P. Emma, et al. LCLS Operations Lectures
|
|
- Preston Glenn
- 5 years ago
- Views:
Transcription
1 P. Emma, et al. LCLS Operations Lectures LCLS 1
2 LCLS Accelerator Schematic 6 MeV 135 MeV 250 MeV σ z 0.83 mm σ z 0.83 mm σ z 0.19 mm σ δ 0.05 % σ δ 0.10 % σ δ 1.6 % Linac-0 L =6 m rf gun L0-a,b Linac-1 L 9 9 m rf 25 ϕ rf Linac-X L =0.6 m rf = 160 ϕ rf Linac-2 L 330 m rf 41 ϕ rf 4.30 GeV σ z mm σ δ 0.71 % Linac-3 L 550 m rf 0 ϕ rf 13.6 GeV σ z mm σ δ 0.01 %...existing linac DL1 L 12 m R b,c,d X BC1 L 6 6 m mm R b 24-6d SLAC linac tunnel BC2 L 22 m mm R a 30-8c Commission in Jan Commission in Jan DL2 L =275 m 56 0 R 56 undulator L =130 m research yard 2
3 Complete & Detailed Optics (cathode to dump) dump cathode L2 BC2 L3 sec-21 sec-30 LTU undulator muon plug wall Full MAD files at: ssrl.slac.stanford.edu/lcls/linac/optics/ 3
4 LCLS Installation and Commissioning Time-Line Drive-Laser Commissioning Drive-Laser Install undulator LTU/und. First FEL hall ready Install Light linac/bc2 Install First Spont. Light MM J J A S O N D J F M A M J J A S O N D J F M A M J J June 2006 Gun/Inj./BC1 Install (8/21 1/5) Gun/Inj./BC1 Commissioning linac/bc2 Commissioning FEL Comm. LTU/undulator Commissioning 4
5 LONG BELLOWS ASSEMBLY SPOOLS FROMVALVE SEAL UHV ALL METAL GATE VALVES RF Gun TREATMENT CHAMBER PORCUPINE CATHODE HOLDER VACUUM PUMPS 6 MeV L0a RF section Injector Layout 62 MeV L0b RF section gun spectrometer 135 MeV Transverse RF deflector L1 RF section (21-1b) 1b) main SLAC Linac injector spectrometer sector 20 sector 21 5
6 LCLS Injector Commissioning Dates ( 06( - 07) July 24: Aug. 29: Dec. 18: Dec. 19: Dec. 20-Jan. 1: Jan. 2: Jan. 12: Jan. 12-Feb. 4: Sector-20 ready for laser installation Laser installation complete Virtual cathode fully characterized (ready to install gun) RF gun installation starts (10 days) + pre-beam checkout Holidays VVS s switched on (RF power available) First laser UV-light on cathode! Electrons in GTL and gun-spect spect.. (RF processing L0a,b, L1, LX) Feb. 5: Beam into L0a, L0b and down to 135-MeV spect. Feb. 20: ~June: Beam into main linac (to TD11 dump) Take beam down full linac (to BSY SL2 stopper) 6
7 OUT OF DATE Microsoft Project Commissioning Schedule DOWN 2007 DOWN
8 pass-1 OUT OF DATE pass-2 pass DOWN pass-1 pass DOWN 8
9 pass-1 pass DOWN OUT OF DATE pass DOWN 9
10 Commissioning Definition and Strategy All components have been installed, aligned, connected, and initially verified by the system engineer, then commissioning starts. Commissioning Sequence (1-4)( 1. Pre-Beam Checkout (tunnel and MCC) Controls/software testing, check cameras, snail hunt, etc Magnet polarities, cable connections, verify motion-control, etc 2. Beam-based Hardware and Software Checkout Establish beam transport, RF setup, MPS/BCS tests, etc Checkout of all wires, screens, BPMs, toroids, magnets, etc 3. First-Order Optics: Measurement and Correction Steering, transmission, oscillation data, feedback setup, etc Beta and dispersion matching, beam-base base align key quads, etc 4. Full Beam Characterization: Measurement and Correction Measure emittance, energy spread, distributions - correct Measure beam sensitivities, optimize tuning, beam experiments No (serious) emittance measurements until all hardware/software checked out! 10
11 Electron Commissioning Organization Project Director J. Galayda Commissioning Don P. Emma Alternating Weekly Run Coordinator One Lead Physicist per shift Shift Physicists Controls & System Engineers MCC & Laser Operators 11
12 LCLS Injector Commissioning Day 24-Hour Cycle (7 days/week, 1/2/07 to 9/1/07,, 32 total weeks) DAY DAY SHIFT SHIFT (8:00-16:00) 1 lead lead physicist, 1 physicist, 1 controls eng., eng., 1 sys. sys. engineer, 1 LCLS LCLS operator, 1 laser laser operator SWING SHIFT SHIFT (16:00-24:00) 1 lead lead physicist, 1 physicist, 1 LCLS LCLS operator, 1 laser laser operator OWL OWL SHIFT SHIFT (0:00-8:00) 1 LCLS LCLS operator, 1 laser laser operator? 12
13 Parameters Parameter RF rate Beam rate Drive-laser rate Bunch charge Drive-laser pulse length Gun gradient Value 30 Hz 30 Hz 120 Hz pc 10 ps fwhm 120 MV/m Comments 30 Hz in linac (possible short-term term 120-Hz rate in L0- BC1 for feedback tests, etc) Hz in gun for short time to verify full rate 30 Hz e beam as baseline possible short term 120- Hz tests in L0-BC1 for feedback tests, etc 120-Hz at all times shutters provide e rate as required above depends on QE and diagnostics some short spans at 10 pc later in 07 we explore 1-nC1 10-ps fwhm startup with possibility of 6-ps 6 at 0.2 nc later early laser tests may provide path to more convenient pulse-length length changes Set as goal, although 110 MV/m is adequate in 07 13
14 Issues Controls will be mixed (SLC & epics) and capabilities may be limited initially Most High-Level Applications (emittance, bunch length, feedback) must done through MATLAB as a temporary solution Most LCLS physicists not yet experienced in SLAC control room with SLC controls Help from operations group will be needed LCLS Lecture Series + Workshop in Oct.? 14
15 Q = 1 nc f = 120 Hz G = 120 MV/m γε x,y = 1 µm τ = 10 ps I = 100 A E = 6 MeV solenoid RF gun cathode RF Photo-Cathode Gun spec. dipole UV laser YAG screens e e 15
16 LONG BELLOWS ASSEMBLY SPOOLS FROMVALVE SEAL UHV ALL METAL GATE VALVES RF Gun YAG screen TREATMENT CHAMBER PORCUPINE CATHODE HOLDER VACUUM PUMPS YAG screen YAG screen YAG screen trajectory (BPMs) emittance (+ (+ slice) energy spread (+ (+ slice) bunch length (+ (+ dist.) charge (+ (+ dark dark current) gun spectrometer Injector Diagnostics YAG screen Transverse RF deflector OTR & wire OTR & wire OTR & wire main SLAC Linac injector spectrometer 16 YAG OTR & wire YAG & OTR
17 Injector Through BC1 Commissioning no laser-heater until 08 RF deflector γε x,y γε and slice σ E E 17
18 Injector Through BC1 Commissioning (2) BC1 relative bunch length monitors X-band RF σ E E slice γε y γε x,y stopper 18
19 Setup of Linac-1, X-band X RF Phases 20-µm m res. BC1 BPM 20-µm m res. BC1 BPM LX RF phase L1 RF phase Linac-1 1 RF phase scan (X-band off, BC1 bends at 295 MeV) Linac-X X RF phase scan (BC1 bends at 250 MeV) rf gun new new set phase to 25 ±0.5 set phase to 160 ±0.5 Linac b 1b 21-1d 1d X Turn on BC1 energy feedback Switch off BC2 chicane Use sec-25 RF-deflector to meas. bunch length ( (σ z1 ) Adjust S-band S RF phase (±0.5( 0.5 ) ) to set σ z1 195 ±10 µm 19
20 40-µm m res. BC2 BPM Setup of Linac-2 2 RF 5-µm m res. LTU BPM wake-loss scan L2 RF phase Linac-2 2 RF phase scan (BC2 bends at 5.9 GeV, or ) L2 phase Scan Linac-2 2 phase & use LTU BPM to find max. wake-induced energy loss across Linac-3 set phase to 41 ±0.5 L2 L3 Turn on BC2 energy feedback Use sec-25 RF-deflector to measure length ( (σ z2 ) Adjust L2 RF phase (±0.5( 0.5 ) ) to set σ z2 20 ± 2 µm Linac-3 3 phasing is trivial (±5 )( 20
21 Longitudinal Beam-Based Based Feedback gun V 0 δ 0 σ z1 σ z2 L0 L0 δ 1 δ 2 δ 3 ϕ 1 V 1 ϕ 2 V 2 V 3 L1 X L2 L3 DL1 BC1 BC2 DL2 21
22 Location of Main Linac Diagnostics 5+ energy spread meas. stations (optimized with small β) 5+ emittance meas. stations designed into optics ( ( ψ x,y ) BPMs at or near most quadrupoles and in each bend syst. RF deflectors for slice ε and σ E measurements (L0 & L3) rf gun L0 L0 T-cav. γε x,y γε x,y γε x,y T-cav. γε x,y...existing linac L1 X L2 L3 γε x,y σ E σ E σ E E E E σ E E σ E E 22
23 Slice-Emittance Measurement Simulation slice OTR 10 times RF-deflector at 1 MV σ y bunch length 135 MeV quad scanned 23
24 Slice-Emittance Measurement Simulation Injector (135 MeV) with S-band RF-deflector at 1 MV (same SLAC slice-ε code used at BNL/SDL) (slice-y-emittance emittance also simulated in BC1-center) = meas. sim. = calc. = y distribution = actual DL1 slice-emit emit on WS02 slice-5 24
25 y-slice-emittance Measurement in BC1 Q21201 scanned ±20% 3.9 mm 0.1 mm 25
26 weak quad setting Slice ε y Measurements at BNL undulators linac (off) linac dump dump 75 MeV 75 MeV 5 MeV medium quad setting strong quad setting 200 pc, 100 A, 75 MeV Data from DUVFEL at BNL: : W. Graves, et al. 26
27 vertical bends Linac-To To-Undulator (LTU) energy centroid & spread meas. (OTR) ( & 10 4 ) + collimation 4 ε-wires, wires, 6 collimators, 1 OTR vertical vertical bends bends horiz. horiz.. jog jog m energy energy diagnostics diagnostics emit. emit. diagnostics diagnostics collimators collimators branch branch points points for for future future undulators undulators 27
28 Slice Energy Spread Measurements in LTU σ E /E 10 4 LTU at 14 GeV with S-band S RF-deflector at 24 MV σ x 12 µm FEL goal 28
29 Summary Injector commissioning starts very soon (Laser:: Aug. 06, Electrons: : Jan. 07) Phase-II of commissioning comes in Jan. 08 LCLS group will need continual help from operations group LCLS is a 30-year machine this is just the start 29
Beam Losses During LCLS Injector Phase-1 1 Operation
Beam Losses During LCLS Injector Phase-1 1 Operation & Paul Emma September 28, 2006 Radiation Safety Committee Review Scope of Phase 1 Operation Request for Three Operating Modes Operating Plan for Phase
More informationLCLS Injector Technical Review
LCLS Injector Technical Review Stanford Linear Accelerator Center November 3&4 2003 Review Committee Members: Prof. Patrick O Shea Chair University of Maryland Dr. E. Colby Stanford Linear Accelerator
More informationRequirements for the Beam Abort Magnet and Dump
Requirements for the Beam Abort Magnet and Dump A beam abort kicker (pulsed dipole magnet) and dump are required upbeam of the LCLS undulator in order to protect the undulator from mis-steered and poor
More informationLCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems
LCLS RF Reference and Control R. Akre Last Update 5-19-04 Sector 0 RF and Timing Systems The reference system for the RF and timing starts at the 476MHz Master Oscillator, figure 1. Figure 1. Front end
More informationWeek 0: PPS Certification and Processing. Mon Feb 11 Tue Feb 12 Wed Feb 13 Thu Feb 14 Fri Feb 15 Sat Feb 16 Sun Feb 17
Week 0: PPS Certification and Processing Mon Feb 11 Tue Feb 12 Wed Feb 13 Thu Feb 14 Fri Feb 15 Sat Feb 16 Sun Feb 17 Work in tunnel Work in tunnel PPS Certification PPS Certification PPS Certification
More informationA Facility for Accelerator Physics and Test Beam Experiments
A Facility for Accelerator Physics and Test Beam Experiments U.S. Department of Energy Review Roger Erickson for the FACET Design Team February 20, 2008 SLAC Overview with FACET FACET consists of four
More informationTWO BUNCHES WITH NS-SEPARATION WITH LCLS*
TWO BUNCHES WITH NS-SEPARATION WITH LCLS* F.-J. Decker, S. Gilevich, Z. Huang, H. Loos, A. Marinelli, C.A. Stan, J.L. Turner, Z. van Hoover, S. Vetter, SLAC, Menlo Park, CA 94025, USA Abstract The Linac
More informationSummary of the 1 st Beam Line Review Meeting Injector ( )
Summary of the 1 st Beam Line Review Meeting Injector (23.10.2006) 15.11.2006 Review the status of: beam dynamics understanding and simulations completeness of beam line description conceptual design of
More informationBeam Instrumentation for X-ray FELs
Beam Instrumentation for X-ray FELs 05/16/2011 1 1 Outline X-ray FEL overview Diagnostics requirements for X-ray FELs Transverse Diagnostics Longitudinal Diagnostics Summary 2 2 X-ray FEL Overview 100
More informationDigital BPMs and Orbit Feedback Systems
Digital BPMs and Orbit Feedback Systems, M. Böge, M. Dehler, B. Keil, P. Pollet, V. Schlott Outline stability requirements at SLS storage ring digital beam position monitors (DBPM) SLS global fast orbit
More informationSPEAR 3: Operations Update and Impact of Top-Off Injection
SPEAR 3: Operations Update and Impact of Top-Off Injection R. Hettel for the SSRL ASD 2005 SSRL Users Meeting October 18, 2005 SPEAR 3 Operations Update and Development Plans Highlights of 2005 SPEAR 3
More informationAn Overview of Beam Diagnostic and Control Systems for AREAL Linac
An Overview of Beam Diagnostic and Control Systems for AREAL Linac Presenter G. Amatuni Ultrafast Beams and Applications 04-07 July 2017, CANDLE, Armenia Contents: 1. Current status of existing diagnostic
More informationFuture Performance of the LCLS
Future Performance of the LCLS J. Welch for many* SLAC National Accelerator Laboratory FLS 2010, ICFA Beam Dynamics Workshop on Future Light Sources, March 1-5, 2010. SLAC National Accelerator Laboratory,
More informationHall-B Beamline Commissioning Plan for CLAS12
Hall-B Beamline Commissioning Plan for CLAS12 Version 1.5 S. Stepanyan December 19, 2017 1 Introduction The beamline for CLAS12 utilizes the existing Hall-B beamline setup with a few modifications and
More informationRF considerations for SwissFEL
RF considerations for H. Fitze in behalf of the PSI RF group Workshop on Compact X-Ray Free Electron Lasers 19.-21. July 2010, Shanghai Agenda Introduction RF-Gun Development C-band development Summary
More informationLinac-Beam Characterizations at 600 MeV Using Optical Transition Radiation Diagnostics *
Linac-Beam Characterizations at 6 MeV Using Optical Transition Radiation Diagnostics * A. H. Lumpkin, W. J. Berg, B. X. Yang, and M. White Advanced Photon Source, Argonne National Laboratory 97 South Cass
More informationPhotoinjector Laser Operation and Cathode Performance
Photoinjector Laser Operation and Cathode Performance Daniele Sertore, INFN Milano LASA Siegfried Schreiber, DESY Laser operational experience Laser beam properties Cathode performances Outlook TTF and
More information30 GHz Power Production / Beam Line
30 GHz Power Production / Beam Line Motivation & Requirements Layout Power mode operation vs. nominal parameters Beam optics Achieved performance Problems Beam phase switch for 30 GHz pulse compression
More informationStatus of CTF3. G.Geschonke CERN, AB
Status of CTF3 G.Geschonke CERN, AB CTF3 layout CTF3 - Test of Drive Beam Generation, Acceleration & RF Multiplication by a factor 10 Drive Beam Injector ~ 50 m 3.5 A - 2100 b of 2.33 nc 150 MeV - 1.4
More informationDesign Studies For The LCLS 120 Hz RF Gun Injector
BNL-67922 Informal Report LCLS-TN-01-3 Design Studies For The LCLS 120 Hz RF Gun Injector X.J. Wang, M. Babzien, I. Ben-Zvi, X.Y. Chang, S. Pjerov, and M. Woodle National Synchrotron Light Source Brookhaven
More information4.4 Injector Linear Accelerator
4.4 Injector Linear Accelerator 100 MeV S-band linear accelerator based on the components already built for the S-Band Linear Collider Test Facility at DESY [1, 2] will be used as an injector for the CANDLE
More informationPEP II Design Outline
PEP II Design Outline Balša Terzić Jefferson Lab Collider Review Retreat, February 24, 2010 Outline General Information Parameter list (and evolution), initial design, upgrades Collider Ring Layout, insertions,
More informationLinac 4 Instrumentation K.Hanke CERN
Linac 4 Instrumentation K.Hanke CERN CERN Linac 4 PS2 (2016?) SPL (2015?) Linac4 (2012) Linac4 will first inject into the PSB and then can be the first element of a new LHC injector chain. It will increase
More informationExperience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation
Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation Matthias Liepe Assistant Professor of Physics Cornell University Experience with the Cornell ERL Injector SRF
More informationSABER A Facility for Accelerator Physics and Test Beam Experiments Roger Erickson SABER Workshop March 15, 2006
SABER A Facility for Accelerator Physics and Test Beam Experiments Roger Erickson SABER Workshop March 15, 2006 FFTB will soon be gone! The Problem: On April 10, 2006, the Final Focus Test Beam (FFTB)
More informationTESLA FEL-Report
Determination of the Longitudinal Phase Space Distribution produced with the TTF Photo Injector M. Geitz a,s.schreiber a,g.von Walter b, D. Sertore a;1, M. Bernard c, B. Leblond c a Deutsches Elektronen-Synchrotron,
More informationTTF / VUV-FEL. Schedule 2005 and Project Management Issues. Schedule 2005 Project Organisation Budget & Controlling
TTF / VUV-FEL Schedule 200 and Project Management Issues Schedule 200 Project Organisation Budget & Controlling Hans Weise / DESY DESY MAC Meeting November 9th, 2004 TTF Linac Start-up After Final Installation
More informationCurrent status of XFEL/SPring-8 project and SCSS test accelerator
Current status of XFEL/SPring-8 project and SCSS test accelerator Takahiro Inagaki for XFEL project in SPring-8 inagaki@spring8.or.jp Outline (1) Introduction (2) Key technology for compactness (3) Key
More informationPhoto cathode RF gun -
Photo cathode RF gun - *),,, ( 05 Nov. 2004 Spring8 UTNL Linac & Mg Photocathode RF Gun Mg photocathode NERL, 18 MeV Linac and the RF gun Electron Beam Mg photocathode Mg photocathode RF gun of SPring8
More informationPresent Status and Future Upgrade of KEKB Injector Linac
Present Status and Future Upgrade of KEKB Injector Linac Kazuro Furukawa, for e /e + Linac Group Present Status Upgrade in the Near Future R&D towards SuperKEKB 1 Machine Features Present Status and Future
More informationSimulations on Beam Monitor Systems for Longitudinal Feedback Schemes at FLASH.
Simulations on Beam Monitor Systems for Longitudinal Feedback Schemes at FLASH. Christopher Behrens for the FLASH team Deutsches Elektronen-Synchrotron (DESY) FLS-2010 Workshop at SLAC, 4. March 2010 C.
More informationDrive Laser Operations
Drive-Laser Operations Drive Laser Thales laser Transport system Recent Laser Milestones Safety Technical Where do we stand today? Laser Acceptance Status Laser Commissioning UV on cathode Injector Commissioning
More informationThe basic parameters of the pre-injector are listed in the Table below. 100 MeV
3.3 The Pre-injector The high design brightness of the SLS requires very high phase space density of the stored electrons, leading to a comparatively short lifetime of the beam in the storage ring. This,
More informationDiamond RF Status (RF Activities at Daresbury) Mike Dykes
Diamond RF Status (RF Activities at Daresbury) Mike Dykes ASTeC What is it? What does it do? Diamond Status Linac Booster RF Storage Ring RF Summary Content ASTeC ASTeC was formed in 2001 as a centre of
More informationFocus of efforts. ILC 2010, Mar/27/10 A. Seryi, BDS: 2
Beam Delivery System Updates Andrei Seryi for BDS design and ATF2 commissioning teams LCWS 2010 / ILC 2010 March 28, 2010 Plan of the program at ILC2010 Focus of efforts Work on parameter set for a possible
More informationScreen investigations for low energetic electron beams at PITZ
1 Screen investigations for low energetic electron beams at PITZ S. Rimjaem, J. Bähr, H.J. Grabosch, M. Groß Contents Review of PITZ setup Screens and beam profile monitors at PITZ Test results Summary
More informationLCLS-II Injector Tuning Procedures. F. Zhou (SLAC) & F. Sannibale (LBNL) 2/6/2017
LCLSII-TN-17-3 LCLS-II Injector Tuning Procedures F. Zhou (SLAC) & F. Sannibale (LBNL) /6/17 1. Introduction Figure 1 shows
More informationBUNCH-COMPRESSOR TRANSVERSE PROFILE MONITORS OF THE SwissFEL INJECTOR TEST FACILITY
Proceedings of IBIC, Tsukuba, Japan MOPB8 BUNCH-COMPRESSOR TRANSVERSE PROFILE MONITORS OF THE SwissFEL INJECTOR TEST FACILITY Gian Luca Orlandi, Masamitsu Aiba, Simona Bettoni, Bolko Beutner, Helge Brands,
More informationPEP II STATUS AND PLANS *
PEP II STATUS AND PLANS * John T. Seeman + Stanford Linear Accelerator Center, Stanford University, Stanford, CA 94309 USA The PEP II B-Factory 1 project is an e + e - colliding beam storage ring complex
More informationTITLE PAGE. Title of paper: PUSH-PULL FEL, A NEW ERL CONCEPT Author: Andrew Hutton. Author Affiliation: Jefferson Lab. Requested Proceedings:
TITLE PAGE Title of paper: PUSH-PULL FEL, A NEW ERL CONCEPT Author: Andrew Hutton Author Affiliation: Jefferson Lab Requested Proceedings: Unique Session ID: Classification Codes: Keywords: Energy Recovery,
More informationCommissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi)
Commissioning of Accelerators Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi) www.europeanspallationsource.se 6 July, 2017 Contents General points Definition of Commissioning
More informationFirst Results and Future of the Photo Injector Test Facility at DESY Zeuthen PITZ. introduction first measurements future schedule
First Results and Future of the Photo Injector Test Facility at DESY Zeuthen PITZ introduction first measurements future schedule Frank Stephan for the PITZ Collaboration, TTF Meeting Saclay, April 3 rd
More informationRUNNING EXPERIENCE OF FZD SRF PHOTOINJECTOR
RUNNING EXPERIENCE OF FZD SRF PHOTOINJECTOR Rong Xiang On behalf of the BESSY-DESY-FZD-MBI collaboration and the ELBE team FEL 2009, Liverpool, United Kingdom, August 23 ~ 28, 2009 Outline Introduction
More informationEUROFEL-Report-2007-DS EUROPEAN FEL Design Study
EUROFEL-Report-2007-DS4-095 EUROPEAN FEL Design Study Deliverable N : D 4.3 Deliverable Title: Task: Authors: Generation of 3rd harmonic photons at 90 nm DS-4 see next page Contract N : 011935 Project
More informationElectron Bypass Line (EBL) Design Electrons to A-line bypassing LCLS T. Fieguth, R. Arnold
September 2007 SLAC-TN-08-001 Electron Bypass Line (EBL) Design Electrons to A-line bypassing LCLS T. Fieguth, R. Arnold Introduction Forty one years ago, September 20, 1966, the first beam entered End
More informationReport on the LCLS Injector Technical Review
Report on the LCLS Injector Technical Review Stanford Linear Accelerator Center November 3&4, 2003 Committee Members Prof. Patrick G. O Shea, Chair, University of Maryland Dr. Eric Colby, Stanford Linear
More informationAREAL- Phase 1. B. Grigoryan on behalf of AREAL team
AREAL- Phase 1 Progress & Status B. Grigoryan on behalf of AREAL team Contents Machine Layout Building & Infrastructure Laser System RF System Vacuum System Cooling System Control System Beam Diagnostics
More informationStart to End Simulations
Start to End Simulations Motivation, Methods, and Examples Michael Borland Operations Analysis Group APS Operations Division March 20, 2005 A Laboratory Operated by The University of Chicago Motivation
More informationSummary of recent photocathode studies
Summary of recent photocathode studies S. Lederer, S. Schreiber DESY L. Monaco, D. Sertore INFN Milano LASA FLASH seminar November 17 th, 2009 Outlook Cs 2 Te photocathodes Pulsed QE measurements laser
More informationAn Operational Diagnostic Complement for Positrons at CEBAF/JLab
An Operational Diagnostic Complement for Positrons at CEBAF/JLab Michael Tiefenback JLab, CASA International Workshop on Physics with Positrons at Jefferson Lab 12-15 September 2017 Operating CEBAF with
More informationTop-Up Experience at SPEAR3
Top-Up Experience at SPEAR3 Contents SPEAR 3 and the injector Top-up requirements Hardware systems and modifications Safety systems & injected beam tracking Interlocks & Diagnostics SPEAR3 Accelerator
More informationSuppression of Timing drift between laser and electron beam driven photo-cathode RF gun
Suppression of Timing drift between laser and electron beam driven photo-cathode RF gun A. Sakumi, M. Uesaka, Y. Muroya, T. Ueda Nuclear Professional School, University of Tokyo J. Urakawa, KEK, Japan
More informationLCLS Linac Technical Design Review Diagnostics and Controls
Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Linac Technical Design Review Diagnostics and Controls December 12, 12, 2003 Requirements for for beamline instrumentation Upgrades
More informationCLIC Feasibility Demonstration at CTF3
CLIC Feasibility Demonstration at CTF3 Roger Ruber Uppsala University, Sweden, for the CLIC/CTF3 Collaboration http://cern.ch/clic-study LINAC 10 MO303 13 Sep 2010 The Key to CLIC Efficiency NC Linac for
More informationHigh Rep Rate Guns: FZD Superconducting RF Photogun
High Rep Rate Guns: FZD Superconducting RF Photogun J. Teichert, A. Arnold, H. Büttig, D. Janssen, M. Justus, U. Lehnert, P. Michel, K. Moeller, P. Murcek, Ch. Schneider, R. Schurig, G. Staats, F. Staufenbiel,
More informationStatus of the X-ray FEL control system at SPring-8
Status of the X-ray FEL control system at SPring-8 T.Fukui 1, T.Hirono 2, N.Hosoda 1, M.Ishii 2, M.Kitamura 1 H.Maesaka 1,T.Masuda 2, T.Matsushita 2, T.Ohata 2, Y.Otake 1, K.Shirasawa 1,M.Takeuchi 2, R.Tanaka
More informationTHE NEXT LINEAR COLLIDER TEST ACCELERATOR: STATUS AND RESULTS * Abstract
SLAC PUB 7246 June 996 THE NEXT LINEAR COLLIDER TEST ACCELERATOR: STATUS AND RESULTS * Ronald D. Ruth, SLAC, Stanford, CA, USA Abstract At SLAC, we are pursuing the design of a Next Linear Collider (NLC)
More informationSTATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR
Proceedings of FEL213, New York, NY, USA STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR F. Loehl, J. Alex, H. Blumer, M. Bopp, H. Braun, A. Citterio, U. Ellenberger, H. Fitze, H. Joehri, T. Kleeb, L.
More informationCathode Studies at FLASH: CW and Pulsed QE measurements
Cathode Studies at FLASH: CW and Pulsed QE measurements L. Monaco, D. Sertore, P. Michelato S. Lederer, S. Schreiber Work supported by the European Community (contract number RII3-CT-2004-506008) 1/27
More informationNext Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack
The Four 50 MW XL4 X-band klystrons installed on the 8-Pack The Demonstrate an NLC power source Two Phases: 8-Pack Phase-1 (current): Multi-moded SLED II power compression Produce NLC baseline power: 475
More informationDetailed Design Report
Detailed Design Report Chapter 4 MAX IV Injector 4.6. Acceleration MAX IV Facility CHAPTER 4.6. ACCELERATION 1(10) 4.6. Acceleration 4.6. Acceleration...2 4.6.1. RF Units... 2 4.6.2. Accelerator Units...
More informationStatus of Elettra, top-up and other upgrades
Status of Elettra, top-up and other upgrades Emanuel Karantzoulis ELETTRA / Trieste, Italy / 2010 November 25-26 Past and Present Configurations 1994-2007 From 2008 No full energy injection Full energy
More informationResults of recent photocathode studies at FLASH. S. Lederer, S. Schreiber DESY. L. Monaco, D. Sertore, P. Michelato INFN Milano LASA
Results of recent photocathode studies at FLASH S. Lederer, S. Schreiber DESY L. Monaco, D. Sertore, P. Michelato INFN Milano LASA FLASH seminar October 21 st, 2008 Outlook Cs 2 Te photocathodes cw QE
More informationSLAC X-band Technology R&D. Tor Raubenheimer DOE Briefing June 11 th, 2010
SLAC X-band Technology R&D Tor Raubenheimer DOE Briefing June 11 th, 2010 Introduction Overall ARD strategy ILC Program X-band program Compact XFEL and other applications Status and development needs Proposed
More informationA Cathode Development Cornell Cultera This scope includes all labor and purchases required produce photocathodes required by CBETA.
A1.01 PROJECT MANAGEMENT BNL/Cornell Michnoff A1.01.01 Milestones BNL/Cornell Michnoff This scope is a placeholder for all project high level milestones for NYSERDA. There is no cost or labor related to
More informationThe Elettra Storage Ring and Top-Up Operation
The Elettra Storage Ring and Top-Up Operation Emanuel Karantzoulis Past and Present Configurations 1994-2007 From 2008 5000 hours /year to the users 2010: Operations transition year Decay mode, 2 GeV (340mA)
More informationPhotocathodes FLASH: Quantum Efficiency (QE)
Photocathodes Studies @ FLASH: Quantum Efficiency (QE) L. Monaco, D. Sertore, P. Michelato J. H. Han, S. Schreiber Work supported by the European Community (contract number RII3-CT-4-568) /8 Main Topics
More informationLHC Beam Instrumentation Further Discussion
LHC Beam Instrumentation Further Discussion LHC Machine Advisory Committee 9 th December 2005 Rhodri Jones (CERN AB/BDI) Possible Discussion Topics Open Questions Tune measurement base band tune & 50Hz
More information3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline
3 cerl 3-1 cerl Overview As described before, the aim of the cerl in the R&D program includes the development of critical components for the ERL, as well as the construction of a test accelerator. The
More informationUndulator Protection for FLASH and for the European XFEL
Undulator Protection for FLASH and for the European FLASH sacrificial undulator: beam loss simulations FLASH BLM system plans FLASH sacrificial undulator FLASH Collimators BC2 scraper gun collimator (Ø
More informationStatus of SOLARIS. Paweł Borowiec On behalf of Solaris Team
Status of SOLARIS Paweł Borowiec On behalf of Solaris Team e-mail: pawel.borowiec@uj.edu.pl XX ESLS-RF Meeting, Villingen 16-17.11.2016 Outline 1. Timeline 2. Injector 3. Storage ring 16-17.11.2016 XX
More informationHigh QE Photocathodes lifetime and dark current investigation
High QE Photocathodes lifetime and dark current investigation Paolo Michelato INFN Milano - LASA Main Topics High QE photocathode lifetime QE vs. time (measurements on several cathodes, FLASH data) QE
More information12GeV CEBAF Commissioning
12GeV CEBAF Commissioning Operations Dept. Accelerator Division JLAB Outline 1 Process Integrated Process Overview Accelerator Readiness Review Process Internal Reviews/Process Process Recap 2 Beam Commissioning
More informationG0 Laser Status Parity Controls Injector Diagnostics
G0 Laser Status Parity Controls Injector Diagnostics G0 Collaboration Mtg Jefferson Lab August 16, 2002 G0 Collaboration Mtg (August 16, 2002), 1 Installed new AOM homebuilt laser G0 Collaboration Mtg
More informationBeam Instrumentation for CTF3 and CLIC
Beam Instrumentation for CTF3 and CLIC Beam loss - Beam halo monitoring developments CLIC diagnostic Common developments with other projects Specific requirements for CLIC Beam Loss and Beam Halo measurement
More informationAccelerator Instrumentation RD. Monday, July 14, 2003 Marc Ross
Monday, Marc Ross Linear Collider RD Most RD funds address the most serious cost driver energy The most serious impact of the late technology choice is the failure to adequately address luminosity RD issues
More informationINSTALLATION STATUS OF THE ELECTRON BEAM PROFILER FOR THE FERMILAB MAIN INJECTOR*
TUPB77 INSTALLATION STATUS OF THE ELECTRON BEAM PROFILER FOR THE FERMILAB MAIN INJECTOR* R. Thurman-Keup #, M. Alvarez, J. Fitzgerald, C. Lundberg, P. Prieto, M. Roberts, J. Zagel, FNAL, Batavia, IL 651,
More informationJefferson Lab Experience with Beam Halo, Beam Loss, etc.
Jefferson Lab Experience with Beam Halo, Beam Loss, etc. Pavel Evtushenko with a lot of input from many experienced colleagues Steve Benson, Dave Douglas, Kevin Jordan, Carlos Hernandez-Garcia, Dan Sexton,
More informationThe FLASH objective: SASE between 60 and 13 nm
Injector beam control studies winter 2006/07 talk from E. Vogel on work performed by W. Cichalewski, C. Gerth, W. Jalmuzna,W. Koprek, F. Löhl, D. Noelle, P. Pucyk, H. Schlarb, T. Traber, E. Vogel, FLASH
More informationUpgrading LHC Luminosity
1 Upgrading LHC Luminosity 2 Luminosity (cm -2 s -1 ) Present (2011) ~2 x10 33 Beam intensity @ injection (*) Nominal (2015?) 1 x 10 34 1.1 x10 11 Upgraded (2021?) ~5 x10 34 ~2.4 x10 11 (*) protons per
More informationFEL TEST PLAN WORKSHEET
FEL TEST PLAN WORKSHEET PROGRAM DEPUTY APPROVAL FEL Exp Coordinator Signoff: Date: PI Reviewer Signoff: Date: Expiration Date (max. 90 days from approval): Presentation Required? yes no COMPLETION INFORMATION
More informationActivities on FEL Development and Application at Kyoto University
Activities on FEL Development and Application at Kyoto University China-Korea-Japan Joint Workshop on Electron / Photon Sources and Applications Dec. 2-3, 2010 @ SINAP, Shanghai Kai Masuda Inst. Advanced
More informationSummary report on synchronization, diagnostics and instrumentation
Summary report on synchronization, diagnostics and instrumentation A.P. Freyberger and G.A. Krafft Jefferson Lab, 12000 Jefferson Avenue, Newport News, VA. 23606 Abstract The proceedings of Working Group
More informationAndrei Seryi, Toshiaki Tauchi. December 15-18, 2008
ATF2 milestones for discussion Andrei Seryi, Toshiaki Tauchi December 15-18, 2008 7th ATF2 Project Meeting What are natural milestones for ATF2? ATF2 design: Nominal IP β y* =0.1 mm & L * =1 m this give
More information5 Project Costs and Schedule
93 5 Project Costs and Schedule 5.1 Overview The cost evaluation for the integrated version of the XFEL with 30 experiments and 35 GeV beam energy as described in the TDR-2001 yielded 673 million EUR for
More informationPEP-II Disassembly Technical Systems
PEP-II Disassembly Technical Systems PEP-II D&D Review 6-Aug-2007 S.DeBarger S.Ecklund, A.Hill, D.Kharakh, M.Zurawel Outline Project safety Disassembly of technical systems Shielding Vac/Mechanical Cable
More informationPOLARIZED LIGHT SOURCES FOR PHOTOCATHODE ELECTRON GUNS AT SLAC?
SLAC-PUB-5965 December 1992 (4 POLARIZED LIGHT SOURCES FOR PHOTOCATHODE ELECTRON GUNS AT SLAC? M. Woods,O J. Frisch, K. Witte, M. Zolotorev Stanford Linear Accelerator Center Stanford University, Stanford,
More informationFirst Simultaneous Top-up Operation of Three Different Rings in KEK Injector Linac
First Simultaneous Top-up Operation of Three Different Rings in KEK Injector Linac Masanori Satoh (Acc. Lab., KEK) for the injector upgrade group 2010/9/16 1 Overview of Linac Beam Operation 2010/9/16
More informationThe PEFP 20-MeV Proton Linear Accelerator
Journal of the Korean Physical Society, Vol. 52, No. 3, March 2008, pp. 721726 Review Articles The PEFP 20-MeV Proton Linear Accelerator Y. S. Cho, H. J. Kwon, J. H. Jang, H. S. Kim, K. T. Seol, D. I.
More informationCONSTRUCTION AND COMMISSIONING OF BEPCII
Abstract CONSTRUCTION AND COMMISSIONING OF BEPCII C. Zhang, J.Q. Wang, L. Ma and G.X.Pei for the BEPCII Team, IHEP, CAS P.O.Box 918, Beijing 100049, China BEPCII is the major upgrade of BEPC (Beijing Electron-
More informationNon-Invasive Energy Spread Monitoring for the JLAB Experimental Program via Synchrotron Light Interferometers
Non-Invasive for the JLAB Experimental Program via Synchrotron Light Interferometers P. Chevtsov, T. Day, A.P. Freyberger, R. Hicks Jefferson Lab J.-C. Denard Synchrotron SOLEIL 20th March 2005 1. Energy
More informationSTATUS OF THE EUROPEAN XFEL
STATUS OF THE EUROPEAN XFEL M. Hüning, DESY, Hamburg, Germany for the European XFEL Accelerator Construction Consortium * Abstract The European XFEL is one of the world's largest accelerators presently
More informationHigh Brightness Injector Development and ERL Planning at Cornell. Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics
High Brightness Injector Development and ERL Planning at Cornell Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics June 22, 2006 JLab CASA Seminar 2 Background During 2000-2001,
More informationNovember 5,1999. The NLC Injector UCRL-JC
Preprint UCRL-JC-13-6450 The NLC Injector System V. Bharadwaj, J.E. Clendenin, P. Emma, J. Frisch, R.K. Jobe, T. Kotseroglou, P. Krejcik, A. V. Kulikov, Z. Li, T. Maruyama, K.K. Millage, B. McKee, G. Mulhollan,
More informationSLAC ILC Accelerator R&D Program
SLAC ILC Accelerator R&D Program SLUO Meeting September 26 th, 2005 Tor Raubenheimer SLAC 2005 ILC Program NLC group was redirected towards ILC Developed a program aimed at the topics identified in the
More informationSTATUS AND COMMISSIONING RESULTS OF THE R&D ERL AT BNL*
STATUS AND COMMISSIONING RESULTS OF THE R&D ERL AT BNL* D. Kayran #,1,2, Z. Altinbas 1, D. Beavis 1, S. Belomestnykh 1,2, I. Ben-Zvi 1,2, S. Deonarine 1, D.M. Gassner 1, R. C. Gupta 1, H. Hahn 1,L.R. Hammons
More informationProduction of quasi-monochromatic MeV photon in a synchrotron radiation facility
Production of quasi-monochromatic MeV photon in a synchrotron radiation facility Presentation at University of Saskatchewan April 22-23, 2010 Yoshitaka Kawashima Brookhaven National Laboratory NSLS-II,
More informationSTATUS OF THE SwissFEL C-BAND LINAC
STATUS OF THE SwissFEL C-BAND LINAC F. Loehl, J. Alex, H. Blumer, M. Bopp, H. Braun, A. Citterio, U. Ellenberger, H. Fitze, H. Joehri, T. Kleeb, L. Paly, J.-Y. Raguin, L. Schulz, R. Zennaro, C. Zumbach,
More informationJae-Young Choi On behalf of PLS-II Linac team
PLS-II Linac 2015. 4. 8. Jae-Young Choi On behalf of PLS-II Linac team Accelerators in Pohang Accelerator Laboratory XFEL (under construction) 400 M$ Machines under installation PLS-II PAL : Chronology
More informationStatus of the Jefferson Lab Polarized Beam Physics Program and Preparations for Upcoming Parity Experiments
Status of the Jefferson Lab Polarized Beam Physics Program and Preparations for Upcoming Parity Experiments P. Adderley, M. Baylac, J. Clark, A. Day, J. Grames, J. Hansknecht, M. Poelker, M. Stutzman PESP
More information