220KV EHV NETWORK AT RELIANCE JAMNAGAR REFINERY COMPLEX

Similar documents
TRANSMISSION ENGINEERING STANDARD TES-P , Rev. 0 TABLE OF CONTENTS 1.0 SCOPE 2.0 CABLES SPLICES

Revision of Qualification Procedures for High Voltage and Extra High Voltage AC Extruded Underground Cable Systems

Bharat Heavy Electricals Limited HIGH PRESSURE BOILER PLANT, TIRUCHIRAPPALLI CONTROLS AND INSTRUMENTATION/FB

Medium Voltage 12/20 (24)kV NF C cable system. Xavier Brosse Luanda May 2009

POLICY & APPLICATION GUIDE FOR 11kV POLYMERIC CABLES

ECONOMICAL 36 kv CABLE SYSTEM FOR THE BELGIAN NETWORK

INSTRUCTION DE SÉCURITÉ SAFETY INSTRUCTION Mandatory as defined in SAPOCO/42 FIRE PREVENTION FOR CABLES, CABLE TRAYS AND CONDUITS

MESP TECHNICAL SPECIFICATION FOR ELECTRIC CABLE 400mm 2 ALUMINIUM CONDUCTOR 1.9kV XLPE INSULATED WITHOUT METALLIC SCREEN

Identification - electrical services

Cable installation guidelines

ELECTRICAL SAFETY FOLLOW UP INSPECTION REPORT (8th) Factory Name Address Factory ID

Student Services & Classroom Addition

ELECTRICAL SAFETY INSPECTION REPORT

Joint paper: Feasibility and technical aspects of partial undergrounding of extra high voltage power transmission lines

Condition Monitoring Program of HV Cable Systems

Diagnostic & Testing Services

ELECTRICAL INCIDENT REPORT BUSHFIRE NEAR 22 NUKKLGUP LOOP YALLINGUP WESTERN AUSTRALIA 5 JANUARY Report prepared by: EnergySafety WA EIS

SWA Cable BS6724 Steel Wire Armoured LSZH Eland Product Group A9L

Trends and Challenges of HV Cable Systems

Connecting cables NEBS, for sensors

LED Driver Compact dimming

Photovoltaic Module Installation Manual (IEC)

3M Sensored Termination (15 kv) QX-T15I-vi1-E

Tab 10 - The NESC and Underground Applications. Restricted Siemens Industry, Inc All rights reserved.

640 kv XLPE HVDC cable system

Using Ultrasound and Infrared Technologies for Metal-Clad Switchgear Inspections

Datasheet. LED Transformers. LED Transformer 120W 24V V. LED Transformers

CLP s first 400kV XLPE cable application

Long Term Analysis of Cables Problems in Egyptian Distribution Network

TRF STEP-DOWN TRANSFORMER USER MANUAL

ELECTRICAL SAFETY INSPECTION REPORT. MTM Garments Ltd.

SINAMICS G130. dv/dt filter plus Voltage Peak Limiter. Operating Instructions 03/2013 SINAMICS

Photovoltaic Module Installation Manual (IEC)

HIGH VOLTAGE CABLE ACCESSORIES - Application, Design, Installation, Testing - Ivan Jovanovic G&W Electric Company

Description Set value in neutral conductor is synchronous with set value Ir of main pole. R.m.s. value measurement and thermal memory CSA 100

B1-00. SPECIAL REPORT FOR SC B1 (Insulated Cables) Walter Zenger. Special Reporter

TERMINATIONS AND JOINTS FOR XLPE-INSULATED kv MEDIUM VOLTAGE CABLES

Preventing Fieldbus Physical Layer Problems

Protective function Systems, cable, selectivity and generator protection. i 2 t constant function: switchable. I r A

SWA Cable - BS5467 Steel Wire Armoured PVC Eland Product Group A9S

I r A Protection against direct contact Finger and back of hand proof to VDE 0106 Part 100

Instructions for Use P.154-UP (9/4) P.155-UP (9/8) P.150-UP-12 (9/12) P.150-UP-16 (9/16)

I r A Protection against direct contact Finger and back of hand proof to VDE 0106 Part 100

BY ADRIAN MESSER, UE Systems, Inc.

Product Manual MNX10015 / REV C MODEL SB142, SB242. Dual Output Series Switch Boxes

640 kv extruded HVDC cable system

ANALYSIS OF FAILURE IN POWER CABLES FOR PREVENTING POWER OUTAGE IN ALEXANDRIA ELECTRICITY DISTRIBUTION COMPANY IN EGYPT

CHAPTER 3. HV and EHV Cable System Aging and Testing Issues

Connecting cables for valves, Sub-D Type codes

Instructions for Use P.160-AP-8 (13/8) P.160-CP-8 (13/8) P.160-CP-12 (13/12) P.160-CP-16 (13/16)

APPLICATION OF POWER SWITCHING FOR ALTERNATIVE LAND CABLE PROTECTION BETWEEN CABLE LANDING STATION AND BEACH MAN HOLE IN SUBMARINE NETWORKS

High Voltage Cables kv. Handling and Operating Instructions

Instructions. Cable with Armor F CAUTION. October Rev A

GA A26497 SOLID-STATE HIGH-VOLTAGE CROWBAR UTILIZING SERIES-CONNECTED THYRISTORS

SECTION MEDIUM VOLTAGE CABLE INSTALLATION. 1. Section Underground Ducts and Manholes.

THE EFFECT OF LOOSE CONNECTORS ON SHIELDING EFFECTIVENESS

Methods of Inspection to Determine the Presence of Potential Arc Flash Incidents

LED Driver Compact fixed output

Description Set value in neutral conductor is synchronous with set value Ir of main pole. CSA 100. conductor. I r A 50-63

ELECTRICAL SAFETY INSPECTION REPORT

Operating Manual (Edition 04/2004) sinamics. Line Reactors SINAMICS G130

HID control gear Electronic. PCIS, PCS outdoor FOX B011 PCI outdoor. Ordering data. Circuit power1. tc/ta for 60,000 h For luminaires with 1 lamp

SCHEDA TECNICA. Amarro per cavi 13,5mm Amarro per cavi 16,5mm. MS217F00 Amarro per cavi 13,5mm MS218F00 Amarro per cavi 16,5mm

Cambria County Association for the Blind and Handicapped 175 Industrial Park Road Ebensburg, PA Prepared for: Prepared by:

TRANSMISSION ENGINEERING STANDARD TES-P , Rev. 0 TABLE OF CONTENTS 1.0 PURPOSE 2.0 SCOPE 3.0 CODES, STANDARDS AND REFERENCES

SPECIAL SPECIFICATION 6559 Telecommunication Cable

SPECIAL SPECIFICATION 8540 Telecommunication Cable

INSULATION CONDITION OF DRY-CURED XLPE CABLES MEASURED OVER A PERIOD OF 13 YEARS

ELECTRICAL. DATA AND INDEX Not all complements shown A shown for reference. Index A leads B, CW (from shaft end) TERMINAL CONNECTIONS COM VCC CASE

NZQA unit standard version 3 Page 1 of 7. Demonstrate knowledge of telecommunications cable systems

HARMONIZATION OF SYNOPTIC BLOCK DIAGRAMS ON THE CONTROL PANELS OF MV SWITCHGEAR AND CONTROLGEAR

3M Super 23 Electrical Tape

HYL-080D1750G358. Constant current LED driver DALI Dimmable. LED Driver. Product description. Benefits. Interfaces.

B DOUBLE 150 kv LINK, 32 km LONG, IN BELGIUM : DESIGN AND CONSTRUCTION. (Belgium)

Installation Guide VL-MV10. Model No.

System solutions: Partial discharge measurement and monitoring systems.

Protective function Systems, cable, selectivity and generator protection. i 2 t constant function: switchable. I r A

AMERICAN NATIONAL STANDARD

Dynatel Advanced Cable Locator 2250

I r A Protection against direct contact Finger and back of hand proof to VDE 0106 Part 100

LEGEND POWER SYSTEMS

Laying of cables and lines in electrical installations and data networks

LED MODULES READYLINE DL

LED Driver Compact fixed output

LED control gear Compact fixed output

EE028: Practical High Voltage Cable Jointing and Termination

Cables for robot applications

PHASED OUT. LED control gear Compact fixed output. Driver LC 40W 900mA fixc C SNC China Domestic ESSENCE series

Effective earthing of screened cables

Operating Instructions 07/2007 Edition. SINAMICS G130/G150 Line harmonics filter. sinamics

Processing Specification MiniBridge IDC

Underground Installation of Optical Fiber Cable by Pulling

Protection against direct contact Finger and back of hand proof to VDE 0106 Part 100

IEEE DESIGN TEST REPORT Report No. TD E00 Type PVR HD Riser Pole Distribution Class Surge Arrester

HighBand 25. TrueNet Category 6 Solutions

Identification of LV Cables

3 Cold Shrink Products

I r A I i = I n x. Protection against direct contact Finger and back of hand proof to VDE 0106 Part 100

POET-1 P.O.E. TEST PORT MEASUREMENT TOOL INSTRUCTION BOOK

PEM1124ENG ENGLISH. STK TERMINATION KIT FOR PLASTIC CABLE WITHOUT ARMOURING 1 kv STKR TERMINATION KIT FOR PLASTIC CABLE WITH ARMOURING 1 kv

Transcription:

220KV EHV NETWORK AT RELIANCE JAMNAGAR REFINERY COMPLEX

JAMNAGAR 220KV CABLE NETWORK: 2

2. DESIGN 2A. NETWORK: 220 KV NETWORK DESIGN IS DESIGNED WITH 100% REDUNDANCY FROM 220 KV BUS TO LOAD. THIS IS ACHIEVED WITH DUAL 220 & 33 KV BUSBARS, DUAL 220 AND 33 KV TRANSFORMERS AND DUAL 220 & 33 KV CABLE NETWORKS. 2B: 220 KV CABLE DESIGN TWO TYPES OF CABLE CIRCUITS WERE IDENTIFIED TO CATER TO THE NETWORK TYPE -1-174 MVA CAPABILITY: SINGLE CORE 400SQ.MM XLPE COPPER CONDUCTOR CABLE IS SELECTED TO LAY IN FLAT FORMATION. TYPE-2-300MVA CAPABILITY: SINGLE CORE 1000SQ.MM XLPE COPPER CONDUCTOR CABLE IS SELECTED TO LAY IN FLAT FORMATION. 3

CABLE SHEATH: LEAD SHEATH IS USED TO PROTECT THE CABLE INSULATION FROM SOLVENTS PRESENT IN THE UNDERGROUND SOIL IN THE REFINERY AND PETROCHEMICAL COMPLEX. CABLE DESIGN PARAMETERS: CABLE 400SQ.MM CABLE 1000SQ.MM CABLE CONDUCTOR COPPER COPPER INSULATION XLPE XLPE METALLIC SHEATH LEAD ALLOY LEAD ALLOY METALLIC SHEATH THICKNESS 1.9MM 2.0MM OVERALL DIAMETER 97MM 108MM WEIGHT 16.6 KG/M CABLES LAID QUANTITY OF 400&1000SQ.MM TRENCHES LAID 140KM 24KM 4

EXECUTION AT CRITICAL LOCATIONS WHERE VEHICLE MOVEMENT CANNOT BE STOPPED AND AT THE SAME TIME DUCTING WORK WAS SUPPOSED TO BE CARRIED OUT, HDD (HORIZONTAL DIRECTION DRILLING) METHOD WAS ENVISAGED. DURING HDD JOB SOIL STRATA WAS NOT CONDUCIVE DUE TO SOLID ROCK BELOW 1METER OF THE SURFACE AND DUE TO WHICH DRILL FAILED AT SEVERAL INSTANCES. 5

SITE ACCEPTANCE TESTS ONCE ALL THE CABLE IS LAID THE CABLE IS TESTED WITH ALL ACCEPTANCE PROCEDURES TO SUCCESSFULLY CHARGE THE CABLE AS PER VENDOR GUIDELINES AND IEC INSULATION RESISTANCE TEST DC CONDUCTOR RESISTANCE TEST LINK BOX CONTACT RESISTANCE TEST: SVL INSULATION TEST: DC JACKET TEST: 24 HR. SOAK TEST: THIS TEST WAS PERFORMED TO ENSURE THAT THE CABLE LAID AND CHARGED ON NO LOAD IS FREE FROM ALL DEFECTS PARTIAL DISCHARGE MEASUREMENT TEST: CAPACTIVE TYPE PD MEASUREMENT SYSTEM IS BEING USED

CASE STUDIES: CASE STUDY-1 220KV CABLE INTERCONNECTED BETWEEN 220KV GIS MRS 4 AND C2 COMPLEX MRS-1 WAS TRIPPED AFTER WAS SUCCESSFULLY CHARGED IN JULY 16 THE CABLE FAULT COULD NOT BE LOCATED EVEN WITH 33KV CABLE FAULT LOCATOR. CABLE WAS TESTED BY KEEPING 2X105MVA POWER TRANSFORMER IN SERIES HAVING AN IMPEDANCE VALUE OF 13.25% AND THEREBY LIMITING THE FAULT CURRENT TO 1KA. NO. OF TIMES SUCH TESTING WAS CARRIED OUT, BUT CABLE IR VALUE IS FOUND NORMAL. LATER IT WAS DECIDED TO DISCONNECT THE CABLE FROM GIS TERMINATION AND TEST THE CABLE WITH SWITCH ON TO FAULT LOCATION. LATER THE FAULT WAS FOUND IN GIS AND WAS VT FAILURE SIEMENS SENT VT TO WORKS IMMEDIATELY FOR INVESTIGATION. TRACKING WAS VISIBLE ON THE EPOXY GAS TIGHT BUSHING INSIDE VT TANK. UPON RELIANCE INSTRUCTIONS HV TEST WAS PERFORMED ON THE SAME. 7

CASE STUDY 1 CONTINUED. 8

CASE STUDY-2: ROUTE-3 1000SQ.MM CABLE RUNNING FROM DTA MRS4 TO C2 MRS-1 CABLE TRIPPED ON JUNE16, 2HOURS AFTER CHARGING. CABLE FAULT WAS LOCATED WITH THE HELP OF CABLE FAULT LOCATOR AND WAS 58M AWAY FROM ONE OF THE JUNCTION IN SINGLE (RED) PHASE FROM MRS4. SITE INSPECTION REVEALED PHYSICAL DAMAGE TO THE CABLE. A SHARP PHYSICAL DAMAGE WAS ALSO OBSERVED ON THE INSULATION. FURTHER TO THIS INCIDENT ALL THE METALLIC SHOVELS WERE REPLACED WITH PLASTIC TO AVOID PHYSICAL DAMAGE TO THE CABLE 9

CASE STUDY-3 400 SQ.MM WITH DIAMETER OVER INSULATION BEING 74.1MM AND 1000 SQ.MM CABLE WITH DIAMETER OVER INSULATION 83.9MM. STRESS CONE USED AS A PART OF 220KV GIS CABLE TERMINATION DID NOT MATCH WITH THE DIAMETER OF THE CABLE RECEIVED AT SITE. STRESS CONE SUPPLIED FOR 400SQ.MM VARIED BETWEEN 76.5MM-81.5MM WHICH WAS NOT SUITABLE TO THE CABLE SUPPLIED. CABLE DIAMETER DIAMETER OVER INSULATION STRESS CONE RECEIVED AT SITE NEW STRESS CONE ENVISAGED 1000 SQ.MM 83.9MM 76.5MM TO 81.5MM 81MM TO 85.5MM 400 SQ.MM 74.1MM 67.5MM TO 72.5MM 72MM TO 75MM 10

CASE STUDY 4 CABLE BETWEEN STG TRANSFORMER AND 220KV GIS WAS CHARGED IN THE MONTH OF MAY 17. MINOR SPARK NEAR SUPPORT CLAMP AT THE TIME OF CLOSING THE BREAKER TO ENERGIZE THE CABLE. MANUFACTURER PERFORMED SWITCHING OVERVOLTAGE STUDY TO INVESTIGATE THE TRANSIENT STATE ASSOCIATED WITH THE ROUTE. BY EMTP SIMULATION APPROXIMATELY THE INDUCED VOLTAGE ONTO THE SURFACE OF THE CABLE WAS 300-600V. THIS SURFACE VOLTAGE OF CABLE RESULTED IN SPARK PHENOMENA BETWEEN CABLE THE INSULATOR/RUBBER CUSHION IN BETWEEN CABLE CLEAT AND CLAMP HAS NOT BEEN PROPERLY LOCATED TO INSULATE THE CABLE FROM THE CLAMP 11

SAT WITH EHV TEST KIT RELIANCE PROCURED THE DAC 300 MEGGER KIT TO TEST EHV CABLES AS SOAK TEST IS GETTING DIFFICULT DUE TO RELIABILITY OF THE NETWORK. THE SELECTION OF THIS TEST KIT IS MAINLY DUE TO PORTABLE IN NATURE AND PD TESTING IS POSSIBLE. HV TEST KIT IS COMMISSIONED IN AUGUST 2017.) TEST KIT INSIDE GIS TEST KIT OUTDOOR 12

MAINTENANCE PROCEDURES LAID FOR RELIABLE OPERATION. : THE 220KV CABLE NETWORK LAID ACROSS THE PLANT IS THE HEART OF THE PROJECT AND ANY HINDRANCE TO THE POWER SUPPLY SHALL HAVE HUGE FINANCIAL EFFECTS TO THE PLANTS DEPENDING ON THIS NETWORK. SO PREVENTIVE MAINTENANCE IS ONLY SOLUTION TO AVOID ANY SHUTDOWNS. FOLLOWING IS THE SUMMARY OF MAINTENANCE ACTIVITIES PERFORMED. SR. NO. ACTIVITY DETAIL OF ACTIVITY FREQUENCY 1 ROUTE SURVEY 2 THERMOGRAPHIC INSPECTIONS 3 PARTIAL DISCHARGE (PD) MEASUREMENT UNDERGROUND: LOOK FOR ANY EXCAVATION JOBS (MANUAL/MECHANIZED) NEAR TRENCHES, STORAGE OF MATERIALS OVER CABLE TRENCH, CONDITION OF ROUTE MARKERS, EXPOSURE OF CABLE TILES DUE TO SOIL EROSION DURING MONSOON. ABOVE GROUND: THIS IS A PATROL CHECK ALONG WHOLE CABLE ROUTE LINE EXPOSED IN THE AIR TO INVESTIGATE CONDITION OF CABLE AND SURROUNDING CONDITION OF ROUTE TO ASSESS PHYSICAL DAMAGE, ARCING OR TRACKING TRACES. ONLINE: THERMOGRAPHY TO BE CARRIED OUT FOR AIS END TERMINATIONS AND SUPPORT STRUCTURE/TRAYS FOR IDENTIFYING LOCAL HEATING. ONLINE: MEASUREMENT OF PARTIAL DISCHARGES TO THE RATED OPERATING VOLTAGE USING PD SENSORS. OFFLINE: MEASUREMENT OF PARTIAL DISCHARGE USING EXTERNAL VOLTAGE SOURCE BY MEGGER DAC 300. 13 WEEKLY 26 WEEKS 26 WEEKS

MAINTENANCE PROCEDURES LAID FOR RELIABLE OPERATION. : 4 SHEATH CURRENT MEASUREMENT 5 LINK BOX INSPECTION 6 EARTHING SYSTEM INSPECTION 7 PD BOX INSPECTION 8 9 10 SHEATH VOLTAGE LIMITER(SVL) PERFORMANCE CHECK CORONA MEASUREMENT ON OUTDOOR TERMINATION HARMONIC CURRENT MEASUREMENT ONLINE: MEASUREMENT OF SHEATH CIRCULATING CURRENT, TO ASSESS HEALTHINESS. THIS MEASUREMENT WILL REVEAL SHEATH PROBLEMS LIKE EXTERNAL DAMAGE OR PIN HOLES IN OUTER SHEATH. OFFLINE: LINK CONTACT RESISTANCE, VISUAL INSPECTION OF LINK BOX FOR MOISTURE INGRESS, CORROSION, ARCING TRACE ETC. ONLINE: MEASUREMENT OF SCREEN CURRENTS IN SINGLE POLE EARTHING CABLES IN TERMINATIONS AIS/GIS OFFLINE: BONDING INSPECTION, OVER SHEATH TEST, SVL TEST, MEASUREMENT OF EARTHING RESISTANCE, CONTINUITY TEST IN EARTHING CABLES OFFLINE: INSPECTION OF PD BOX FOR MOISTURE INGRESS, CORROSION, ARCING TRACE ETC. OFFLINE: VISUAL INSPECTION ONLINE: TO DETECT INSULATION SYSTEM FOR OUTDOOR TERMINATIONS AND SURROUNDINGS WITH CORONA CAMERA ONLINE: MEASUREMENT OF HARMONIC CURRENT WITH POWER ANALYSER 52 WEEKS 3 MONTHS 26 WEEKS 52 WEEKS 14

MAINTENANCE PROCEDURES LAID FOR RELIABLE OPERATION. : 11 INSULATION RESISTANCE OF OUTER SHEATH 12 HIGH VOLTAGE TESTING 13 INSPECTION OF CONNECTION POINT OFFLINE: IR VALUE OF SHEATH TO BE MEASURED USING DC VOLTAGE TEST. THIS IS TO BE DONE ALONG WITH OFFLINE HIGH VOLTAGE TESTING AND PD MEASUREMENT. OFFLINE: HIGH VOLTAGE TESTING TO BE CARRIED OUT BY USING EXTERNAL VOLTAGE SOURCE MEGGER DAC 300 OFFLINE: INSPECTION OF CONNECTION POINT FOR AIS TERMINATIONS TO BE CARRIED OUT FOR IDENTIFYING OVERHEATING OR CORROSION ON CONNECTION POINT OF CABLES. 15