Electron Clouds in the SPS: progress in the analysis of cures/mitigations measures and potential schedule of implementation J.M.

Similar documents
Control of Intra-Bunch Vertical Motion in the SPS with GHz Bandwidth Feedback

FILLING SCHEMES AND E-CLOUD CONSTRAINTS FOR 2017

PICS IN THE INJECTOR COMPLEX WHAT ARE WE TALKING ABOUT?

SUMMARY OF SESSION 4 - UPGRADE SCENARIO 2

Equipment Installation, Planning, Layout, organisation and updates

2008 JINST 3 S LHC Machine THE CERN LARGE HADRON COLLIDER: ACCELERATOR AND EXPERIMENTS. Lyndon Evans 1 and Philip Bryant (editors) 2

Mechanical aspects, FEA validation and geometry optimization

LHC Beam Instrumentation Further Discussion

Feedback Control of SPS E-Cloud/TMCI Instabilities

New Filling Pattern for SLS-FEMTO

PEP II Design Outline

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

SPEAR 3: Operations Update and Impact of Top-Off Injection

PEP-I1 RF Feedback System Simulation

TRANSVERSE DAMPING AND FAST INSTABILITIES

THE ANTIPROTON DECELERATOR (AD)

The Elettra Storage Ring and Top-Up Operation

Session 07 - What did we learn with beam in 2008? LHC Performance Workshop Chamonix Rhodri Jones on behalf of BE/BI & all our collaborators

Status and Plans for PEP-II

EPJ Web of Conferences 95,

The LEP Superconducting RF System

Bunch-by-bunch feedback and LLRF at ELSA

P. Emma, et al. LCLS Operations Lectures

The 2011 LHC Run - Lessons in Beam Diagnostics

arxiv:hep-ex/ v1 27 Nov 2003

Report on the LCLS Injector Technical Review

ANKA Status Report. N.Smale, A.-S. Müller, E. Huttel, M.Schuh Slides courtesy of A.-S. Müller and C.Heske.

Status of CTF3. G.Geschonke CERN, AB

beam dump from P2 losses this morning

AREAL- Phase 1. B. Grigoryan on behalf of AREAL team

LCLS Injector Technical Review

OPERATIONAL EXPERIENCE WITH CIRCULATING BEAM

SPS BPM system renovation. Roadmap & Milestones

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

Accelerator Instrumentation RD. Monday, July 14, 2003 Marc Ross

OPERATIONAL EXPERIENCE AT J-PARC

Upgrading LHC Luminosity

PEP II STATUS AND PLANS *

Minutes of the ALICE Technical Board, November 14 th, The draft minutes of the October 2013 TF meeting were approved without any changes.

Linac 4 Instrumentation K.Hanke CERN

Precision measurements of beam current, position and phase for an e+e- linear collider

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

Focus of efforts. ILC 2010, Mar/27/10 A. Seryi, BDS: 2

ABORT DIAGNOSTICS AND ANALYSIS DURING KEKB OPERATION

Top-Up Experience at SPEAR3

Implementing a Proton Beam Scanning System within an Operating Clinical Facility

The field cage for a large TPC prototype

Preparations for Installation, Testing and Commissioning based on Experience at CERN, SNS and Siemens

CLIC Feasibility Demonstration at CTF3

arxiv: v1 [physics.ins-det] 1 Nov 2015

Assembly of the HIE-ISOLDE accelerator cavities in a clean room.

Status of the Jefferson Lab Polarized Beam Physics Program and Preparations for Upcoming Parity Experiments

RF Power Generation II

RF upgrade program in LHC injectors and LHC machine

Program Risks Risk Analysis Fallback Plans for the. John T. Seeman DOE PEP-II Operations Review April 26, 2006

High Brightness Injector Development and ERL Planning at Cornell. Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics

An extreme high resolution Timing Counter for the MEG Upgrade

A HIGH POWER LONG PULSE HIGH EFFICIENCY MULTI BEAM KLYSTRON

Full IEFC workshop Feb.

Summary of the 1 st Beam Line Review Meeting Injector ( )

Digital BPMs and Orbit Feedback Systems

1. General principles for injection of beam into the LHC

Status of SOLARIS Arkadiusz Kisiel

PoS(EPS-HEP2015)525. The RF system for FCC-ee. A. Butterworth CERN 1211 Geneva 23, Switzerland

Development of an Abort Gap Monitor for High-Energy Proton Rings *

ANKA RF System - Upgrade Strategies

Proceedings of the 1997 Workshop on RF Superconductivity, Abano Terme (Padova), Italy

PEP-II longitudinal feedback and the low groupdelay. Dmitry Teytelman

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

A Fifteen Year Perspective on the Design and Performance of the SNS Accelerator

Status of Elettra, top-up and other upgrades

HHH. report from MULCOPIM 08. Frank Zimmermann LCU Meeting, 1 October 2008

Review of the CMS muon detector system

RF considerations for SwissFEL

STATUS OF THE SwissFEL C-BAND LINAC

PEP II Status and Plans

Development of Multiple Beam Guns for High Power RF Sources for Accelerators and Colliders

PUBLICATION. Measurement setup at light source operational: Milestone M4.3

PEP-II Disassembly Technical Systems

Detailed Design Report

Commissioning of the ATLAS Transition Radiation Tracker (TRT)

LEP OPERATION AND PERFORMANCE WITH ELECTRON-POSITRON COLLISIONS AT 209 GEV

An Operational Diagnostic Complement for Positrons at CEBAF/JLab

Monthly Progress Report Stanford Synchrotron Radiation Laboratory

New Results on the Electron Cloud at the Los Alamos PSR

FINAL DESIGN OF ILC RTML EXTRACTION LINE FOR SINGLE STAGE BUNCH COMPRESSOR

ILC Damping Ring Lattice Status Report. Louis Emery and Aimin Xiao Argonne National Laboratory Presented at KEK workshop Dec 18th, 2007

EUROFEL-Report-2007-DS EUROPEAN FEL Design Study

Commissioning and Performance of the ATLAS Transition Radiation Tracker with High Energy Collisions at LHC

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems

LEP Status and Performance in 2000

LHC COMMISSIONING PLANS

Tutorial: Trak design of an electron injector for a coupled-cavity linear accelerator

PEP-II Overview & Ramp Down Plan. J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007

Design and Simulation of High Power RF Modulated Triode Electron Gun. A. Poursaleh

A Cathode Development Cornell Cultera This scope includes all labor and purchases required produce photocathodes required by CBETA.

DESIGN AND PERFORMANCE OF L-BAND AND S-BAND MULTI BEAM KLYSTRONS

KEKB Accelerator Physics Report

Linac3 experience for LHC ion runs

Pseudospark-sourced Micro-sized Electron Beams for High Frequency klystron Applications

Transcription:

Electron Clouds in the SPS: progress in the analysis of cures/mitigations measures and potential J.M. Jimenez This talk is a summary of my views meant for a recommendation. For detailed results and pictures, please report to presentation given by M. Taborelli (TE/VSC on behalf of SPS-U SG) during the LIU Day http://indico.cern.ch/conferencedisplay.py?confid=112934

Main Topics Introduction Review of the studies made so far Proposed milestones Closing Remarks Acknowledgments: SPSU SG: G. Arduini, J. Bauche, C. Bhat, F. Caspers, S. Calatroni, P. Chiggiato, K. Cornelis, S. Federmann, E. Mahner, E. Metral, G. Rumolo, B. Salvant, M. Taborelli, C. in Vallgren, F. Zimmermann, H. Bartosik,. Pappaphilipou + speakers BE/RF: W. Hofle LIU/TF: R. Garoby, B. Goddard, V. Mertens EN/MME: for their continuous support TE/VSC: for the support in Labs and SPS tunnel (my apologizes for the missing names/groups)

Introduction Operating the SPS with: High bunch intensity, up to 2.5 10 11 p/bunch and Small emittances (LHC requirements) cannot be guaranteed since electron cloud limitations have been identified: Pressure rise: beam gas scattering, dose rates to tunnel and components Beam instabilities: transverse emittance blow-up and single bunch vertical instability This statement is confirmed by many studies and MDs carried out in the frame of the SPS-U Working Group chaired by E. Shapochnikova Identification and understanding of the potential limitations Significant progresses made on the effects on beams Beam scrubbing and other mitigation solutions mainly amorphous carbon a-c studied in the SPS

Review of the studies made so far Beam Scrubbing Beam scrubbing is successfully used since 1999 to reduce the electron cloud activity, BUT: Suppression was never achieved except in field free regions Residual electron cloud activity in the bending sections after 1 week of scrubbing Corresponds to a mitigation solution and NOT to a suppressing method Has an intrinsic limitation Reaching smaller SE (d) need larger electron bombardment doses (log behaviour) The closer to the threshold for a given bunch population and the lower the electron bombardment dose Electron cloud is a threshold mechanism with a build-up varying with train length Use higher bunch population and smaller bunch spacing during scrubbing Run at lower bunch population and larger bunch spacing Allows to profit from threshold effect, NO build-up

Feasibility and Status-of-the-art Review of the studies made so far Coatings (1/3) Magnetron sputtering is a mastered technology at CERN Amorphous carbon (a-c) selected since: Provides low SE (<1.2) and is only slightly affected by venting to atmosphere Does not require any activation (bake-out) M. Taborelli and al. Two options are possible: Coating made without removing the beampipe from the magnets Using the dipole field to enhance the glow discharge was not entirely successful: no homogeneity of the coating Using an internal magnetron sputtering looks more promising, successfully tested for 50 cm, tooling being prepared to coat a 2 m dipole chamber Coating made prior to installation of the beampipe in the magnets Magnetron sputtering in the test bench used for the LHC beampipes (LSS NEG) Best solution to get an homogeneous coating BUT need to open the magnets to install the new beampipes

Hard limits and Open questions Review of the studies made so far Coatings (2/3) Diagnostics available in the accelerator Indirect measurements of coating efficiency, not always very conclusive Coating optimization Cleaning the beampipe prior to coating is a concern: easier to do on a new beampipe Studies made in Bld867 on 15 magnets showed no activation of the liquids used Lower deposition rate to keep magnet s temperature to stay bellow 150 C during the coating Outgassing rate is 10 times higher (static vacuum) Considering to coat only part of the top/bottom surface Lifetime and peel off is of concern, positive feedback so far 1-2 year without ageing observed with samples installed on an ecloud monitor No evidence of peel off, good adherence» No dust coming out from the samples, event though exposed to electron bombardment and radiation dose Limited effect of venting, more studies needed Acceptable electron cloud load from remaining non-coated length? Short straight sections, radiation and alignment issues, etc.

Required infrastructures and tooling Review of the studies made so far Coatings (3/3) Option to do these activities in a building at the surface has major disadvantages No building available, building a new one is not compatible in term of schedule and costs Too many transports will increase the duration Go for ECX5 cavern solution (done for magnet consolidation campaign) Schedule implications Coating of the existing magnet beampipes is the preferred solution Transport dominates (up to 4 stands in parallel) Inserting a new coated chamber will be difficult to do in the ECX5 cavern Faster for coating BUT much more demanding for Magnet crew J. Bauche and al. Duration of magnet opening and closure dominate by far all activities if we go for new beampipes Phasing feasibility es BUT only if shutdown duration are at least 4 months: 3 shutdowns required Preparation and dismantling of ECX5 is taking time

Feasibility and Status-of-the-art Review of the studies made so far Clearing electrodes (1/2) Vertical configuration to take into account the trapping of the electrons spiraling along the dipole field lines Not pushed forward since resulting in a aperture restriction (~1 mm in total) Validated at low magnetic field in the PS Studies are much less advanced than coatings Hard limits and open questions Required clearing voltage to be assessed Can we found a value that works for all energies and beam characteristics? Cost and maintenance of the cabling and required power supplies Long term reliability: active system with feedthroughs Results in a vertical aperture restriction and impedance issue Difficult to equip the quadrupoles and short straight sections Engineering issues F. Caspers and al. Equipping new chambers will result in a significant increase in cost since mechanical tolerances for manufacturing (twist and straightness) shall be significantly decreased as compared to existing beampipes

Review of the studies made so far Clearing electrodes (2/2) Required infrastructures and tooling Similar to the one to be prepared for coatings In the tunnel, in ECX5 cavern In the surface, in an existing building or by building a new one Retrofitting in existing dipole chambers will require development of complex tooling Schedule implications and Phasing feasibility As for the coatings, phasing can be foreseen Must equip at least 2/3 of the SPS ring to be able to see an effect Transport time dominates if retrofitting the clearing electrodes in existing beampipes Duration of magnet opening and closure dominate by far all activities if we go for new beampipes

Review of the studies made so far High bandwidth feedback systems (1/3) Feasibility of the high bandwidth feedback system Study being carried out in the framework of LARP, this system requires: New pick-up for high bandwidth feedback system Long strip lines (at least 1.5 m) Complex design (accuracy and 50 Ohm impedance) Technically challenging but feasible Can be done at CERN, collaboration RF/MME? W. Hofle and al. New kicker for high bandwidth feedback system Complex design Technically challenging but feasible EM Simulations can be done by L Berkeley Lab in the framework of LARP High speed digitization and digital treatment Prototype system being developed in the framework of LARP, will be able to treat a small number of bunches only

Potential showstoppers Review of the studies made so far High bandwidth feedback systems (2/3) Emittance growth could be dominated by incoherent effects which cannot be damped Excessive power required to correct effects on all bunches due to the fast growth rates Challenging but not thought to be showstoppers Adjustment of the loop delay will be very delicate for the high frequency high bandwidth system (GHz) Mix-up with longitudinal motion possible if bunches not stable longitudinally Suppression of common mode signal crucial to avoid amplifier saturation and to allow good usage of dynamic range available Could be required to split the system into several bands in order to be able to cover the entire frequency range

Required infrastructures Review of the studies made so far High bandwidth feedback systems (3/3) Electronics and amplifiers shall be partially installed in the tunnel close to the wide-band pick-up and kickers Radiation and shielding issues, could require civil engineering: platform, concrete shielding New pick-up and kicker need modifications in the tunnel Layout modification, electronics, hardware and significant cabling Preferred location BA3 (dispersion suppressor), alternatively BA5 Schedule implications and Phasing feasibility Demonstrator for wide-band feedback Installation could take place during the 2011-12 winter stop (cabling) Validation of FB with demonstrator in 2013 decision for go-ahead Final system with new pick-up and kicker Pick-ups and kicker could be ready for late 2013 Final version of electronics could be available 2 years after complete validation with demonstrator: 2014-15 Layout modification and cabling could be advanced to 2012

Proposed milestones Feasibility studies on clearing electrodes Industrialisation of a-c coatings Enhancement of electron cloud for scrubbing purposes Deadline: end Sept 11 Development of additional electron cloud diagnostics SPS MD measurements to validate efficiency of proposed solutions Deadline: end Sept 11 Preparation of a prototype section: 1 or 2 half-cells for 2011-12 Technical Stop With all diagnostics Deadline: end Dec 11 Proceed to a complete evaluation Deadline: Sept 12 Define the strategy for 2013 Deadline: Oct 12 (Chamonix is too late) Installation of the pilot sector During shutdown 2013 Validation using a pilot sector (half an arc?) as from 2014 until 2017-18 shutdown: Deadline for final decision: end 2016 Full installation: Shutdown 2017-18

Closing Remarks Existing accelerator limited by electron cloud Suppression Mitigation Cures Clearing electrodes Coatings a-c Scrubbing Run Feedback systems Status in 10 R&D completed Prototyping Validation Industrialisation N N N N /N Started - /N - /N N N /N Status in 11 R&D completed Prototyping Validation Industrialisation? /N N - - /N N /N

Suppression: Clearing electrodes Closing Remarks Questions still to be answered Aperture, impedance, technical solution, full-scale feasibility, lifetime, quads, LSS, cabling, powering, etc. Mitigations a-c coatings Lifetime, stability with venting, outgassing rates, in-situ coating, LSS. Scrubbing runs Cures Feasibility and margin, MD time. High bandwidth feedback systems Simulations High speed digitization and digital treatment E-cloud budget, stability expected, emittance growth, impedance from electrodes, effectiveness of bandwidth feedback, etc. If we rely on beam scrubbing in the LHC why not in the SPS?

Closing Remarks Priorities versus Resources Satisfactory situation with mitigation solutions Scrubbing run is scheduled, MMDs have been requested We ll also learn from LHC scrubbing run Coating are progressing well, new approach recently tested showed very promising results from the industrialization point of view Strengthen efforts on diagnostics to improve the validation of the proposed solution with beams in the SPS Feedback systems can be on track with reasonable efforts Collaboration framework (LARP) exist Engineering and manufacturing to be internalized Clearing electrodes running out-of-phase as compared to other ongoing studies Resources to be allocated to achieve a status which could allow a decision making are still reasonable in theory, in practice, where to find them? Going for industrialization is another story Hollow cathode squared cell prototype