What the experiments have planned

Similar documents
The CMS Detector Status and Prospects

Minutes of the ALICE Technical Board, November 14 th, The draft minutes of the October 2013 TF meeting were approved without any changes.

CMS Upgrade Activities

First LHC Beams in ATLAS. Peter Krieger University of Toronto On behalf of the ATLAS Collaboration

A new Scintillating Fibre Tracker for LHCb experiment

Status of CMS and preparations for first physics

SciFi A Large Scintillating Fibre Tracker for LHCb

The ATLAS Tile Calorimeter, its performance with pp collisions and its upgrades for high luminosity LHC

CERN-RRB April 2005 Status of the LHCb Experiment Report to April 2005 RRB By the LHCb Collaboration

TORCH a large-area detector for high resolution time-of-flight

The hybrid photon detectors for the LHCb-RICH counters

Diamond detectors in the CMS BCM1F

Commissioning and Performance of the ATLAS Transition Radiation Tracker with High Energy Collisions at LHC

Electronics procurements

Muon Forward Tracker. MFT Collaboration

The LEP Superconducting RF System

The Silicon Pixel Detector (SPD) for the ALICE Experiment

ATLAS muon spectrometer varia, status, and upgrades. Gerjan Bobbink Steenwijk 16-june-2017

LHCb and its electronics. J. Christiansen On behalf of the LHCb collaboration

Commissioning of the ATLAS Transition Radiation Tracker (TRT)

IPRD06 October 2nd, G. Cerminara on behalf of the CMS collaboration University and INFN Torino

Evaluation of ALICE electromagnetic calorimeter jet event trigger performance for LHC-Run2 by simulation

The Status of the ATLAS Inner Detector

The Scintillating Fibre Tracker for the LHCb Upgrade. DESY Joint Instrumentation Seminar

Status and Plans for PEP-II

ALICE Muon Trigger upgrade

Compact Muon Solenoid Detector (CMS) & The Token Bit Manager (TBM) Alex Armstrong & Wyatt Behn Mentor: Dr. Andrew Ivanov

CGEM-IT project update

CSC Data Rates, Formats and Calibration Methods

arxiv: v1 [physics.ins-det] 1 Nov 2015

ATLAS Pixel Subsystem and Simulation

PEP-II Overview & Ramp Down Plan. J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007

TRT Software Activities

AREAL- Phase 1. B. Grigoryan on behalf of AREAL team

An Overview of Beam Diagnostic and Control Systems for AREAL Linac

arxiv:hep-ex/ v1 27 Nov 2003

A Cathode Development Cornell Cultera This scope includes all labor and purchases required produce photocathodes required by CBETA.

5 Project Costs and Schedule

The Alice Silicon Pixel Detector (SPD) Peter Chochula for the Alice Pixel Collaboration

Mechanical Considerations in the Outer Tracker and VXD. Bill Cooper Fermilab

Electron Clouds in the SPS: progress in the analysis of cures/mitigations measures and potential schedule of implementation J.M.

Data Quality Monitoring in the ATLAS Inner Detector

Review of the CMS muon detector system

Performance of a double-metal n-on-n and a Czochralski silicon strip detector read out at LHC speeds

R&D on high performance RPC for the ATLAS Phase-II upgrade

li, o p a f th ed lv o v ti, N sca reb g s In tio, F, Z stitu e tests o e O v o d a eters sin u i P r th e d est sezio tefa ectro lity stem l su

2008 JINST 3 S LHC Machine THE CERN LARGE HADRON COLLIDER: ACCELERATOR AND EXPERIMENTS. Lyndon Evans 1 and Philip Bryant (editors) 2

Instrument Status Review. GSC Meeting October 2009

Drift Tubes as Muon Detectors for ILC

LHC Physics GRS PY 898 B8. Trigger Menus, Detector Commissioning

ATLAS Group LPNHE. ATLAS upgrade activities. Biennale du LPNHE Tirrenia (Pise)

PICS IN THE INJECTOR COMPLEX WHAT ARE WE TALKING ABOUT?

The 2011 LHC Run - Lessons in Beam Diagnostics

Upgrades of the Tracker and Trigger of the CMS experiment at the CERN LHC

LHCb and its electronics.

Scintillation Tile Hodoscope for the PANDA Barrel Time-Of-Flight Detector

Dick Loveless. 20 November 2008 SLHC Workshop. Dick Loveless SLHC Workshop 20 Nov

RF upgrade program in LHC injectors and LHC machine

Studies of large dynamic range silicon photomultipliers for the CMS HCAL upgrade

Closed Cycle Cryogenic Probe Station

Report from the Tracking and Vertexing Group:

Test Beam Wrap-Up. Darin Acosta

The Full Scale Prototype of the Cylindrical-GEM as Inner Tracker in Kloe2

WHAT IS NEW AT CERN?

Status of the LHCb Experiment

Full IEFC workshop Feb.

Status of the LHCb Upgrade

LHC Beam Instrumentation Further Discussion

DAQ Systems in Hall A

A pixel chip for tracking in ALICE and particle identification in LHCb

PIXEL2000, June 5-8, FRANCO MEDDI CERN-ALICE / University of Rome & INFN, Italy. For the ALICE Collaboration

The CALICE test beam programme

Commissioning the TAMUTRAP RFQ cooler/buncher. E. Bennett, R. Burch, B. Fenker, M. Mehlman, D. Melconian, and P.D. Shidling

SLHC tracker upgrade: challenges and strategies in ATLAS

Commissioning and Initial Performance of the Belle II itop PID Subdetector

Present Status and Future Upgrade of KEKB Injector Linac

Tracking Detector R&D at Cornell University and Purdue University

ABORT DIAGNOSTICS AND ANALYSIS DURING KEKB OPERATION

PEP II Status. H. - Ulrich (UZi) Wienands PEP-II Run Coordinator. SLAGEPAC Meeting November 8,200O. Intro; 11/7/O 19:55

Neutron Irradiation Tests of an S-LINK-over-G-link System

FRONT-END AND READ-OUT ELECTRONICS FOR THE NUMEN FPD

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

Trigger Report. Wesley H. Smith CMS Trigger Project Manager Report to Steering Committee February 23, 2004

Future Circular Collider Study

Sensors for the CMS High Granularity Calorimeter

Trigger Cost & Schedule

LARGE HADRON COLLIDER COMMITTEE Minutes of the one-hundredth-and-thirty-second meeting held on Thursday and Friday, 30 November -1 December 2017

LSD Review December 2012 Schedule, Re-Baseline, & Resource Analysis

Linac3 experience for LHC ion runs

Time Resolution Improvement of an Electromagnetic Calorimeter Based on Lead Tungstate Crystals

LHC COMMISSIONING PLANS

Equipment Installation, Planning, Layout, organisation and updates

Glast beam test at CERN

Management Board, Thursday 31 st August 2017 Minutes (

An extreme high resolution Timing Counter for the MEG Upgrade

Trigger Menus and Rates

SCT Activities. Nick Bedford, Mateusz Dyndal, Alexander Madsen, Edoardo Rossi, Christian Sander. DESY ATLAS Weekly Meeting 03. Jun.

PEP-II Disassembly Technical Systems

Test beam data analysis for the CMS CASTOR calorimeter at the LHC

Status of GEM-based Digital Hadron Calorimetry

Transcription:

What the experiments have planned Chamonix: 25 Jan 2011 AB Austin Ball, with many thanks to J. Baechler, R. Lindner, M. Nessi, W. Riegler. Pattern of shutdowns & technical stops, current baseline timing Experience from Year-end Technical Stops First Long Shutdown and possible delay from 2011-13 to 2012-14 Likely task lists of: ALICE ATLAS CMS LHCb TOTEM Points to watch Quick look at the 2 nd Long Shutdown Conclusion

Chamonix: 25 Jan 2011 AB Baseline planning LS 1 LS 2 - from now to 2020 ~60 months of p-p running - 4 weeks of Heavy Ion Collisions every year (8 runs) - Annual year-end shutdown for ~10 weeks - 15 mo shutdown in 2012/2013 -> LHC to nominal energy - 15 mo shutdown in 2016 -> Phase 1 upgrade - 19+ mo shutdown in 2020(+x) -> HL-LHC upgrade LS 3

Shutdowns & year-end Tech Stops Chamonix: 25 Jan 2011 AB For each experiment, activities form part of a cunning coherent plan covering extended technical stops & shutdowns (LS 1, LS 2) over the next 6-7 years and beyond to LS 3 in 2020+x, in tune with the developing performance of LHC. Detailed objectives for each tech stop/shutdown period are interdependent and will evolve progressively depending on -the timing & duration of future stops/shutdowns -the achievements in past stops/shutdowns -the physics achievements (potential) for past (future) operation periods Postponing the 2011-13 shutdown (LS 1) to 2012-14, will, in most cases: -delay the whole LS 1 task-list by one year. -allow some tasks scheduled for LS 2 to be pre-empted -tend to put pressure for more maintenance and repair tasks (& even upgrade tasks) during year-end stop 2011-12. Once the schedule is confirmed, further evolution is likely

Chamonix: 25 Jan 2011 AB Year-end Technical Stops The experience of 2009-10 and 2010-11 shows that all 4 experiments can successfully complete complex interventions requiring partial opening in a year-end Technical Stop of ~10-12 weeks, with work spanning the CERN closure if necessary. Activities have already included : consolidation & first installation/upgrade : emergency repair and routine maintenance. The year-end Tech stops are an important ingredient in the overall consolidation and upgrade plan as well as being essential for maintenance and repair. (support from technical groups in BE,EN,GS,PH,TE is a pre-requisite for success) So far experiment work stayed ~ within the shadow of LHC work. --> may not always be possible Substantial routine work and consolidation also gets done in the regular (few day) Technical Stops during the running periods. Frequency and duration could be tuned. (but let s avoid drive it til it breaks down?)

25 Jan 2011 AB ALICE/LHCb: 2010-11 Ext Tech. Stop EMCAL 2010/2011 ALICE Status 6 5 4 3 2 7 1 8 9 TRD 2011/2012 0 17 10 16 0 11 12 13 14 15 4 TRD 2010/2011 TB 2.9.10 1 2 3 P2 issues, Xmas shutdown plans ALICE: partial opening to install 3 TRD supermodules 6 EMCAL supermodules LHCb: Removal of both RICH1 HPD boxes, exchange of electronics and HPDs followed by their re-installation in January 2011.

ATLAS: 2010-11 extended technical stop: opening for LAr,TILECAL,RPC + a 25 Jan 2011 AB Major maintenance/consolidation exercise in course of completing on-schedule

25 Jan 2011 AB CMS/TOTEM: 2009-10 & 10-11 Ext Tech Stops -z end: Locating T1 frame on guides -z end: First T1 in place Bushings repair 2009-10 -z end: insertion by halves, then together

First long shutdown: ALICE 25 Jan 2011 AB Full opening of the detector --> moving TPC to parking position and accessing Silicon Tracker --> repair and consolidation of Tracker, specifically the Silicon Pixel cooling system. --> installation of EMCAL extension (upgrade) consisting of 6 super-modules. --> new support structures including new support cradle for Photon Spectrometer. Moving TPC to parking position for Silicon Tracker maintenance. EMCAL extension (DCAL) 6 supermodules due to be ready for 2012

First long shutdown: ATLAS Full opening -Beampipe: - replace steel beam pipes, flanges and ion pumps with aluminum ones, (factor 3 gain in activation/induced backgrounds). - R&D done, production started 25 Jan 2011 AB - Pixel detector SQP project - extract pixel and bring to surface, replace all services and optical transmitters, then reinstall (anticipates faults possible from 2015 onward due to failing optical transmitters inside detector) -precautionary preparations already underway (new SQP project). - decision to extract or not during 2012. This is a major operation! Pixel IBL=Insertable B Layer. --> improve vertexing and b-tagging capabilities at nominal luminosity and beyond. -first approved ATLAS upgrade project, now under construction, originally targeting 2016. -ATLAS is discussing accelerating construction to be ready to install in 2013. ( for LS 1) --> profit from detector being on surface for SQP. - requires new Be central beam pipe with smaller diameter (45 mm).

First long shutdown: ATLAS 25 Jan 2011 AB -Inner detector: -install new C3F8 ID evaporative cooling plant based on passive syphon concept. -R&D done, now in the procurement phase. -keep existing plant (based on compressors) as a spare -Calorimeters (LAr and Tiles) -replace all LV power suppliers (on-detector DC-DC converters) with a new generation of devices. -R&D done, production ongoing. First production batch under qualification -Muon detector -Complete installation of the EE chambers (better coverage of transition region between barrel and toroid end-caps). -Instrument existing trigger chambers in the toroid feed region, to improve geometrical acceptance -Improve radiation shielding inside the detector (forward region) and between caverns -Fix faults where needed and where access allows -Do the yearly maintenance of the infrastructure and safety systems -Infrastructure consolidation where necessary

New C3F8 ID evaporative cooling plant (passive) 25 Jan 2011 AB EE chambers Pixel Service Quarter Panels IBL

First long shutdown: CMS 25 Jan 2011 AB Timeframe Est Integ Tasks lumi /fb -1 2012-14 1-3 Yoke Endcap disk 4 construction at +z and z ends in situ. 4 th muon endcap stations +z and z (CSC & RPC) (-z only if 2012) 1 st endcap muon station readout granularity restoration +z and Beampipe region shielding + forward region opening under vacuum -forward systems CASTOR, ZDC, (TOTEM?) removable for p-p. (Reinstallable for ion-ion or special runs.) HF phototube replacement +z and z HO & CASTOR calorimeter phototransducer change Pixel Luminosity Telescope (PLT) installed (if not in 2011-12) Beam Scintillation Counter upgrade/replacement. Barrel endcap seal revision for colder Tracker operations + very many infra & common systems consolidations. currently no provision for bakeout ( ~2 months more needed) After which CMS should be ready for 13-14 TeV, 50fb -1 and 2+ x 10 33 cm -2 s -1

CMS forward muon upgrade 25 Jan 2011 AB 4 th muon station: CSC/RPC YE4 shielding disk Push-back system decoupling disk installation from CSC/RPC installation

25 Jan 2011 AB CMS: Shutdown 2012: + z seq Martin Gastal EN-MEF A G E H C The detailed planning already reached 230 discrete tasks and spans 5 Dec 2011 to 13 Mar 2012 (15.5 months) B 6/7 configs

First long shutdown: LHCb 25 Jan 2011 AB Beam Pipe: Exchange of the largest Be section (3rd ~6000mm), this requires moving out the fourth section as well. Replacements for machined aluminium bellows between Sections 1 & 2 and between Sections 2 & 3 based on formed bellows technology Replacement of spider-web fix point supports for further transparency. (Support from TE/VSC, BE/ABP) Inner Silicon Tracker: Replacement of one or more detector modules with scintillating fiber technology (as part of the upgrade project) Requires: Survey of the sub detector Vertex Locator: Depending on the accumulated radiation dose, exchange of both VeLo halves, including the RF boxes.

--> possible impact on LHC tunnel planning First long shutdown: TOTEM 25 Jan 2011 AB Maintenance options on T1 & T2 telescopes (integrated in CMS) (Teams: TOTEM+CMS+PH-DT) T1: Two detector elements in each CMS end cone (+/- side) Service requirements : CMS HF on two risers Service option : extraction of T1 quarter, electronics, cooling T1 T2:Two detector elements on each side of CMS Service requirement : HF on two risers Service option : exchange of GEM planes, electronics,cooling --> impact on CMS opening & closing sequence & timescales. T2 HF Maintenance of Roman Pots (integrated in LHC) : 24 Roman Pots (6 RPs at -147m, 6 RPs at +147m, 6 RPs at -220 m, 6 RPs at +220 m) Service requirements : LHC Tunnel access Service option : dismount single RP detector (sensor + electronics) motor control & calibration, cooling & vacuum, FESA, PXI, interlock CMS forward region

Infrastructure: All experiments require very substantial consolidation of : shielding, ventilation, cryogenics, cooling, inertion & dry air, RP measures, safety systems, beam diagnostics etc, between now and end of LS 1, to maintain the performance of 2010, matching that expected from LHC. Chamonix: 25 Jan 2011 AB Points to watch Beampipes: Change of schedule may lead to more overlap between experiments in both construction and installation of improved beampipes. eg ATLAS, LHCb & possibly CMS all changing Be pipes in 2013? -need to continuously monitor NEG effectiveness and predict saturation. -bakeout is complex and will require extra time in shutdown scheduling (especially CMS, 4 months + forced pixel removal, replacement, recalibration --> present CMS plan has first bakeout opportunity in Long Shutdown 2) Survey: Despite contributing substantially to their own survey effort, each experiment needs a minimum of one staff surveyor to oversee the survey programme, make sure survey is carried out coherently throughout CERN and ultimately to take responsibility for survey work of complex-wide criticality.

Chamonix: 25 Jan 2011 AB Future year-end Technical Stops The story so far for 2011-12 and 2014-15: (italics = tentative) ALICE ATLAS CMS LHCb 2011-2012 Install 8 TRD supermodules Install EE muon stations in transition region Install ZDC crane. Revise heavy moving system Exchange EMT302/8X transformer. Revise cranes. Maintain fwd pixel and install PLT. Revise dipole cooling. Install cryo backup. 2014-2015 Install 45mm central beampipe. --> Annual infrastructure & safety maintenance and consolidation needed every time! --> Decision about major works and time required in preceding September

What about the 2 nd Long Shutdown? Chamonix: 25 Jan 2011 AB Programme likely to be strongly affected by a decision to postpone 1 st Long Shutdown Recall 2016 was a good compromise between different interests requesting 2015 & 2017. LS 2 start date and duration to be re-considered based on: - Physics: achieved pre LS 1, and targeted between LS1 and LS2 - Actual start/duration of LS 1: eg Nov 2012-Feb 2014 or Dec 2012-June 2014? (Presumably not sensible to have < 2 full running years between LS1 and LS 2) - Status/capabilities of LHC & Experiments on completion of LS1 & pre LS2 - Credible ready date of various upgrades wrt shutdown timing. - Performance consolidation/improvement/risk reduction expected from LS 2. Change brings stress but also provokes the imagination! (i) CMS is considering ways to avoid delays to (already delayed) work on: - HCAL consolidation (HPD replacement & depth segmentation), ready 2015. - Installing low-mass 4-layer pixel tracker, (also ready 2015) on 45mm beampipe. --> possible upgrade of beampipe in 2013, pixel in later tech stop (3mo min) (ii) ATLAS considering pre-emptive completion of : IBL project in LS1. HL-LHC pix & cal upgrades in LS2

Chamonix: 25 Jan 2011 AB 2 nd long shutdown: LS 2 ALICE ATLAS CMS LHCb New beampipe < 40mm. Si tracker upgrade If not done in LS 1: IBL upgrade (45mm bp) Fast Tracking Trigger If not done in LS 1 / ETS 45mm beampipe Pixel upgrade Major tracking upgrade Pixel VeLo (FTK) L 1 trigger upgrade Fwd small muon chs MDT trigger (Low mass 4 layer) Fix HCAL vulnerability. Replace photo-transducer and segment in depth. New Tracker to cope with higher luminosity Anticipate upgrades Forward cals Extended PID Muon system Readout & processors Shielding upgrade DAQ & HLT revision Infrastructure overhaul RP shielding & procedures Anticipate HL-LHC: Pixel, warm fwd cal. Seals for Tracker cold operation. Upgrade beam monitors. Upgrade barrel muon FE. Level 1 trigger upgrade DAQ & HLT revision RP Shielding & procedures Prepare whole detector for 40 MHz Subsystem electronics, trigger, DAQ

Chamonix: 25 Jan 2011 AB Conclusion First Long Shutdown (LS 1: baseline 2011-13) Intensive programme of maintenance, consolidation & upgrade work planned. Part of an interdependent and coherent set of objectives for 3 Long Shutdowns and the intervening year-end Technical Stops. Activity overlap and possible resource conflicts identified for: -beampipe construction and replacement -survey -infrastructure modifications Delaying 2011-13 to 2012-14 will: postpone most of task list by 1 year without serious consequence, but exceptions will put more pressure on 2011-12 year-end stop. Possible feed-forward of delay to LS 2 (baseline 2015-17) will likely feedback more tasks to LS 1 and the intervening year-end Technical Stops.

not What the experiments have planned 25 Jan 2011 AB