Status of the LHCb Experiment

Similar documents
CERN-RRB April 2005 Status of the LHCb Experiment Report to April 2005 RRB By the LHCb Collaboration

LHCb and its electronics. J. Christiansen On behalf of the LHCb collaboration

A pixel chip for tracking in ALICE and particle identification in LHCb

A new Scintillating Fibre Tracker for LHCb experiment

Performance of a double-metal n-on-n and a Czochralski silicon strip detector read out at LHC speeds

CGEM-IT project update

The hybrid photon detectors for the LHCb-RICH counters

The Silicon Pixel Detector (SPD) for the ALICE Experiment

CMS Upgrade Activities

arxiv:hep-ex/ v1 27 Nov 2003

The CMS Detector Status and Prospects

Status of the LHCb Upgrade

SciFi A Large Scintillating Fibre Tracker for LHCb

Trigger Cost & Schedule

WBS Trigger. Wesley Smith, U. Wisconsin CMS Trigger Project Manager. DOE/NSF Review April 11, 2000

Trigger Report. Wesley H. Smith CMS Trigger Project Manager Report to Steering Committee February 23, 2004

Status of the LHCb Upgrade

Electronics procurements

LHCb and its electronics.

The CALICE test beam programme

arxiv: v1 [physics.ins-det] 1 Nov 2015

The Scintillating Fibre Tracker for the LHCb Upgrade. DESY Joint Instrumentation Seminar

TORCH a large-area detector for high resolution time-of-flight

The Read-Out system of the ALICE pixel detector

ALICE Muon Trigger upgrade

Design, Realization and Test of a DAQ chain for ALICE ITS Experiment. S. Antinori, D. Falchieri, A. Gabrielli, E. Gandolfi

PIXEL2000, June 5-8, FRANCO MEDDI CERN-ALICE / University of Rome & INFN, Italy. For the ALICE Collaboration

SciFi A large Scintillating Fibre Tracker for LHCb

A Review of Tracking Sessions

FRANCO MEDDI CERN-ALICE / University of Rome & INFN, Italy. For the ALICE Collaboration

The Alice Silicon Pixel Detector (SPD) Peter Chochula for the Alice Pixel Collaboration

FRONT-END AND READ-OUT ELECTRONICS FOR THE NUMEN FPD

Drift Tubes as Muon Detectors for ILC

Local Trigger Electronics for the CMS Drift Tubes Muon Detector

CMS Note Mailing address: CMS CERN, CH-1211 GENEVA 23, Switzerland

Compact Muon Solenoid Detector (CMS) & The Token Bit Manager (TBM) Alex Armstrong & Wyatt Behn Mentor: Dr. Andrew Ivanov

and progress report first mip measurement with a complete chain of detector slab Silicon wafers for the prototype Mechanics PCB for prototype

What the experiments have planned

Status of GEM-based Digital Hadron Calorimetry

li, o p a f th ed lv o v ti, N sca reb g s In tio, F, Z stitu e tests o e O v o d a eters sin u i P r th e d est sezio tefa ectro lity stem l su

KEK. Belle2Link. Belle2Link 1. S. Nishida. S. Nishida (KEK) Nov.. 26, Aerogel RICH Readout

Status of CMS and preparations for first physics

The Status of the ATLAS Inner Detector

SuperFRS GEM-TPC Development Status Report

Sensors for the CMS High Granularity Calorimeter

Time Resolution Improvement of an Electromagnetic Calorimeter Based on Lead Tungstate Crystals

Status of the CUORE Electronics and the LHCb RICH Upgrade photodetector chain

The ATLAS Tile Calorimeter, its performance with pp collisions and its upgrades for high luminosity LHC

A Cylindrical GEM Detector with Analog Readout for the BESIII Experiment. Gianluigi Cibinetto (INFN Ferrara) on behalf of the BESIIICGEM consortium

HARDROC, Readout chip of the Digital Hadronic Calorimeter of ILC

A fast and precise COME & KISS* QDC and TDC for diamond detectors and further applications

HAPD and Electronics Updates

Upgrading LHC Luminosity

The ALICE on-detector pixel PILOT system - OPS

DEPFET Active Pixel Sensors for the ILC

Review of the CMS muon detector system

IPRD06 October 2nd, G. Cerminara on behalf of the CMS collaboration University and INFN Torino

Progress on the development of a detector mounted analog and digital readout system

Note on the preliminary organisation for the design, fabrication and test of a prototype double-sided ladder equipped with MAPS

Commissioning and Initial Performance of the Belle II itop PID Subdetector

First LHC Beams in ATLAS. Peter Krieger University of Toronto On behalf of the ATLAS Collaboration

Muon Forward Tracker. MFT Collaboration

GOL/Aux Boards and Optical Links

University of Oxford Department of Physics. Interim Report

The Large TPC Prototype: Infrastructure/ Status/ Plans

Rome group activity since last meeting (4)

Silicon Microstrip Detectors for the ATLAS SCT

Upgrades of the Tracker and Trigger of the CMS experiment at the CERN LHC

R&D on high performance RPC for the ATLAS Phase-II upgrade

Atlas Pixel Replacement/Upgrade. Measurements on 3D sensors

BABAR IFR TDC Board (ITB): requirements and system description

with Low Cost and Low Material Budget

Data Quality Monitoring in the ATLAS Inner Detector

The Full Scale Prototype of the Cylindrical-GEM as Inner Tracker in Kloe2

CMS Conference Report

The Pixel Trigger System for the ALICE experiment

Commissioning of the ATLAS Transition Radiation Tracker (TRT)

Front End Electronics

ILC requirements Review on CMOS Performances: state of the art Progress on fast read-out sensors & ADC Roadmap for the coming years Summary

New gas detectors for the PRISMA spectrometer focal plane

TRT Software Activities

Report from the 2015 AHCAL beam test at the SPS. Katja Krüger CALICE Collaboration Meeting MPP Munich 10 September 2015

ATLAS Pixel Subsystem and Simulation

A flexible FPGA based QDC and TDC for the HADES and the CBM calorimeters TWEPP 2016, Karlsruhe HADES CBM

Upgrades of the Tracker and Trigger of the CMS experiment at the CERN LHC

Scintillation Tile Hodoscope for the PANDA Barrel Time-Of-Flight Detector

LHC Beam Instrumentation Further Discussion

A Serializer ASIC at 5 Gbps for Detector Front-end Electronics Readout

THE ATLAS Inner Detector [2] is designed for precision

CSC Data Rates, Formats and Calibration Methods

PoS(Vertex 2017)052. The VeloPix ASIC test results. Speaker. Edgar Lemos Cid1, Pablo Vazquez Regueiro on behalf of the LHCb Collaboration

Novel Data Acquisition System for Silicon Tracking Detectors

READOUT ELECTRONICS FOR TPC DETECTOR IN THE MPD/NICA PROJECT

Proposal by the Ohio State University High Energy Physics to join the BABAR Collaboration

Front End Electronics

ATLAS Group LPNHE. ATLAS upgrade activities. Biennale du LPNHE Tirrenia (Pise)

Global Trigger Trigger meeting 27.Sept 00 A.Taurok

Advanced Front End Signal Processing Electronics for ATLAS CSC System: Status And Post Production Performance.

The ATLAS Pixel Detector

The field cage for a large TPC prototype

Transcription:

LHCb RRB-T 2001-38 Status of the LHCb Experiment LHCb RRB meeting CERN, 23 October 2001 on behalf of the LHCb Collaboration Tatsuya Nakada 1

France: Germany: Italy: Netherlands: Poland: Spain: Switzerland: UK: CERN Brazil: China: Romania: Russia: Ukraine: Technical Associate: The LHCb Collaboration (October 2001) Annecy, Clermont-Ferrand, CPPM Marseille, LAL Orsay Tech. Univ. Dresden, Phys. Inst. Univ. Heidelberg, KIP Univ. Heidelberg, MPI Heidelberg, Bologna, Cagliari, Ferrara, Firenze, Frascati, Genoa, Milan, Univ. Rome I (La Sapienza), Univ. Rome II (Tor Vergata) NIKHEF Cracow Inst. Nucl. Phys., Warsaw Univ. Univ. Barcelona, Univ. Santiago de Compostela Univ. Lausanne, Univ. Zürich Univ. Bristol, Univ. Cambridge, Univ. Edinburgh, Univ. Glasgow, IC London, Univ. Liverpool, Univ. Oxford, RAL UFRJ, CPBF IHEP(Beijing), Tsinghua Univ. IFIN-HH (Bucharest) BINP, INR, ITEP, IHEP, PNPI Inst. Phys. Tech. (Kharkov), Inst. Nucl. Research (Kiev) Espoo-Vantaa Inst. Tech. (Finland), Geneva Engineering School (Switzerland) CFET-RJ (Brazil) 45+3 institutes 2

MoU signatures are still missing from Brazil China BMBF (Germany) Poland Spain 3

LHCb Collaboration Collaboration Board Chair: C. Matteuzzi Management Spokesperson: Deputy: Technical and Resource Coordinator: T. Nakada B. d Almagne H.J. Hilke 4

Contents of the presentation I) Physics II) Experimental Area III) Subsystems 1) Magnet 2) VELO 3) RICH 4) Tracking: Outer Tracker, Inner Tracker 5) Calorimeters 6) Muon 7) Trigger 8) Computing, DAQ and ECS, Offline, Computing infrastructure IV) Overall re-optimisation V) Conclusions 5

I) Physics 2001 Summer results from the B factories. B-meson system: sin 2β BABAR (2001) = 0.59 ± 0.15 BELLE (2001) = 0.99 ± 0.15 CP in B system is established. 6

Physics contribution of LHCb after one year of data taking New aspect: CP asymmetries in B s system Quantity improvement: σ CP (LHCb one year) < σ CP ( [BABAR+BELLE+CDF+D0]dt) First time (ρ,η) CP with an accuracy comparable to (ρ,η) side theoretically and statistically. If there exists new physics unambiguous extraction of new physics contribution. 7

II) Experimental area DELPHI dismantling completed. Necessary modification work started. Cost: 4MCHF (MoU) 8 Funding: Common Fund

III) Subsystems Magnet Cost: 6 MCHF (TDR) Funding: Common Fund Al conductor (~50 t, ~9 km): committed Steel plates for Yoke (~1.5 kt): committed Construction of two coils: committed ~3.7 MCHF Autumn 2002 Dec. 2002 May 2003 Start yoke assembly Coil delivery Complete magnet assembly 9

VELO Cost: 4.822 MCHF (TDR) Funding:CH, Germany, Netherlands, UK May 2001 TDR submitted October 2001 TDR recommended for approval Baseline technology: Sensors: 300µm n-on-n short strips double metal layer for readout Electronics: SCTA-VELO (DMILL) or 10 BEETLE (0.25µm CMOS)

Silicon Jul 2002 Tests of prototypes completed design review and start of tendering Dec 2002 Place final order Jun 2003 Sensor production finished Jun 2004 Module production finished Front-end chip Dec 2001 Characterization of chips completed Dec 2002 Front-end chip decision Dec 2002 Production/testing completed L1 electronics Sep 2001 Read-out board 3 prototype Dec 2001 Analogue links tested on large scale Mar 2002 Final prototype of digitisers board Mar 2003 L1 electronics production starts Aug 2003 10 % of boards completed Apr 2004 50 % of boards completed Mar 2005 Production/testing completed Mechanics/Vacuum Feb 2002 Production readiness review with LHC groups Mar 2003 All production drawings finished Jun 2004 Production/testing completed Installation Dec 2004 Start installation in IP 8 Oct 2005 Commissioning of DAQ with other sub-detectors Dec 2005 Installation completed being constructed 11

Machine related issues are crucial: wake field and vacuum RF test tank Gravity valve test wake field suppressor secondary vacuum box validating simulation results 12

RICH Cost: 7.677 MCHF (TDR) Funding: CERN, Italy, UK TDR submitted in September 2000 approved February 2001 Baseline Technology Two RICH detectors with three radiators: aerogel+c 4 F 10 CF 4 Photon detector: Pixel HPD MaPMT as backup 13

Mechanics and Optics Mar 2002 Sep 2002 Jan 2003 Jun 2003 Jan 2004 Jul 2004 Photodetectors Jun 2001 Sep 2001 Nov 2001 Mar 2002 Dec 2002 Jun 2003 Feb 2004 Mar 2004 L1 electronics May 2002 Jul 2002 Mar 2003 Dec 2003 Dec 2002 Jun 2003 Dec 2003 Jan 2004 finish optimising engineering design 10% of mirrors produced 50% of mirrors produced finish mirror production begin RICH-1 assembly in IP8 begin RICH-2 installation in IP8 finish prototype HPD technical choice production readiness review place photodetector order 10% of detectors produced 50% of detectors produced finish detector production finish detector testing finish prototype chain tests 10 % of Level-0 units produced 50 % of Level-0 units produced finish Level-0 unit production 30 % of Level-1 units produced 60 % of Level-1 units produced finish Level-1 unit production finish production and testing to be reviewed 14

ALICE/LHCb pixel readout chip readout speed < 20 MHz Problems were found and corrected. New submission: November HPD base plate with Bump-bonded pixel+readout chip Two base plates sent to DEP for encapsulation. Expected to be back in November. 15

It was foreseen to have: a working HPD with 20MHz chip a working 40MHz chip Both are missed by several months Status will be reviewed this month. 16

Tracker: Outer and Inner Cost: 9.300 MCHF (TDR) and ~5.150 MCHF (MoU) Funding: CERN, CH, China, Germany, Netherlands, Poland, Spain, Ukraine + Common Fund Outer Tracker TDR submitted on September 2001 - Technology well defined: straw tube custom made TDC - Construction technique and plan well understood: 17

18

Inner Tracker Geometry of the Inner Tracker: All Si solution adopted. defined by the occupancy of the outer tracker. beam pipe Cross design: minimising the Si area 19

First beam test at CERN test Si ladder (300 µm p-on-n oxygenated detectors) read by HELIX chip (not LHC speed) reference Si detectors Spring 2002:read by SCTA-VELO and BEETLE (40 MHz) S/N as a function of the strip length (10, 20, 30 cm?). Increased size of the Si more R&D needed Better synchronization with the re-optimisation work. TDR submission planned for the end of 2001 to be delayed to the end of 2001 20

Order all Si sensors by 1 July 2003, - 15 months for the construction of the detector, - 6 months for the installation and commissioning. Delay of TDR does not cause any problem for the overall plan. 21

Calorimeters Cost: 15.360 MCHF (TDR) Funding:CERN, France, Romania, Russia, Spain, Ukraine, + Common Fund TDR submitted in September 2000 approved February 2001 Adopted Technology Scintillator-Pb-Scintillator (SPD and Preshower) Shashlik E-cal Fe-Scintillator tile H-cal Photon detector 22 PMT

ECAL May 2001 Jun 2001 Dec 2002 Jul 2003 Aug 2004 Nov 2004 Feb 2005 finish optimising engineering design start serial production 10% of modules produced 50% of modules produced finish module production finish module assembly finish installation see next HCAL Jun 2001 Oct 2001 Jul 2002 Jul 2003 May 2004 Jun 2004 Dec 2004 finish optimising engineering design start serial production 10% of modules produced 50% of modules produced finish module production finish module assembly finish installation see next 23

E-cal and H-cal Engineering Design Reviews completed (with external reviewers) Module-0 construction completed and tested @ CERN Shashlik front face E-cal Shashlik back side 200 outer-most modules construction@ ITEP 24 (~3300 modules total)

H-Cal module-0 Mechanical assembly @ IHEP Optical assembly @ CERN (52 modules total) 25

No major surprise in the Module-0 production. Based on this experience Production Readiness Reviews for E-cal and H-cal are being conducted. Raw material (Pb, steel, scintillators, fibres etc.) have been ordered. -committed ~3MCHF TDR costing- Series production of E-cal and H-cal will start very soon. -a couple of months later than planned- 26

SPD/Preshower Jul 2001 finish optimising engineering design Jul 2001 start serial production Jul 2002 10% of modules produced Jul 2003 50% of modules produced Jul 2004 finish module production Dec 2004 finish module assembly Mar 2005 finish installation Jan 2002 Apr 2002 Delay is not critical: Only 466 modules 2 boxes have been made. 27

Electronics SPD Dec 2002 finish optimising engineering design Mar 2003 start serial production May 2003 10% of ASIC produced Sep 2003 50% of ASIC produced Sep 2004 finish acceptance test Apr 2005 finish installation Preshower Jun 2002 finish chip engineering design Jul 2002 start chip serial production Dec 2002 finish optimising engineering design Dec 2003 10% of cards produced Jul 2004 50% of cards produced Nov 2004 finish acceptance test Apr 2005 finish installation E/H Cal Sep 2002 finish optimising engineering design Oct 2003 start serial card production Nov 2003 10% of cards produced Aug 2004 50% of cards produced Jan 2005 finish acceptance test Apr 2005 finish installation completed Front-end ASIC s design completed. 28

Muon Cost: 10.83 MCHF (TDR) Funding: Brazil, CERN, Italy, Russia May 2001 TDR submitted October 2001 TDR recommended for approval Single gap RPC (2 in OR) for low rate region < 1 khz/cm 2 (48% of area) MWPC with cathode and/or wire readout for high rate region <100 khz/cm 2 3GEM or MWPC for a small region >100 khz/cm 2 (<1%, 3 m 2 ) 29 R&D in progress

MWPC detectors Jan 2002 Engineering design completed Jan 2003 Begin chamber construction and tests Jun 2003 10 % of chamber construction done Mar 2004 50 % of chamber construction done Dec 2004 Chamber construction completed RPC detectors Dec 2001 Decision on use of linseed oil Jan 2002 RPC engineering design completed May 2003 Begin RPC assembly and tests Sep 2003 10 % of chamber construction done Jun 2004 50 % of chamber construction done Dec 2004 Chamber construction completed Chambers for the inner part of M1 Jan 2003 Technology choice Dec 2004 Chamber construction completed Electronics Mar 2002 CARIOCA design and test completed Mar 2002 DIALOG design and test completed Jun 2002 SYNC design and test completed Oct 2002 Full chain electronics test completed Jan 2003 Begin FE-board production Jun 2003 10 % of FE-board production done Feb 2004 50 % of FE-board production done Jan 2004 10 % of IM- SB- and ODE-production done Jul 2004 50 % of IM- SB- and ODE-production done Dec 2004 Electronics assembly and test completed Muon filter and support structures Dec 2003 Iron filter installation completed Jun 2004 Chamber support structures installed 30

Chamber prototypes and FE-chips For RPC: BiCMOS front-end chip developed for CMS For MWPC: custom made 0.25 µm CMOS 31 (CARIOCA)

Trigger Level-0 and Level-1 Cost: 3.400 MCHF (MoU) Funding: France, CH, Germany, Italy (Higher levels are under the online CPU farm) TDR completion: delayed end of 2001 end of 2002 -Better synchronization with the re-optimisation work -No effect on the construction schedule: Planned production starting in 2003. 32

All the L-0 components have been designed and simulated. LEds Analog Input connectors n o i t a t p a d A s e n i l y a l e D Prototype production has started. Calo front-end card Muon trigger Shaper ADC 12 bits/ 40Mhz Low Frequency noise rejection L0 Data Trigger Data Max Cluster Channel 7 32 15 23 31 ExtChannel 3 2 32 1 0 clkfromtoprv Monitoring FIFO 1K/16 Serializer 21/4 16 Deserializer 21/4 16 ExtChannel 12..4 72 clk4lvdsrv Serializer 21/4 GTL Trv Adress/Data Pulser Comands Timing Adjustment Setup Delay lines 256 L0-L1 sequencer Channel 7..0 clk4gtlrv GTL Trv clk4gtltr Address Decode 384 L0 Lattency L0 Derandomiser L1 buffer Serializer 21/4 Jtag Serial link Clock Specs Slave Power Supplies L0 decision unit prototype also ~April 2002. 33

Level-1 trigger is like online farm, but with small data size @ high frequency. 1 MHz ~150 Byte Decision Unit From VELO CPU s ~ 3 Gbyte/s 1 MHz RUs subevent Prototype is being built 34 using SCI technology

Computing Cost: 6.800 MCHF (MoU, Online part only) Funding: CERN, CH, Germany, Italy, Spain, UK + Common Fund Online TDR end of 2001 Complete DAQ architecture defined and simulated: Experiment Control System (ECS) Based on SCADA (outcome of JCOP) 35

Readout system technology choices Readout Unit baseline: Network processor very flexible and bright future. backup: FPGA based custom solution prototypes have been built and are working. Readout network Baseline: Gb Ethernet 36

Offline Projects OO software framework: GAUDI - Consolidation phase (three new releases) - Development of interactivity, visualisation etc. - Joint development with ATLAS OO applications - Reconstruction (BRUNEL): used in production mixture of C++ and Fortran physics algorithm - Simulation (GAUSS) integration of GAUDI with GEANT4 RICH and Calorimeter work started GEANT3 based SICBMC still used in production - Analysis (DAVINCI) physicists started to use it Computing Infrastructure Participation in EU DataGrid project (WP8) Preparation of Tier 1 centres new comers are NIKHEF and Bologna Preparation of Data Challenges 37

IV) Re-optimisation Effort to reduce the material budget: ideas are Improving VELO (e.g. rf shield) & RICH-1 (e.g. mirror) removing magnet stations a la fixed target tracking 38

Our road map By the end of 2001 1) Establish the validity of the new tracking strategy 2) Establish realistic new designs of RICH-1 and VELO Late Spring 2002 Re-optimised LHCb detector Autumn 2002 Addendum to LHCC on fully re-optimised LHCb detector No large scale design change is involved: compatible with our construction plan. (NB: RICH-2 and large OT stations not affected) Cost neutral: design improvement & simplification. 39

V) Conclusions With knowledge by BABAR, BELLE, CDF and D0, LHCb should unambiguously identify new physics in CP violation. TDR approved: Magnet, Calo, RICH. completed: VELO, Muon and OT. Magnet, E-cal and H-cal construction started. Remaining TDR s: Online end of 2001. IT, Trigger and Computing end of 2002. The LHCb detector is planed to be ready for the pilot run in April 2006 with full physics potential. No indication for any additional cost beyond the MoU cost for the moment (and every efforts are made to stay so). 40