Monthly Progress Report Stanford Synchrotron Radiation Laboratory

Similar documents
TABLE OF CONTENTS. Page. A. Project Summary 1. Technical Progress 3 2. Cost Reporting 5

The SPEAR 3 Upgrade Project Close-out Report April 2004

PEP-II Disassembly Technical Systems

SPEAR 3: Operations Update and Impact of Top-Off Injection

LSD Review December 2012 Schedule, Re-Baseline, & Resource Analysis

PEP-II Overview & Ramp Down Plan. J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007

Summary of CBETA Independent Cost Reviews. R. Michnoff January 19, 2017

Next Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack

AREAL- Phase 1. B. Grigoryan on behalf of AREAL team

Advanced Photon Source - Upgrades and Improvements

A Cathode Development Cornell Cultera This scope includes all labor and purchases required produce photocathodes required by CBETA.

Program Risks Risk Analysis Fallback Plans for the. John T. Seeman DOE PEP-II Operations Review April 26, 2006

5 Project Costs and Schedule

The LEP Superconducting RF System

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

Spear3 RF System Sam Park 11/06/2003. Spear3 RF System. High Power Components Operation and Control. RF Requirement.

LCLS Injector Technical Review

Full IEFC workshop Feb.

Radiation Safety System for Stanford Synchrotron Radiation Laboratory*

Top-Up Experience at SPEAR3

Summer / Fall 2004 Downtime AEG Preparation Work

Operating Experience and Reliability Improvements on the 5 kw CW Klystron at Jefferson Lab

WBS Trigger. Wesley Smith, U. Wisconsin CMS Trigger Project Manager. DOE/NSF Review April 11, 2000

Status of the FAIR Project. Jürgen Henschel FAIR Project Leader / Technical Director GSI & FAIR

Trigger Cost & Schedule

ANKA Status Report. N.Smale, A.-S. Müller, E. Huttel, M.Schuh Slides courtesy of A.-S. Müller and C.Heske.

P. Emma, et al. LCLS Operations Lectures

March 4 th, Addendum No. 1. Brooklyn College Systems Integrator Broadcast Television Equipment Project No: BY019/

PEP-I1 RF Feedback System Simulation

GLAST Large Area Telescope:

CBETA Quarterly Report 7

ANKA RF System - Upgrade Strategies

Development of Multiple Beam Guns for High Power RF Sources for Accelerators and Colliders

12GeV CEBAF Commissioning

Grid Code Modification Register. March 2018

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems

TRIUMF CYCLOTRON MAIN MAGNET POWER SUPPLY REPLACEMENT

6MSD Weekly Scheduling Meeting. 1:30, MCC Conference Room

A Facility for Accelerator Physics and Test Beam Experiments

ADF-2 Production Readiness Review

QT Plus Quick Launch Overview Guide. Revised February 2018

Upgrading LHC Luminosity

PEP II Design Outline

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting

Linac 4 Instrumentation K.Hanke CERN

Status of CTF3. G.Geschonke CERN, AB

Detailed Design Report

Equipment Installation, Planning, Layout, organisation and updates

North Damping Ring RF

Periodic Seasonal Variation of Magnets Level of the STB ring

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

Present Status and Future Upgrade of KEKB Injector Linac

Mechanical aspects, FEA validation and geometry optimization

ELECTRICAL SAFETY INSPECTION REPORT. MTM Garments Ltd.

ABORT DIAGNOSTICS AND ANALYSIS DURING KEKB OPERATION

Extraction/Separator Setup. Michael Spata Operations Stay Treat July 16, 2015

ELECTRICAL SAFETY INSPECTION REPORT

Status and Plans for PEP-II

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

High QE Photocathodes lifetime and dark current investigation

CEBAF Accelerator Update. Michael Tiefenback CASA Accelerator Physics Experimental Liaison June 14, 2017

Upgrade of CEBAF to 12 GeV

RADIATION SAFETY SYSTEM OF THE B-FACTORY AT THE STANFORD LINEAR ACCELERATOR CENTER

HPS Slow Controls Overview

Development of an Abort Gap Monitor for High-Energy Proton Rings *

Pulsed Klystrons for Next Generation Neutron Sources Edward L. Eisen - CPI, Inc. Palo Alto, CA, USA

Energy Upgrade Options for the LCLS-I Linac

COMMISSIONING OF THE ALBA FAST ORBIT FEEDBACK SYSTEM

US CMS Endcap Muon. Regional CSC Trigger System WBS 3.1.1

New Filling Pattern for SLS-FEMTO

Mosaic 1.1 Progress Report April, 2010

Modulator Overview System Design vs. Tunnel Topologies. Snowmass Workshop August 16, 2005 Ray Larsen for the SLAC ILC Group

RF Upgrades & Experience At JLab. Rick Nelson

Thoughts on Project Standard in Japan

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

The Elettra Storage Ring and Top-Up Operation

AARHUS UNIVERSITET November, ASTRID2 Status. Heine Dølrath Thomsen on behalf of the ASTRID2 Team

Mechanical Design of Recirculating Accelerator Experiments for Heavy-Ion Fusion

ELECTRICAL SAFETY INSPECTION REPORT

SECTION 683 VIDEO OPTICAL TRANSCEIVER WITH BI-DIRECTIONAL DATA CHANNEL DESCRIPTION

Beam Losses During LCLS Injector Phase-1 1 Operation

A Unique Power Supply for the PEP II Klystron at SLAC*

VSAT Installation and Maintenance. Presenter: E. Kasule Musisi ITSO Consultant Cell:

The FAIR plinac RF Systems

ILC Damping Ring Lattice Status Report. Louis Emery and Aimin Xiao Argonne National Laboratory Presented at KEK workshop Dec 18th, 2007

BILOXI PUBLIC SCHOOL DISTRICT. Biloxi Junior High School

ACADEMIC SUCCESS CENTER THE COLLEGE AT BROCKPORT STATE UNIVERSITY OF NEW YORK PROJECT NO

SECTION MEDIUM VOLTAGE CABLE INSTALLATION. 1. Section Underground Ducts and Manholes.

INSTALLATION INSTRUCTIONS FOR

Availability and Reliability Issues for the ILC

City of Winter Springs, FL

LHC Beam Instrumentation Further Discussion

SPECIAL SPECIFICATION :1 Video (De) Mux with Data Channel

STATUS OF THE SwissFEL C-BAND LINAC

SITE All work shall be performed at Center Park Substation (1895 Kernan Blvd, Jacksonville, Fl ). DATE: 04/03/2018

Status of the X-ray FEL control system at SPring-8

US-ILC Waveguide Industrialization Study. Marc Ross, Chris Nantista and Chris Adolphsen

PEP II STATUS AND PLANS *

Transcription:

Monthly Progress Report Stanford Synchrotron Radiation Laboratory April 2003

TABLE OF CONTENTS A. Project Summary 1. Technical Progress 3 2. Cost Data 5 B. Design and Fabrication Reports 1.1 Magnets & Supports 7 1.2 Vacuum System 7 1.3 Power Supplies 8 1.4 RF System 8 1.5 Instrumentation & Controls 8 1.7 Beam Line Front Ends 9 1.8 Facilities 9 C. Installation Reports 1.9.1 Magnet & Supports 10 1.9.2 Vacuum System 10 1.9.3 Power Supply System 10 1.9.4 RF System 11 1.9.6 Cable Installation 11 1.9.7 Beamline Front Ends 11 1.9.8 Facilities 11 1.9.9 Management and ES&H 11 2.0.1 S2 Decommissioning and S3 Rigging 12 2.0.2 Survey and Alignment 14 Page 2

1. Technical Progress A. SPEAR 3 PROJECT SUMMARY SPEAR 2 is gone SPEAR tunnel near the end of April SPEAR 2 Boneyard 3

SPEAR 3 begins The SPEAR 3 Installation Program began ON SCHEDULE March 31, 2003. The SPEAR 2 beam turn-off occurred at 6:00 am followed by a brief celebration during which Burton Richter and Keith Hodgson highlighted the history and the significant research from SPEAR 2 as well as a vision of the bright future anticipated with SPEAR 3. The Installation Program involves 3 phases: demolition of SPEAR 2, modification of the facilities to meet SPEAR 3 needs, and finally the actual installation of SPEAR 3 technical systems and components. Each phase is a complex procedure that is planned in great detail with overall completion projected by the end of October 2003. Phase one was completed ON SCHEDULE near the end of this month. In phase one, the first two weeks included the regimented shutdown process for electrical and vacuum systems together with radiation measurements within the tunnel followed by the removal of useful components of the ring. All magnet power supply units were removed from bldg. 118. The removal process of various cable systems for power, controls, and monitoring was initiated. This overall effort was completed ahead of schedule thanks to the outstanding efforts of many SSRL and SLAC staff members. During the third week, the cable cutting process inside the tunnel was completed. Appropriate shielding blocks were removed such that all of the Insertion Devices could be removed and stored. The fourth week initiated the removal of the eighteen main magnet girders. Most of these 30 foot long concrete supports with installed magnets and vacuum chambers were transported through the tunnel to a roof opening near the West straight section, removed by crane, and transported to the salvage area pictured above. The remaining work including cable removal outside the tunnel, removal of beam line front end components, and overall tunnel clean up was completed on May 5 allowing tunnel excavation (the beginning of phase two) to begin on schedule. The overall timeline for the major installation activities is provided below. SPEAR 3 Installation timeline Begin Apr 2003 SPEAR 2 remove: Mar 31 May 8 B118 renovation: Mar 31 Oct 6 Pour concrete floor: May 8 Jun 20 Install new monuments: Jun 20 Jul 25 Install mounting plates & holes: Jul 1 Aug 11 Install Girder & Straights & shielding: Aug 11 Aug 29 Install cable plant: Aug 25 Oct 15 Install vacuum hardware & BL Front Ends: Aug 18 Oct 16 Leakcheck ring/beamlines-pumpdown: Sep 8 Oct 22 Final survey: Oct 22 Oct 30 Lock Ring-Installation complete: Oct 30, 2003 4

2. Cost Data The total project costs and commitments through April 2003 are provided in Table A1. The integrated costs and commitments per month are plotted in Fig. A1 Table A1 Costs and Obligations (through April 2003) K$ Direct & Direct Indirects Costs 39,978 45,305 Commitments 3,926 4,318 Total 43,904 49,623 Funding Profile FY 99 $14M FY 02 10M FY 00 14M FY 03 10M FY 01 10M. Total 58M SPEAR 3 Summary (in $K) Directs & Indirects Actual Costs Actual Costs + Commitments Budget Costs Budgetted Costs + Commitments Funding Profile 60,000 55,000 50,000 45,000 40,000 35,000 30,000 25,000 20,000 15,000 10,000 5,000 - SEP AUG JUL JUN MAY APR MAR FEB JAN DEC NOV OCT SEP AUG JUL JUN MAY APR MAR FEB JAN DEC NOV OCT SEP AUG JUL JUN MAY APR MAR FEB JAN DEC NOV OCT SEP AUG JUL JUN MAY APR MAR FEB JAN DEC NOV OCT SEP AUG JUL JUN FY 99 FY 00 FY 01 FY 02 FY 03 Figure A1 An analysis has been made for the remaining cost to completion. The results are given in Table A2 for each WBS 2 area. Column one provides the actual costs through April 2003 and column two gives the current projected costs to completion from May through October 2003. Column three provides the associated total project costs projected at completion. The remaining costs to completion total 10,707 K$ with remaining contingency of 1,988 K$ which is 18.6%. Appropriate CCB s relative to the baseline budget established August 2002 are underway to reflect the current estimate. Accordingly the budgeted projected costs and costs plus commitments shown in Fig. A1 will be revised in next month s report. 5

As indicated above, the focus of the SPEAR 3 project is changing from Design, Fabrication, and Production to Installation. The Installation program is based on a fast track schedule and future reports will be on a monthly basis. While we will continue to report on the remaining WBS 2 level efforts until their completion, the major focus of the monthly report will be the Installation effort (WBS 1.9) as provided in Section C of this report. Table A2 Project Costs (K$) WBS Actual April 30 Estimate to Completion Total at Completion 1.1 Magnets 8,588 117 8,705 1.2 Vacuum 10,195 1,755 11,950 1.3 Power Supply 2,708 398 3,106 1.4 RF 4,227 305 4,532 1.5 I&C 3,040 1,016 4,056 1.6 Cable 2,084 0 2,084 1.7 Beam Line 1,039 76 1,115 1.9 Installation 873 5,499 6,372 2.0 Management 3,837 178 4,015 Direct Total 39,378 49,571 Indirects 5,328 6,441 Total Cost 45,306 56,012 Contingency 1,988 Project Total 58,000 6

1.1 Magnets and Supports B. Design and Fabrication Reports The magnet raft assembly program was paused for two weeks due to the SPEAR 2 removal. Production of 47 rafts is complete (17 rafts type 50Q, 14 rafts type 145D-T1, 14 rafts 145D-T2, 2 rafts MCA-QT). Work continued on preassembling magnets on the 7 remaining rafts and jumpering the LCW lines on the vacuum chambers. The templates to mark the anchor holes to be drilled on the SPEAR 3 concrete floor are being manufactured. The installation of magnets and vacuum chambers on the injection Beam Transport System raft was started. The magnetic measurements of the septum magnet were started. A first quick measurement of the injected beam integrated transfer function with a translating wire showed good agreement with the design parameters and no saturation effects up to 3 GeV were noticed. Next measurement will be the integrated leakage field at the stored beam using a translating wire. 1.2 Vacuum System Bake-out continued on the final 3 magnet raft chambers (54 total). Tubes were cut and formed for the straight sections. Septum magnet chamber production halted pending resolution of mirror plate interference. The Personnel Protection System beam stopper is partially assembled and awaiting brazement. Girder and straight section bellows parts completed. RF bellows brazements completed. Tune driver bellows parts completed. DCCT parts completed except center chamber and shielding. Isolation valve order placed. Valve support design complete and out for purchase. Designs partially completed for support of girder pumps, RF section pumps, and b15 section vacuum. Design of anchor bolt templates completed. Requisition placed for anchor bolt and grout installation. 7

1.3 Magnet Power Supplies All magnet power supplies have been delivered with the following exceptions: Seventeen Intermediate (rack-mounted) power supplies. These are due by the end of May from IE Power. Their delivery will support installation. Twenty recently-ordered MCOR30s. These are due by the end of June from BiRa. The delivery will support the field test program. All power supplies have been bench tested with the two exceptions noted above and the dipole bulk power supply. Because of its large electrical size the dipole bulk power supply will be bench tested in Building 758 in May. This power supply will be ready when needed for installation. 1.4 RF System The first two SPEAR 3 cavities have been successfully processed up to 850kv accelerating voltage. See processing record for the first unit below. The third cavity has arrived and being prepared for tests. Design reviews were held for the klystron power supply oil secondary containment system and the required overhead hoist for servicing. In Building 118 wiring of the control termination box was completed and the enclosure for a programmable logic controller was installed. In Building 132 the termination tank was secured to the floor and all cables terminated with the exception of the RG220 HV cable and a ground wire. These items will be completed in May. 1.5 Instrumentation and Control Systems Work on the computer control system continued with the configuration of the power supply control software, the BPM data acquisition system, digital output module hardware, and field bus application. The network system was specified and Ethernet switches were ordered. Software has been written to automate the testing of the 60 4-button-multiplexed BPM processing modules from Bergoz. Interconnection components needed between the BPM processing system are being fabricated. The first BPM-ADC Interconnect chassis was tested successfully. The design of the LO, Clock and Test Tone fan-out units continues, as does the design of the tune monitor, bunch monitor, and BPM-based current monitor. Detailed configuration of the programmable logic controller systems for the vacuum and magnet water protection interlocks continues. The first Orbit Interlock Position Limit Detector chassis is complete and is being tested. The design of the Beam Current Interlock that prevents beam lines not rated for high current operation from being opened above specified beam current levels is in progress. I&C equipment racks were delivered. 8

1.7 Beam Line Front Ends The machining of all ID fixed masks is now complete. The Beam Line 10 moveable mask has successfully completed all braze and weld operations. Final assembly and alignment fiducialization is in progress. The moveable masks for Beam Lines 4, 7, and 9 have commenced braze assembly. Several heats have been completed successfully. 1.8 Facilities The final piping drawings and specifications for the HCW system (required for the RF systems) have been completed and will be out for bid May 16. The skid for the HCW system has been completed (see photo below). Installation is scheduled for early June. Phase 1 of the LCW piping modifications for distribution in the East and West straight section areas has been completed. The completion of this work (Phase 2) is scheduled for June after the new concrete floor for the tunnel has been completed. 9

C. Installation Reports Approximately 480 tons of SPEAR 2 hardware was successfully removed from the ring tunnel during the month of April. Vacuum chambers and other hardware that were to be saved were prepared and removed before the rigging contractor began the major removal work. LCW piping was modified and prepared for concrete work in the East and West straights. The SPEAR tunnel was emptied by the end of April and ready for new tunnel floor construction on schedule 1.9.1 Mechanical Systems SPEAR 2 girders being removed from the ring housing The staff supported the removal of SPEAR 2 components and the continued planning for installation of SPEAR 3. 1.9.2 Vacuum System The staff supported the removal of SPEAR 2 components and the continued planning for installation of SPEAR 3. 1.9.3 Power Supplies The lockout procedures that were developed by the Lockout Committee were successfully implemented and there were no discoveries of live electrical circuits in B118 after the shutdown and lock out. Farris Electric completed B118 electrical demolition on schedule. They are waiting for cable tray and other minor material so they can begin the installation of the feeders from Substation 507 to two new B118 switchboards that will be installed after the new B118 floor is in place. Farris Electric will also install all the other new B118 electrical equipment. Installation of this equipment will begin after the new B118 floor has been poured. 10

1.9.4 RF System Work centered on installation completion of the RF High Voltage power supply. 1.9.6 Cable Plant The demolition of SPEAR 2 Tray and Cableplant System (Building and Ring) was the primary task this month. This major undertaking was accomplished on schedule, within budget, and without incident/injury. We conducted intensive coordination between many different organizations of both SLAC and SSRL to acquire a large number of demolition workers. Workers were trained on SLAC Safety together with formal briefings to familiarize them with the demolition work specifics. Nineteen T&M staff were released at the completion of the demolition work except for journeyman electricians reassigned to the SPEAR 3 RF HV power supply installation. Work in preparation for the installation of the new cableplant system has intensified this month in order to produce the complete and detailed listing of cable, connectors, and routings for the next, and final, contract package to be released for bid. Interaction continues with SSRL engineering in our goal of quantifying cable and connector types and quantities. This is the last precursor to ordering the balance of cable material. 1.9.7 Beam Line Front Ends All FE and in-alcove beam line components scheduled for removal from the ring have been successfully removed. All remaining in-alcove beam line components have been protected from dust and debris associated with the tunnel floor excavation. All bend beam line out-of-alcove hardware has been coarse re-aligned. Over half the outof-alcove bend beam line hardware has been fine re-aligned as well. 1.9.8 Facilities Efforts continued in preparation for the contract start for excavation of the tunnel floor and the Building 118 (power supply building) floor. The work is scheduled to begin May 6. 1.9.9 Management The main tasks and responsibilities underway for the management group by the Installation effort include the following: Detailed planning, scheduling, and monitoring of all efforts. Coordination efforts involving project staff, several contractors, and T&M labor. Oversee contracts and modifications. Execute change orders when required. Monitoring of Costs and Schedule variations. Insure that all safety rules and regulations are followed and that staff and contractors are properly informed of these regulations. 11

2.0.1 SPEAR 2 Decommissioning/SPEAR 3 Rigging The Decommissioning of SPEAR 2 was the major effort in April. The staff in other areas above participated in this work which is summarized below. In progress views of the activities are provided below. A total of 46 roof and wall shielding blocks were removed to allow access to the ring for removal of SPEAR 2. They are stored in areas close to SPEAR until replacement near the end of the shutdown. These weigh in excess of 500,000 lbs. Replacement of several weakened roof blocks is anticipated. All 18 magnet rafts were removed from SPEAR and transported to the RMMA storage area at Sector 0. The weight of these components is about 750,000 lbs. All components from the SPEAR ring straight sections were removed. Five of the Insertion Devices were transported to workshop areas where they will be prepared for installation into SPEAR 3. The two electro-magnet devices will be used on other projects. The 11 beam line front ends (from the ring to the injection stoppers) were removed. Support frames were also un-bolted and removed, or cutoff, as required. The remaining components were boxed to prevent damage during the ring floor excavation and forming process. SPEAR 2 Raft pulled through tunnel 12

SPEAR2 Raft removal from tunnel SPEAR 2 Raft in sector 0 storage area 13

2.0.2 Survey and Alignment Summary of the Alignment Engineering Group progress and accomplishments: Set new monumentation for all bending beamlines. This activity was completed ahead of schedule on April 24. Realigned bending magnet beamlines. This activity started ahead of schedule in accordance with Hal Tompkins. Surveyed concrete test pad for tunnel floor. Surface plots were generated from leveling and total station measurements. The 3D monuments were surveyed weekly for deformation studies. Test pad met specifications. Building 750 raft assembly. o Final alignment of rafts 73 and 74. o Pre-alignment of rafts 75 and 76. Miscellaneous o Provided elevation on BL10 ID pads. o Fiducialized BTS septum. 14