B1-00. SPECIAL REPORT FOR SC B1 (Insulated Cables) Walter Zenger. Special Reporter

Size: px
Start display at page:

Download "B1-00. SPECIAL REPORT FOR SC B1 (Insulated Cables) Walter Zenger. Special Reporter"

Transcription

1 CIGRE 2016 B1-00 SPECIAL REPORT FOR SC B1 (Insulated Cables) Walter Zenger Special Reporter 1. General Study Committee (SC) B1 is responsible for all aspects regarding land and submarine insulated cable systems. The scope of work of SC B1 is theory, design, applications, manufacture, installation, testing, operation, maintenance and diagnostic techniques for AC and DC cable systems. The four strategic directions given by the Cigre Technical Committee serve as a basis for the performed work. These are preparation of the electrical power system of the future, to make the best use of existing systems, focus on environment and sustainability and communication on power system issues for decision makers. For the 2016 Group Discussion Session, three preferential subjects were proposed to stimulate discussion in the light of the strategic directions. The total number of published papers is Preferential Subject No. 1 The title for PS1 is Feedback from newly installed or up graded cable systems. The subject covers all four strategic directions and involves the following sub-items: Design, qualification, installation techniques, operation Environmental issues This preferential subject attracted 9 contributions. wzenger@usi-power.com 1

2 2.1 Papers for Preferential Subject No. 1 B1-101: This paper describes activities to underground two 40 year old overhead lines in a now very dense urban area in Brazil. The utility had to deal with a narrow right-of-way that in addition had experienced several ROW encroachments. The work needed to satisfy necessary information requests from authorities such as environmental studies, EMF mitigation measures, traffic plans and special demands regarding the civil work. The authors showed that undergrounding of overhead lines is not a simple process even when utilizing existing ROW. The permitting process is still in progress. B1-102: Due to the Great East Japan Earthquake a new underground power line was necessary to be commissioned in a very short time. To reduce the installation time by 50%, pre-molded joints for 275kV were used in Japan for the first time. New test procedures needed to be developed to prove the reliability of the new connections including determination of the maximum permissible contamination size, visual detectability of contaminations by splicers and long duration verification tests including partial discharge measurements. The new high voltage withstand test combined with PD measurements successfully confirmed the validity of the existing process control methods. In addition the installation faced challenges of a long tunnel and a steep slope section. The circuit went into operation in B1-103: This contribution presents a project to reinforce transmission capacity in New Zealand. It covers cable design of a 220kV XLPE cable system, installation along a 1.4km bridge and inside manholes. The challenges include the mitigation of thermo-mechanical forces in joint bays, cable attachment and clamping within the bridge structure including evaluation and full scale testing of its thermo-mechanical, seismic and vibration stresses. Design of snaking arrangements to greatly restrain the cable thrust into manholes has been verified by tests. Modelling and tests of a dilation mechanism at the bridge showed that supports allow for horizontal and vertical bridge movements and aimed to simulate 80 years of TMB activity. B1-104: Maintaining underground cable network in Mumbai City is a challenging task. Some cables were installed more than 100 years ago. Since the System Operator has Gas Filled, Oil Filled and XLPE cables, maintenance practices are different and adapted to each type of cable. The report presents various techniques and methods to monitor and upgrade the Underground Cable Network of Mumbai City. B1-105: Multiple parallel cable systems can exhibit a complex network of conductors, metallic shields and grounding conductors. Modelling of mutual inductive and ohmic interference of a multi-phase conductor 400kV cable system is presented in this paper. Starting with a definition of modelling parameters an impedance matrix is computed using self impedances and coupling impedances. Together with earthing resistances a chain model is formed to calculate voltage and current distributions on all accessible sites along the circuit. Measurements at an existing 400kV cable system were performed at low load operations. The results show good correlation with the model. B1-106: This paper describes the development, design, installation, commissioning and field testing of a novel, gravitational water cooling system for cables. After the installation of a new 230kV XLPE cable system, fiber optic temperature measurements revealed that an existing hot spot mitigation around a steam pipe was insufficient, forcing a derating of the 2

3 EHV system by about 20%. Rating studies and mathematical models showed that a gravitational closed-loop water cooling system should be sufficient. This largely maintenance free cooling, would accommodate the required heat transfer away from the hot spot resulting in a reduction of the ambient backfill temperature. Initial tests show a good agreement between model and actual measurements. B1-107: HVAC submarine connections are increasing in numbers due to interconnections, offshore windfarms and connections to oil & gas platforms. This contribution reports on the designing and testing of a 400kV HVAC submarine cable system in Korea. The system includes the cable, factory and repair joints, and terminations. Based on Cigre recommendations a program of development, type and pre-qualification tests, both electrical and mechanical, was established. In addition a test for long-term accelerated aging was devised. The development and type tests were successfully completed. The pre-qualification test is scheduled to be completed in October B1-108: Transient overvoltages in cross-bonded systems induced by lightning have been dealt with in Cigre TB 283. This Spanish paper presents how the Cigre analytical equations are deduced to model unconventional grounding of cross-bonding joints as well as outdoor and GIS terminations protected by sheath voltage limiters (SVL). The authors also show the impact mixed coaxial and unipolar grounding leads can have on the protective margin of the system. Similar important is the consideration for the length of the grounding lead. The resulting overvoltages can by far exceed the withstand level of the outer sheath or the accessories. The new equations were applied to 150 circuits of 220 and 400kV in the Spanish network leading to the proper protection level for a total of 392km of EHV cable systems. B1-109: This paper describes the qualification process for the Italy France 320kV HVDC intertie across the Alps. Since international standards are currently unavailable, the specifications and testing requirements were based on present Cigre recommendations of TB 496. The two TSO s requested additional tests beyond the Cigre TB 496 to make sure the cable system withstands the specific environmental conditions of this particular installation. The tests included space charge measurements on full size cables and a superimposed impulse voltage tests at very cold temperatures down to -25C. Challenges for the installation were long viaduct crossings and long pulling length to reduce the number of joints and the necessary use of large drums. The successful completion of the qualification tests has given confidence to users and suppliers. 2.2 Discussion of Preferential Subject No. 1 The papers submitted for Preferential Subject No.1 show the wide range of topics related to newly installed or up-graded cable systems worldwide. The papers cover three overarching subjects Increase of transmission capability Improvement of reliability New and novel designs or installation methods Transmission capability is increased by installing new systems such as in New Zealand or by replacing overhead lines in existing right-of-way as done in Brazil. Emergencies such as the large Japanese earthquake necessitate a quick system reinforcement challenging existing selection of accessories and installation procedures. A novel gravitational water cooling 3

4 system is now mitigating an existing hot spot thus preventing a derating of an EHV system in Canada. System performance and reliability can be improved by verification of design parameters. This has been shown by a full scale mechanical testing for new types of installations on bridges and in manholes, determining and testing the criticality of contaminations in accessory interfaces, confirming the voltage and current distribution along a cross-bonded system, and rating audits on installed systems. Transient overvoltages that exceed the insulation level of cable sheaths or accessories can be hazardous. Thus modelling, testing and implementing a design to limit these transients improve reliability of the system. New cable system designs require development, type, pre-qualification and commissioning tests. Several papers address these requirements for EHV/HV AC and HVDC cable systems. Test specifications are based on Cigre recommendations, IEC standards, and customer needs. Utilities now specify additional project specific requirements, some of these might later be included in industry standards. In addition new types of installation techniques are presented such as attachments to long bridges or viaducts, cable installation on steep slopes or placement of a closed-loop gravitational cooling system next to a new EHV system. 2.3 Questions from Preferential Subject No. 1 The review of the papers and the discussion implied the following questions for Preferential Subject No. 1 (Feedback from newly installed or up graded cable systems): Question PS1 Q1: Several papers address the modelling of cable and system parameters. Are there other methods available that confirm these findings? How do they relate to voltage and current distribution in cables, to overvoltages in shields, to cable ratings or to thermomechanical properties? Question PS1 Q2: Quality control and testing during commissioning is crucial for reliability. Both can be performed separate or combined. What is the advantage of either approach? Are users inclined to verify process control through testing or is the combined QC and test beneficial. What could be the future process? Question PS1 Q3: Qualification test procedures for AC EHV cables are well established. Additional requirements are stipulated for submarine cables. What test requirements for HVAC cable systems are missing as users still require additional testing? Is there a need for additional long-term aging tests? Is there a need to update TB 303? Question PS1 Q4: HVDC cable systems are growing in numbers and are now increasingly used for land based systems. What environmental conditions do they have to withstand? What is the optimal laying length for such cables? Are current Cigre recommendations for HVDC cables sufficient? Is it time to prepare recommendations for Extension of Qualification of HVDC Cable Systems? 4

5 3. Preferential Subject No. 2 The title for PS2 is Best use of existing cable systems. The subject addresses the second strategic direction. The subject covers: Condition assessment and diagnostic testing of cable systems Trends in monitoring cables and accessories Upgrading methodologies and related experiences Trends in maintenance strategies This preferential subject attracted 16 contributions. 3.1 Papers for Preferential Subject No. 2 B1-201: This paper describes the development of a new maintenance plan for EHV XLPE cable systems in Latin America. The specification is based on Cigre TB 279 and TB 379 and selected a Reliability Centered Maintenance (RCM) approach. Experience has shown that physical location and condition of the maintenance access points is of high importance. Manholes and link boxes need to be accessible and free of water for PD or sheath current measurements and thermographic inspections. The specifications for manholes and link boxes have been revised to aid the new maintenance procedures. B1-202: The condition assessment method for HV and EHV transmission cable systems at a US utility is shown in this paper. The practice covers both extruded dielectric and pipe-type cable systems. Extensive evaluations and repeated field examinations are needed to ensure early identification for reliable operation over the expected design life of 40 years and more. The authors list the key inspection items including possible degradations and remediation possibilities. Corrosion even for new circuits can be an important factor. It is also shown that different cable manufacturer apply different techniques for maintenance concerns. B1-203: This contribution presents the selection process of an optimal field test system for 115kV extruded dielectric cables in Thailand. The utility experienced frequent follow-on failures after DC commissioning tests. The selection process was focused on the local needs such as portability and power consumption but also included test effectiveness, cable length and adoptability to PD measurements; although PD measurements proved to be challenging in a field environment. The selection process that also included multi-criteria decision making led the utility to select a Damped AC test system. B1-204: Cancelled B1-205: Online PD monitoring for medium voltage cable systems is increasingly applied to detect weak spots prior to a failure. This new technology incorporates two sensors at both ends of a circuit enabling the detection and location of PD sources. The measurement is aided by injecting a time synchronization pulse. The system can be applied not only to radial systems but also to distribution networks. Online PD detection can be advantageous since PD occurrence can be sporadic and changing in magnitude over time. The authors report that PD can last months to years prior to failure. Dutch utilities have demonstrated that the application can improve their reliability indices such as SAIDI and SAIFI. 5

6 B1-206: This contribution is focusing on armor losses of three conductor submarine cables. Cigre TB 640 has reported that armor losses calculated with IEC standards result in higher than actual losses and thus resulting in lower ratings. The authors developed a measurement system and a FEA simulation model for armor losses on actual cables. Several different types of cables were tested and modeled. Measurements were conducted at room and operating temperature. The tests showed armor losses up to 60% lower than the IEC values. The FEM, correlated with the measurements, can be used for cables with other conductors and armors types. B1-207: Dissolved Gas Analysis (DGA) has been a useful tool for fluid filled cable systems to inspect abnormalities or for regular maintenance procedures. The issue is what level of detected gases is critical and needs to be addressed by corrective maintenance. Improved precision in prediction is necessary to be able to repair prior to failure. This paper Japanese presents a new updated criterion matrix for SCLF cables with highly accurate diagnosis based on pattern analysis. A second part of the paper describes how gas analysis (GA) for fluid filled XLPE HV terminations can be used to diagnose tracking degradation between the cable and stress cone due to solidification of silicone oil. B1-208: The paper describes the development of a robot maintenance system for a long cable tunnel across the Pyrenees between France and Spain. The 8.5km long tunnel with a diameter of 3.5m contains two HVDC circuits. Due to environmental constraints the tunnel is only accessible at its ends. Regulatory restrictions define the tunnel as accessible but not visitable, requiring the development of an automated maintenance robot vehicle. This vehicle can carry out preventive maintenance tasks without the need of workers but also is able to transport workers into the tunnel for corrective maintenance work. Sensors and cameras ensure a safe and reliable operation of the train. B1-209: This contribution presents efforts by a Spanish utility to analyse sheath currents to detect abnormal conditions such as damage to the oversheath, performance of surge voltage limiters whether during faults or their possible malfunction, incorrect sheath bonding during installation or removal of earthing leads by theft. The utility develops systems that monitor sheath bonding systems, basically an easy measurement but not typically employed, to optimize the maintenance process. Theoretical studies have been conducted regarding sheath currents in normal and abnormal conditions. Research is continuing to develop automatic interpretation of monitored currents to estimate the probable nature of defects. B1-210: Connections to off-shore windfarms in Germany face a special requirement where the temperature difference between the sea ground and cable surface must be less than 2K. Thus cable losses can limit the transfer capacity of the submarine cables below their maximum operating temperature. As an interim solution parallel cables provide necessary reserves. The final solution is a predictive feed forward dynamic rating strategy explained in this paper. The algorithm is based on metaheuristic optimization and takes into account predicted low wind conditions. With the presented solution 22% more energy can be transmitted. B1-211: This paper describes condition monitoring approaches by UK operators of medium and high voltage submarine cable networks for renewable off-shore generation. While historically time based maintenance (TBM) had been applied, users now move to condition based maintenance (CBM). Cigre TB379 and TB398 contain strategies for land based systems. It is argued in this paper that submarine cables have a shorter service life and thus 6

7 need to have a different maintenance approach compared to land cables. The paper explains applications of electrical detection diagnostic methods such as online PD, sheath current and power quality monitoring. Two case studies show that 90% of electrical issues would be identified by the diagnostics. B1-212: This contribution focuses on the Life Cycle Assessment (LCA) of a 380kV HVAC double circuit in Italy. LCA evaluates the environmental burdens of a product, a process or an activity, quantifies the needed resources and pollution emissions and assesses opportunities for improvement. The work was based on ISO standards and used existing software packages. The interpretation of the results showed that the operational phase is dominant with cable losses and land occupation over a 40 year life span. Next highest importance was assigned to the realization phase and impacts due to mining and production of copper. B1-213: Renewable energy systems pose new challenges to TSO s. In the past, new cable systems rarely were loaded up to the maximum design ratings. The Belgian TSO decided to use a real time thermal rating (RTTR) system to better control load flow in a strategic 150kV circuit. This includes a safe and controlled overloading of the cable with help of distributed temperature sensing (DTS) and RTTR. The paper explains the TSO s experience with installation, typical problems and final recommendations for integration and overload capabilities. Critical actions are early involvement between cable experts and IT, and focus on follow-up actions after installation that are listed in the paper. B1-214: The tracking of combustion test standards for cables is the focus of this Chinese paper. It addresses Chinese and international standards based on the relevance and development track, applied combustion tests for new and aged cables as well as the toxicity of the combustion gases. Cables have been the cause of many fire accidents in power grids. In China two thirds of all fires in cities are caused by cables. The authors present a test framework for cable combustion tests in the laboratory based on international and local standards. It is also proposed to include toxicity tests in standards including the laboratory emissions during these tests. B1-215: This paper describes new technology developments for the location of submarine cables. Determining the correct position of submarine cable is essential for installation, maintenance and repair. For protection against damage, many of these cables have been buried thereby increasing the difficulty of location. New 3 axis magnetometers improve the efficiency of reliable location for both AC and HVDC submarine cables. The new technologies are also complemented by sophisticated signal processing and filtering techniques. Applications on installed links are presented. The authors also present a new, remote controlled tone generator to locate and identify multiple cables in a narrow corridor. B1-216: Breakdown of HVDC mass impregnated non-draining (MIND) cables can be caused by large cavities in the laminated paper dielectric. These voids can be created by excessive load cycling. MIND cables, for a long time, have been the dominate dielectric for the highest DC voltages. Operators now increasingly demand a faster change of the load flow to better adapt to renewable generation. This paper presents mechanisms that can lead to excessive voids near the conductor. It shows how conductor temperature, the temperature across the insulation and external pressure are driving cavity formation. Parameters of existing systems are presented. 7

8 B1-217: This contribution from Bahrain presents the application of PD diagnostics to EHV GIS terminations for the early detection of incipient failures. It describes the importance of PD measurements and outlines a case study for the periodic monitoring with the timely detection of PD in a 220kV wet type GIS termination. It explains the application of high frequency current transformers (HFCT) with focus on practical problems and the challenges experienced during the PD measurements. The paper also recommends an online silicone oil level measurement for oil inside the terminations. 3.2 Discussion of Preferential Subject No. 2 Papers submitted for Preferential Subject No.2 Best Use of Existing Cable Systems illustrate a large scope of topics targeting the operation and maintenance of existing assets. Maintenance plans for land and submarine cables show different approaches on how to select plans for specific needs whether they focus on time based, condition based or reliability based parameters. Access to the infrastructure can be an issue that can be addressed by either new specifications or development of robotic equipment. Cable condition monitoring needs to provide essential information for necessary corrective actions. Corrosion of infrastructure components has been shown to be an issue even for fairly new installations and needs attention. Electrical measurements such as sheath currents can provide helpful feedback for the asset owner and research effort point to an automated interpretation of results in the future. New test techniques are discussed in four papers. Some point to difficulties of testing in the field. A key question for users is how new techniques can improve system reliability and the ways to quantify the benefits. Location of submarine cables can be improved with two new test systems and a paper recommends toxicity of combustion testing to be included in international standards. Renewable generation is growing rapidly and with it is challenging cable technology with new requirements. Overall it needs to be discussed whether many of the condition and monitoring parameters established for land cables are also applicable for submarine cables. With regards to cable losses, there can be impacts on the marine environment. There can be also a desire for a safe and controlled overload of cables connecting to renewable generation. Cigre TB 640 indicated that the actual losses in 3 conductor armoured cables are less than calculated and thus the ampacity for such cables could be higher. A test procedure to verify the losses of armoured cable is presented. Are there other parameters where specifications are too limiting? MIND cables are susceptible to void formation during load cycles and are challenged with requests of faster load changes. A better understanding of the mechanism can increase the possible transfer capacity. 3.3 Questions from Preferential Subject No. 2 The review of the papers and the discussion implied the following questions for Preferential Subject No. 2 (Best use of existing cable systems): Question PS2 Q1: New renewable generation presents a number of challenges for cable system operators. For submarine cable connections is there a need to change condition 8

9 monitoring compared to land cable? What is the environmental impact of such cables and how can it be mitigated? For land cables, is there a need for RTTR and temporary overload? Question PS2 Q2: Selection of maintenance approaches for cables is discussed in a number of papers. What is the selection criteria for time based, condition based or reliability based plans? Will maintenance robots be used in the future for not readily accessible spaces? Question PS2 Q3: Correct and in-time knowledge of the cable condition is paramount for reliable cable operation. Will there be automated interpretation of results. Can DGA or other cumulative tests replace spontaneous measurements such as PD to detect degradation and how? Question PS2 Q4: Losses are an important consideration for cable operations. Do present loss calculations reflect the true conditions? How can system operation be modified for MIND cables? What impact have losses on the environment and how can they be reduced to an optimal value? How can LCA be a helpful tool for losses in the planning process? Question PS2 Q5: New test techniques are presented in several papers. What are the challenges for testing the condition of cables in the field? Can an impact on system reliability through periodic or online testing be quantified and by what method? What tests can best locate submarine cables? Question PS2 Q6: Corrosion has been mentioned as an important non electrical condition, should Cigre engage in this? Is there a need to include toxicity in combustion tests in our standards? 4. Preferential Subject No. 3 The title for PS3 is Insulated cables in the power system of the future. The subject addresses the first strategic direction. The subject covers: Higher voltage level for AC and DC cables New functionalities expected from cable systems Integration of cables and accessories in the network Innovative cable types This preferential subject attracted 14 contributions. 4.1 Papers for Preferential Subject No. 3 B1-301: HVDC cable systems with ever higher voltages and transmitted power are becoming essential components for renewable energy delivery. This Swedish paper describes the successful development of an extruded XLPE HVDC cable system for 525kV including an oil and porcelain-free termination, a land joint and a flexible sea joint. The new system can transmit 50% more power compared to the present 320kV voltage level. Development steps are outlined showing use of a new insulation material for cables but also relying on new and existing technologies for stress control in accessories. Extensive modelling and testing procedures have been applied in the development process aided by Cigre TB 496. B1-302: As off-shore wind farms are growing, some countries need to rely on floating wind generator platforms due to marine conditions. This Japanese contribution shows the 9

10 development of a dynamic cable system for 22kV and 66kV, suitable for the connection to floating generators and substations. Starting with an analytic simulation the system was designed for a 20 year service life. This included fatigue analysis as well as experimental tests on actual cables. A connection via a lazy-wave arrangement with intermediate buoys was selected. The cable system to a 7MW wind turbine, as part of a demonstration project, has been successfully installed and is in operation. B1-303: The cost of cables contributes significantly to the overall cost of off-shore generation. Increased attention is given to improve the transfer capabilities of inter-array and export cables. This Danish analysis shows that these cables rarely reach the designed service temperature. The paper suggests a new systematic method where load profiles, a load step function and thermal properties of the surroundings provide data for the cable rating. FEM together with methods outlined in Cigre TB 610 can model installation conditions. The authors propose to apply a Thermoelectric Equivalent (TEE) model as an analytical numerical solution to quickly calculate daily temperature response based on several years of data. B1-304: Three core armored submarine cables are the cables of choice for both array and transmission cables for off-shore wind farms. Ampacities calculated in accordance with IEC have shown to underestimate cable ampacity. This Danish paper investigates the impact of different parts of the cable with regards to the total losses even though hysteresis losses are not incorporated. It is suggested that the loss inaccuracy is based more on the screen loss factor than on the armor loss factor. Estimation of shield losses is determined by the shield currents. New research is proposed to improve shield current calculation and to use EMTP simulations for pipe-type cables even though the magnetic parameters are currently not accessible for calculation. B1-305: This paper describes the development of a transition joint between XLPE and selfcontained oil filled cables for the 132kV grid in Argentina. The drivers for the development were reduced delivery lead times, speed of installation, use of local splicers and the application of a pluggable design. The development was initiated by a local utility. The design successfully passed the tests in accordance with IEEE 404. The authors present the installation process of the new joint together with a comparison of the installation of a conventional transition joint. B1-306: Selection of the optimal material for conductors and screens has always been key to efficient cable design. Considerations are given to weight, conductivity, volume, ease of installation, health and environmental aspects. Materials of choice for conductors are Aluminium or Copper while the choice for screens can be Aluminium, Copper or Lead. The authors present their design considerations and two case studies for a 380kV and a 150kV application that resulted in the selection of Aluminium for both conductor and screens as the best solution. Test programs for the cable designs are included in the contribution. B1-307: This contribution presents what effect ultraviolet (UV) radiation and sandstorms have on the flashover voltage of silicone rubber cable terminations. These types of terminations are increasingly applied in Egyptian distribution networks. UV exposure of the test samples was followed by flash over and leakage current tests with water of varying conductivity. There was a decrease in flash over voltage based on the severity and duration of exposure to UV and simulated sand storms. The impact of sand storm damage has shown to be more severe than UV radiation. 10

11 B1-308: High Temperature Superconducting (HTS) cable systems have been long associated with future solutions for power transmission. This European paper presents a concept for a 400kV HTS cable system to partially underground major HVAC overhead transmission lines near urban areas. The designed system will have operating currents in range of 4kA. Thus only a single cable system will be able to carry the current of an overhead circuit. Cables can be placed closer together, a double circuit requires a trench width of 2m versus 20m compared to a traditional XLPE cable system. The losses of a HTS system at 4kA are over 50% lower than for a XLPE system. Suitable joint and termination designs are presented. Testing of a 220kV prototype has been completed successfully. B1-309: This French paper describes commissioning tests for long HV AC (up to 400kV) and HV DC cable systems up to 320kV as well as alternative tests and future trends. It also addresses cable system design with special consideration to safety and cost efficiency. Alternatives to the traditional testing can be resonant AC, partial discharge or DTS systems. The adequacy of DC vs AC tests on long HVDC cables is discussed. The paper reviews the French practices, shows the experiences while testing a number of recent large scale projects and discusses test parameter with proposed test levels and durations. B1-310: This contribution presents the planning, design, testing, installation and commissioning of a 4.6km long double circuit 400kV submarine cable crossing of the Dardanelles strait in Turkey. This project consists of 6 parallel submarine cable plus one spare. Justification of the project from a systems operations point of view, cable design criteria, installation and testing are discussed. Cable plowing had been selected as a protection against external damage. Planning also needed to address switching and temporary overvoltages. The system has been commissioned in April B1-311: An optimizing strategy for the armor design of submarine cables is the focus of this Chinese paper. An EMTP model is used to analyze the impact of cable components on ampacity. The analysis for this application found that at optimum sheath and armor currents should be about equal. The optimal armor design calls for 53 galvanized steel armor wires with two added copper wires. A cross-section of the cable is presented. The optimized configuration results in ampacity increase of 20%. Due to the higher voltage between sheath and armor a semiconducting sheath is required. B1-312: This paper describes the design and type testing of a new deep water 420kV HVAC submarine cable to be installed across two Norwegian fjords and having a combined length of about 32km. The development and system test include factory and repair joints. Due to an record installation depth of 390m special tests such as radial water penetration tests of joints, longitudinal and radial water penetration tests on the cable have been devised. The test program was developed based on Cigre TB 303 and TB 490 recommendations. The challenges of manufacturing in long length and of future developments are outlined. B1-313: For protection submarine cables are mostly installed in trenches. The knowledge of the thermal properties of the sediment surrounding these cables is therefore important. As part of the HVDC NordLink connector between Norway and Germany traditional geotechnical surveys were conducted to characterize soils and identify thermal bottlenecks. Inconsistent Thermal Conductivity (TC) measurement results raised questions about instruments, methods and sample handling. This European paper describes new in-situ measurements during a resurvey. In situ measurements need to be careful evaluated but when interpreted correctly can be an important addition to traditional techniques. 11

12 B1-314: This contribution presents a case study to assess the thermal effect water mains can have on the ampacity of cables. A 380kV HVAC cable in Saudi Arabia is installed part of the route parallel along a water main. An improved implementation of the well-known FEM method shows different dependencies of installation, soil and backfill as well as thermal resistivity. The most influential parameter is the temperature of the water pipe. 4.2 Discussion of Preferential Subject No. 3 A large number of papers have been submitted for this subject about Insulated Cables in the Power System of the Future. As with many other papers this year, focus is on submarine cables for renewable energies. Cost and efficiencies are another key topic for this year s Cigre session. The main aim is how to install new systems quicker and at less cost. The optimum selection of conductor material is one of the addressed options. New extruded HVDC cables systems with improved materials and higher operating voltage can increase the transmitted power significantly. New developments for HTS cables aim at the highest transmission voltages and transfer of power one for one with overhead lines. Submarine cable armouring design is optimized to increase power transfer by partially replacing steel wires with copper wires. While wind generators anchored in the sea floor are now commonplace, new developments aim at areas in the sea where only floating units can be installed thus challenging reliable cable connection technologies. The cost reduction of submarine cables and application of submarine cables for connectors, array or transmission cables is subject of four papers. Another group of papers deals with application of existing cable systems for new applications such as submarine cables for great depth, crossing of busy water ways, and new transition joints. Testing and system modelling will provide new solutions and systems for the future be it commissioning testing for long HVAC and HVDC systems or the thermal environment in submarine or land installations. 4.3 Questions from Preferential Subject No. 3 The review of the papers and the discussion implied the following questions for Preferential Subject No. 3 (Insulated cables in the power system of the future): Question PS3 Q1: Extruded HVDC cable systems are proposed with ever higher voltage levels. What is the driving force for higher voltages? What will be the future for extruded HVDC cables and is there still a future place for laminar (lapped) HVDC systems? Question PS3 Q2: EHV HTS cable systems are now in development. Are there limits on the magnitude of transmission capacity for a single circuit so that it is manageable from a view point of cable technology, system operation or short circuit forces? What other applications can be seen for EHV HTS systems? 12

13 Question PS3 Q3: Higher ratings and cost efficiency for submarine cables are of concern to current designers and users. What key questions need to be addressed and solved in the future? Do we see an increasing demand for floating wind farm installations? What additional specific testing is necessary? Question PS3 Q4: Commissioning testing of installed systems can impact the future reliability. How can we make sure that the type of test, the voltage level and duration is appropriate to detect defects while not damaging sound cable? In the future, do we need to make adjustments to the cable or accessory design to better accommodate commissioning testing? Question PS3 Q5: Armour loss calculation has been a major concern of cable engineers over the past years but also losses in conductors and screens are being discussed. What future actions do we need to take and what type of modelling will be necessary? How can we correctly assess permeability of carbon steel? Is there a better way to assess the overall cost of losses and how can cable design be adjusted for this in the future? IMPORTANT NOTE: it is expected that above questions relevant to the three Preferential Subjects will attract a number of prepared contributions. The timing of the B1 session usually allows a maximum of 45 prepared contributions. Contributors are invited to comply with Cigre rules i.e. to send their contributions two weeks in advance to the Session and to be ready to discuss contents and allocated speaking time on Wednesday 24 th of August in room 361, the day before the Group Meeting. Contributions shall be prepared on the basis of the templates that can be found on the Cigre website. These templates will be also posted on Cigre B1 website together with the latest information regarding SC B1. The SC B1 session held on Thursday August 25 th will start at 8h45 in Salle Bleue and the lunch time will be from 12h30 to 14h00 (sharp). A questionnaire prepared by the Customer Advisory Group of SC B1 will be circulated to better understand the expectations of Insulated Cables community. 13

220KV EHV NETWORK AT RELIANCE JAMNAGAR REFINERY COMPLEX

220KV EHV NETWORK AT RELIANCE JAMNAGAR REFINERY COMPLEX 220KV EHV NETWORK AT RELIANCE JAMNAGAR REFINERY COMPLEX JAMNAGAR 220KV CABLE NETWORK: 2 2. DESIGN 2A. NETWORK: 220 KV NETWORK DESIGN IS DESIGNED WITH 100% REDUNDANCY FROM 220 KV BUS TO LOAD. THIS IS ACHIEVED

More information

640 kv XLPE HVDC cable system

640 kv XLPE HVDC cable system 640 kv XLPE HVDC cable system World s most powerful extruded cable system enables utilization of renewable energy resources nkt.com Demand for higher voltages NKT s new 640 kv XLPE DC cable system is the

More information

Revision of Qualification Procedures for High Voltage and Extra High Voltage AC Extruded Underground Cable Systems

Revision of Qualification Procedures for High Voltage and Extra High Voltage AC Extruded Underground Cable Systems Revision of Qualification Procedures for High Voltage and Extra High Voltage AC Extruded Underground Cable Systems Tutorial vor the ICC Educational Session on November 11 2009 in Scottsdale, AZ by Wim

More information

HVDC cable accessories

HVDC cable accessories ^=r SVENSKA KRAFTNÄT SWEDISH NATIONAL GRID UNIT, BUSINESS AREA OUR REFERENCE TR14-02-5E DATE 2018-09-21 CONSULTATIÖNS NT, NB TECHNICAL GUIDELINE EDITION 1 APPROVED TD HVDC cable accessories This technical

More information

ECONOMICAL 36 kv CABLE SYSTEM FOR THE BELGIAN NETWORK

ECONOMICAL 36 kv CABLE SYSTEM FOR THE BELGIAN NETWORK ECONOMICAL 36 kv CABLE SYSTEM FOR THE BELGIAN NETWORK J. Becker NEXANS BENELUX S.A. F. Musique ELECTRABEL S.A. ABSTRACT In order to tackle the deregulated market with confidence and in a realistic way,

More information

640 kv extruded HVDC cable system

640 kv extruded HVDC cable system 640 kv extruded HVDC cable system World s most powerful extruded cable system Pehr Bergelin, Marc Jeroense, Tobias Quist, Hans Rapp NKT Summary In this paper, NKT s new 640 kv extruded DC cable system

More information

2004 SC B1 PROGRESS REPORT (INSULATED CABLES)

2004 SC B1 PROGRESS REPORT (INSULATED CABLES) 2004 SC B1 PROGRESS REPORT (INSULATED CABLES) by Y. MAUGAIN, Secretary of the Study Committee Page 1 / 14 TABLE OF CONTENTS 1 OVERVIEW... 3 2 SC ORGANISATION... 3 3 PUBLICATIONS... 4 4 2005 MAIN EVENTS...

More information

HIGH VOLTAGE CABLE ACCESSORIES - Application, Design, Installation, Testing - Ivan Jovanovic G&W Electric Company

HIGH VOLTAGE CABLE ACCESSORIES - Application, Design, Installation, Testing - Ivan Jovanovic G&W Electric Company HIGH VOLTAGE CABLE ACCESSORIES - Application, Design, Installation, Testing - Ivan Jovanovic G&W Electric Company 1 Year 1905 First detachable porcelain pothead for 4 kv systems Year 2015 Terminations

More information

Joint paper: Feasibility and technical aspects of partial undergrounding of extra high voltage power transmission lines

Joint paper: Feasibility and technical aspects of partial undergrounding of extra high voltage power transmission lines Joint paper: Feasibility and technical aspects of partial undergrounding of extra high voltage power transmission lines Brussels, December 2010 1. Introduction Page 4 2. Executive Summary 5 3. Partial

More information

Emerging Subsea Networks

Emerging Subsea Networks NEW SUBSEA OPTICAL FIBRE JUNCTION BOX FOR REDUCED TENSILE LOAD APPLICATIONS Craig Beech (Global Marine Systems Ltd.), Peter Christian (Global Marine Systems Ltd.) Email: craig.beech@globalmarinesystems.com

More information

TRANSMISSION ENGINEERING STANDARD TES-P , Rev. 0 TABLE OF CONTENTS 1.0 SCOPE 2.0 CABLES SPLICES

TRANSMISSION ENGINEERING STANDARD TES-P , Rev. 0 TABLE OF CONTENTS 1.0 SCOPE 2.0 CABLES SPLICES 1.0 SCOPE TABLE OF CONTENTS 2.0 CABLES SPLICES 2.1 Definitions 2.2 Scope of Specifications and Drawings 2.3 General Requirements 2.4 Routing Cables 2.5 Connectors 2.6 Conductor Connections 2.7 Heat Shrinkable

More information

CLP s first 400kV XLPE cable application

CLP s first 400kV XLPE cable application CLP s first 400kV XLPE cable application Chris Cheung CLP Power Hong Kong Limited 9 October 2017 Information Classification : PROPRIETARY Information Classification : PROPRIETARY Project Requirement Due

More information

EE028: Practical High Voltage Cable Jointing and Termination

EE028: Practical High Voltage Cable Jointing and Termination EE028: Practical High Voltage Cable Jointing and Termination EE028 Rev.001 CMCT COURSE OUTLINE Page 1 of 5 Training Description: The range of voltage and capacity of power transmitted through cables is

More information

Diagnostic & Testing Services

Diagnostic & Testing Services Diagnostic & Testing Services Diagnostic & Testing Services Prysmian Cables & System B.V., based in Delft, the Netherlands, provides a full spectrum of pre and post sales services for its customers, including

More information

MESP TECHNICAL SPECIFICATION FOR ELECTRIC CABLE 400mm 2 ALUMINIUM CONDUCTOR 1.9kV XLPE INSULATED WITHOUT METALLIC SCREEN

MESP TECHNICAL SPECIFICATION FOR ELECTRIC CABLE 400mm 2 ALUMINIUM CONDUCTOR 1.9kV XLPE INSULATED WITHOUT METALLIC SCREEN Engineering Specification Electrical Networks MESP 030000-02 TECHNICAL SPECIFICATION FOR ELECTRIC CABLE 400mm 2 ALUMINIUM CONDUCTOR 1.9kV XLPE INSULATED Version: 1 Issued: March 2014 Owner: Electrical

More information

High Temperature Operation of Extruded Distribution Cable Systems. White Paper

High Temperature Operation of Extruded Distribution Cable Systems. White Paper High Temperature Operation of Extruded Distribution Cable Systems White Paper October 2018 NOTICE The information contained herein is, to our knowledge, accurate and reliable at the date of publication.

More information

Trends and Challenges of HV Cable Systems

Trends and Challenges of HV Cable Systems Trends and Challenges of HV Cable Systems Bruno Arnold Electrical Engineer FH Global Sales Far East, Latin America and India Pfisterer Business Unit PTS Cable Trends and Challenges of HV Cable Systems

More information

ANALYSIS OF FAILURE IN POWER CABLES FOR PREVENTING POWER OUTAGE IN ALEXANDRIA ELECTRICITY DISTRIBUTION COMPANY IN EGYPT

ANALYSIS OF FAILURE IN POWER CABLES FOR PREVENTING POWER OUTAGE IN ALEXANDRIA ELECTRICITY DISTRIBUTION COMPANY IN EGYPT 24 th International Conference on Electricity Distribution Glasgow, 2- June 27 Paper 89 ANALYSIS OF FAILURE IN POWER CABLES FOR PREVENTING POWER OUTAGE IN ALEXANDRIA ELECTRICITY DISTRIBUTION COMPANY IN

More information

TERMINATIONS AND JOINTS FOR XLPE-INSULATED kv MEDIUM VOLTAGE CABLES

TERMINATIONS AND JOINTS FOR XLPE-INSULATED kv MEDIUM VOLTAGE CABLES Accessories TERMINATIONS AND JOINTS FOR XLPE-INSULATED 12 36 kv MEDIUM VOLTAGE CABLES Cable Systems, Cables and Accessories Test values for terminations 1) Testing to DIN VDE 0278-629-1 (Testing methods

More information

INSTRUCTION DE SÉCURITÉ SAFETY INSTRUCTION Mandatory as defined in SAPOCO/42 FIRE PREVENTION FOR CABLES, CABLE TRAYS AND CONDUITS

INSTRUCTION DE SÉCURITÉ SAFETY INSTRUCTION Mandatory as defined in SAPOCO/42 FIRE PREVENTION FOR CABLES, CABLE TRAYS AND CONDUITS CERN INSTRUCTION DE SÉCURITÉ SAFETY INSTRUCTION Mandatory as defined in SAPOCO/42 Edms 335813 TIS IS 48 Edited by: TIS/GS Publication Date: June 2001 Original: English FIRE PREVENTION FOR CABLES, CABLE

More information

Condition Monitoring Program of HV Cable Systems

Condition Monitoring Program of HV Cable Systems Condition Monitoring Program of HV Cable Systems Mrs. Heena Sharma 1, Mr.M.T.Deshpande 2 and Mr. Rahul Pandey 3 1 M.E(Power System) student, Department of Electrical and Electronics Engineering, SSTC Junwani,Bhilai,CSVTU,

More information

CHAPTER 3. HV and EHV Cable System Aging and Testing Issues

CHAPTER 3. HV and EHV Cable System Aging and Testing Issues CHAPTER 3 HV and EHV Cable System Aging and Testing Issues Nigel Hampton 3-1 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES This document was prepared by Board of Regents of the University System

More information

APPLICATION OF POWER SWITCHING FOR ALTERNATIVE LAND CABLE PROTECTION BETWEEN CABLE LANDING STATION AND BEACH MAN HOLE IN SUBMARINE NETWORKS

APPLICATION OF POWER SWITCHING FOR ALTERNATIVE LAND CABLE PROTECTION BETWEEN CABLE LANDING STATION AND BEACH MAN HOLE IN SUBMARINE NETWORKS APPLICATION OF POWER SWITCHING FOR ALTERNATIVE LAND PROTECTION BETWEEN LANDING STATION AND BEACH MAN HOLE IN SUBMARINE NETWORKS Liyuan Shi (Huawei Marine Networks) Email: Huawei

More information

HVDC DEVELOPMENT OPTIONS CABLE CAPACITY 27 June 2005

HVDC DEVELOPMENT OPTIONS CABLE CAPACITY 27 June 2005 HVDC DEVELOPMENT OPTIONS CABLE CAPACITY 27 June 2005 1.0 Introduction This paper summarizes the issues which may be relevant when considering the need or otherwise to provide spare submarine cable capacity.

More information

System solutions: Partial discharge measurement and monitoring systems.

System solutions: Partial discharge measurement and monitoring systems. System solutions: Partial discharge measurement and monitoring systems. Australia Pty Ltd www.cablegrid.com.au A potential need. An increasing number of users consider additional tests and surveying of

More information

Recovering and Relaying Cables

Recovering and Relaying Cables Upgrades Edition 79 Recovering and Relaying Cables For Building New Subsea Systems Bertrand Clesca Why Cable Relay? With the prevalence of submarine cable systems in international communications, two trends

More information

POLICY & APPLICATION GUIDE FOR 11kV POLYMERIC CABLES

POLICY & APPLICATION GUIDE FOR 11kV POLYMERIC CABLES 1. SCOPE This document provides information and guidance on the application of polymeric cables on the SPEN 11kV network. Throughout this document, references to 11kV shall by inference also relate to

More information

ELECTRICAL SAFETY INSPECTION REPORT. MTM Garments Ltd.

ELECTRICAL SAFETY INSPECTION REPORT. MTM Garments Ltd. ELECTRICAL SAFETY INSPECTION REPORT MTM Garments Ltd. 15934/16004, Chanpara, Medical Road, Uttarkhan, Dhaka, Bangladesh. Factory List MTM Garments Ltd. Inspected by: Hemlal Dahal Report Generated by: Hemlal

More information

Innovative Rotary Encoders Deliver Durability and Precision without Tradeoffs. By: Jeff Smoot, CUI Inc

Innovative Rotary Encoders Deliver Durability and Precision without Tradeoffs. By: Jeff Smoot, CUI Inc Innovative Rotary Encoders Deliver Durability and Precision without Tradeoffs By: Jeff Smoot, CUI Inc Rotary encoders provide critical information about the position of motor shafts and thus also their

More information

Power and Control T YPE BY RAVI GANATR November/December IAEI NEWS

Power and Control T YPE BY RAVI GANATR November/December IAEI NEWS Power and Control 26 1999 November/December IAEI NEWS T YPE BY RAVI GANATR This article discusses how the requirements in both the installation code and the product standard are utilized to manufacture

More information

Cable installation guidelines

Cable installation guidelines The Quality Connection Cable installation guidelines Business Unit Industrial Projects 2 Cable installation guidelines www.leoni-industrial-projects.com GENERAL Installation methods Many different methods

More information

Aging test: integrated vs. non-integrated splices shield continuity systems.

Aging test: integrated vs. non-integrated splices shield continuity systems. Aging test: integrated vs. non-integrated splices shield continuity systems. George Fofeldea Power Engineer, 3M Canada November 2018 Abstract To maximize long-term splice performance, the implications

More information

Colour Explosion Proof Video Camera USER MANUAL VID-C

Colour Explosion Proof Video Camera USER MANUAL VID-C Colour Explosion Proof Video Camera USER MANUAL VID-C Part Number: MAN-0036-00 Rev 4 Copyright 2002 Net Safety Monitoring Inc. Printed in Canada This manual is provided for informational purposes only.

More information

On-Line Monitoring of Cable Trench and Cable Pit by Using Metal Armored FBG Temperature Sensors

On-Line Monitoring of Cable Trench and Cable Pit by Using Metal Armored FBG Temperature Sensors International Journal of Smart Grid and Clean Energy On-Line Monitoring of Cable Trench and Cable Pit by Using Metal Armored FBG Temperature Sensors Zhen Wang a,c, Min Cao b, Da-Da Wang b, Shao-Quan Zhang

More information

Selecting the correct cable type for Outside Plant Application

Selecting the correct cable type for Outside Plant Application Application Notes Selecting the correct cable type for Outside Plant Application Issued December 2012 Abstract Organized selection methodology of optical cable for a specific application is important.

More information

How to Implement PoE in Your Harsh Industrial Environment

How to Implement PoE in Your Harsh Industrial Environment Produced by: Engineering 360 Media Solutions July 2018 How to Implement PoE in Your Harsh Industrial Environment Sponsored by: Quabbin Wire & Cable Co., Inc. There is little doubt that the internet of

More information

Medium Voltage 12/20 (24)kV NF C cable system. Xavier Brosse Luanda May 2009

Medium Voltage 12/20 (24)kV NF C cable system. Xavier Brosse Luanda May 2009 Medium Voltage 12/20 (24)kV NF C 33-226 cable system Xavier Brosse Luanda May 2009 1 Evolution of French standard for MV cables Late 70 s : NF C 33-223 Cable Standard in France result of the move from

More information

C I R E D 19 th International Conference on Electricity Distribution Vienna, May Transition Joints Behaviour. Paper 457 INTRODUCTION

C I R E D 19 th International Conference on Electricity Distribution Vienna, May Transition Joints Behaviour. Paper 457 INTRODUCTION DIAGNOSI FOR ABLE SYSEM ASSE MANAGEMEN AND PREVENIVE MAINENANE A EDF hierry ESPILI Fabrice ZORZI Roger AMBRUN EDF R&D France EDF R&D France EDF EGD - France thierry.espilit@edf.fr fabrice.zorzi@edf.fr

More information

from ocean to cloud ADAPTING THE C&A PROCESS FOR COHERENT TECHNOLOGY

from ocean to cloud ADAPTING THE C&A PROCESS FOR COHERENT TECHNOLOGY ADAPTING THE C&A PROCESS FOR COHERENT TECHNOLOGY Peter Booi (Verizon), Jamie Gaudette (Ciena Corporation), and Mark André (France Telecom Orange) Email: Peter.Booi@nl.verizon.com Verizon, 123 H.J.E. Wenckebachweg,

More information

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala) 2 Work Package and Work Unit descriptions 2.8 WP8: RF Systems (R. Ruber, Uppsala) The RF systems work package (WP) addresses the design and development of the RF power generation, control and distribution

More information

High Voltage Cables kv. Handling and Operating Instructions

High Voltage Cables kv. Handling and Operating Instructions High Voltage Cables 52 145 kv Handling and Operating Instructions 1 (24) HANDLING AND OPERATING DRYREX High voltage cables 52 145 kv Contents Scope of application...3 General...3 Professional skills, tools

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT A PLUS INDUSTRIES LIMITED. Plot-28, Milk Vita Rd., Section-07, Mirpur, Dhaka Factory List: 1. A Plus Industries Ltd. Inspected by: Yoon Report Generated by: Nezar Inspected

More information

LED MODULES READYLINE DL

LED MODULES READYLINE DL LED MODULES READYLINE DL BUILT-IN MODULE LED-MODULE READYLINE DOWNLIGHT DL WU-M-538 / WU-M-539 / WU-M-540 Typical Applications Downlights Replacement for CFL DIRECT MAINS CONNECTION REDUCED FLICKER HIGH

More information

HYL-080D1750G358. Constant current LED driver DALI Dimmable. LED Driver. Product description. Benefits. Interfaces.

HYL-080D1750G358. Constant current LED driver DALI Dimmable. LED Driver.   Product description. Benefits. Interfaces. Linear / area dimming Constant current LED driver DALI Dimmable Product description Dimmable built-in constant current LED Driver Adjustable output current between 1,050 and 1,750mA via DIP switch Max.

More information

SECTION MEDIUM VOLTAGE CABLE INSTALLATION. 1. Section Underground Ducts and Manholes.

SECTION MEDIUM VOLTAGE CABLE INSTALLATION. 1. Section Underground Ducts and Manholes. SECTION 33 71 49.23 MEDIUM VOLTAGE CABLE INSTALLATION PART 1 GENERAL 1.1 SCOPE A. Work included in this Section: Medium Voltage Cable (4 kv and 12 kv) Installation and Termination. Removal and return of

More information

Special Specification 6293 Adaptive Traffic Signal Control System

Special Specification 6293 Adaptive Traffic Signal Control System Special Specification Adaptive Traffic Signal Control System 1. DESCRIPTION 2. MATERIALS Furnish, install, relocate, or remove adaptive traffic signal control (ATSC) system software and equipment at locations

More information

INSULATION CONDITION OF DRY-CURED XLPE CABLES MEASURED OVER A PERIOD OF 13 YEARS

INSULATION CONDITION OF DRY-CURED XLPE CABLES MEASURED OVER A PERIOD OF 13 YEARS 2 rd International Conference on Electricity Distribution Lyon, -8 June Paper 47 INSULATION CONDITION OF DRY-CURED XLPE CABLES MEASURED OVER A PERIOD OF YEARS ABSTRACT Jens Zoëga HANSEN Danish Energy Association

More information

TRANSMISSION ENGINEERING STANDARD TES-P , Rev. 0 TABLE OF CONTENTS 1.0 PURPOSE 2.0 SCOPE 3.0 CODES, STANDARDS AND REFERENCES

TRANSMISSION ENGINEERING STANDARD TES-P , Rev. 0 TABLE OF CONTENTS 1.0 PURPOSE 2.0 SCOPE 3.0 CODES, STANDARDS AND REFERENCES TABLE OF CONTENTS 1.0 PURPOSE 2.0 SCOPE 3.0 CODES, STANDARDS AND REFERENCES 4.0 ORDER OF PRECEDENCE 5.0 SYSTEM PARAMETERS 5.1 Frequency 5.2 System Voltage 5.3 Short Circuit Rating 5.4 Insulation Levels

More information

Emerging Subsea Networks

Emerging Subsea Networks THE CHALLENGES OF COMPLETING AN OIL & GAS CABLE SYSTEM ORDER Jerry Brown, Rendong Xu, Guilin Sun, Lei Zhang, Changji Hao, Xiong Wang, Hongli Qu, Di Wu, Fu Feng, Yin Jiang (Hengtong Marine Cable Systems)

More information

AMERICAN NATIONAL STANDARD

AMERICAN NATIONAL STANDARD ENGINEERING COMMITTEE Interface Practices Subcommittee AMERICAN NATIONAL STANDARD ANSI/SCTE 153 2008 Drop Passives: Splitters, Couplers and Power Inserters NOTICE The Society of Cable Telecommunications

More information

B DOUBLE 150 kv LINK, 32 km LONG, IN BELGIUM : DESIGN AND CONSTRUCTION. (Belgium)

B DOUBLE 150 kv LINK, 32 km LONG, IN BELGIUM : DESIGN AND CONSTRUCTION. (Belgium) , rue d'artois, F-75008 Paris http://www.cigre.org B-05 Session 004 CIGRÉ DOUBLE 50 kv LINK, km LONG, IN BELGIUM : DESIGN AND CONSTRUCTION A. Gille *, V. Beghin G. Geerts, J. Hoeffelman D. Liémans, K.

More information

Jul03 Rev C EC

Jul03 Rev C EC Product Specification Coaxial BNC Solder Receptacle Connector 108-12079 10Jul03 Rev C EC 0990-0940-03 1. SCOPE 1.1. Content This specification covers the performance, tests and quality requirements for

More information

Sharif University of Technology. SoC: Introduction

Sharif University of Technology. SoC: Introduction SoC Design Lecture 1: Introduction Shaahin Hessabi Department of Computer Engineering System-on-Chip System: a set of related parts that act as a whole to achieve a given goal. A system is a set of interacting

More information

Innovation in Magnetic Measuring Instruments. Operation Manual for. Mag648 and Mag649 Low Power Three-Axis Magnetic Field Sensors.

Innovation in Magnetic Measuring Instruments. Operation Manual for. Mag648 and Mag649 Low Power Three-Axis Magnetic Field Sensors. Innovation in Magnetic Measuring Instruments Operation Manual for Mag648 and Mag649 Low Power Three-Axis Magnetic Field Sensors www.bartington.com Table of Contents 1. Legal notices 3 1.1. Copyright 3

More information

M4000 Diagnostic Test System For Power Apparatus Condition Assessment

M4000 Diagnostic Test System For Power Apparatus Condition Assessment Knowledge Is Power SM The World Leader in Diagnostic Test Instruments and Knowledge Services for Electric Power M4000 Diagnostic Test System For Power Apparatus Condition Assessment The world s most advanced

More information

Installation Manual IPT Installation of skillet systems with 125 A track current. MV a-E.

Installation Manual IPT Installation of skillet systems with 125 A track current. MV a-E. www.wampfler.com Page 1 of 27 Index Page 1 Basics...4 2 Basic understanding of an IPT -system...5 3 General rules regarding metal parts in close proximity...6 3.1 Envelope free of ferromagnetic material...6

More information

-Technical Specifications-

-Technical Specifications- Annex I to Contract 108733 NL-Petten: the delivery, installation, warranty and maintenance of one (1) X-ray computed tomography system at the JRC-IET -Technical Specifications- INTRODUCTION In the 7th

More information

I r A Protection against direct contact Finger and back of hand proof to VDE 0106 Part 100

I r A Protection against direct contact Finger and back of hand proof to VDE 0106 Part 100 DATASHEET - NZMH2-A100 Circuit-breaker, 3p, 100A Part no. NZMH2-A100 Catalog No. 259099 Similar to illustration Delivery program Product range Circuit-breaker Protective function System and cable protection

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT A & B OUTERWEAR LTD. Plot # 29-30, CEPZ, Chittagong, Bangladesh. Factory List: 1. Inspected by: Al-Amin Report Generated by: Al-Amin Inspected on March 7 th 2015 SUMMARY

More information

Underground Cable Diagnostic Testing Utilizing Partial Discharge Technique

Underground Cable Diagnostic Testing Utilizing Partial Discharge Technique Underground Cable Diagnostic Testing Utilizing Partial Discharge Technique (An Update to the April 29, 2001 Report) Potomac Electric Power Company Reliability Services (Asset Management) Mostafa Hassani,

More information

KRF EMC Filters Installation, Operation and Maintenance Manual

KRF EMC Filters Installation, Operation and Maintenance Manual KRF EMC Filters Installation, Operation and Maintenance Manual KRF EMC Filters limit high frequency noise, as well as: Reduce interference Protect sensitive equipment Eliminate drive cross-talk Meet FCC

More information

Description Set value in neutral conductor is synchronous with set value Ir of main pole. R.m.s. value measurement and thermal memory CSA 100

Description Set value in neutral conductor is synchronous with set value Ir of main pole. R.m.s. value measurement and thermal memory CSA 100 DATASHEET - NZMN3-4-AE400 Circuit-breaker, 4p, 400A Part no. NZMN3-4-AE400 Catalog No. 265891 Similar to illustration EL-Nummer (Norway) 0004358857 Delivery program Product range Circuit-breaker Protective

More information

HYL-035D0850G103. Constant current LED driver DALI Dimmable. LED Driver. Product description. Benefits. Interfaces.

HYL-035D0850G103. Constant current LED driver DALI Dimmable. LED Driver.   Product description. Benefits. Interfaces. Constant current LED driver DALI Dimmable Product description Dimmable Independent constant current Adjustable output current between 350 and 1,050mA via DIP switch Max. output power 35 W Up to 88 % efficiency

More information

Design for Testability

Design for Testability TDTS 01 Lecture 9 Design for Testability Zebo Peng Embedded Systems Laboratory IDA, Linköping University Lecture 9 The test problems Fault modeling Design for testability techniques Zebo Peng, IDA, LiTH

More information

Media Kit. Print & Digital. Best view in desktops & laptops Last update: November, 2016

Media Kit. Print & Digital. Best view in desktops & laptops Last update: November, 2016 2017 Media Kit Print & Digital Best view in desktops & laptops Last update: November, 2016 about about INMR INMR surge arresters, bushings and cable accessories, as well as inspection equipment & laboratory

More information

Lt DELTA USA, Inc

Lt DELTA USA, Inc Infrared LOOP SCANNER Rota-Sonde TS2006 Infrared - high sensitivity 480 F or 750 F Quick and easy commissioning Self-monitoring and alarm functions Lt 1037 1 Applications R o t a - S o n d e TS2 0 0 6

More information

Re-defining the utility-scale inverter

Re-defining the utility-scale inverter Re-defining the utility-scale inverter We believe in green energy in the ability to meet and contribute to growing power demand while supporting a smart grid that serves a smart society. Solution at a

More information

I r A Protection against direct contact Finger and back of hand proof to VDE 0106 Part 100

I r A Protection against direct contact Finger and back of hand proof to VDE 0106 Part 100 DATASHEET - NZMC1-A160 Circuit-breaker, 3p, 160A Part no. NZMC1-A160 Catalog No. 283296 Similar to illustration Delivery program Product range Circuit-breaker Protective function System and cable protection

More information

Mitigation of Cascading Outages and Prevention of Blackouts:System-Wide Corrective Control

Mitigation of Cascading Outages and Prevention of Blackouts:System-Wide Corrective Control 10th Mediterranean Conference on Power Generation, Transmission, Distribution and Energy Conversion 6-9 November 2016 Belgrade, Serbia Mitigation of Cascading Outages and Prevention of Blackouts:System-Wide

More information

Fieldbus Testing with Online Physical Layer Diagnostics

Fieldbus Testing with Online Physical Layer Diagnostics Technical White Paper Fieldbus Testing with Online Physical Layer Diagnostics The significant benefits realized by the latest fully automated fieldbus construction & pre-commissioning hardware, software

More information

Catalogue Ignitors and power switches for HID

Catalogue Ignitors and power switches for HID Catalogue 2012 Ignitors and power switches for HID Overview Product overview Ignitor matrix Standards Page 6 Page 7 Page 8 Product information Ignitors and power switches for HID Page 9 Superimposed-pulse

More information

Projectors EFFORTS FOR PROJECTOR QUALITY

Projectors EFFORTS FOR PROJECTOR QUALITY Projectors EFFORTS FOR PROJECTOR QUALITY Projectors require a strong power of expression to build effective communication in business. We envision all circumstances from a wide range of installation methods

More information

Protective function Systems, cable, selectivity and generator protection. i 2 t constant function: switchable. I r A

Protective function Systems, cable, selectivity and generator protection. i 2 t constant function: switchable. I r A DATASHEET - NZMN3-VE630 Circuit-breaker, 3p, 630A Part no. NZMN3-VE630 Catalog No. 259133 EL-Nummer (Norway) 0004358791 Similar to illustration Delivery program Product range Circuit-breaker Protective

More information

Aerial Cable Installation Best Practices

Aerial Cable Installation Best Practices Aerial Cable Installation Best Practices Panduit Corp. 2007 BEST PRACTICES Table of Contents 1.0 General... 3 2.0 Introduction... 3 3.0 Precautions... 4 4.0 Pre-survey... 5 5.0 Materials and Equipment...

More information

ADS Basic Automation solutions for the lighting industry

ADS Basic Automation solutions for the lighting industry ADS Basic Automation solutions for the lighting industry Rethinking productivity means continuously making full use of all opportunities. The increasing intensity of the competition, saturated markets,

More information

Gigabit Multi-mode SX to Single Mode LX Converter. User s Manual NGF-728 Series. Warning COPYRIGHT

Gigabit Multi-mode SX to Single Mode LX Converter. User s Manual NGF-728 Series. Warning COPYRIGHT COPYRIGHT Gigabit Multi-mode SX to Single Mode LX Converter User s Manual NGF-728 Series All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted

More information

Drop Passives: Splitters, Couplers and Power Inserters

Drop Passives: Splitters, Couplers and Power Inserters ENGINEERING COMMITTEE Interface Practices Subcommittee AMERICAN NATIONAL STANDARD ANSI/SCTE 153 2016 Drop Passives: Splitters, Couplers and Power Inserters NOTICE The Society of Cable Telecommunications

More information

AMERICAN NATIONAL STANDARD

AMERICAN NATIONAL STANDARD Interface Practices Subcommittee AMERICAN NATIONAL STANDARD ANSI/SCTE 129 2017 Drop Passives: Bonding Blocks (Without Surge Protection) NOTICE The Society of Cable Telecommunications Engineers (SCTE) Standards

More information

Real-time QC in HCHP seismic acquisition Ning Hongxiao, Wei Guowei and Wang Qiucheng, BGP, CNPC

Real-time QC in HCHP seismic acquisition Ning Hongxiao, Wei Guowei and Wang Qiucheng, BGP, CNPC Chengdu China Ning Hongxiao, Wei Guowei and Wang Qiucheng, BGP, CNPC Summary High channel count and high productivity bring huge challenges to the QC activities in the high-density and high-productivity

More information

GE Interlogix Fiber Options S700V & S702V. Instruction Manual FIBER-OPTIC VIDEO TRANSMISSION SYSTEM

GE Interlogix Fiber Options S700V & S702V. Instruction Manual FIBER-OPTIC VIDEO TRANSMISSION SYSTEM g GE Interlogix Fiber Options Instruction Manual S700V & S702V FIBER-OPTIC VIDEO TRANSMISSION SYSTEM Federal Communications Commission and Industry Canada Radio Frequency Interference Statements This equipment

More information

HD/SD-SDI Over Fiber Transmitter and Receiver Extender Kit. User Manual L-1SDI-SFE-TX/RX

HD/SD-SDI Over Fiber Transmitter and Receiver Extender Kit. User Manual L-1SDI-SFE-TX/RX HD/SD-SDI Over Fiber Transmitter and Receiver Extender Kit User Manual L-1SDI-SFE-TX/RX Table of Contents Table of Contents---------------------------------------------------------------------------------1

More information

Generator protection relay

Generator protection relay Page 1 Issued: April 1999 Status: New Data subject to change without notice Features Off-the-shelf generator protection relay for small and medium sized power generators Three-phase time overcurrent and

More information

AMERICAN NATIONAL STANDARD

AMERICAN NATIONAL STANDARD Interface Practices Subcommittee AMERICAN NATIONAL STANDARD ANSI/SCTE 108 2018 Test Method for Dielectric Withstand of Coaxial Cable NOTICE The Society of Cable Telecommunications Engineers (SCTE) / International

More information

A New 4MW LHCD System for EAST

A New 4MW LHCD System for EAST 1 EXW/P7-29 A New 4MW LHCD System for EAST Jiafang SHAN 1), Yong YANG 1), Fukun LIU 1), Lianmin ZHAO 1) and LHCD Team 1) 1) Institute of Plasma Physics, Chinese Academy of Sciences, Hefei, China E-mail

More information

SINAMICS G130. dv/dt filter plus Voltage Peak Limiter. Operating Instructions 03/2013 SINAMICS

SINAMICS G130. dv/dt filter plus Voltage Peak Limiter. Operating Instructions 03/2013 SINAMICS SINAMICS G130 Operating Instructions 03/2013 SINAMICS s dv/dt filter plus Voltage Peak Limiter Safety information 1 General 2 SINAMICS SINAMICS G130 Operating Instructions Mechanical installation 3 Electrical

More information

Gamma instabus. Technical product information

Gamma instabus. Technical product information Gamma instabus Technical product information Universal dimmer N 554D31, 4 x 300 VA / 1x 1000 VA, AC 230 V Universal dimmer N 554D31 Control of dimmable lamps, including LED without minimum load Output

More information

THE NEW LASER FAMILY FOR FINE WELDING FROM FIBER LASERS TO PULSED YAG LASERS

THE NEW LASER FAMILY FOR FINE WELDING FROM FIBER LASERS TO PULSED YAG LASERS FOCUS ON FINE SOLUTIONS THE NEW LASER FAMILY FOR FINE WELDING FROM FIBER LASERS TO PULSED YAG LASERS Welding lasers from ROFIN ROFIN s laser sources for welding satisfy all criteria for the optimized laser

More information

GA A26497 SOLID-STATE HIGH-VOLTAGE CROWBAR UTILIZING SERIES-CONNECTED THYRISTORS

GA A26497 SOLID-STATE HIGH-VOLTAGE CROWBAR UTILIZING SERIES-CONNECTED THYRISTORS GA A26497 SOLID-STATE HIGH-VOLTAGE CROWBAR by J.F. Tooker, P. Huynh, and R.W. Street JUNE 2009 DISCLAIMER This report was prepared as an account of work sponsored by an agency of the United States Government.

More information

CABLE CLEAT FAQs. Engineering Series. 1. What is a cable cleat?

CABLE CLEAT FAQs. Engineering Series. 1. What is a cable cleat? 1. What is a cable cleat? A cable cleat is a cable restraint device (e.g. cable clamp) that is designed and tested to provide securing and retention of cables when installed at intervals along the length

More information

BTC and SMT Rework Challenges

BTC and SMT Rework Challenges BTC and SMT Rework Challenges Joerg Nolte Ersa GmbH Wertheim, Germany Abstract Rising customer demands in the field of PCB repair are a daily occurrence as the rapid electronic industry follows new trends

More information

SCHEDA TECNICA. Amarro per cavi 13,5mm Amarro per cavi 16,5mm. MS217F00 Amarro per cavi 13,5mm MS218F00 Amarro per cavi 16,5mm

SCHEDA TECNICA. Amarro per cavi 13,5mm Amarro per cavi 16,5mm. MS217F00 Amarro per cavi 13,5mm MS218F00 Amarro per cavi 16,5mm SCHEDA TECNICA Amarro per cavi 13,5mm Amarro per cavi 16,5mm Material: Galvanized steel MS217F00 Amarro per cavi 13,5mm MS218F00 Amarro per cavi 16,5mm For cable 13,5mm For cable 16,5mm 3. Weight The weight

More information

I/A Series Hardware Fiber Optic LAN Converter

I/A Series Hardware Fiber Optic LAN Converter I/A Series Hardware PSS 21H-7F3 B4 The provides bidirectional conversion between coaxial and fiber optic media. The converter is compatible with existing I/A Series system hardware, utilizes industry standard

More information

ACADEMIC SUCCESS CENTER THE COLLEGE AT BROCKPORT STATE UNIVERSITY OF NEW YORK PROJECT NO

ACADEMIC SUCCESS CENTER THE COLLEGE AT BROCKPORT STATE UNIVERSITY OF NEW YORK PROJECT NO SECTION 270536 - CABLE TRAYS FOR COMMUNICATIONS SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

SnapStak Stackable Snap-In Cable Hanger Electrical and Mechanical Testing Performance

SnapStak Stackable Snap-In Cable Hanger Electrical and Mechanical Testing Performance SnapStak Stackable Snap-In Cable Hanger Electrical and Mechanical Testing Performance Table of Contents Introduction................................1 Axial pull test and horizontal shear test............2

More information

DEVELOPMENT OF A 270 kv XLPE CABLE SYSTEM FOR HVDC APPLICATION

DEVELOPMENT OF A 270 kv XLPE CABLE SYSTEM FOR HVDC APPLICATION DEVELOPMENT OF A 270 kv XLPE CABLE SYSTEM FOR HVDC APPLICATION Mohamed MAMMERI, Marie Laure PAUPARDIN, Bernard POISSON, Silec Cable, Montereau, France, mohamed.mammeri@sileccable.com,marie-laure.paupardin@sileccable.com,

More information

Agilent N9355/6 Power Limiters 0.01 to 18, 26.5 and 50 GHz

Agilent N9355/6 Power Limiters 0.01 to 18, 26.5 and 50 GHz Agilent N9355/6 Power Limiters 0.01 to 18, 26.5 and 50 GHz Technical Overview High Performance Power Limiters Broad frequency range up to 50 GHz maximizes the operating range of your instrument High power

More information

Children cannot always recognize potential hazards properly. This 5.1 system is not designed for operation in a heavy industry environment.

Children cannot always recognize potential hazards properly. This 5.1 system is not designed for operation in a heavy industry environment. 5.1 FLAT PANEL SPEAKER SYSTEM WITH POWERED SUBWOOFER Table of Contents: SAFETY AND SERVICE... 2 Operational Safety... 2 Location... 2 Ambient Temperature... 3 Electromagnetic Compliance... 3 Service...

More information

LED Driver Linear / area dimming industry. Driver LC 200W 1050mA UNV ADV IND ADVANCED series

LED Driver Linear / area dimming industry. Driver LC 200W 1050mA UNV ADV IND ADVANCED series Driver LC 200W 1050mA UNV ADV IND ADVANCED series Product description Independent constant current LED Driver For dry, damp and wet locations Max. output power 200 W Up to 93.7 % efficiency For luminaires

More information

NZQA unit standard version 3 Page 1 of 7. Demonstrate knowledge of telecommunications cable systems

NZQA unit standard version 3 Page 1 of 7. Demonstrate knowledge of telecommunications cable systems Page 1 of 7 Title Demonstrate knowledge of telecommunications cable systems Level 4 Credits 20 Purpose This unit standard covers underpinning knowledge necessary for technicians employed in installation

More information

Instructions for Use P.154-UP (9/4) P.155-UP (9/8) P.150-UP-12 (9/12) P.150-UP-16 (9/16)

Instructions for Use P.154-UP (9/4) P.155-UP (9/8) P.150-UP-12 (9/12) P.150-UP-16 (9/16) Satellite multiswitch Instructions for Use P.154-UP (9/4) P.155-UP (9/8) P.150-UP-12 (9/12) P.150-UP-16 (9/16) EMP-CENTAURI is a registered trademark Dear Customer, Thank you for buying the EMP-Centauri

More information