SECTION COMMUNICATIONS CABLING. (Sub-Sub-Bid Required, Part of Sub-Bid Section ELECTRICAL)

Similar documents
BILOXI PUBLIC SCHOOL DISTRICT. Biloxi Junior High School

Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR October 19, 2018 Construction Documents

California Polytechnic State University ITS Telecommunications PART 1 GENERAL SECTION AUDIO VISUAL STATION CABLES 1.

DESIGN!!GUIDELINES!!!!!

STRUCTURED CABLE SYSTEM (SCS)

SECTION COMMUNICATIONS HORIZONTAL CABLING

Primex Wireless, Inc. July, Wells Street Lake Geneva, WI

UNIFIED FACILITIES GUIDE SPECIFICATIONS

PROJECT SPECIFICATIONS UCO STEM TEACHING AND RESEARCH CENTER AV PACKAGE

REQUEST FOR QUOTE: TELECOMMUNICATIONS CABLING Library/Classroom Building, Beltline Campus

Minimum qualifications for the Telecommunications Engineer are: A. Texas Licensed Profession Engineer (PE)

Telecommunication Infrastructure Project September 20, 2002

Pre-bid Supplement #01 Communications Specifications and Additional Scope Project Bid: CM Date: 05/26/2017

Sapling Synchronous Communication Clock System Section Master Guide Specification Page 1 October 2013

Special Specification 6293 Adaptive Traffic Signal Control System

ADDENDUM NO. 2 This addendum consists of 8 pages. Kenai Peninsula Borough Purchasing & Contracting

MIDDLESEX COUNTY COLLEGE WIRE AND CABLE NETWORK REQUIREMENTS BH, CB, CH, ED, MH, LH, Camera Project

CASS COUNTY, MICHIGAN CASSOPOLIS, MI REQUEST FOR PROPOSAL SPECIFICATIONS

SPECIAL SPECIFICATION 6559 Telecommunication Cable

A. All communications equipment rooms shall be installed in a neat and workmanlike manner.

Sapling IP Clock System Section Master Guide Specification Page 1 October 2013

Sapling Wireless Clock System Section Master Guide Specification Page 1 October 2013

HONEYWELL VIDEO SYSTEMS HIGH-RESOLUTION COLOR DOME CAMERA

Category 6A UTP cables shall be tested and proved to conform to TIA-568-C.2 standards.

ACADEMIC SUCCESS CENTER THE COLLEGE AT BROCKPORT STATE UNIVERSITY OF NEW YORK PROJECT NO

SPECIAL SPECIFICATION 8540 Telecommunication Cable

CASS COUNTY, MICHIGAN CASSOPOLIS, MI REQUEST FOR PROPOSAL SPECIFICATIONS

WJHW, Inc. 6 April 2016 Texas Tech University Issue for CD Set Sports Performance Complex Lubbock, Texas

UNIVERSITY of NORTH DAKOTA LOW VOLTAGE COMMUNICATIONS STANDARDS FOR CABLING, PATHWAYS, AND SPACE

Telecommunciations Infrastructure Project September 20, A. Broadband radio frequency active and passive components

CHIEF BROADCAST ENGINEER

SPECIAL SPECIFICATION :1 Video (De) Mux with Data Channel

SECTION TESTING, IDENTIFICATION AND ADMINISTRATION

Section COMMUNICATION EQUIPMENT ROOM FITTINGS. Section Communications Cable Management and Ladder Rack

SECTION TESTING OF COPPER CABLES

AWT150C/AWT150CS/ AWT151C CCD Camera

VGA / Audio Extender Single CAT5 / CAT6 with RGB Delay Control & EQ

NYULMC AMBULATORY CARE CENTER FIT-OUT PHASE 1 Perkins & Will Architects PC 222 E 41st ST, NYC Project: Issued for GMP March 15, 2017

SECTION 5900 TRAFFIC SIGNALS CITY OF LEE S SUMMIT, MISSOURI DESIGN CRITERIA

Request for Purchase DESIGN AND INSTALLATION OF STRUCTURED COMMUNICATIONS CABLE SYSTEMS

HD Digital MPEG2 Encoder / QAM Modulator

Multi-Channel Passive Transceiver Hubs Installation Sheet

SECTION COMMUNICATIONS HORIZONTAL CABLING

SOLICITATION ADDENDUM NO. 1 ITB THE FOLLOWING CHANGES TO THE ABOVE CITED SOLICITATION ARE ANNOUNCED.

1x4, 1x8, 1x12, 1x16 VGA Extender / Splitter over Single CAT5

Request for Quote E- Rate Eligible Services Scope of Work - Wireless LAN and Cabling for Access Points

CHABOT- LAS POSITAS COMMUNITY COLLEGE DISTRICT

Colour Explosion Proof Video Camera USER MANUAL VID-C

Power Injector 1520 Series

User Manual. HDTV Cat 5 Extender Video and Audio Over One Cat 5 Cable Model SCP-11 and SCP-11D

HD Digital MPEG2 Encoder / QAM Modulator

CGA0101 Wireless Cable Gateway Quick Installation Guide

4, 8, 16 Port VGA/ Audio Extender / Splitter With Local Output with SPDIF Model #: VGA-C5SP-8

MWT-FM. Operation Manual. FM Single Channel Transmitter. man_mwtfm.

Introduction. Package Contents. Installation Requirements

Enable-IT 821P PoE Extender Quickstart Guide Professional Grade Networking

Sapling Wireless TalkBack Technology Clock System Section Master Guide Specification Page 1 October 2013

Register your product and get support at SDV5122/27. EN User manual

City of Winter Springs, FL

A. Section Includes: Division 1 applies to this section. Provide GPS wireless clock system, complete.

The University of Texas at Austin September 30, 2011

Owner s Manual. HDBaseT HDMI Over Cat5e/6/6a Extenders

HD Digital MPEG2 Encoder / QAM Modulator Get Going Guide

PHYSICAL FACILITIES Consultant s Handbook Specifications Division 27 Communication 0553 Identification for Communications Systems

Family Health Centers, Inc. Request for Proposal. for. Family Health Centers East Broadway Data and Communications Cabling Project

SECTION INTERCOMMUNICATIONS AND PROGRAM SYSTEMS

Request for Quote E- Rate Eligible Services Scope of Work Network Infrastructure and Structured Cabling

Information & Communications Technology Network Infrastructure Group. Network Infrastructure Standards June 2008

CABLING STANDARDS FOR

SECTION 686 VIDEO DECODER DESCRIPTION

4, 8, 16 Port VGA and Audio Extender / Splitter with Audio over Single CAT5

Instant 802.3af Gigabit Outdoor PoE Converter. Model: INS-3AF-O-G. Quick Start Guide


Effective earthing of screened cables

SECTION FIBER OPTIC STATION CABLES

1X4 HDMI Splitter with 3D Support

VGA & Audio Receiver SET over Single CAT5 with RGB Delay Control

RFIs AND RESPONSES; ANSWERS ARE IN RED.

IPSTB1200 /IPC3200 Media Client User guide

P.S.C. No. 2- Telephone. FRONTIER TELEPHONE OF ROCHESTER, INC. Section 7 Original Page No. 1

Tender Report for Supply and installation of LAN in *Biomedical Imaging and Bioinformatics Lab*

BUSD Ramona Middle School Gymnasium Project AV Project

Enable-IT 824WP Outdoor Waterproof PoE Extender Kit Quickstart Guide Professional Grade Networking

Owner s Manual. HDMI over Cat5/Cat6 Active Extender with Built-in 4K Upscaler. Models: B126-1A0-SC4K and B126-1A1-SC4K

USER GUIDE. AXIS T8640 Ethernet Over Coax Adaptor PoE+ ENGLISH

Class B digital device part 15 of the FCC rules

384A Adapter Installation Instructions

Passive DVI Extenders Over single Cat5/6/7 AT-DVI60SRS


Kramer Electronics, Ltd. USER MANUAL. Model: VM Video Component Distributor

17 19 PROFESSIONAL LCD COLOUR MONITOR ART

UNM IT/Telecommunications Guide Specification Labeling 11/07/

VGA & RS232 Extender SET over Single CAT5 with RGB Delay Control

blink USER GUIDE Bluetooth capable Reclocker Wyred 4 Sound. All rights reserved. v1.0

User Guide. Centrex Recording Interface

LF-IRX. 12 Month Limited Warranty LF-IRX. Remote Control Extender. Owner s manual. For customer service and technical information::

How to Implement PoE in Your Harsh Industrial Environment

Indoor/Outdoor Analog Wired Camera Model P-520 USER'S MANUAL

VGA, Audio & RS232 Extender SET over Single CAT5 with RGB Delay Control & IR Pass Through

HDMI 1.4 OVER SINGLE CAT5/6/7 EXTENDER WITH BI-DIRECTIONAL IR and RS232 TRANSMITTER & RECEIVER AT-HD4-100SR

Transcription:

SECTION 270000 (Sub-Sub-Bid Required, Part of Sub-Bid Section 260001-ELECTRICAL) PART 1 - GENERAL... 3 1.01 GENERAL REQUIREMENTS... 3 1.02 RELATED DOCUMENTS... 3 1.03 SECTION INCLUDES... 4 1.04 RELATED SECTIONS... 6 1.05 DEFINITIONS... 7 1.06 REGULATORY REFERENCES... 9 1.07 PERFORMANCE REQUIREMENTS... 11 1.08 SUBMITTALS... 11 1.09 QUALIFICATIONS... 15 1.10 INTERPRETATION OF DRAWINGS... 17 1.11 OBTAINING INFORMATION... 18 1.12 PERMITS, FEES, RULES AND REGULATIONS... 19 1.13 DELIVERY, STORAGE, AND HANDLING:... 19 1.14 PROTECTION OF WORK AND PROPERTY... 20 1.15 MATERIAL AND EQUIPMENT STANDARDS... 20 1.16 SEQUENCING AND SCHEDULING... 22 1.17 WARRANTY... 22 1.18 MAINTENANCE... 23 1.19 CERTIFICATES OF APPROVAL... 24 1.20 SUBSTANTIAL AND FINAL COMPLETION... 25 1.21 OPERATING INSTRUCTIONS AND MAINTENANCE MANUALS... 26 1.22 SEISMIC REQUIREMENTS... 27 PART 2 - PRODUCTS... 28 2.01 MANUFACTURERS:... 28 2.02 EQUIPMENT RACKS... 28 2.03 CABLE MANAGEMENT... 29 2.04 RACK SURGE-PROTECTED POWER STRIP... 29 2.05 WORK AREA OUTLETS... 30 2.06 CABLE SUPPORTS... 37 2.07 BONDING AND GROUNDING JUMPER CABLE... 38 2.08 UNSHIELDED TWISTED PAIR (UTP) CABLING SYSTEMS... 38 2.09 FIBER OPTIC CABLING SYSTEMS... 43 2.10 BROADBAND RF CABLING SYSTEMS... 46 2.11 AUDIO/VIDEO OUTLETS AND PATCH CABLING SYSTEM... 52 2.12 VGA OUTLETS AND CABLE... 53 2.13 PATCH PANEL, PATCH CABLE, AND LINE (STATION) CORD QUANTITIES... 55 2.14 ACCESS CONTROL SYSTEM WIRING... 56 2.15 SURGE AND LIGHTNING PROTECTION... 57 270000-1

PART 3 - EXECUTION... 60 3.01 GENERAL... 60 3.02 WORK... 62 3.03 ENTRANCE FACILITIES... 63 3.04 WIRING METHODS... 63 3.05 EQUIPMENT RACKS, CABINETS, AND BRACKETS... 64 3.06 WORK AREA OUTLETS... 65 3.07 TERMINATIONS... 66 3.08 CABLE PATHWAYS... 66 3.09 SEALING OF PENETRATIONS AND OPENINGS... 67 3.10 SEISMIC SUPPORTS, SUPPLEMENTARY STEEL AND CHANNELS... 68 3.11 CABLE SUPPORTS... 70 3.12 CABLE PROTECTION... 70 3.13 INSTALLATION OF CABLES... 71 3.14 UTP DATA CABLING SYSTEMS... 75 3.15 FIBER OPTIC CABLING SYSTEMS... 77 3.16 LABELING... 78 3.17 TELECOMMUNICATIONS IDENTIFICATION... 78 3.18 GROUNDING... 84 3.19 SLEEVING AND BUSHINGS... 85 3.20 TELECOMMUNICATIONS SYSTEMS TESTING... 86 3.21 TELECOMMUNICATIONS SYSTEMS DOCUMENTATION... 92 3.22 TRAINING... 93 3.23 ACCEPTANCE DEMONSTRATION... 94 3.24 PROJECT OWNER COORDINATION... 95 3.25 CLEANING UP... 95 3.26 PROJECT CLOSEOUT... 96 270000-2

SECTION 270000 (Sub-Sub-Bid Required, Part of Sub-Bid Section 260001-ELECTRICAL) PART 1 - GENERAL 1.01 GENERAL REQUIREMENTS A. Filed Sub-Sub Bids Required: 1. SUB-SUB-BID REQUIRING A PARAGRAPH E LISTING on the FORM FOR SUB-BID required per M.G.L. Chapter 149 Section 44A to 44L, as amended to date. The Electrical Subcontractor shall be responsible for all related building preparation and coordination as required, see specification for additional Paragraph E Listing requirements of the Listed Contractor, and coordination of responsibilities. Failure to meet or exceed the requirements of the Contractor, as detailed in this specification, shall be grounds to reject the applicable bidder. 2. It is the sole intent of this Paragraph E Listing to ensure to the end-user, single source responsibility from a single qualified Contractor. 3. Bidders listing themselves must provide documentation that they themselves are factory-authorized representatives of all systems specified. Bidders listing themselves may NOT sub-contract any portion of this specification. 4. This Section shall be provided/installed, in its entirety, and as follows by a single firm/company that is a qualified Contractor. a. The Contractor must be DCAM Certified by the state of Massachusetts Division of Capital Asset Management, in the category of: TELECOMMUNICATION SYSTEMS. b. The Contractor must customarily furnish the size, scope and nature of this section IN ITS ENTIRETY WITH LABOR CONSISTING OF EMPLOYEES WITH WHOM ARE ON THEIR PAYROLL and must be an authorized manufacturers representative, certified, experienced and qualified to provide, install, program, troubleshoot, train, warrant and service all the systems in this section in there entirety. B. Examine all Project Specifications and Drawings for requirements that affect this SECTION, whether or not such work is specifically mentioned in this SECTION. 1.02 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 270000-3

B. Examine all Project Specifications and Drawings for requirements which affect this Section whether or not such work is specifically mentioned in this Section. C. Examine all Project Specifications and Drawings for requirements that affect this SECTION, whether or not such work is specifically mentioned in this SECTION. 1.03 SECTION INCLUDES A. The work under this Section includes provision of all material, labor, equipment, and supplies, and the performance of all operations to provide a complete working Tel/Data and Video Communications Cabling System, as required by the Drawings and details, and as specified herein. Where the Drawings, Specifications, Codes, Regulations, Laws, or the requirements of the local Authority conflict, provide the higher quality and higher quantity indicated or required, and follow the strictest requirement. In general, the work includes, but is not limited to, the following: 1. Data and Voice Network Fiber and UTP Cabling Systems including: a. Horizontal UTP Cabling. b. Backbone Fiber and Multi-Pair UTP Cabling. c. Cable connecting hardware, patch panels, and cross-connects. d. Cable Management. e. Network Interface Outlet Faceplates. f. Modular Jacks. g. Patch Panels. h. Cross Connect Blocks. i. Cross Connect Cabling. j. Patch Cables and Line Cords. k. Innerduct. l. Connectors and Couplings. m. Equipment Racks and Cabinets. 2. Video Cabling including: a. Horizontal RF Broadband Coax Cabling. b. RF Broadband Coax Backbone Cabling. c. Outlet Faceplates. d. Modular Jacks. e. Line Cords. 3. Cabling for Access Control Equipment Provided by Others and for Interfaces to other Systems including: a. Wiring between control panel and card readers. b. Wiring between control panel and door hardware. c. Wiring between control panels. d. Wiring to interface control panel to Data Network. 270000-4

e. Wiring to interface control panel to CCTV cameras provided by others. 4. DEMARC to MDF/MCER Cabling: Extend all Data, Voice, and Video system backbone cabling including District Wide/WAN fiber cabling from DEMARC locations to MDF/MCER Room. 5. Nameplates, Labels, and Tags. 6. Cabling system identification products. 7. Terminations. 8. UL 497 Primary and UL 497A secondary line lightning and Surge Protection: a. Surge and Lightning Protection for UTP Backbone Cabling run through underground PVC conduits. b. Surge and Lightning Protection for Coax Backbone Cabling run through underground PVC conduits. 9. Pathways: conduits, sleeves, bushings and J-Hooks for Technology Infrastructure System pathways not shown on the Electrical drawings and not included in the Electrical Contractorʼs scope of work under Section 260001. 10. Protection of work. 11. Record Drawings and Documentation. 12. Staging. 13. Fireproofing of Penetrations and Openings provided by Electrical Contractor. 14. Access panels and doors. 15. Coordination with manufacturers, other trades, and Owner. 16. Testing and Certification of all cabling systems. 17. Operation and Maintenance Instructions and Manuals for the Section's work. 18. Documentation: As-built Drawings and Test Reports. 19. Training for all systems under the work of this Section. B. Provide and maintain in safe adequate condition all staging and scaffolding required for the proper execution of the work of this Section. C. The Contractor shall remove and re-install all ceiling tiles as required for the work of this section. 1. Replace all ceiling tiles damaged as a result of the work of this section at no cost to the owner. D. Removal of all trash from site and clean up of all areas of work under this SECTION E. Each Contractor shall perform daily clean-up of areas of work under this section and removal of all trash from the site. F. Coordinate work with that of all other trades affecting or affected by work of this Section. Cooperate with such trades to assure the steady progress of all work under the Contract. 270000-5

G. Perform additional work as directed by the architect per the requirement of Section 012200-UNIT PRICES. 1.04 RELATED SECTIONS A. Related Sections include the following: 1. SECTION-260001-ELECTRICAL for Pathways for Communication Systems, and Raceways and Boxes. 2. SECTION-087100-FINISH HARDWARE for Access Control System and Door Hardware. B. Except for coordination, or unless otherwise indicated, the following work is not included as part of the Communications Systems Contractorʼs responsibilities in this SECTION, and is to be performed by others as indicated: 1. Power Requirements provided by Electrical Contractor. 2. Cutting, channeling, and core drilling up to 5 in diameter shall be provided by Electrical Contractor. 3. Surface-mounted metal raceway shall be provided by the Electrical Contractor. 4. Cable tray, ladder rack, and snake tray shall be provided by the Electrical Contractor. 5. Sleeves and empty conduits to accessible point above ceiling or below floor shall be provided by the Electrical Contractor. 6. Floor boxes and poke-through devices shall be provided by the Electrical Contractor. 7. Standard device boxes with plaster rings for the Communications Cabling System shall be provided by the Electrical Contractor. 8. All required specialty boxes for the Communications System shall be furnished by this Contractor and installed by the Electrical Contractor. 9. Structural blocking to support wall and ceiling-mounted televisions/monitors shall be provided by SECTION 061000 ROUGH CARPENTRY. 10. Intrusion Detection cabling and equipment shall be provided by the Electrical Contractor. 11. Access Control equipment shall be provided under SECTION 087100-FINISH HARDWARE. 12. Video Surveillance CCTV, equipment shall be provided under SECTION 282300- VIDEO SURVEILLANCE AND DOOR ACCESS CONTROL. 13. Master Clock/Secondary Clock cabling and equipment shall be provided under SECTION 275300-CLOCK AND PROGRAM CONTROL. 14. Local Sound System cabling and equipment shall be provided by the Electrical Contractor. 15. Public Address/Intercom cabling and equipment shall be provided under SECTION 275116-PUBLIC ADDRESS/INTERCOM SYSTEM. 16. Voice/Telephone equipment shall be provided by Owner under separate contract. 270000-6

17. Data electronic equipment (computers, active data electronics, etc.) and final connections to wall outlets shall be provided by the Owner under separate contract. 18. Video Presentation equipment shall be provided by Owner under separate contract. 19. Interface with public utilities telephone service shall be arranged by the Ownerʼs service provider, and coordinated with the Communications Systems Contractor. 20. I-Loop and Wide Area Network outside cabling plant shall be provided by the Ownerʼs service providers and coordinated with the Communications Systems Contractor. C. The installation, operating cost, and maintenance of the controlled environmental conditions for equipment located on site, as required by the manufacturer, NFPA 70B, or as specified in these specifications, shall be the responsibility of the Owner. 1.05 DEFINITIONS A. Furnish: The term "furnish" is used to mean "supply and deliver to the project site, ready for unloading, unpacking, assembly, installation, and similar operations." B. Install: The term "install" is used to describe operations at project site including the actual unloading, unpacking, rigging in place, assembly, erection, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning, and similar operations. C. Provide: The term "provide" means to "furnish and install, complete and ready for the intended use". D. SECTION, Section, and Contract: SECTION, Section, and Contract refer to the requirements of the work to be preformed as specified herein. E. Basket Cable Tray: A fabricated structure consisting of wire mesh bottom and side rails. F. BICSI: Building Industry Consulting Service International. G. Channel Cable Tray: A fabricated structure consisting of a one-piece, ventilatedbottom or solid-bottom channel. H. Consolidation Point: A location for interconnection between horizontal cables extending from building pathways and horizontal cables extending into furniture pathways. I. Cross-Connect: A facility enabling the termination of cable elements and their interconnection or cross-connection. J. IDC: Insulation displacement connector. 270000-7

K. Ladder Cable Tray: A fabricated structure consisting of two longitudinal side rails connected by individual transverse members (rungs). L. Outlet/Connectors: A connecting device in the work area on which horizontal cable or outlet cable terminates. M. Solid-Bottom or Non-ventilated Cable Tray: A fabricated structure consisting of longitudinal side rails and a bottom without ventilation openings. N. Trough or Ventilated Cable Tray: A fabricated structure consisting of longitudinal side rails and a bottom having openings for the passage of air. O. UTP: Unshielded twisted pair. P. Acronyms: 1. AFF Above Finished Floor 2. AOR Area of Refuge/Rescue 3. AV Audio Visual 4. BAS Building Automation Systems 5. BDF Building Distribution Frame 6. CAT Category 7. CATV Cable Television 8. CCTV Closed Circuit Television 9. DEMARC Demarcation Point 10. EF Entrance Facility 11. EIA Electronics Industries Association 12. EMI Electromagnetic interference 13. ER Equipment Room 14. HVAC Heating, Ventilating, and Air-conditioning 15. IDC Insulation-Displacement Connections 16. IDF/ICER Intermediate Distribution Frame or Intermediate Communications Equipment Room 17. LAN Local Area Network 18. MDF/MCER Main Distribution Frame or Main Communications Equipment Room 19. MH Maintenance Hole. 20. MM Multi-mode 21. MUTOA Multi-user telecommunications outlet assembly, a grouping in one location of several telecommunications outlet/connectors. 22. OEM Original Equipment Manufacturer 23. OTDR Optical Time Domain Reflectometer 24. PoE Power over Ethernet, IEEE 802.3af standard 25. PP Pull Point 26. PVC Polyvinyl Chloride. 27. RCDD Registered Communications Distribution Designer 28. RF Radio Frequency 270000-8

29. RMU Rack Mount Unit 30. RPS Redundant Power Supply 31. SM Single-mode 32. SMATV Satellite Master Antennae Television 33. SP Standards Proposal (EIA/TIA) 34. STP Shielded Twisted Pair 35. TLT Telecommunications Infrastructure Layout Technician 36. TR Telecommunications Room 37. UPS Uninterruptible Power Supply 38. UTP Unshielded Twisted Pair 39. VoIP Voice over IP Telephone System. 40. VMIU Video Mask Interdiction Unit 41. WAO Work Area Outlet 42. WAP Wireless Access Point 43. WI-FI Wireless Fidelity 44. WLAN Wireless Local Area Network 1.06 REGULATORY REFERENCES A. Comply with applicable requirements of the following standards and those others referenced in their SECTION. B. All work and materials shall conform in every detail to the rules and requirements of the National Fire Protection Association, the local Electrical Code and present manufacturing standards. C. All materials shall be UL Listed and shall be marked as such. If UL has no published standards for a particular item, then other national independent testing standards shall apply and such items shall bear those labels. Where UL has an applicable system listing and label, the entire system shall be so labeled. D. All materials shall be ETL Verified (not just tested) to be Category 6A component and channel compliant. E. Materials and equipment shall be manufactured, installed and certified as specified in the latest editions of applicable publications, standards, rulings and determinations: The Contractor shall comply and reference the latest editions of the following standards including any related addendum or TSBʼs not listed below: 1. ANSI/TIA/EIA-568-B1, Commercial Building Telecommunications Cabling Standard Part 1: General Requirements 2. ANSI/TIA/EIA-568-B.2-1, Commercial Building Telecommunications Cabling Standard Part 2: Balanced Twisted Pair Cabling Components 3. ANSI/TIA/EIA-568-B.2-1, Commercial Building Telecommunications Cabling Standard Part 2: Balanced Twisted Pair Cabling Components 4. ANSI/TIA/EIA-568-B.2-1-2000, Commercial Building Telecommunications Cabling Standard Part 2: Balanced Twisted Pair Cabling Components, 270000-9

Addendum 1 - Transmission performance specification for 4 pair 100 Ohm Category 6A cabling 5. ANSI/TIA/EIA-568-B.2-1, Commercial Building Telecommunications Cabling Standard Part 3: Optical Fiber Cabling Components 6. ANSI/TIA/EIA-569-A, Commercial Building Standard for Telecommunications Pathways and Spaces 7. ANSI/TIA/EIA-570-A, Residential Telecommunications Cabling Standard 8. ANSI/TIA/EIA-606-A. Administration Standards for the Telecommunications Infrastructure of Commercial Buildings 9. ANSI/TIA/EIA-607, Commercial Building Grounding and Bonding Requirements for Telecommunications 10. ANSI-J-STD-607A-2002, Commercial Building Grounding and Bonding Requirements for Telecommunications 11. ANSI/TIA/EIA 758, Customer Owned Outside Plant Telecommunications Cabling Standard 12. ANSI/ICEA, Insulated Cable Engineers Association 13. BICSI TDMM, Telecommunications Distribution Methods Manual (TDMM) - 11 th Edition 14. BICSI Customer Owned Outside Plat Design Manual 3 rd Edition 15. FCC Part 15 (addresses electromagnetic radiation). 16. FCC Part 68 (connection of premises equipment and wiring to the network).nec National Electric Code (NEC) 17. National Electrical Safety Code Handbook. (NESC) 18. NFPA-70 National Fire Protection Association (NFPA 70) F. Descriptions: 1. ANSI - American National Standards Institute 2. EIA Electronics Industries Association 3. BICSI Building Industry Consulting Service International 4. FCC Federal Communications Commission 5. NEC National Electrical Code 6. NEMA National Electrical Manufactures Association 7. NFPA National Fire Protection Association 8. OSHA Occupational Safety and Health Administration 9. SCTE Society of Cable Television Engineers 10. SP Standards Proposal (EIA/TIA) 11. TIA Telecommunications Industry Association 12. TIA/EIA Telecommunications Industry Association/Electronics Industry Alliance 13. TSB Technical Systems Bulletin (EIA/TIA) 14. UL Underwriters Laboratories G. EIA/TIA Building Telecommunications Wiring Standards: 1. Sound Systems, EIA 160. 2. Loudspeakers, Dynamic Magnetic Structures, and Impedance, EIA 299 A. 3. Racks, Panels, and Associated Equipment, EIA 310 A. 270000-10

4. Amplifiers for Sound Equipment, SE 101 A. 5. Speakers for Sound Equipment, SE 103. 6. No. 568B Series - Telecommunications Wiring Standards 7. No. 569A - Telecommunications Pathways and Spaces 8. No. 606 - The Administration Standard For the Telecommunications Infrastructure 9. No. 607 - Grounding/Bonding 10. Article 300, Part A. Wiring Method. NFPA 70. 11. Article 250, Grounding, NFPA 70. 12. Article 310, Conductors for General Wiring, NFPA 70. 13. Article 725, Remote Control, Signaling Circuits, NFPA 70. 14. Article 800, Communication Systems, NFPA 70. H. Materials and workmanship shall conform to the latest issue of all industry standards, publications, or regulations referenced in this SECTION and with the following references as applicable. 1. NFPA 70 National Electrical Code. 2. NFPA 72 National Fire Alarm Code. 3. NFPA 101 - Life Safety Code. 1.07 PERFORMANCE REQUIREMENTS A. Include GENERAL CONDITIONS, SUPPLEMENTARY GENERAL CONDITIONS and Division 1 as part of this Section. B. Examine all Project Specifications and Drawings for requirements that affect work of this Section, whether or not such work is specifically mentioned in this Section. C. General Performance: Backbone cabling system shall comply with transmission standards in TIA/EIA-568-B.1, when tested according to test procedures of this standard. D. General Performance: Horizontal cabling system shall comply with transmission standards in TIA/EIA-568-B.1, when tested according to test procedures of this standard. 1.08 SUBMITTALS A. Submit complete shop drawings, data, schedule of values, and samples in accordance with SECTION 013300 SUBMITTALS. B. Submit all related Submittal information at one time. 270000-11

1. SUBMIT ALL ITEMS IN A SPECIFICATION SECTION AT THE SAME TIME. An incomplete submittal will be held until a complete submittal is accumulated, or may be rejected without further review and returned to the applicable parties. Include a copy of the Specification Paragraphs pertaining to each item submitted. C. Submit Installer Qualifications. D. Schedule of Values: Provide a schedule of values itemizing costs for labor and materials with additional breakdowns for rough and finish work. As a minimum, provide the following breakdown, by phase where applicable: 1. Each major piece of equipment 2. Other equipment by category 3. Material and labor for each item. 4. Equipment installation by category and each major piece of equipment. a. Roughing work. b. Finish work. 5. Testing. 6. Owner training. 7. Operation and Maintenance Manuals. 8. Record drawings. E. Submit for review, within thirty days after signing the Contract and prior to the submission of any Submittal, an itemized list of manufacturers of material and equipment and of Contractors proposed to be used under this Contract. Include a schedule of anticipated submittal and anticipated lead times after release of reviewed Submittal. F. Provide a Submittal Bill of Materials, with column headings that clearly identify the information requested herein for each and every item submitted. 1. Each and every specification sheet submitted shall include a page number in the lower outside corner of the sheet. Double-sided specification sheets shall be identified by two (2) separate page numbers. 2. On each and every specification sheet submitted, indicate the applicable part numbers(s) on the sheet(s) by one of the following methods: a. Circling the applicable part number(s) b. Putting an arrow next to the applicable part number(s) c. Highlighting the applicable part number(s) G. The Submittal Bill of Materials Index/Equipment List column headings shall identify the following minimum information. Submittals must be submitted using the following headings in the order indicated from left-to-right on the Bill of Materials Index/Equipment List: 270000-12

1. All Bill of Material items shall be listed in the Bill of Material Index / Equipment List, in the same order as they appear in the specification. 2. Specification Section Number, reference specification section number/location, that identifies each individual item, for every item specified and submitted. a. Example of Specification Section number/location: 2.13, B., 7., c., 4), e) 3. Description of each item 4. Manufacturerʼs Name for each item 5. Manufacturerʼs Model # for each item 6. Quantity of each item being provided 7. Submittal Page Number(s) of specification sheet(s) for each item H. Any Submittal that does not include a submittal Bill of Materials, and provide a minimum of the information requested herein, shall be rejected without further review and returned to the applicable parties. I. Submittal shall include complete Specifications and all applicable addendums, including type of materials, electrical characteristics, capacities, performance, and power requirements, to determine compliance with Contract Documents. All data submitted, including wiring diagrams, shall be complete for all equipment, and shall apply only to this specific project. All extraneous material shall be deleted or marked out. Items to be supplied shall be specifically indicated, using a method that will be visible after photocopying. 1. Submit equipment prints, inter-panel and intra-panel, full electronic wiring diagrams and specification sheets for each item specified herein. Specification Sheets shall be submitted on all items, including cable types. 2. Submit three copies of all repair and maintenance manuals. 3. Shop drawings detailing the Instructional technology network system including, but not limited to, the following: a. Built-in station arrangement. b. Equipment cabinet arrangement. 4. Wiring diagrams, detailing wiring for power, signal, and control, differentiating clearly between manufacturer-installed wiring and field-installed wiring. Identify terminals to facilitate installation, operation, and maintenance. 5. Submit wiring diagrams showing typical connections for all equipment. 6. Provide a riser diagram for the system showing in technically accurate detail all connections, interconnections, and provisions available, and made for adaptability of all specified future functions, and including all calculations, charts, and test data necessary to demonstrate that all systems and system components deliver the specified signals, grades, and levels at all required points and locations. 7. Submit a valid certificate from the manufacturer(s) indicating the Communications System Bidder is an authorized installer for the system (or systems) being submitted. 270000-13

8. Submit a valid certificate of completion of installation and service training on the latest up-to-date version of the manufacturerʼs equipment being provided for a present employee. J. Regardless of any information included in the submittal submitted for review, the requirements of the Drawings and Specifications shall not be superseded in any way by the review. Review by the Architect does not relieve responsibility for submittal errors or from meeting the requirements of the Contract Documents. K. It is intended that Submittal data be complete and accurate at the first submission L. A minimum period of 15 working days, exclusive of transmittal time, will be required in the Architectʼs office each time Shop Drawings, Product Data, layout drawings, catalog data and brochures are submitted or resubmitted for review. A minimum period of 20 working days, exclusive of transmittal time, will be required for reviewing substitute materials or manufacturer. These time periods shall be considered when scheduling the work. M. If proposed equipment deviates from the Specifications or Drawings, indicate in writing on Company letterhead those differences and provide sufficient data to justify acceptance. FAILURE TO INDICATE DEVIATIONS OR SUBSTITUTIONS IMPLIES FULL COMPLIANCE WITH DRAWINGS AND SPECIFICATIONS. N. The term by others or similar wording shall not be used on Submittal. Submittal shall state by whom related items of work are to be provided. Where not indicated, it is implied that the work or item is provided under this Contract. O. Indicate clearly all equipment, components or assemblies that are not NRTL listed or labeled. Failure to indicate otherwise implies NRTL-listing or labeling. Products found not to be NRTL-listed or labeled where such listing or labeling is available shall be replaced. P. Include in Submittal: 1. Application conditions and limitations of use stipulated by product testing agency specified under regulatory requirements. 2. Instructions for storage, handling, protection, examination, preparation, operation, and installation of product. Q. Maintain at the job site the latest equipment submittal showing the action taken by the Architect. Make this submittal available to Architect. R. Product Data: Submit catalog data sheets or other published materials showing appearances, electrical ratings characteristics and connection requirements, performance characteristics, dimensions, weights, installation methods, and space requirements of equipment and its accessories, as listed below and required by the individual paragraphs: 270000-14

1. Identification Methods 2. Grounding and Bonding 3. Electrical Connections for Equipment 4. Supports and Supplementary Steel 5. Electrical Identification 6. Test Report Formats 7. Test Equipment S. Shop Drawings: Submit shop drawings that indicate physical size and arrangement, (plans and elevations) construction details, provisions for conduits, access requirements for installation and maintenance, finishes, and materials used in fabrication. Supplement shop drawings with wiring diagrams and information as described under Product Data. Provide shop drawings as required by the individual paragraphs. 1.09 QUALIFICATIONS A. The Communications Systems Contractor (Firm and Employees) shall be experienced in the operations they are engaged to perform. B. Bidders must provide documentation that they themselves are factory-authorized representatives of all systems specified. C. This Section shall be provided/installed, in its entirety, as follows by a qualified Communications Systems Contractor 1. The Communications Systems Contractor must customarily furnish the size, scope and nature of this section and must be an authorized manufacturerʼs representative, certified, experienced and qualified to provide, install, program, troubleshoot, train, warrant and service all the systems in this section in there entirety. 2. The Communications Systems Contractor must provide (as part of the submittal process) a list of at least five (5) projects (provide the following information for each project: name, address, contact person, title of contact person, telephone number of contact person) of similar size, scope, and nature, and demonstrate that these projects were; furnished with persons on the Communications Systems Contractorʼs payroll whom were authorized, certified, experienced and qualified to provide, install, program, troubleshoot, train, warrant and service these projects, in their entirety, satisfactorily. a. For each project listed by the Communications Systems Contractor, provide the following information: 1) List all the systems provided for the project. 2) Manufacturerʼs name and model number of each system provided on the project. 3) Manufacturerʼs telephone numbers. 270000-15

4) A valid certificate from each manufacturer, indicating that the Telecommunications Systems Contractor is an authorized distributor for the system (or systems). 5) A valid certificate of completion of installation and service training from each applicable manufacturer by a present employee of the Communications Systems Contractor. D. Submit documentation certifying a minimum of five years of continuous, recent experience on similar projects, and demonstrating previous success with commercial communication systems as specified herein. 1. The Communications Systems shall hold recent, up-to-date licenses, certifications, and training certificates for the equipment to be installed, in the area where the project is located. E. UL Compliance: The communication system supplied shall be listed by Underwritersʼ Laboratories under UL Standard 1459 for Telephone Appliance and Equipment. A copy of the UL listing card for the proposed system shall be included with the Contractor's submittal. F. UL Compliance: Systems having UL listings on components only, such as power supplies, amplifiers, trunk cards, etc. shall not be acceptable. G. FCC Approval: The system shall be approved for direct interconnection to the telephone utility under Part 68 of FCC rules and regulations. Systems that are not FCC approved or that utilize an intermediary device for connection, shall not be considered. Provide the FCC registration number of the system being proposed as a part of the submittal process. H. Qualification Statement: Submit the following for Owner review and verification of qualifications. 1. Documented evidence demonstrating bidder has been in business for at least five continuous years, and that his/her primary business is providing telecommunication systems similar to those specified herein. 2. References: Furnish all contact names from the last five (5) similar projects, including the General Contractor, Owner's Representative, Architect and Electrical Engineer. Indicate project locations, scope, date of installation and current phone numbers where all the contacts can be reached. 3. Evidence of ability: Qualified Instructional Technology Network System Installation firms shall have demonstrable design and installation training, with certifications of competence. Certified training shall be industry recognized and at least equal to: a. Building Industry Consulting Service International, Inc. (BICSI) b. Siemon Cabling System Certified Installer. c. Authorized Belden-ADC Cabling System Certifier. d. AVAYA SCS Certified PDS Installer. 270000-16

e. IBM Qualified Installer. I. Provide a full time on site Project Manager to supervise the project. J. Maintain at the site an updated copy of the Manufacturer Trained Installers list, including a copy of their training documentation from the manufacturer. This documentation shall be made available to the Architect upon request. K. Product Demonstration: The system Contractor may be required to provide product demonstrations and interviews with the owner and his representatives, or may be required to provide side-by-side demonstrations with other vendors. These demonstrations may be required before a contract is issued. Offerers should be prepared to demonstrate each feature called for in this specification. 1.10 INTERPRETATION OF DRAWINGS A. All work indicated on the Drawings is intended to be approximately correct to scale, but figures, dimensions, and detailed Drawings are to be followed in every case. The Drawings shall be taken in a sense as diagrammatic. Size of raceways and methods of running them are indicated, but it is not intended to show every offset and fitting, nor every structural difficulty that may be encountered. B. Locations indicated on the Drawings are approximate, and it is intended that all equipment shall be located in accordance with the general and detail Drawings of the construction proper. Coordinate the location, mounting heights, and routing of cabling work with other tradesʼ requirements and with field conditions. C. All measurements shall be taken at the building before fabrication commences. D. Schematic diagrams shown on the Drawings indicate the required functions. Standard diagrams of the manufacturer may be used for the functions indicated without exact adherence to the Schematic Drawings shown. Work required for such deviations shall be provided. E. Items referred to in singular number in Contract Drawings shall be provided in quantities necessary to complete work. F. The right is reserved to make reasonable changes in locations of work prior to rough-in at no additional cost. G. Where Drawings or Specifications conflict or are unclear, advise the Architect in writing before Award of Contract. Otherwise, interpretations of Contract Documents by the Architect shall be final, and no additional compensation shall be permitted due to discrepancies or ambiguities that are resolved according to the Architect's interpretation. 270000-17

H. Drawings and Specifications form complimentary requirements. Provide work indicated on the Drawings, but not specified; and work specified, but not indicated on the Drawings as though explicitly required by both. I. Drawings and Specifications do not undertake to indicate every item required to produce a complete and properly operating installation. Materials, equipment, or labor that is not indicated, but that can be reasonably inferred to be necessary for a fully complete, secure, and properly operating installation suitable for the intended use, shall be provided. J. Drawings do not limit responsibility of determining full extent of work required by Contract Documents. Refer to all Drawings and Specifications that indicate types of construction in which work shall be installed, and work of other trades with which work of this Section must be coordinated. K. Except where modified by a specific notation to the contrary, it shall be understood that the indication or description of any item, in the Drawings or Specifications or both, carries with it the instruction to provide the item, regardless of whether this instruction is explicitly stated as part of the indication or description. L. Where Drawings or Specifications do not coincide with manufacturer's recommendations, or with applicable Codes and Standards, alert the Architect in writing before installation. Otherwise, make changes in installed work as the Architect requires without additional cost. M. It is the intent of these Contract Documents to have systems and components that are fully complete and operational, and fully suitable for the intended use. There may be situations in the documents where insufficient information exists to precisely describe a certain component or subsystem, or the routing of a component. In such cases, where the Installer has failed to notify the Architect in writing of the situation prior to Contract Award, the Installer shall provide the specific component or subsystem with all parts necessary for the intended use, fully complete and operational, and installed in workmanlike manner, either concealed or exposed per the design intent. N. In situations where potential conflict exists, or where the Installer believes guidance is required, submit a sketch identifying proposed solution, and the Architect shall review, note if necessary, and return this sketch appropriately marked for use by the Installer. 1.11 OBTAINING INFORMATION A. Obtain from the manufacturer the proper method of installation and connection of the equipment that is to be furnished or installed. Obtain all information that is necessary to facilitate the work and to complete the project. Include all such information in Operation and Maintenance Manuals. 270000-18

1.12 PERMITS, FEES, RULES AND REGULATIONS A. Give the proper Authorities all requisite notices or information relating to the work under this Section. Obtain and pay for all fees, licenses, permits and certificates. Comply with the rules and regulations of all local, state, and federal authorities having jurisdiction, Building Codes, the rules and regulations of the National Board of Fire Underwriters, and the public utility companies serving the building. B. Public utility back charges will be paid for by the Owner and are not to be included in the base bid. Markups on utility back-charges will not be allowed. C. Perform work in accordance with Nationally Recognized Testing Laboratory (NRTL) listing or labeling requirements, OSHA regulations, NFPA Standards, Electrical Code, the Americans with Disabilities Act Accessibility Guidelines (ADAAG), EIA/TIA, and BICSI. The Drawings and Specifications do not attempt to indicate all work required by codes, regulations, and authorities. D. Nothing in these Contract Documents shall be construed to permit work not conforming to applicable codes and regulations. When conflicts occur, the more restrictive requirements shall govern. E. Toxicity: Comply with applicable codes and regulations regarding toxicity of combustion products used or hazardous materials used, or disposed of. F. Legally dispose of all material. Adhere to all regulations regarding disposal of hazardous material. Recycle hazardous material where recycling is possible. Submit certificates of legal recycling or disposal to the Architect. Include copy in the Owner and Maintenance Manual. G. Should the Facility have established building standards, rules, or regulations, obtain a copy from the Building Owner, and comply with them. 1.13 DELIVERY, STORAGE, AND HANDLING A. Do not deliver items to the site until all specified submittals have been submitted to, and approved by, the Architect. B. Deliver materials in original packages, containers, or bundles bearing brand name, or identification of manufacturer or supplier. C. Deliver, store, protect, and handle products in accordance with recommended practices listed in Manufacturer's Installation and Maintenance Manuals. D. Protect materials from damage due to moisture, direct sunlight, excessive temperatures, surface contamination, corrosion, and damage from construction operations and other causes. 270000-19

1.14 PROTECTION OF WORK AND PROPERTY A. Be responsible for the care and protection of all work included under this Section until it has been tested and accepted. B. Protect all equipment and materials from damage from all causes, including theft. All materials and equipment damaged or stolen shall be replaced with equal material or equipment at the option of the Architect and Owner. C. Materials and equipment stored for this project shall be protected and maintained according to the manufacturer's recommendations and requirements, and according to the applicable requirements of NFPA 70B. D. Protect all equipment, outlets and openings with temporary plugs, caps and covers. Protect work and materials of other trades from damage that might be caused by work or workmen, and make reparations for any damage caused. E. Use caution to avoid damage to existing work, and to prevent harm to personnel working in all areas. F. Observe all safety precautions and requirements for the construction. G. When open-flame or spark-producing tools, such as blower torches, welding equipment, etc., are required in the process of executing the work, the General Contractor shall be notified not less than twenty four hours in advance of the time that the work is to begin and the location where the work is to be performed. Provide, where necessary, fire protective covering and maintain a constant non-working fire watch where work is being performed, and until it is completed. H. The General Contractor and the Installer are responsible for initiating, maintaining, and supervising all safety precautions and requirements during construction. 1.15 MATERIAL AND EQUIPMENT STANDARDS A. Manufactures: 1. Manufacturers are listed for the purpose of establishing a specification standard for that particular item. Other manufacturersʼ shall be considered for approval, provided they meet or exceed all the specification requirements. B. Except where no substitutions are indicated, where materials or equipment are specified by patent proprietary name, or name of the manufacturer, such specification is used for the purpose of establishing a standard for that particular item. If more than one manufacturer is listed, the Contract Documents are based on the first manufacturer listed, and every other manufacturer is considered a substitution. 270000-20

C. If three or more manufacturers are indicated without the term "or equal", or "or approved equal", then the material and equipment shall be supplied by one of those indicated and that material and equipment shall conform in all respects to the Drawings and Specifications. D. No equipment or material shall be used, furnished, or installed unless previously reviewed and accepted by the Architect. E. Substitutions may be offered for review, provided the material, equipment, or process offered for consideration is equal in every respect to that indicated or specified. The request for each substitution must be accompanied by a letter from an Authorized Representative of the manufacturer and the Installer, indicating that the substitution meets or exceeds all specified requirements. Provide complete specifications, drawings, or samples to properly appraise the materials, equipment, or process. Acceptance of substitutions shall be based on performance, appearance, use, maintenance requirements, durability, aesthetics, physical arrangement, size, and quality. F. If a substitution of materials or equipment, in whole or in part, is made, bear the cost of any changes, engineering, or construction, necessitated as a result of said substitution. G. Materials shall be new, unused, of recent manufacture, not previously installed, full weight, standard, the best quality of its kind, and acceptable to the Architect. H. Provide NRTL-listed or labeled products whenever there are NRTL standards, listings, or labeling available for that product category. I. The Specifications or notes and description following a catalog number is basically to identify the item, but may also call for accessories, options, or modifications that are not indicated in the catalog number. J. Reviewed submittals on substitute equipment shall only allow the Installer to proceed with installation. The substitution shall not be considered equal until such time as the Architect and Owner's Representative have completely accepted the installation. All costs for removal, relocation, or replacement of said Substitution shall be at the risk of the Installer. K. Provide products of one manufacturer for each classification of equipment. L. Provide documentation from both specified Product Manufacturer and the proposed substitute Product Manufacturer with separate comparative analysis sheet that matches product specification item for item. Substitutes shall not be considered unless accompanied by this documentation. 270000-21

1.16 SEQUENCING AND SCHEDULING A. Coordinate the work of this Section with the respective trades responsible for installing interface work, and ensure that the work performed hereunder is acceptable to such trades for the installation of their work. B. Refer to the overall scheduling of the work of the project. Schedule work, process Submittal and order materials and equipment to conform to this schedule, and install work to not delay nor interfere with the progress of the project. C. Inform Architect immediately of any delays or potential delays. Furnish manufacturer's letter to verify order date, equipment delays, expected shipment date, order number, and potential remedies to speed up delivery. Any costs to speed up delivery shall be implemented at no cost to the project if the equipment or material was not ordered as soon as possible after Contract award or within the time frames indicated with the Submittal. D. Include premium time required to comply with the project scheduling and phasing. E. Be aware of, and plan for, project scheduling and phasing. Provide for complete continuous operation of all systems. Coordinate scheduling and phasing with the Architect, Owner, other Trades, and the General Contractor. 1.17 WARRANTY A. Provide a warranty for one (1) year against defects in material and workmanship on all data cabling components, equipment, software, systems, cabling, etc. specified. Warranty shall start at time of substantial completion or routine use, which ever comes first. Warranty shall include all materials, equipment, and work furnished or installed under this Section. Any failure due to defective material, equipment, installation, or workmanship that may develop shall be corrected at no expense to the Owner, including all materials, labor, travel, expenses, system diagnostics, and damage to areas, materials, and other systems resulting from such failures. B. Provide a warranty for two (2) years against defects in material and workmanship on all RF Broadband video cabling components, equipment, software, systems, cabling, etc. specified. Warranty shall start at time of substantial completion or routine use, which ever comes first. Warranty shall include all materials, equipment, and work furnished or installed under this Section. Any failure due to defective material, equipment, installation, or workmanship that may develop shall be corrected at no expense to the Owner, including all materials, labor, travel, expenses, system diagnostics, and damage to areas, materials, and other systems resulting from such failures. C. Provide a manufacturerʼs twenty-five (25) Year Mission Critical Warranty for voice and data structural cabling system. 270000-22

1. The Communications Systems Contractor shall provide proof that he/she is authorized and certified, in good standing, to provide this 25 year warranty. 2. The warranty shall include connecting hardware products and installed cable as part of the structural cabling system. 3. The structural cabling system shall include: a. Work area outlets b. Horizontal cable c. Fiber Optic cable d. The connecting hardware in the horizontal cross-connect 4. The warranty and system performance guarantees: a. The structural cabling system shall be free from defects in materials and workmanship, for the duration of the warranty. b. The structural cabling system shall support any current or future application ratified by IEEE, ANSI, ISO, designed to operate compliant category 3, 5, 5E or 6 drafts or standard in effect at the time of the installation, for the duration of the warranty. 5. If the structural cabling system is determined to be defective within the scope of this warranty, the product found to be non-conforming shall be repaired or replaced under this warranty. D. Manufacturers shall provide replacement warranties for material and equipment furnished under this Section. Such warranties shall be in addition to and not in lieu of, all liabilities that the Manufacturer and the Installer may have by law or by provisions of the Contract Documents. E. Include copies of all warranties, maintenance contracts, and training contracts or performance bonds in the Operation and Maintenance Manuals. 1.18 MAINTENANCE A. Provide installerʼs maintenance contract quote upon request, for a period equal to warranty. B. Upon receipt of notice from the Owner of failure of any part of the systems during the warranty period, the affected parts shall be replaced. Any equipment requiring excessive service, consisting of more than two unscheduled service calls, shall be considered defective and shall be replaced. 1. Response times to warranty issues shall differ according to the level of the problem. 2. A problem is considered to be corrected when the system and its components operate according to specified requirements. 270000-23