LHC Machine check out

Similar documents
S67: PRE-CYCLE & RAMP

1. General principles for injection of beam into the LHC

Beam systems without failures what can be done?

WHAT WE WILL DO FOR BEAM PREPARATION IN 2009 : BEAM INTERLOCKS

Injectors. Injectors ready

LHC Nominal injection sequence

beam dump from P2 losses this morning

Friday 05/03/ :00 13:00 : Establishing reference orbit golden Jorg Wenninger. Problems Wrong polarity on MCBXH3.L8 Polarity flag changed in DB

Procedures for the Commissioning of the Beam Interlock System for the CNGS and SPS-LHC Transfer Lines

REVIEW OF LHC OPERATION

LHC COMMISSIONING PLANS

INITIAL BEAM COMMISSIOMING OF INJECTION AND BEAM DUMP

2008 JINST 3 S LHC Machine THE CERN LARGE HADRON COLLIDER: ACCELERATOR AND EXPERIMENTS. Lyndon Evans 1 and Philip Bryant (editors) 2

Full IEFC workshop Feb.

Accelerator Controls Part2: CERN central timing system

What can be learned from HERA Experience for ILC Availability

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

LHC Beam Instrumentation Further Discussion

THE ARCHITECTURE, DESIGN AND REALISATION OF THE LHC BEAM INTERLOCK SYSTEM

The 2011 LHC Run - Lessons in Beam Diagnostics

MACHINE PROTECTION WORKSHOP REVISITED OPEN ISSUES, PROGRESS AND DECISIONS ON MAJOR TOPICS

Beam Loss Detection for MPS at FRIB

OPERATIONAL EXPERIENCE WITH CIRCULATING BEAM

A Fast Magnet Current Change Monitor for Machine Protection in HERA and the LHC

Commissioning of the CNGS Extraction in SPS LSS4

Session 07 - What did we learn with beam in 2008? LHC Performance Workshop Chamonix Rhodri Jones on behalf of BE/BI & all our collaborators

Information here generates the timing configuration and is hence the definitive source. The situation is quite volatile, new events and telegram

CLIC Feasibility Demonstration at CTF3

Linac3 experience for LHC ion runs

Equipment Installation, Planning, Layout, organisation and updates

RF PERFORMANCE AND OPERATIONAL ISSUES

LHC_MD292: TCDQ-TCT retraction and losses during asynchronous beam dump

Bunch-by-bunch feedback and LLRF at ELSA

SUMMARY OF SESSION 4 - UPGRADE SCENARIO 2

FILLING SCHEMES AND E-CLOUD CONSTRAINTS FOR 2017

Status of the X-ray FEL control system at SPring-8

The Elettra Storage Ring and Top-Up Operation

arxiv: v1 [physics.acc-ph] 9 Aug 2016

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

ANKA RF System - Upgrade Strategies

Linac 4 Instrumentation K.Hanke CERN

LLRF at SSRF. Yubin Zhao

SPEAR 3: Operations Update and Impact of Top-Off Injection

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

Commissioning of the ATLAS Transition Radiation Tracker (TRT)

Detailed Design Report

LESSONS LEARNT FROM BEAM COMMISSIONING AND EARLY BEAM OPERATION OF THE BEAM LOSS MONITORS (INCLUDING OUTLOOK TO 5 TEV)

PICS IN THE INJECTOR COMPLEX WHAT ARE WE TALKING ABOUT?

Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi)

North Damping Ring RF

PoS(EPS-HEP2015)525. The RF system for FCC-ee. A. Butterworth CERN 1211 Geneva 23, Switzerland

Availability and Reliability Issues for the ILC

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

Commissioning and Performance of the ATLAS Transition Radiation Tracker with High Energy Collisions at LHC

Digital BPMs and Orbit Feedback Systems

The ESRF Radio-frequency Data Logging System for Failure Analysis

RF upgrade program in LHC injectors and LHC machine

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems

1 Digital BPM Systems for Hadron Accelerators

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

Present Status and Future Upgrade of KEKB Injector Linac

FIRST SIMULTANEOUS TOP-UP OPERATION OF THREE DIFFERENT RINGS IN KEK INJECTOR LINAC

Upgrading LHC Luminosity

A Cathode Development Cornell Cultera This scope includes all labor and purchases required produce photocathodes required by CBETA.

5 Project Costs and Schedule

The FAIR plinac RF Systems

CLEX (CLIC Experimental Area)

First LHC Beams in ATLAS. Peter Krieger University of Toronto On behalf of the ATLAS Collaboration

System: status and evolution. Javier Serrano

Requirements for the Beam Abort Magnet and Dump

Commissioning the TAMUTRAP RFQ cooler/buncher. E. Bennett, R. Burch, B. Fenker, M. Mehlman, D. Melconian, and P.D. Shidling

Testing and Characterization of the MPA Pixel Readout ASIC for the Upgrade of the CMS Outer Tracker at the High Luminosity LHC

P. Adamson, Fermi National Accelerator Laboratory, Batavia, IL 60510, USA. Abstract

5 MeV Mott Polarization Measurement Procedure--DRAFT

Development of an Abort Gap Monitor for High-Energy Proton Rings *

Proceedings of the 1997 Workshop on RF Superconductivity, Abano Terme (Padova), Italy

TRIUMF CYCLOTRON MAIN MAGNET POWER SUPPLY REPLACEMENT

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting

Status of SOLARIS Arkadiusz Kisiel

Week 0: PPS Certification and Processing. Mon Feb 11 Tue Feb 12 Wed Feb 13 Thu Feb 14 Fri Feb 15 Sat Feb 16 Sun Feb 17

RF2TTC and QPLL behavior during interruption or switch of the RF-BC source

LEP Status and Performance in 2000

Status of RF Power and Acceleration of the MAX IV - LINAC

Study of the performances of the ALICE muon spectrometer

HD Review March 30, 2011 Franz Klein

Control of Intra-Bunch Vertical Motion in the SPS with GHz Bandwidth Feedback

Radiation Safety System for Stanford Synchrotron Radiation Laboratory*

P. Emma, et al. LCLS Operations Lectures

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

Glast beam test at CERN

Assembly of the HIE-ISOLDE accelerator cavities in a clean room.

Synchrotron Light Facility. Operation of ALBA RF. Angela Salom on behalf of RF team: Francis Perez, Bea Bravo and Jesus Ocampo

PEP-II longitudinal feedback and the low groupdelay. Dmitry Teytelman

ABORT DIAGNOSTICS AND ANALYSIS DURING KEKB OPERATION

Spear3 RF System Sam Park 11/06/2003. Spear3 RF System. High Power Components Operation and Control. RF Requirement.

Scavenger Extraction. Karen Goldsmith Shawn Alverson

HIGH POWER BEAM DUMP AND TARGET / ACCELERATOR INTERFACE PROCEDURES *

Status of Elettra, top-up and other upgrades

A FOUR GAIN READOUT INTEGRATED CIRCUIT : FRIC 96_1

COGGING & FINE ADJUST OF THE BEAM BEAM PHASE

Transcription:

LHC Machine check out R.Giachino / M.Albert 1v1 Be/op 12th March 2012

Hardware Commissioning: M. Pojer, R. Schmidt and M. Solfaroli Summary of week 10 Machine checkout: R. Giachino, M.Albert and J. Wenninger Aims of the week Finish HWC Prepare machine for first beam LHC 8:30 meeting

LHC check-out Main targets of the week: Finish HWC, Close the beam interlock loop, Test the beam dump, Test the injection kickers, Run the LHC through a full machine cycle, Check the control system. LHC 8:30 meeting

Progress : HWC & checkout From Monday to Friday HWC and machine checkout activities had to be performed in parallel. Priorities were defined every day for HWC and for checkout activities, the focus shifting from HWC to checkout along the week. Collaboration HWC-machine checkout, was very smooth due to a better planning of the activities. LHC 8:30 meeting

Status of powering tests In total, 8185 tests steps (including preparations of powering tests) have been done Progressive availability of cryogenic conditions

Powering status Heat runs: All sectors were tested Pre-cycles work well. Several full machine cycles were performed Without hardware powering faults. RQT13.L8B1 increased IPNO from 400 to 450(B*.6m) LHC 8:30 meeting

HWC was completed Wednesday afternoon when the machine was handed over to beam operation. The same evening, the machine was pushed through the nominal proton cycle: Pre-cycling of the magnets, Injection, Ramp, Squeeze. control issues were identified have been fixed or will be fixed in the coming days. Machine cycle LHC 8:30 meeting

LHC progress : beam interlock and kickers To close the beam interlock loop requires a number of conditions, the most difficult ones to achieve were: LHC closed no access (also experiments), No powering failures, Vacuum valves open, BLM system operational. >> tough constraints given parallel HWC activities. The BIS loop was closed the first time Friday evening. Saturday late night both dump and injection kicker systems were pulsing. LHC 8:30 meeting

LHC progress: LBDS & MKI tests BETS fully tested at 450GeV and 4GeV. Injection inhibitions between LBDS and MKI are OK. TSU clients tested: BIS BETS Internal failure (frev switch off) LBDS trigger Circulate & dump Inject & dump -> functionality OK issue with XPOC (see below) TSU synchronisation. TSU IPOC thresholds have been adjusted. MKI synchronisation checks with beam show a shift of the kick by +160ns w.r.t. beam (to be decided how to adjust it) Inject & dump status is badly returned by one of the 2 CPLDs on the TSU (to be decided) 9

LHC 8:30 meeting Controls Along the week the OP teams with support from numerous equipment groups tested applications, front-ends, LSA core etc..

The Vacuum system was operational on Friday evening after a big effort in point 2&8. RF was ready to ramp for the week end. BI was extensively tested without beam. Collimators setting and calibration is finished. The cryogenic system, has been stable all along the HWC. EN/EL, EN/CV at nominal configuration. LHC 8:30 meeting

Injectors and transfer lines (1) PSB started up with beam 20 th February. LHC-indiv Lhc50 LHC-probe LHC25 PS started up with beam 23 th February. LHC-probe, LHC-indiv. LHC50 12b setting up SPS started up with beam 25 th February. SPS aligned, probe bunch ready to be extracted to the LHC. LHC-Indiv, LHC-probe, LHC50 multibatch Scrubbing LHC 25 72 Bunches LHC 8:30 meeting

Injectors and transfer lines (2) Thursday probe bunches were extracted into the TT60 & TT40. Saturday afternoon beams were sent down the 3 km long TI2 and TI8 transfer lines to the downstream (LHC end) dumps. Saturday night stability checks were performed. TI8 TI2 LHC 8:30 meeting

Open issues TI 2 Transfer line PC RBIV26407 tripped (to be checked) RQT13.L8B1 increased from IPNO from 400 to 450 (b*.6m) Done ok RCBV27R4B1 communication lost RCBXH1.L1 tripped (circuit super-locked) RQTL11.R1B2 problem on TT893 temperature sensor RD34.LR3 ramp-down settings are out of limits RQX.R2 QPS controller communication problem; oscillating RQTD/F circuits unable to load ramp/squeeze function (Fidel on Monday) RQF/RQD require higher commissioning current for high beta (50 A) Inject & dump status is badly returned by one of the 2 CPLDs on the TSU MKI synchronisation checks with beam show a shift of the kick by +160ns w.r.t. beam (to be decided how to adjust it RF) 14

Access Radiation veto after machine closed!!! Access system PAD problem PM25 Possible intervention Monday morning Alfa Monday morning Point 1 BT Access point 6 for TSU inject and Dump R2E Monday morning TX76 1Hr X ray 2 & 8 Monday afternoon point 8 Tuesday morning point 2

16 Planning

Situation of the machine: Summary The LHC magnet and powering system is fully commissioned and the machine is in a very good state as demonstrated by the cycling of the machine. RF need 2-4 hrs for fine tuning before beam. LBDS & MKI minors adjustments before declaring operational. Essential beam instrumentation and feedbacks tested. fine tuning with beam. Control system operational smaller issues will be fixed in the coming days. First beam hopefully Tuesday afternoon! LHC 8:30 meeting

Saturday 09:00 Start LBDS tests 09:13 Starting ramp of RF and ADT. stay at flat top with the RF to stress the cavities. 15:30 Beams down TI8 & TI2 Application Collimator Scan is tested and worked fine. 18

Last night 22:30 Alfa interlock. Tests couldn t be performed Problems related to the movement of their XRPs there s presumably a problem with their logic control; experts will check it this morning 22:50 Etienne finished the tests on MKI. Now left to do the circulate and dump for both Beams. Circulate & DUMP B1&B2 (~50 shots each) Short access for ATLAS to verify the cooling system; They will need to intervene this morning to fix a problem they have identified (estimate: ~4h, to be scheduled) Ramp of PCs (except RQTD/F) Squeeze without RQT13.L8B1 (out of limits error) and RQTD/F circuits 19

Last night RQX.R1, RTQX1.R1 and RTQX2.R1 tripped while executing RAMPDOWN[START] function but no fault present (only PC_PERMIT went away) RD34.LR3 gives a "out of limit" when loading the ramp-down function ALICE requested some time for a cosmic.. Executed ramp of PCs (without RQTD/F & RCS/O/D) & RF 20

LBDS MKI tests BETS fully tested at 450GeV and 4GeV. Ramp was OK. Error check during the ramp still to be done on Monday by Nicolas V. Injection inhibitions between LBDS and MKI are OK. Response times are within specification TSU clients tested: BIS -> OK BETS -> OK Internal failure (frev switch off) -> OK LBDS trigger --> OK Circulate & dump -> OK Inject & dump -> functionnality OK issue with XPOC (see below) TSU synchronisation -> OK TSU IPOC thresholds have been adjusted All OK now MKI synchronisation checks with beam show a shift of the kick by +160ns w.r.t. beam (to be decided how to adjust it) Inject & dump status is badly returned by one of the 2 CPLDs on the TSU (to be decided) 21

LBDS tests BIS loop closed and arm beam dump- done Check injection inhibition from LBDS- done TSU tests for about 4 hours to test clients (BIS, BETS, )- done Circulate and dump for TSU testing for about one hour. Done Mask modules in XPOC which are not yet receiving data.- Check IQC- ok Synchronization of MKI with AGK without beam, loops closed.-checked Beam down TL TI2 and TI8. Rough steering.- done TCDI machine protection tests done TCDI set-up tests.- chiara Direct interlock of LASS to LBDS-.>>> done LBDS energy tracking interlocks by trimming only needs BETS armed, not BIS.- done Check BIS timestamps and redundancy of signals to LBDS (with CM, if time available)- Other tests from MP Web page. 22

Injection status Managed to pulse both kickers. Need to check why only the TCDIs beam 1 are interlocking in parking and not beam. Problem with timing system: hidden tables loaded in MTG. Cannot see them and cannot unload them, but they are played (injection, injection_bi). Inject & dump does not work currently. Circulate & dump is fine (uses the hidden tables automatically). Running circulate & dump in a loop not possible masking on XPOC not working anymore. (Roman). >>Done 23

MKI MPS tests MKI MPS tests Toggling MKI status and checking input state on injection BIC, both beams - Verifying and adapting soft-start settings (normal and extended), both beams - adjusted operational limits around nominal value (entries 7 and 8) - changed voltage step size for extended settings (entry 14) Probed voltage limit for which MKIs not pulsing anymore (1 kv above nominal value, 1 kv below conditioning value), only for P8 done Loading kicker soft-start settings from TRIM and FESA, not possible to change without MCS role, possible with MCS role Changing critical settings in MKI application only possible with MCS role 24

MKI MPS tests Tried to do the energy tracking tests: changing LHC energy: SIS injection energy consistency check stopped us from trimming the RBs above the BETS limit of 0.96 GeV, need a workaround for the commissioning to still perform this test in the next days - changing MKI voltage: within operational limits the kickers are pulsing, need to check with limits further open (MCS role needed) MKI tests not finished. MPS interlock tests for collimators TCDI, TDI, TCLI and TCDD in P2 done 25

Injection status IQC all data collection is fine, but the soft-start buffer is pushed to PM too early before it is updated after the pulse. -> The IQC does not find it having pulsed. Done. OASIS for MKI signals still needs follow up next week. Currently not fully operational. Done 26

Summary TSU test (both beams) Check TSU clients: - BIS triggering --> OK - BETS triggering --> OK - Internal failure triggering --> OK - LBDS slow control triggering --> OK - Inject and dump triggering --> Works fine but bad status acquisition from CPLD2 (XPOC error) - Circulate and dump --> OK Issues to be followed: - Inject and dump detection (TSU card CPLD2) - Spurious bad XPOC analysis on TSU (missing dump request detection, XPOC event builder synchronisation) ALL dumps properly synchronised... Thresholds adjusted for TSU-IPOC analysis: - re-trigger detection decreased to 199us - DBRF length detection adjusted to 1us - BRF length detection adjusted to 0.9us - BAGK length reduced to 10.9us 27

ABT Software ABT and BI had to adapt many FESA devices in a manner to have their PM buffers properly saved into PM data store for IQC and XPOC analysis. Impacted systems are:- MKI/BETS- MKI/IPOC- LBDS/TSU- BTVDD Now everything is fine for both IQC and XPOC. We only miss Vacuum data for XPOC, so we had to mask the VAC module temporarily. It seems that work is ongoing on TE/VSC side to find a solution to the problem. 28

Safe Machine Parameters System 29