ESS: The Machine Bucharest, 24 April 2014 Håkan Danared Deputy Head Accelerator Division H. Danared Industry & Partner Days Bucharest Page 1 2025 ESS construction complete 2009 Decision: ESS will be built

More information

Towards an X-Band Power Source at CERN and a European Structure Test Facility

Towards an X-Band Power Source at CERN and a European Structure Test Facility Towards an X-Band Power Source at CERN and a European Structure Test Facility Erk Jensen and Gerry McMomagle CERN The X-Band Accelerating Structure Design and Test-Program Workshop Day 2: Structure Testing

More information

WG2 Group Summary. Chris Adolphsen Terry Garvey Hitoshi Hayano

WG2 Group Summary. Chris Adolphsen Terry Garvey Hitoshi Hayano WG2 Group Summary Chris Adolphsen Terry Garvey Hitoshi Hayano Linac Options Fest On Thursday afternoon, various experts summarized the linac baseline options. Although hard choices have yet to be made,

More information

Upgrade of CEBAF to 12 GeV

Upgrade of CEBAF to 12 GeV Upgrade of CEBAF to 12 GeV Leigh Harwood (for 12 GeV Accelerator team) Page 1 Outline Background High-level description Schedule Sub-system descriptions and status Summary Page 2 CEBAF Science Mission

More information

XFEL High Power RF System Recent Developments

XFEL High Power RF System Recent Developments XFEL High Power RF System Recent Developments for the XFEL RF Group Outline XFEL RF System Requirements Overview Basic Layout RF System Main Components Multibeam Klystrons Modulator RF Waveguide Distribution

More information

EUROFEL-Report-2007-DS EUROPEAN FEL Design Study

EUROFEL-Report-2007-DS EUROPEAN FEL Design Study EUROFEL-Report-2007-DS4-095 EUROPEAN FEL Design Study Deliverable N : D 4.3 Deliverable Title: Task: Authors: Generation of 3rd harmonic photons at 90 nm DS-4 see next page Contract N : 011935 Project

More information

Status of the FAIR Project. Jürgen Henschel FAIR Project Leader / Technical Director GSI & FAIR

Status of the FAIR Project. Jürgen Henschel FAIR Project Leader / Technical Director GSI & FAIR Status of the FAIR Project Jürgen Henschel FAIR Project Leader / Technical Director GSI & FAIR Finland France Germany India Poland Romania Russia Slovenia Sweden UK FAIR Strategic objectives FAIR phase

More information

ESS Linac WP8 Radio Frequency Systems and Test Facilities

ESS Linac WP8 Radio Frequency Systems and Test Facilities ESS Linac WP8 Radio Frequency Systems and Test Facilities ESS/SPL Collaboration Meeting Lund, 29 June 2010 Roger Ruber (Uppsala University) for the ESS Linac RF Team ESS Linac WP8: RF Systems Outline Work

More information

L-Band RF R&D. SLAC DOE Review June 15 th, Chris Adolphsen SLAC

L-Band RF R&D. SLAC DOE Review June 15 th, Chris Adolphsen SLAC L-Band RF R&D SLAC DOE Review June 15 th, 2005 Chris Adolphsen SLAC International Linear Collider (ILC) RF Unit (TESLA TDR Layout) Gradient = 23.4 MV/m Bunch Spacing = 337 ns Fill Time = 420 µs Train Length

More information

The LEP Superconducting RF System

The LEP Superconducting RF System The LEP Superconducting RF System K. Hübner* for the LEP RF Group CERN The basic components and the layout of the LEP rf system for the year 2000 are presented. The superconducting system consisted of

More information

The TESLA RF System. S. Choroba. for the TESLA Collaboration. DESY Notkestr. 85, D Hamburg, Germany

The TESLA RF System. S. Choroba. for the TESLA Collaboration. DESY Notkestr. 85, D Hamburg, Germany The TESLA RF System S. Choroba for the TESLA Collaboration DESY Notkestr. 85, D-22603 Hamburg, Germany Abstract. The TESLA project proposed by the TESLA collaboration in 2001 is a 500 to 800GeV e+/e- linear

More information

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project Workshop on the future and next generation capabilities of accelerator driven neutron and muon sources

More information

RF plans for ESS. Morten Jensen. ESLS-RF 2013 Berlin

RF plans for ESS. Morten Jensen. ESLS-RF 2013 Berlin RF plans for ESS Morten Jensen ESLS-RF 2013 Berlin Overview The European Spallation Source (ESS) will house the most powerful proton linac ever built. The average beam power will be 5 MW which is five

More information

What can be learned from HERA Experience for ILC Availability

What can be learned from HERA Experience for ILC Availability What can be learned from HERA Experience for ILC Availability August 17, 2005 F. Willeke, DESY HERA Performance Critical Design Decisions What could be avoided if HERA would have to be built again? HERA

More information

Current status of XFEL/SPring-8 project and SCSS test accelerator

Current status of XFEL/SPring-8 project and SCSS test accelerator Current status of XFEL/SPring-8 project and SCSS test accelerator Takahiro Inagaki for XFEL project in SPring-8 inagaki@spring8.or.jp Outline (1) Introduction (2) Key technology for compactness (3) Key

More information

Digital BPMs and Orbit Feedback Systems

Digital BPMs and Orbit Feedback Systems Digital BPMs and Orbit Feedback Systems, M. Böge, M. Dehler, B. Keil, P. Pollet, V. Schlott Outline stability requirements at SLS storage ring digital beam position monitors (DBPM) SLS global fast orbit

More information

SRS and ERLP developments. Andrew moss

SRS and ERLP developments. Andrew moss SRS and ERLP developments Andrew moss Contents SRS Status Latest news Major faults Status Energy Recovery Linac Prototype Latest news Status of the RF system Status of the cryogenic system SRS Status Machine

More information

A Cathode Development Cornell Cultera This scope includes all labor and purchases required produce photocathodes required by CBETA.

A Cathode Development Cornell Cultera This scope includes all labor and purchases required produce photocathodes required by CBETA. A1.01 PROJECT MANAGEMENT BNL/Cornell Michnoff A1.01.01 Milestones BNL/Cornell Michnoff This scope is a placeholder for all project high level milestones for NYSERDA. There is no cost or labor related to

More information

Suggested ILC Beam Parameter Range Rev. 2/28/05 Tor Raubenheimer

Suggested ILC Beam Parameter Range Rev. 2/28/05 Tor Raubenheimer The machine parameters and the luminosity goals of the ILC were discussed at the 1 st ILC Workshop. In particular, Nick Walker noted that the TESLA machine parameters had been chosen to achieve a high

More information

TESLA FEL-Report

TESLA FEL-Report Determination of the Longitudinal Phase Space Distribution produced with the TTF Photo Injector M. Geitz a,s.schreiber a,g.von Walter b, D. Sertore a;1, M. Bernard c, B. Leblond c a Deutsches Elektronen-Synchrotron,

More information

SABER A Facility for Accelerator Physics and Test Beam Experiments Roger Erickson SABER Workshop March 15, 2006

SABER A Facility for Accelerator Physics and Test Beam Experiments Roger Erickson SABER Workshop March 15, 2006 SABER A Facility for Accelerator Physics and Test Beam Experiments Roger Erickson SABER Workshop March 15, 2006 FFTB will soon be gone! The Problem: On April 10, 2006, the Final Focus Test Beam (FFTB)

More information

Accelerator Instrumentation RD. Monday, July 14, 2003 Marc Ross

Accelerator Instrumentation RD. Monday, July 14, 2003 Marc Ross Monday, Marc Ross Linear Collider RD Most RD funds address the most serious cost driver energy The most serious impact of the late technology choice is the failure to adequately address luminosity RD issues

More information

ANKA RF System - Upgrade Strategies

ANKA RF System - Upgrade Strategies ANKA RF System - Upgrade Strategies Vitali Judin ANKA Synchrotron Radiation Facility 2014-09 - 17 KIT University of the State Baden-Wuerttemberg and National Laboratory of the Helmholtz Association www.kit.edu

More information

Energy Upgrade Options for the LCLS-I Linac

Energy Upgrade Options for the LCLS-I Linac Energy Upgrade Options for the LCLS-I Linac LCLS-II TN-14-10 11/12/2014 John Sheppard, F.J. Decker, R. Iverson, H.D. Nuhn, M. Sullivan, J. Turner November 18, 2014 LCLSII-TN-14-07 LCLS 1 Linac Energy Increase

More information

30 GHz Power Production / Beam Line

30 GHz Power Production / Beam Line 30 GHz Power Production / Beam Line Motivation & Requirements Layout Power mode operation vs. nominal parameters Beam optics Achieved performance Problems Beam phase switch for 30 GHz pulse compression

More information

RUNNING EXPERIENCE OF FZD SRF PHOTOINJECTOR

RUNNING EXPERIENCE OF FZD SRF PHOTOINJECTOR RUNNING EXPERIENCE OF FZD SRF PHOTOINJECTOR Rong Xiang On behalf of the BESSY-DESY-FZD-MBI collaboration and the ELBE team FEL 2009, Liverpool, United Kingdom, August 23 ~ 28, 2009 Outline Introduction

More information

CLIC Feasibility Demonstration at CTF3

CLIC Feasibility Demonstration at CTF3 CLIC Feasibility Demonstration at CTF3 Roger Ruber Uppsala University, Sweden, for the CLIC/CTF3 Collaboration http://cern.ch/clic-study LINAC 10 MO303 13 Sep 2010 The Key to CLIC Efficiency NC Linac for

More information

A HIGH POWER LONG PULSE HIGH EFFICIENCY MULTI BEAM KLYSTRON

A HIGH POWER LONG PULSE HIGH EFFICIENCY MULTI BEAM KLYSTRON A HIGH POWER LONG PULSE HIGH EFFICIENCY MULTI BEAM KLYSTRON A.Beunas and G. Faillon Thales Electron Devices, Vélizy, France S. Choroba DESY, Hamburg, Germany Abstract THALES ELECTRON DEVICES has developed

More information

Interim Report of the Scientific and Technical Issues (XFEL-STI) Working Group on a European XFEL Facility in Hamburg

Interim Report of the Scientific and Technical Issues (XFEL-STI) Working Group on a European XFEL Facility in Hamburg 1 XFEL The European X-Ray Laser Project XFEL X-Ray Free Electron Laser Interim Report of the Scientific and Technical Issues (XFEL-STI) Working Group on a European XFEL Facility in Hamburg January 11,

More information

The FLASH objective: SASE between 60 and 13 nm

The FLASH objective: SASE between 60 and 13 nm Injector beam control studies winter 2006/07 talk from E. Vogel on work performed by W. Cichalewski, C. Gerth, W. Jalmuzna,W. Koprek, F. Löhl, D. Noelle, P. Pucyk, H. Schlarb, T. Traber, E. Vogel, FLASH

More information

High Brightness Injector Development and ERL Planning at Cornell. Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics

High Brightness Injector Development and ERL Planning at Cornell. Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics High Brightness Injector Development and ERL Planning at Cornell Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics June 22, 2006 JLab CASA Seminar 2 Background During 2000-2001,

More information

DESIGN OF 1.2-GEV SCL AS NEW INJECTOR FOR THE BNL AGS*

DESIGN OF 1.2-GEV SCL AS NEW INJECTOR FOR THE BNL AGS* DESIGN OF 1.2-GEV SCL AS NEW INJECTOR FOR THE BNL AGS* A. G. Ruggiero, J. Alessi, M. Harrison, M. Iarocci, T. Nehring, D. Raparia, T. Roser, J. Tuozzolo, W. Weng. Brookhaven National Laboratory, PO Box

More information

Assembly of the HIE-ISOLDE accelerator cavities in a clean room.

Assembly of the HIE-ISOLDE accelerator cavities in a clean room. Final adjustments being made in the LHC tunnel before the return of beams. On 5 April, particles began circulating in the accelerator for the first time following the Long Shutdown. (CERN-PHOTO-201503-058-1)

More information

Full IEFC workshop Feb.

Full IEFC workshop Feb. How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix How does one keep a 50 51 year old running for another 25 years? accelerator How

More information

Welcome and FRIB Project Status. FRIB Highlights and Plan Ahead

Welcome and FRIB Project Status. FRIB Highlights and Plan Ahead Welcome and FRIB Project Status Thomas Glasmacher Project Manager This material is based upon work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC0000661.

More information

ESS Linac WP8 Radio Frequency Systems and Test Facilities

ESS Linac WP8 Radio Frequency Systems and Test Facilities ESS Linac WP8 Radio Frequency Systems and Test Facilities ESS TAC Lund, 8 July 2010 Roger Ruber (Uppsala University) for the ESS Linac RF Team Outline Work Package description Objectives Organization Technical

More information

RF Upgrades & Experience At JLab. Rick Nelson

RF Upgrades & Experience At JLab. Rick Nelson RF Upgrades & Experience At JLab Rick Nelson Outline Background: CEBAF / Jefferson Lab History, upgrade requirements & decisions Progress & problems along the way Present status Future directions & concerns

More information

!"!3

!!3 Abstract A single-mode 500 MHz superconducting cavity cryomodule has been developed at Cornell for the electronpositron collider/synchrotron light source CESR. The Cornell B-cell cavity belongs to the

More information

Report on the LCLS Injector Technical Review

Report on the LCLS Injector Technical Review Report on the LCLS Injector Technical Review Stanford Linear Accelerator Center November 3&4, 2003 Committee Members Prof. Patrick G. O Shea, Chair, University of Maryland Dr. Eric Colby, Stanford Linear

More information

Modulator Overview System Design vs. Tunnel Topologies. Snowmass Workshop August 16, 2005 Ray Larsen for the SLAC ILC Group

Modulator Overview System Design vs. Tunnel Topologies. Snowmass Workshop August 16, 2005 Ray Larsen for the SLAC ILC Group Modulator Overview System Design vs. Tunnel Topologies Snowmass Workshop August 16, 2005 Ray Larsen for the SLAC ILC Group Outline! I. Modulator Options vs. Topologies! II. Preliminary Cost Estimates!

More information

SPEAR 3: Operations Update and Impact of Top-Off Injection

SPEAR 3: Operations Update and Impact of Top-Off Injection SPEAR 3: Operations Update and Impact of Top-Off Injection R. Hettel for the SSRL ASD 2005 SSRL Users Meeting October 18, 2005 SPEAR 3 Operations Update and Development Plans Highlights of 2005 SPEAR 3

More information

Operating Experience and Reliability Improvements on the 5 kw CW Klystron at Jefferson Lab

Operating Experience and Reliability Improvements on the 5 kw CW Klystron at Jefferson Lab Operating Experience and Reliability Improvements on the 5 kw CW Klystron at Jefferson Lab Richard Walker & Richard Nelson Jefferson Lab, Newport News VA Jefferson Lab is a $600M Department of Energy facility

More information

News from HZB / BESSY Wolfgang Anders at ESLS-RF Meeting September 2010 Trieste

News from HZB / BESSY Wolfgang Anders at ESLS-RF Meeting September 2010 Trieste News from HZB / BESSY Wolfgang Anders at ESLS-RF Meeting September 2010 Trieste Outline Status Klystrons / IOT Modifications of transmitters New LINAC for BESSY II Status BERLinPro HoBiCaT Extension --

More information

III. Proton-therapytherapy. Rome SB - 3/5 1

III. Proton-therapytherapy. Rome SB - 3/5 1 Outline Introduction: an historical review I Applications in medical diagnostics Particle accelerators for medicine Applications in conventional radiation therapy II III IV Hadrontherapy, the frontier

More information

High Rep Rate Guns: FZD Superconducting RF Photogun

High Rep Rate Guns: FZD Superconducting RF Photogun High Rep Rate Guns: FZD Superconducting RF Photogun J. Teichert, A. Arnold, H. Büttig, D. Janssen, M. Justus, U. Lehnert, P. Michel, K. Moeller, P. Murcek, Ch. Schneider, R. Schurig, G. Staats, F. Staufenbiel,

More information

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems LCLS RF Reference and Control R. Akre Last Update 5-19-04 Sector 0 RF and Timing Systems The reference system for the RF and timing starts at the 476MHz Master Oscillator, figure 1. Figure 1. Front end

More information

BBU threshold current study for 6 GeV beam in 12 GeV beamline setup

BBU threshold current study for 6 GeV beam in 12 GeV beamline setup BBU threshold current study for 6 GeV beam in 12 GeV beamline setup Ilkyoung Shin and Byung C. Yunn JLAB-TN-09-004 January 12, 2009 1. Introduction The study of BBU threshold current is done for a 6 GeV

More information

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY A. Wheelhouse ASTeC, STFC Daresbury Laboratory ESLS XVIII Workshop, ELLETRA 25 th 26 th November 2010 Contents Brief Description ALICE

More information

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

Diamond RF Status (RF Activities at Daresbury) Mike Dykes Diamond RF Status (RF Activities at Daresbury) Mike Dykes ASTeC What is it? What does it do? Diamond Status Linac Booster RF Storage Ring RF Summary Content ASTeC ASTeC was formed in 2001 as a centre of

More information

PRESENT STATUS OF J-PARC

PRESENT STATUS OF J-PARC PRESENT STATUS OF J-PARC # F. Naito, KEK, Tsukuba, Japan Abstract Japan Proton Accelerator Research Complex (J-PARC) is the scientific facility with the high-intensity proton accelerator aiming to realize

More information

Next Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack

Next Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack The Four 50 MW XL4 X-band klystrons installed on the 8-Pack The Demonstrate an NLC power source Two Phases: 8-Pack Phase-1 (current): Multi-moded SLED II power compression Produce NLC baseline power: 475

More information

Program Risks Risk Analysis Fallback Plans for the. John T. Seeman DOE PEP-II Operations Review April 26, 2006

Program Risks Risk Analysis Fallback Plans for the. John T. Seeman DOE PEP-II Operations Review April 26, 2006 Program Risks Risk Analysis Fallback Plans for the PEP-II B-FactoryB John T. Seeman DOE PEP-II Operations Review April 26, 2006 OPS Review Topics Are there any PEP-II program risks? Has the laboratory

More information

Beam Loss Detection for MPS at FRIB

Beam Loss Detection for MPS at FRIB Beam Loss Detection for MPS at FRIB Zhengzheng Liu Beam Diagnostics Physicist This material is based upon work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC0000661.

More information

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team Status of SOLARIS Paweł Borowiec On behalf of Solaris Team e-mail: pawel.borowiec@uj.edu.pl XX ESLS-RF Meeting, Villingen 16-17.11.2016 Outline 1. Timeline 2. Injector 3. Storage ring 16-17.11.2016 XX

More information

HIGH-INTENSITY PROTON BEAMS AT CERN AND THE SPL STUDY

HIGH-INTENSITY PROTON BEAMS AT CERN AND THE SPL STUDY HIGH-INTENSITY PROTON BEAMS AT CERN AND THE STUDY E. Métral, M. Benedikt, K. Cornelis, R. Garoby, K. Hanke, A. Lombardi, C. Rossi, F. Ruggiero, M. Vretenar, CERN, Geneva, Switzerland Abstract The construction

More information

The PEFP 20-MeV Proton Linear Accelerator

The PEFP 20-MeV Proton Linear Accelerator Journal of the Korean Physical Society, Vol. 52, No. 3, March 2008, pp. 721726 Review Articles The PEFP 20-MeV Proton Linear Accelerator Y. S. Cho, H. J. Kwon, J. H. Jang, H. S. Kim, K. T. Seol, D. I.

More information

Status of SOLARIS Arkadiusz Kisiel

Status of SOLARIS Arkadiusz Kisiel Status of SOLARIS Arkadiusz Kisiel Solaris National Synchrotron Light Source Jagiellonian University Czerwone Maki 98 30-392 Kraków www.synchrotron.uj.edu.pl Arkadiusz.Kisiel@uj.edu.pl On behalf of SOLARIS

More information

Status of RF Power and Acceleration of the MAX IV - LINAC

Status of RF Power and Acceleration of the MAX IV - LINAC Status of RF Power and Acceleration of the MAX IV - LINAC Dionis Kumbaro ESLS RF Workshop 2015 MAX IV Laboratory A National Laboratory for synchrotron radiation at Lunds University 1981 MAX-lab is formed

More information

THE JLAB 12 GEV ENERGY UPGRADE OF CEBAF *

THE JLAB 12 GEV ENERGY UPGRADE OF CEBAF * THE JLAB 12 GEV ENERGY UPGRADE OF CEBAF * Leigh Harwood (for the JLab 12 GeV project team) Thomas Jefferson National Accelerator Facility, Newport News, VA 23606 USA Abstract CEBAF at Jefferson Lab was

More information

PEP II Design Outline

PEP II Design Outline PEP II Design Outline Balša Terzić Jefferson Lab Collider Review Retreat, February 24, 2010 Outline General Information Parameter list (and evolution), initial design, upgrades Collider Ring Layout, insertions,

More information

LCLS Injector Technical Review

LCLS Injector Technical Review LCLS Injector Technical Review Stanford Linear Accelerator Center November 3&4 2003 Review Committee Members: Prof. Patrick O Shea Chair University of Maryland Dr. E. Colby Stanford Linear Accelerator

More information

Summary of the 1 st Beam Line Review Meeting Injector ( )

Summary of the 1 st Beam Line Review Meeting Injector ( ) Summary of the 1 st Beam Line Review Meeting Injector (23.10.2006) 15.11.2006 Review the status of: beam dynamics understanding and simulations completeness of beam line description conceptual design of

More information

CLEX (CLIC Experimental Area)

CLEX (CLIC Experimental Area) CLEX (CLIC Experimental Area) Status and plans G.Geschonke for Hans Braun CERN CT3 coll meetg 2005 CLEX 1 CT3 objectives R1.1 CLIC accelerating structure, R1.2 rive beam scheme with a fully loaded linac

More information

P. Emma, et al. LCLS Operations Lectures

P. Emma, et al. LCLS Operations Lectures P. Emma, et al. LCLS Operations Lectures LCLS 1 LCLS Accelerator Schematic 6 MeV 135 MeV 250 MeV σ z 0.83 mm σ z 0.83 mm σ z 0.19 mm σ δ 0.05 % σ δ 0.10 % σ δ 1.6 % Linac-0 L =6 m rf gun L0-a,b Linac-1

More information

Evaluation of Performance, Reliability, and Risk for High Peak Power RF Sources from S-band through X-band for Advanced Accelerator Applications

Evaluation of Performance, Reliability, and Risk for High Peak Power RF Sources from S-band through X-band for Advanced Accelerator Applications Evaluation of Performance, Reliability, and Risk for High Peak Power RF Sources from S-band through X-band for Advanced Accelerator Applications Michael V. Fazio C. Adolphsen, A. Jensen, C. Pearson, D.

More information

Proceedings of the 1997 Workshop on RF Superconductivity, Abano Terme (Padova), Italy

Proceedings of the 1997 Workshop on RF Superconductivity, Abano Terme (Padova), Italy BEAM RELATED THERMAL LOSSES ON THE CRYOGENIC AND VACUUM SYSTEMS OF LEP G. Cavallari, Ph. Gayet, G. Geschonke, D. Kaiser, J.M. Jimenez CERN, 111 GENEVA 3 (Switzerland) Abstract The LEP Collider was operated

More information

PoS(EPS-HEP2015)525. The RF system for FCC-ee. A. Butterworth CERN 1211 Geneva 23, Switzerland

PoS(EPS-HEP2015)525. The RF system for FCC-ee. A. Butterworth CERN 1211 Geneva 23, Switzerland CERN 1211 Geneva 23, Switzerland E-mail: andrew.butterworth@cern.ch O. Brunner CERN 1211 Geneva 23, Switzerland E-mail: olivier.brunner@cern.ch R. Calaga CERN 1211 Geneva 23, Switzerland E-mail: rama.calaga@cern.ch

More information

Future Performance of the LCLS

Future Performance of the LCLS Future Performance of the LCLS J. Welch for many* SLAC National Accelerator Laboratory FLS 2010, ICFA Beam Dynamics Workshop on Future Light Sources, March 1-5, 2010. SLAC National Accelerator Laboratory,

More information

The SPL at CERN. slhc. 1. Introduction 2. Description. 3. Status of the SPL study. - Stage 1: Linac4 - Stage 2: LP-SPL - Potential further stages

The SPL at CERN. slhc. 1. Introduction 2. Description. 3. Status of the SPL study. - Stage 1: Linac4 - Stage 2: LP-SPL - Potential further stages The SPL at CERN 1. Introduction 2. Description - Stage 1: Linac4 - Stage 2: LP-SPL - Potential further stages 3. Status of the SPL study slhc Roa Garoby for the SPL team 1. Introduction Motivation for

More information

The Elettra Storage Ring and Top-Up Operation

The Elettra Storage Ring and Top-Up Operation The Elettra Storage Ring and Top-Up Operation Emanuel Karantzoulis Past and Present Configurations 1994-2007 From 2008 5000 hours /year to the users 2010: Operations transition year Decay mode, 2 GeV (340mA)

More information

Pulsed Klystrons for Next Generation Neutron Sources Edward L. Eisen - CPI, Inc. Palo Alto, CA, USA

Pulsed Klystrons for Next Generation Neutron Sources Edward L. Eisen - CPI, Inc. Palo Alto, CA, USA Pulsed Klystrons for Next Generation Neutron Sources Edward L. Eisen - CPI, Inc. Palo Alto, CA, USA Abstract The U.S. Department of Energy (DOE) Office of Science has funded the construction of a new accelerator-based

More information