MASTERCLASS TUTORIAL 4 The Thin Route Environment. John Hibbard (Hibbard Consulting) Maja Summers (Apollo SCS)

Similar documents
The Emergence of Affordable Broadband Services for Remote Locations Using SFOC Technology Dr. William J. Barattino Mr. Nicholas Koopalethes

Recovering and Relaying Cables

Aspects of Submarine Cable Retirement

ITU/PITA Workshop on Submarine Cable Access in the Pacific Islands Countries Holiday Inn Hotel, Suva, Fiji, 31 July-3 August 2017

Working Group on Extending the life of Submarine Cable Systems

The DTH teleport - challenges and opportunities

USO OFCOM Consultation Comments

RFO RF VIDEO EXTENDER REACH FARTHER, SPEND LESS EXTEND YOUR RF OVERLAY COVERAGE WITH A LOW COST SOLUTION

INTERNATIONAL TELECOMMUNICATION UNION DIGITAL SECTIONS AND DIGITAL LINE SYSTEMS DEFINITION OF TERMS RELEVANT TO OPTICAL FIBRE SUBMARINE CABLE SYSTEMS

Australian Broadcasting Corporation Submission Digital Conversion of Self-Help Television Retransmission Sites

Microwave Backhaul Solutions SUPER HIGH PERFORMANCE ANTENNAS. Not just a new backhaul solution a whole new backhaul strategy

CASE STUDY. Smart Motorways Project. Temporary CCTV Monitoring Systems for England s Motorway network.

No monopoly for High Throughput Satellite (HTS) services at sea

COMMISSIONING AND ACCEPTANCE

The long term future of UHF spectrum

COE Group plc. Contents

DTH. Direct-to-Home SOLUTION GUIDE. How to maintain quality and availability while going for profitability.

Satellite Technology Products and services Overview

Datasheet. Licensed Backhaul Radio. Models: AF-11FX-L, AF-11FX-H. Full-Duplex, Point-to-Point Radio. 11 GHz Frequency Operation

REFURBISHMENT OF SECONDARY SYSTEMS IN HIGH VOLTAGE SUBSTATIONS LESSONS LEARNED IN VENEZUELA

Impacts on Cable HFC Networks

COMMUNICATIONS OUTLOOK 1999

Intelsat-29e Interference Mitigation Testing Interference Scenarios and Mitigation Techniques Enabled by the Intelsat Epic NG Class Satellites

The Future of Satellites. Alex Epshteyn Senior Principal Regulatory Engineer

The Satellite Communications Perspective in Pacific Island Countries

Annex J: Outline for Bhutan DTV Road Map

2. SUPERPATH Mbps Digital Service 2.1. General

KANZ BROADBAND SUMMIT DIGITAL MEDIA OPPORTUNITIES DIGITAL CONTENT INITIATIVES Kim Dalton Director of Television ABC 3 November 2009

How to Specify MTP Pre-terminated Optical Cabling. January White Paper. Published

Submission to the Australian Communications and Media Authority Earth Station Siting discussion paper. 21 October 2011

SATELLITE DEVELOPMENT in TONGA. TONGA Country Presentation. Keith Moala (Chief Engineer, MEIDECC, Government of Tonga)

VNP 100 application note: At home Production Workflow, REMI

White Paper. Fibre Optic Technologies for Satellite Communication and Broadcast Industries. By Tom Lacey Applications Engineering Group PPM Ltd, UK

Intelsat-29e Interference Mitigation Testing. Interference Scenarios and Mitigation Techniques Enabled by the Intelsat Epic NG Class Satellites

Before the FEDERAL COMMUNICATIONS COMMISSION Washington, DC 20554

Fronthaul solutions

Canada Gazette, Part I, December 18, 2014, Notice No. SLPB Consultation on Repurposing the 600 MHz Band Eastlink s reply comments

John Stankey President and CEO AT&T Operations

Technology Advances. Ashaad Rambharos CSE Intelsat Africa

Aqua Turf International, Inc.

APPLICATION OF POWER SWITCHING FOR ALTERNATIVE LAND CABLE PROTECTION BETWEEN CABLE LANDING STATION AND BEACH MAN HOLE IN SUBMARINE NETWORKS

THE FUTURE OF NARROWCAST INSERTION. White Paper

MARGINS ON SUBMARINE SYSTEMS

International Civil Aviation Organization METEOROLOGY PANEL (METP) FIRST MEETING. Montréal, Canada, 20 to 24 April 2015

Reduction of operating costs

OECD COMMUNICATIONS OUTLOOK 2001 Broadcasting Section

DIGITAL TELEVISION: MAINTENANCE OF ANALOGUE TRANSMISSION IN REMOTE AREAS PAPER E

700 MHz clearance programme timescale review. Review of progress, risks and readiness

GEO-Netcast White Paper Final Draft 9 December Improving access to data, products and services through GEOSS

THE IMPORTANCE OF CABLE RECORDS MANAGEMENT

Guatemala Capital Area Digital Telephone Network Improvement and Expansion Project

Network Infrastructure for the Television beyond 2000

Credits. Guidance Note. Status of Guidance Note. Key Editorial Standards. Issued: 11 April 2011

from ocean to cloud ADAPTING THE C&A PROCESS FOR COHERENT TECHNOLOGY

Australian Broadcasting Corporation. submission to. National Cultural Policy Consultation

OECD COMMUNICATIONS OUTLOOK 2001 Broadcasting Section

Presented By: Andy Louis, Chairperson of NAB Technical Committee Date: 3 October National Association Of Broadcasters 1

REGIONAL NETWORKS FOR BROADBAND CABLE TELEVISION OPERATIONS

Deutsche Bank Conference June 2005

The Telecommunications Act Chap. 47:31

AsiaSat Satellite Fleet Operations using EPOCH IPS

Official Journal of the European Union L 117/95

ESA Ground Segment Technology Workshop 5-June-08. Ka band for Broadband and IPTV

A Case Study for Business Studies HSC Course - Stage 6

Frequently Asked Questions: Cable TV and Next Generation CAP EAS

Introduction. Introductory remarks

Internet driven convergence: innovation and discontinuity

DragonWave, Horizon and Avenue are registered trademarks of DragonWave Inc DragonWave Inc. All rights reserved

AN EXPLORATION OF THE BENEFITS OF MIGRATION TO DIGITAL BROADCASTING

SES ASTRA. DLR / ESA ARTES XI Workshop June 2006, Rottach-Egern 2006/06/29 SES ASTRA PROPRIETARY

Before the Federal Communications Commission Washington, D.C ) ) ) ) ) REPLY COMMENTS OF PCIA THE WIRELESS INFRASTRUCTURE ASSOCIATION

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

A Report on Migration from Analogue to Digital Broadcasting in Ghana

4K & DVB-S2X HOW OPERATORS CAN BE COST-EFFECTIVE. Market Trend. Introduction. 4K & DVB-S2X. How Operators Can Be Cost-effective

COMMUNICATIONS OUTLOOK 1999

SECTION 686 VIDEO DECODER DESCRIPTION

RECENT FRANCHISE RENEWAL PEG ACCESS OUTCOMES (re HD, VOD, EPG, Funding)

Committed to connecting the World ITU ACTIVITIES IN DIGITAL BROADCASTING TRANSITION. JO, GueJo

Reconfiguration Along the U.S.-Mexico Border Meeting in NPSPAC Region 3: Arizona May 16, 2013

ITU-T Y Functional framework and capabilities of the Internet of things

The Impact of the DTV Transition on Consumers and Consumer Choice. Overview of the DTV Transition Situation

Bankability of PV Power Plants Shanghai, 19 th March Jason Sun ( 孙嵩劼 ), PV Power Plants & Systems

Presentation: Mythbusting the Future of Free to Air Television RadComms 2018 Tuesday 30 November, 11.15am Bridget Fair Chief Executive Officer

The Lerbäck theatre barn conversion of an old barn into a theatre

Intelsat Maritime Solutions

Datasheet. Carrier Backhaul Radio. Model: AF-2X, AF-3X, AF-5X. Up to 687 Mbps Real Throughput, Up to 200+ km Range

SATELLITE RELATED SERVICES

COMMUNICATIONS OUTLOOK 1999

Dish Diversity Switch

CABLE S FIBER OUTLOOK SURVEY REPORT

SERVICES PRICELIST. L1 L1 Services - RIX Hosting Fees Fee. Rack Space Allocation Activation fee. RIX Bitstream activation fee 573,30

High Performance Coaxial Jumpers The Link for a better Network Quality SITE SOLUTIONS

MGT602 Online Quiz#1 Fall 2010 (525 MCQ s Solved) Lecture # 1 to 12

10G SFP+ Modules. 10G SFP+ Module Series

Satellite Services and Interference: The current situation. ITU International Satellite Communication Symposium Geneva, June 2016

Signalling Cable Equivalent Sizes (formerly RT/E/C/11213)

Ultrafast Fibre UFB Services Agreement. Price List

COMMUNICATIONS OUTLOOK 1999

Digital Video Engineering Professional Certification Competencies

Extended Reach, Client-Side SFP, Multi-Rate, Multi-Protocol, DWDM, 3R Transponder WaveReady Transponder 740 XLR

Transcription:

MASTERCLASS TUTORIAL 4 The Thin Route Environment Presenters: John Hibbard (Hibbard Consulting) Maja Summers (Apollo SCS)

Presenter Profile John is based in Sydney. After 38 years with Telstra, John set up his own consulting company. In the past decade he has focussed on international communications, particularly submarine cables. John has been involved in the APNG2, ASH, SAS, Honotua, PPC1, Tonga- Fiji, Interchange and SOCC cables John was President PTC for 2009-2012 and is now a Board Member Name: John Hibbard Title: CEO, Hibbard Consulting Email: jhibbard@bigpond.com

Presenter Profile Maja has been with Apollo SCS since 2009, initially as the Operations Director and since recently as the Sales & Marketing Director. Prior to joining Apollo Maja was the Head of the Submarine Systems Engineering team in Cable & Wireless. In that role Maja was involved with the design, implementation and operation of a number of private and consortium submarine cable systems Photo Maja Summers Sales & Marketing Director, Apollo Maja.summers@apollo-scs.com

What We ll Discuss Today 1. SETTING THE SCENE 2. BUILDING THE CASE A. TECHNICAL ELEMENTS B. COMMERCIAL ASPECTS 3. IMPLEMENTATION & OPERATION 4. DISCUSSION

What s a Thin Route Low capacity typically < 20 Gbps In South Pacific, currently 55,000 kms of cable, of which 15,000 are thin route In the Indian Ocean south of Mumbai, Red Sea, currently 60,000 kms of cable of which 8500 are thin route

Characteristics Single/first international cable from a country ( umbilical cord ) Could be domestic cable or festoon Small population countries/centres, often remote Tired of high priced, lower quality satellite International cable to a point where internet access possible Limited availability of capex, opex, customers

Madang spur AJC Endeavour APNG2 PPC1 Gondwana Southern Cross Honotua Southern Cross

Developing the Business Plan Developing the business plan Identifying the demand forecast (capacity requirements day one and long term) Identifying the capacity price Postulating a route and cost of build Assessing the O&M alternatives and cost Assessing the potential return Analyse do nothing alternative

Main Options: Dedicated cable System Design Parameters Spur of another cable Main Considerations for the low capacity design What are the limitations introduced by the low capacity design? What is trade off between the savings made vs the limitation introduced? Can those limitations be removed with future technology advances?

Dedicated cable New build Cheaper cable less protected cable will potentially bring large opex cost due to frequent faults if used in hostile area Fewer repeaters thin routes by design will have smaller capacity requirements, design with repeaters spaced as far apart as possible is unlikely to have an impact Longer reach unrepeated system

Dedicated cable New build Cheaper terminal equipment Given that this is probably the only cable on that route removing equipment protection is not always the right choice. PFE options Can redundancy be added at a later stage?

Dedicated cable - redeployed What is the highest cost component in the submarine system build? In the case of redeployed cable compare the cost of cable recovery and transfer vs cost of new build cable and transfer Location of the cable that is available for redeployment; Availability of cable ship installer to recover and redeploy. How can it be acquired? What elements of the donor system can be reused? What technical expertise is available for project planning? This is required to make the project successful

Commercial considerations: Cable redeployment Warranty original supplier warranty is not available. If additional submerged plant can be recovered for extra spares it can mitigate the lack of warranty. Reliable donor system may bring no disadvantage. Timescales compared to standard lead time for new cable build timescales for cable recovery are often better, assuming good vessel availability. Timing on recovery is flexible, as cable is always available. Risk different risk profile when compared with new build, mainly related to the integrity of the donor cable and lack of warranty. System design life

Technical Considerations: Cable Redeployment Submersible plant: Reliability and fault history of the donor system; Cable integrity after recovery; Can the donor system be tested prior to recovery; Donor system cable type, fibre type, repeater type. Transmission performance; Maximum capacity achievable; Desired system capacity and configuration.

When it would not work: Cable Redeployment The type of the donor cable is not suitable fibre types, repeater spacing, cable type The geographical locations of the donor cable in comparison with the new system long transit after cable recovery would introduce high additional cost Condition of the donor cable not good The cost saving is too small

Spur off another cable Reasons for introducing the spur BU type Optimisation of the branch design to achieve the most cost effective solution O&M arrangements

Spur off another cable Spur off another cable New BU on new cable with spur needs to be planned from the outset New spur on stubbed BU already included in the design, and therefore a simpler solution New BU and spur on existing cable not planned from the outset; what is the optimal design.

Ownership Structure Funding Thin Route Cables Consortium, however limited carriers Incumbent carrier Government ownership (part/whole) Provident fund Private entrepreneur Mixture

Equity Few carriers have capacity for all equity Partial equity, some debt Pre-sales Limited funds, PAYG schemes Sources of Debt Funds Commercial banks Provident funds Government loans Development banks (World Bank, ADB, EXIM, etc) low interest potential

Issues and Challenges Limited pre-sales Perceived Sovereign risk Interest rates and bank fees Development bank processes Banks sceptical of demand forecasts Decisions made by those remote from location

Bright spots Increasing experience of the stimulus Recognition of importance of good comms Dev banks have difficulty finding projects which will help economic development Cables fit the regional allocation Well suited to NPFs because generates development and wealth Growing evidence that it can help the well-being of a nation

Pacific Cable Stimulus Cable1 Routing Demand prior to RFS APNG2 then PPC1 PNG - Australia Gondwana New Cal - Australia ASH Pago - Hawaii Capacity shortly after RFS 22 Mbps 45 Mbps (2007) 150 Mbps 450 Mbps (2008) 35 Mbps 90 Mbps (2009) SAS Apia - Pago 15 Mbps 45 Mbps (2009) Honotua Tahiti - Hawaii 500 Mbps 1500 Mbps (2010) Capacity 800 Mbps 3000 Mbps 500 Mbps 135 Mbps 4000 Mbps

What s different? RFT Development Looking for creative thin route solutions. Don t need a terabit/sec Solutions that keep costs down However may need to comply with DB requirements Can be limited scope for judgement, negotiation Spurs off BUs present particular issues

Setting a price Better than satellite at start Substantial volume discounts Pricing & Pre-selling Need to recognise capacity to pay vs need for upfront money to fund cable Selling Early bird discounts

Leases (Minimum 45 Mbps) IRUs (min STM1) Financed IRUs Lease converting to IRU Ethernet Products

GEO satellites Competition $1500-2000 per simplex Mbps/month Equates to $2000+ for cable equivalent Significant latency Limited capacity at times Subject to weather, sunspots, etc

O3B Competition Still to fly due for service in Oct 2013 Transponder will carry about STM4 equivalent Cost for full transponder believed about $600-$800 per cable equivalent Mbps/month Higher with less than full transponder Lower latency than GEO, near cable KA band, rain performance unproven

Setting the price Now needs to start at $1000 or less (on a lease basis) Significant volume discounts $600 for a STM4 $400 for a STM16 IRUs substantially cheaper (say 48 months) Obviously higher than on major routes where we are talking <$50

Regulatory Issues Single cable, potential bottleneck Scope for price gouging Regulatory oversight needed Cable entity must be able to survive Compounded if owner is Govt or NPF Complicated if owner is one of the carriers Need to ensure benefits to the country

Ongoing Financial issues Collection difficulties Having enough cash for O&M Reserve fund for a cable break Enough for debt servicing Help unlikely from Dev banks Dividend expectations

New cable Local facilities Implementation Requirement to build new cable station(s); what infrastructure is available What are the backhaul facilities Requirement for expertise for implementation and on going system maintenance

Redeployed cable Implementation What is the fault history of the donor cable; how long since it was switched off; Is it necessary to perform sea trials before recovery What is the likely speed of recovery, how many cable crossings; Availability and choice of recovery vessel

Redeployed cable Implementation What is the donor system configuration, cable type and fibre type; Cable engineering - Reconfiguration to be done on board the ship during recovery and transit Terminal equipment Terminal equipment new or redeployed; Reduced footprint and power benefits vs redeployment of equipment PFE reuse when can it bring benefits Specialised training required

Spur of existing cable Type of BU used BU deployment Stub BU - testing Implementation

Testing and Commissioning Product assurance both for new build and redeployed cable and equipment Low day 1 capacity; ensure sufficient spares are provided for testing as well as O&M Performance to be optimised for low volume

Operations and Maintenance Training for station staff; Experienced station staff required Maintaining skills; Requirement for retraining in the case of high staff turnaround; Equipment vendor support; Adequate sparing policy used Marine maintenance costs

System Upgrades Thin routes are unlikely to need frequent upgrades Cost of upgrades due to low volume NMS upgrades are they needed to ensure vendor support

QUESTIONS