B DOUBLE 150 kv LINK, 32 km LONG, IN BELGIUM : DESIGN AND CONSTRUCTION. (Belgium)

Similar documents
ECONOMICAL 36 kv CABLE SYSTEM FOR THE BELGIAN NETWORK

220KV EHV NETWORK AT RELIANCE JAMNAGAR REFINERY COMPLEX

Medium Voltage 12/20 (24)kV NF C cable system. Xavier Brosse Luanda May 2009

Revision of Qualification Procedures for High Voltage and Extra High Voltage AC Extruded Underground Cable Systems

High Voltage Cables kv. Handling and Operating Instructions

REFURBISHMENT OF SECONDARY SYSTEMS IN HIGH VOLTAGE SUBSTATIONS LESSONS LEARNED IN VENEZUELA

POLICY & APPLICATION GUIDE FOR 11kV POLYMERIC CABLES

MESP TECHNICAL SPECIFICATION FOR ELECTRIC CABLE 400mm 2 ALUMINIUM CONDUCTOR 1.9kV XLPE INSULATED WITHOUT METALLIC SCREEN

Joint paper: Feasibility and technical aspects of partial undergrounding of extra high voltage power transmission lines

TRANSMISSION ENGINEERING STANDARD TES-P , Rev. 0 TABLE OF CONTENTS 1.0 PURPOSE 2.0 SCOPE 3.0 CODES, STANDARDS AND REFERENCES

SURGE PROTECTIVE DEVICES

Drop Passives: Splitters, Couplers and Power Inserters

HVDC cable accessories

AMERICAN NATIONAL STANDARD

SECTION MEDIUM VOLTAGE CABLE INSTALLATION. 1. Section Underground Ducts and Manholes.

INSULATION CONDITION OF DRY-CURED XLPE CABLES MEASURED OVER A PERIOD OF 13 YEARS

HYL-080D1750G358. Constant current LED driver DALI Dimmable. LED Driver. Product description. Benefits. Interfaces.

B1-00. SPECIAL REPORT FOR SC B1 (Insulated Cables) Walter Zenger. Special Reporter

ANALYSIS OF FAILURE IN POWER CABLES FOR PREVENTING POWER OUTAGE IN ALEXANDRIA ELECTRICITY DISTRIBUTION COMPANY IN EGYPT

3M Sensored Termination (15 kv) QX-T15I-vi1-E

High Temperature Operation of Extruded Distribution Cable Systems. White Paper

Diagnostic & Testing Services

TRANSMISSION ENGINEERING STANDARD TES-P , Rev. 0 TABLE OF CONTENTS 1.0 SCOPE 2.0 CABLES SPLICES

Operating Manual (Edition 04/2004) sinamics. Line Reactors SINAMICS G130

APPLICATION OF POWER SWITCHING FOR ALTERNATIVE LAND CABLE PROTECTION BETWEEN CABLE LANDING STATION AND BEACH MAN HOLE IN SUBMARINE NETWORKS

Installation Manual IPT Installation of skillet systems with 125 A track current. MV a-E.

Fibre Optic Modem ODW-622

SPECIAL SPECIFICATION 6559 Telecommunication Cable

AMERICAN NATIONAL STANDARD

SPECIAL SPECIFICATION 8540 Telecommunication Cable

Guide for installers. METTLER TOLEDO MultiRange System solution analog Ex1. Hazardous area. Safe area

Installation Guide VL-MV10. Model No.

Dynatel Advanced Cable Locator 2250

Underground Cable Diagnostic Testing Utilizing Partial Discharge Technique

LED Driver Linear / area fixed output

SWA Cable BS6724 Steel Wire Armoured LSZH Eland Product Group A9L

1 Power Protection and Conditioning

ORDERING Page 6 BASLER RELAY STANDARDS, DIMENSIONS, ACCESSORIES Request bulletin SDA

TERMINATIONS AND JOINTS FOR XLPE-INSULATED kv MEDIUM VOLTAGE CABLES

Bharat Heavy Electricals Limited HIGH PRESSURE BOILER PLANT, TIRUCHIRAPPALLI CONTROLS AND INSTRUMENTATION/FB

HYL-035D0850G103. Constant current LED driver DALI Dimmable. LED Driver. Product description. Benefits. Interfaces.

640 kv extruded HVDC cable system

LED Driver Linear / area dimming industry. Driver LC 200W 1050mA UNV ADV IND ADVANCED series

Instructions for Use P.154-UP (9/4) P.155-UP (9/8) P.150-UP-12 (9/12) P.150-UP-16 (9/16)

Identification - electrical services

Instructions for Use P.160-AP-8 (13/8) P.160-CP-8 (13/8) P.160-CP-12 (13/12) P.160-CP-16 (13/16)

IndyGo Facility Upgrades Project 35671EE

M4000 Diagnostic Test System For Power Apparatus Condition Assessment

Fibre Optic Modem ODW-611

640 kv XLPE HVDC cable system

ODW-621. RS-232 Point-to-point applications

LED Driver Compact fixed output

Design of Fault Coverage Test Pattern Generator Using LFSR

ELECTRICAL SAFETY INSPECTION REPORT. MTM Garments Ltd.

I r A Protection against direct contact Finger and back of hand proof to VDE 0106 Part 100

Protective function Systems, cable, selectivity and generator protection. i 2 t constant function: switchable. I r A

LED Driver Compact fixed output

10 Mb/s Single Twisted Pair Ethernet Preliminary Cable Properties Steffen Graber Pepperl+Fuchs

EMC Solutions Noise filtering

SURGE PROTECTIVE DEVICES

LONWORKS Fibre Optic Converter

LED Driver Compact dimming

For Sales & Information, Call Toll Free: (888)

SCHEDA TECNICA. Amarro per cavi 13,5mm Amarro per cavi 16,5mm. MS217F00 Amarro per cavi 13,5mm MS218F00 Amarro per cavi 16,5mm

Non-metallic Aerial Distribution Optical Cables for FTTH Networks

INSTRUCTION DE SÉCURITÉ SAFETY INSTRUCTION Mandatory as defined in SAPOCO/42 FIRE PREVENTION FOR CABLES, CABLE TRAYS AND CONDUITS

SINAMICS G130. dv/dt filter plus Voltage Peak Limiter. Operating Instructions 03/2013 SINAMICS

LED Driver Compact fixed output

Generator protection relay

Toronto Hydro - Electric System

SITE All work shall be performed at Center Park Substation (1895 Kernan Blvd, Jacksonville, Fl ). DATE: 04/03/2018

TOSHIBA Industrial Magnetron E3328

Cambria County Association for the Blind and Handicapped 175 Industrial Park Road Ebensburg, PA Prepared for: Prepared by:

FUNCTION IN FIRE EXPERT JUDGEMENT REPORT WITH CLASSIFICATION FIRES-JR NURE

PHASED OUT. LED control gear Compact fixed output. Driver LC 40W 900mA fixc C SNC China Domestic ESSENCE series

NZQA unit standard version 3 Page 1 of 7. Demonstrate knowledge of telecommunications cable systems

Catalogue Ignitors and power switches for HID

ImproX (TRT) Twin Remote Terminal INSTALLATION MANUAL

Flicker Caused by Operation of Industrial Technology

APPLICATION NOTE. Practical Tips for Using Metalic Time Domain Reflectometers (The EZ Way) What is a Time Domain Reflectometer?

DEVELOPMENT OF A 270 kv XLPE CABLE SYSTEM FOR HVDC APPLICATION

Lt DELTA USA, Inc

Emerging Subsea Networks

ORDERING Page 6 STANDARDS, DIMENSIONS and ACCESSORIES Request bulletin SDA

Commissioning the TAMUTRAP RFQ cooler/buncher. E. Bennett, R. Burch, B. Fenker, M. Mehlman, D. Melconian, and P.D. Shidling

PRINCIPLES AND APPLICATIONS

If you want to get an official version of this User Network Interface Specification, please order it by sending your request to:

Fibre optic router for TP/FT-10 LRW-112PP

LONWORKS Fibre Optic Router

ANSI DESIGN TEST REPORT Report No. EU1250-HR-00 Type PVI Intermediate Class Surge Arrester

SWA Cable - BS5467 Steel Wire Armoured PVC Eland Product Group A9S

ACADEMIC SUCCESS CENTER THE COLLEGE AT BROCKPORT STATE UNIVERSITY OF NEW YORK PROJECT NO

NC-1000 INSTALLATION MANUAL NC-1000 FIBRE OPTIC CROSS-CONNECTION SYSTEM

Innovation in Magnetic Measuring Instruments. Operation Manual for. Mag648 and Mag649 Low Power Three-Axis Magnetic Field Sensors.

HARMONIZATION OF SYNOPTIC BLOCK DIAGRAMS ON THE CONTROL PANELS OF MV SWITCHGEAR AND CONTROLGEAR

MCR3 POWER EQUIPMENT. Microprocessor Controlled Constant Current Regulator. Compliance with Standards. Uses. Features

Effective earthing of screened cables

I/A Series Hardware Fiber Optic LAN Converter

Description Set value in neutral conductor is synchronous with set value Ir of main pole. R.m.s. value measurement and thermal memory CSA 100

KNX Dimmer RGBW - User Manual

Transcription:

, rue d'artois, F-75008 Paris http://www.cigre.org B-05 Session 004 CIGRÉ DOUBLE 50 kv LINK, km LONG, IN BELGIUM : DESIGN AND CONSTRUCTION A. Gille *, V. Beghin G. Geerts, J. Hoeffelman D. Liémans, K. Van Gucht BEL ENGINEERING ELIA NEXANS (Belgium). INTRODUCTION The construction of the double 50 kv link between Tihange nuclear power plant and the new highvoltage substation in Avernas is the Belgium s largest underground link ever built. These double link, which has been energized in November 00, had a dual aim : first, with the contribution of three other new links (Avernas - Tienen: two km links ; Avernas - Brustem - Landen: one 4 km link), to secure power supplies in the area extending between Brussels and Liège and, second, to supply power to the high-speed train line between Brussels and the German border (see figure ). Figure : Diagram of the different links. HISTORICAL BACKGROUND OF THE LINK The initial project of a 80 kv overhead line between Tihange and Landen had been included in Belgium s 985-995 national development plan for power generation and transmission facilities, and the project was started accordingly in 989. * Alain.Gille@Bel-Engineering.com

After a series of modifications, the federal government finally accepted in 999 a mixed overheadunderground design for the link, which would start overhead for 4.5 km (80 kv) and continue underground for some 7 km with a bundle of 50 kv cable. Due to the advice of the regional government and some opposition from the public, the project was further modified and resulted in the present project: the exit from the nuclear plant site and the crossing of the river Meuse where the plant is situated ( km) is overhead and includes a new 80/50 kv substation; via a transition compound the remainder of the link is underground (0 km).. PROPERTIES OF THE CONTROLLED BACKFILL Elia, the Belgian Transmission System Operator (BTSO) imposed very strict transmission capacity requirements, which resulted in having a 50 kv link comprising three cables per phase, the third cable being installed only to face the situation in case one circuit should fail. However, in order to avoid the cost of a third cable, the option has been chosen to have a system with two cables per phase laid in flat configuration. This was based on a number of hypotheses; one of these is the adoption of a backfill resistivity value (generalised in Belgium) of 0.7 K.m/W instead of the usually adopted K.m/W. In order to verify this calculated value, a series of in situ tests were performed applying the innovative TDR technique (Time Domain Reflectometry). The paper referenced [] describes the organisation and the conditions under which these tests were performed, and gives the results, which substantiated the hypotheses. 4. AUTHORIZATIONS The various permits (for which the requests have been introduced in May 000) were issued mid- 00. Furthermore, in order to reassure the authorities and the public, a series of monthly consultation meetings were organised in each municipality along the route of the underground cable while the construction was in progress. Nevertheless, numerous appeals were presented by local committees to the Belgium s highest judicial body (the State Council) in order to stop the link crossing their land, but all these appeals were finally rejected. Also several stipulations were included in the permits, resulting in the route of the link having to be repositioned locally to avoid running along roads with housing on either sides. Among these stipulations, one of the most important was the requirement for installing a special shielding against magnetic fields each time the links were distant of less than 0 m from housings and schools (in application of the precaution principle). 5. SHIELDING AGAINST MAGNETIC FIELDS Underground cables are often presented as the solution to avoid any problem due to EMF. This is of course true for the electric field, but not that obvious as far as the magnetic field is concerned. Mainly when the cables are laid in flat configuration in order to ensure a higher ampacity, as it is the case here, the magnetic field in the immediate vicinity of the cable is far from being negligible. Although it decreases very quickly with the distance it remains quite high in the close vicinity of the cables. Due to stipulations included in the permits, about one fifth (about 7 km) of the total length had to be shielded. 5.. Choice of the shielding technique Shielding techniques for cables are studied by the BTSO since 996. All kinds of shielding techniques have been considered: ferromagnetic materials (grain oriented steel ), use of highly conductive materials like aluminium or copper and use of passive loops. The first approach was experimental, followed by computer modelling (FEM-BEM) after validation. The comparison of these different techniques led to the conclusion that the use of conductive material offered more advantages than that of ferromagnetic materials. The main reasons were that, with ferromagnetic materials, the shield needs to be closed (or nearly closed) around the cables and also requires a good protection against corrosion (at present, however, these problems seem to have been overcome). Therefore, the proposed solution was to use aluminium plates of mm thickness. These plates can be put horizontally or folded on the

edges in order to form a U-shape shield laid as a lid on the cables. The shielding mechanism results from the eddy currents flowing into the plates (Lenz law). It has be shown [], [], that the efficiency of such plates is not much different whether purely horizontal or folded. However, with folded plates the width of the trench can be reduced significantly. On the other hand, a U-lid cannot easily be installed because it interferes with the backfilling (risk of void under the lid and impact on the thermal behaviour). For this reason, the U-shape was replaced by a H-shape made of two vertical plates, placed in the trench before the backfilling, and horizontal plates installed at the suitable depth during the backfilling (see figure ). This approach has important consequences on the construction work. Indeed, for practical reasons, the shielding is not continuous but made of separated m length plates. For a horizontal or a U-shape shielding, the continuity between adjacent plates, although important, is not decisive, because the eddy currents can always flow in a closed loop in each plate. This is no longer the case for a H-shape shield where a very good continuity needs to be achieved between the successive vertical plates. Moreover, in the absence of contact between vertical and horizontal plates, the vertical plates need to constitute a close loop. Therefore, at regular interval, a bridge is installed between the lateral plates. In that respect, the technique resembles the passive loop technique but it has a better efficiency thanks to its lower inductance (no need to tune with capacitors at 50 Hz). All these features could not be analysed by the classical D models, which have been validated on horizontal and U-shape layouts but not on the H-shape. Hence, they have been analysed first on laboratory models and then validated by D mathematical models. These studies showed also that the continuity between the horizontal plates was not important at all. Therefore they were installed with a gap of several centimetres between each other and the vertical plates in order to ensure easy fault location and repair in case of oversheath fault in the cable. The final layout used for shielding the link is shown on figure. Shielding 50 5 0 Figure : Profile of the trench with shielding Picture : shielding 5.. Corrosion and thermal behaviour It has been shown that the corrosion by the soil was not an important concern as long as the ph of the soil remains between specific limits and the alloy contains more than 95 % aluminium and no copper. A long duration control of the electrical potential of the plates was decided anyway. DC and AC corrosion has also been addressed. This kind of corrosion depends on the current density of the stray currents. In order to reduce the leakage currents between vertical and horizontal plates it was decided to keep a gap between them.

On the other hand, if the leakage currents remain very low, the eddy currents in the plates are quite high and could lead to unacceptable losses. This limits the minimal distance between the horizontal plates, responsible for the highest losses, and the cables. 5.. Practical results and costs Figure shows measurement results taken at two different places of the link with and without shielding. At those places, the distance between both circuits is about 4 to 5 m. However, as it is not exactly the same it is difficult to calculate a shielding factor. The order of magnitude here is about 8. Depending of the fastening technique used (bolts, rivets, welding) lower or higher efficiencies can be achieved. Shielding factors higher than 0 have been measured in places where the welding technique was systematically applied; this result is close to the theoretical maximum given by the D computer model. The total cost involved by the shielding is not easy to evaluate because it is the first time this technique is applied. For the present project, the additional cost per shielded unit length was about 6 %. 5 0 5 µt/ka 0 5 0 5 0-0 -0 0 0 0 distance to the axis of the link (m) 0 m - shield m - shield 0 m - without m - without Figure : Magnetic field, with and without shielding, measured at 0 and m above ground (distance between circuits: 4 to 5 m) 6. CROSS-BONDING 6.. Cross-bonding (of the metallic screens) In order to suppress the circulation currents in the metallic screens that reduce the ampacity of the link, two possibilities exist: single point bonding or cross-bonding of the screens [4]. As the link is very long (0 km), single point bonding would generate unacceptable voltages on the metallic screens. Using a cross-bonding method, advantage is taken of the fact that the induced voltages are symmetrical: by adding three vectors of the same amplitude, but phase-shifted by 0, resulting in a null vector. A major section (distance between two points of the link were the screens are bonded together) is divided into three equal minor sections (L, L, L). The cable screens are interrupted at the cable joints between L and L and between L and L and the screen connections can be bonded to another joint in the manhole (cross-bonding). 6.. Transposition (of the phases) The condition of having equal lengths of minor sections is enough to get a null resulting vector if the system is symmetrical, which is the case when a trefoil configuration is used (same distance between 4

the phases). In the case of flat configuration, the distances between the phases are not equal. To cope with this, transposition of the phases (similar with long-distance overhead lines) is performed at the same locations where the cross-bonding of the metallic screens is applied [4]. 6.. Direct cross-bonding With classic cross-bonding, the interruptions on the screens at the joints are protected against overvoltages with surge voltage limiters (SVLs). Checking (and maintenance) of the SVLs would be a huge task on such a long double link, and should be avoided, as it must be performed during availability of the link. As the SVLs only have a protective function, they can be avoided if the elements they protect have sufficient intrinsic protection. The electrical constraints on Belgium s 50 kv network have been calculated before, and have resulted in imposing the interruption of the elements in the joint in order to withstand 50 kv surge voltage, and 75 kv surge voltage between each element and the earth. A special joint technique has been designed and qualified by the cable manufacturer in order to meet these requirements in addition to the tests specified in IEC 60840 [5]. Direct cross-bonding system is systematically applied in Belgium on the 50 kv underground link since 000. 6.4. Installation of SVLs in the two minor sections following the transition compound Overvoltages of atmospheric origin would result in the propagation, through the cable, of the surge waves caused by lightning strikes on the overhead line to which the underground link is connected. The characteristics of the lightning surge adopted after a sensitivity analysis on the various parameters were : 00 ka peak./50 µs, which is a deterministic approach of the problem, consistent with the reports presented in the scientific literature Electra n 8 [6] and 47 [7]. The results of the first simulations (without SVLs) showed that the amplitude of the surges between screens decreases in the underground link with the distance to the location of the lightning stroke in the overhead line and that the amplitude is at its highest at the first permutation of screens (gradual attenuation of the surge wave with the propagation in the cable). In order to avoid oversizing of the direct cross-bonding joints, only the first minor sections of the circuit (nearest the overhead line) need to be protected by SVLs (see figure 4). Earthing box Direct cross-bonding Direct cross-bonding Earthing box Cross-bonding with SVL Cross-bonding with SVL Type W : direct cross-bonding joint Type X : straight joint Type Y : joint with possible disconnection of the screens (for oversheath test and fault location) Type Z : cross-bonding joint with SVL Figure 4: Principle of the direct cross-bonding and position of the SVLs New simulations demonstrate that a reduction of the surges in the first major section of the circuit was clearly noticeable but a shift of the surge was noticed at the screen interruptions of the next major section of circuit. Nevertheless, the surges in this section were strongly reduced and acceptable for the current design of the joints. 5

7. CONSTRUCTION AND SCHEDULING The energizing of the link was planned at the beginning of November 00 to schedule with a maintenance of the nuclear power plant. Taking into account this requirement, the dates on which the building permits were received and the agreements with the Belgian railways (regarding power supply for the high speed train), the construction had to be complete within about one year. As most of the route of this double link runs along a disused railway line, it was possible to provide a track parallel to the trenches, allowing to work simultaneously on several sections of the underground link. This solution made possible a high progress rate. The contractor provided also throughout the construction period a high number of teams charged with specific tasks (clearing of brush, road crossing, cable pulling, ). The workforce for the construction numbered 70 in all. The construction was completed on time. 8. TESTS AFTER INSTALLATION Two major dielectric tests were performed after the installation of a high-voltage cable link: DC test on the PE- oversheath AC test on the high-voltage insulation 8.. DC tests on the oversheath The dielectric integrity of the sheath gives a good indication on the way the cables have been installed in the trench. The voltage applied depends on the thickness of the sheath and on the involved length (partial or complete). For the partial length (one drum), the applied DC voltage is.5 e + 5 kv during minutes (e = thickness of oversheath). On the complete finished cable length, the test voltage is 0 kv during minute. 8.. AC test on the high-voltage insulation This test, performed after installation of the complete finished cable system aims at checking the integrity of the system for commissioning - mainly that of the accessories assembled on site. In Cigré report [8], a first recommendation was made for AC testing on site after installation. The conclusions were that AC voltage withstand testing at levels of U 0 to U 0 will give the most reliable results. Since 997, BTSO imposed the AC tests after installation for XLPE cables on the 70 and 50 kv network. The test voltage is U 0 (8 kv or 74 kv) respectively 0 minutes for 70 kv and 5 minutes for the 50 kv links. AC - test conditions for the double 0 km link With the actual available test installation (see picture ) and a test level of 74 kv, the maximum available power is MVA at 5 Hz. In order to test the total length of 0 km in one time, the needed power is 47 MVA. Picture : AC-test Picture : Stop joints 6

The Belgian experience with the premoulded joints at 50 kv, where about 00 similar joints have been successfully tested, allows to work on a statistical basis. The link was divided in parts, two parts of about km length (needed power was about 9 MVA) that have been tested, and a remaining part of 6 km that has not been tested. Nevertheless, before delivering power to the network, the complete link has been connected to the network for at least 6 hours. Tests were carried out on part using the overhead line of.5 km from the 80/50 kv transformer substation to the transition compound and on part from the 50 kv substation. At the end of each test length, temporally stop joints were installed (see picture ). This principle avoids having to install on-field terminations for testing. Part tested Part not tested Part tested Feeder A 60 9 60 Feeder B 66 60 Table I: Number of tested joints 77 % of the total number of joints were successfully tested at U 0 5 minutes. 9. OPERATION OF THE LINK UNDER EMERGENCY CONDITIONS Considering the nominal characteristics of the monobloc transformers 400/65/6 kv with a basic power of 85 MVA each and the ampacity of the cable = 00 A, it can be concluded that with the double link in service, the limit is given by the transformer (0 % in the summer, duration of maximum hours). In practice, the double link will be normally used at 60 % of its maximal cable load possibilities. This means that with only one link, the load on one cable will reach a maximum of 0 %. During operation under such conditions, it is important to know where hot spots on the link are situated, and to monitor them. This monitoring is possible thanks to the integrated optical fibres for temperature measurements embedded in one phase of each cable link. The distributed temperature of the two types of integrated optical fibres (multimode and singlemode types) will be measured with the commercially available systems. The integrated optical fibre link of 0 km is divided in several parts for the multimode principle, with a maximum length of about 4 km and a spatial resolution of metre. Complementary, the entire link can be measured with the singlemode principle having a maximum length of about 0 km and a spatial resolution of 0 metres. 0. FAULT LOCATION Once a year, the link will be tested on the integrity of the PE-oversheath. Indeed, the locating of a cable insulation fault is often achieved through sheath fault location (i.e. important damage on the cable). The use of magnetic shielding over several metres makes classic pinpoint location impossible. For this reason, each section of aluminium shielding is electrically connected at each end to the next closest earthing box. A galvanic insulation (gap of about 0 cm) is present between successive horizontal plates and the interconnected vertical plates. Two steps are still necessary when supposing that there is a fault under a shielded section: Firstly, through preliminary location by reflectometry, using the propagation between the screen of the cable and the shielding which is connected with an aluminium wire to the place of measurement (earthing box). Secondly, pinpoint location on the horizontal plates. The maximum precision of this location will be m (dimensions of the plates). 7

. CONCLUSIONS After 4 years of technical studies and discussions with authorities and administrations, the double 50 kv mixed (overhead-underground) link between Tihange nuclear power plant and the new highvoltage substation of Avernas has been energized in November 00. The construction itself took one year. Among the conditions imposed by the authorities in the permits, was the obligation to reduce the magnetic field in those areas where the underground cables run at a distance less than 0 m from housing and schools. Various systems were compared, and finally the option was taken to use highly conductive materials. An H-shape layout was chosen, composed of aluminium plates installed over one-fifth of the total length of the link, entailing a significant extra cost. Fortunately, the results matched the expectations. Like systematically in Belgium since 000 for underground 50 kv links, the direct cross-bonding principle was applied, thereby avoiding for the BTSO the constraints relating to SVLs, except at the first two junctions closest to the overhead line, where, for reasons of not wanting to pointlessly oversize the direct cross-bonding joints, the choice was made to install SVLs. The BTSO has adopted since 997 the AC test for post-installation testing of all the 70 and 50 kv links. Considering the length of this link, a technical and economic study was performed, which permitted working on a statistic basis by successfully testing only 77% of the link. Taking into account the very strict stipulations imposed by the BTSO regarding the transmission capacity of the link, it was essential that the locations of the hot spots be known. This requirement was met by incorporating optical fibres in one of the three phases. The 50 kv double link between Tihange nuclear power plant and Avernas substation is the longest ever (0 km) underground link built in Belgium.. BIBLIOGRAPHY [] A. Gille, G. Geerts, J-P. Mella, Pr. Dimitri Xanthoulis, N. Fonder: On-site follow-up of the characteristics of controlled backfill, using the Time Domein Reflectometry moisturemeasurement method (Jicable 00 Article C.8..7.). [] A. Canova, A. Manzin, M. Tartaglia: Evaluation of different Analytical and Semi-Analytical Methods for the Design of ELF Magnetic Field Shields (IEEE Trans. On Industry Applications, vol 8, no, May/June 00). [] O. Bottauscio, D.Chiarabaglio, M. Chiampi, M.Repetto: A numerical Approach to the Design of Conducting Shields for ELF Magnetic Field Reduction (ETEP, vol, No, March/April 00). [4] M. Fallou : Analyse des procédés permettant de supprimer les pertes dans les gaines métalliques de câbles unipolaires à courant alternatif (Revue Générale de l Electricité, Tome 74, n 6, juin 965). [5] P. Couneson, B. Brijs, J. Becker, G. Geerts, X. Delrée: 50 kv underground links in Belgium: a new technical stage for XLPE insulated cables (Cigré 000, Article -0). [6] Report of WG -07: The design of specially bonded cable systems (Electra n 8, p. 55-8, 97). [7] Second Report of WG -07: The design of specially bonded cable circuits (part II) (Electra n 47, p.6-86, 976). [8] Report of WG -09: After laying tests on high voltage extruded cable systems (Electra n 7, p. -4, August 997). 8