FACILITIES STUDY MID AMERICAN TRANSMISSION SERVICE REQUESTS. OASIS Revision: 4

Similar documents
ICTE TLR 5 Investigation Report Flowgate (West Memphis Xmfr 161/500kv ftlo San Souci Shelby 500kv) TLR Level 5: June 20, 2011 Report Issued:

ELIGIBLE INTERMITTENT RESOURCES PROTOCOL

Alberta Electric System Operator

1. EXPERT MEETING EXPERT MEETING EXPERT MEETING Feedback from the meeting attendees...

10/13/2011 Planning Coordination Committee. Standards

0.1. Outage Management Process Summary

Plan for Generic Information Collection Activity: Submission for. National Transportation Safety Board (NTSB).

SECTION MEDIUM VOLTAGE CABLE INSTALLATION. 1. Section Underground Ducts and Manholes.

Unofficial Comment Form Project Establish and Communicate System Operating Limits (SOL and SOL Exceedance Definitions)

Our world. Anytime, anywhere, live. Your world.

TARIFF DISTRIBUTION TARIFF SECTION PAGE NUMBER PAGE REVISION E E E E E

Load Frequency Control Structure for Ireland and Northern Ireland

Country Experience On Satellite Service Regulatory Framework

Toronto Hydro - Electric System

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

AltaLink Management Ltd.

CHIEF BROADCAST ENGINEER

FINAL REPORT LOAD SHEDDING IN TASMANIA ON 20 DECEMBER 2016 REVIEWABLE OPERATING INCIDENT REPORT FOR THE NATIONAL ELECTRICITY MARKET

BPA s Network Open Season

Florida Department of Education CURRIUCULUM FRAMEWORK. Digital Television and Media Production

NERC Reliability Standard PRC-024 Generator Frequency and Voltage Protective Relay Settings

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

Objectives and Methodology for the Over-the-air Television Transition

Marc Richter Vice President Regulatory Services. June 3, 2015 CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION. By Electronic Delivery

New York State Board of Elections Voting Machine Replacement Project Task List Revised

Definitions. Common Corridor:

3 Resolution of the Board of Supervisors, acting as responsible agency with respect to

Meeting the Challenge of a Difficult Job Speciality Contractor ACE Awards

This SOP is applicable to all WMATA personnel working on the Rail System, contractors performing the work and WMATA contractor escorts.

PART A - Project summary

SOUTHWESTERN BELL TELEPHONE COMPANY TARIFF F.C.C. NO. 73 1st Revised Page 9-1 Cancels Original Page 9-1

Jemena Electricity Networks (Vic) Ltd

KENT COUNTY WATER AUTHORITY MINUTES OF THE REGULAR MEETING OF THE BOARD. June 16, 2016

Satellite Services and Interference: The current situation. ITU International Satellite Communication Symposium Geneva, June 2016

Specification. NGTS Issue 1 October 1993

REFURBISHMENT OF SECONDARY SYSTEMS IN HIGH VOLTAGE SUBSTATIONS LESSONS LEARNED IN VENEZUELA

Escorting / Supervision of service providers and contractors

1. Can companies based outside of the United States respond to this RFP?

GLX Project Green Line Extension Project. March 2, 2016 Public Meeting

Incorrect Temperature Measurements: The Importance of Transmissivity and IR Viewing Windows

BEFORE THE NEW JERSEY BOARD OF PUBLIC UTILITIES

CITY OF LOS ANGELES CIVIL SERVICE COMMISSION CLASS SPECIFICATION POSTED JUNE VIDEO TECHNICIAN, 6145

SPECIAL SPECIFICATION :1 Video (De) Mux with Data Channel

HONEYWELL VIDEO SYSTEMS HIGH-RESOLUTION COLOR DOME CAMERA

Start Recording on Site

The 2017/18 Rooftop Movies season will run from 1 December 2017 to 31 March 2018.

HEALTH AND SAFETY MANUAL

Design Project Proposal

Using Digital Fault Recorders As Phasor Measurement Unit Devices

Licence for the transmission of digital terrestrial television multiplex service

IMS Brochure. Integrated Management System (IMS) of the ILF Group

Metuchen Public Educational and Governmental (PEG) Television Station. Policies & Procedures

Environmental Impact Statement (EIS)/ Section 106 Public Meeting Level 1 Concept Screening. May 16, 2017

SUMMARY REPORT. Consultation Summary Report. January 2016

ITU-T Y Functional framework and capabilities of the Internet of things

Grid Code Modification Register. March 2018

Capital Works process for Medium Works contracts

Action: Karl Tammar indicated that Lydia Vollmer and Herb Yan had both left PECO and that replacement participants from PECO should be sought.

MISO Reliability Coordination expansion 6/1/2013

Rental Information For Campus Clients

Department of Corrections Facilities Bureau Security Equipment Solicitation #TO8133

Instructions to Authors

21. OVERVIEW: ANCILLARY STUDY PROPOSALS, SECONDARY DATA ANALYSIS

Questions about these materials may be directed to the Obstetrics & Gynecology editorial office:

MISO Market Participant Cutover Briefing #5: Notable Market Developments. December 19, 2013

Working With Music Notation Packages

FORENSIC CASEBOOK. By Bob Huddleston, Eastman Chemical Co. One of the most common. reasons for marriage failure

PART 14 - Wireless Services SECTION 3 - Cellular Mobile Carrier Service - Type 1 Original Sheet No. 1

Secondary Sources and Efficient Legal Research

2. SUPERPATH Mbps Digital Service 2.1. General

2 Higher National Unit credits at SCQF level 7: (16 SCQF credit points at SCQF level 7)

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

BUFORD COMMUNITY CENTER, TOWN PARK & THEATRE THEATRE AND STAGE RENTAL AGREEMENT

VERIZON MARYLAND INC.

Intelligent solutions for Onshore Power Supply

Building Your DLP Strategy & Process. Whitepaper

New York MX700 Room. PWD-NY5-MX700-P60 List Price: $11, SLA Price: $1,100.00/year (Other options available See Appendix B)

Analog to Digital conversion of HD video. The HD-Now provides a simple method of upgrading ROVs for live HD. Keep existing infrastructure intact.

Selecting Cables for Power over Ethernet

ITU-T Y.4552/Y.2078 (02/2016) Application support models of the Internet of things

Transmission App for Real Time Monitoring and Growth

emedical Frequently Asked Questions (FAQs) Guide

Bendigo Theatre Company Inc. POSITION DESCRIPTIONS INDEX

1C.5.1 Voltage Fluctuation and Flicker

Facilities Management Design and Construction Services

Demonstration of geolocation database and spectrum coordinator as specified in ETSI TS and TS

A Unique Power Supply for the PEP II Klystron at SLAC*

1.2 The NAB is the leading representative of South Africa s broadcasting industry representing:

APPLICATION AND EFFECTIVENESS OF THE SEA DIRECTIVE (DIRECTIVE 2001/42/EC) 1. Legal framework CZECH REPUBLIC LEGAL AND ORGANISATIONAL ARRANGEMENTS 1

Synergy SIS Attendance Administrator Guide

21. OVERVIEW: ANCILLARY STUDY PROPOSALS, SECONDARY DATA ANALYSIS

Questions to Ask Before Beginning a Digital Audio Project

COMMUNICATIONS OUTLOOK 1999

ORDER NO * * * * * * * * * On December 21, 2018, the Maryland Public Service Commission

ATTACHMENT 2: SPECIFICATION FOR SEWER CCTV VIDEO INSPECTION

Chapter 2 Radio Republik Indonesia Surakarta

APPENDIX J Richmond High School Performing Arts Theater Usage Policy (December 2018)

of New York, Inc. Original Sheet No. 81 SCHEDULE 3 Black Start Capability

Hampshire College Theatre. Space Contract

Demand Side Engagement Document

Transcription:

TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:EAI CUSTOMER: MID AMERICAN ENERGY. FACILITIES STUDY EJO # F4PPAR0422 MID AMERICAN TRANSMISSION SERVICE REQUESTS OASIS 1468288 Revision: 4 Rev Issue Date Description of Revision Revised By 0 9/11/07 Final Draft Issued to ICT GWR Project Manager 1 9/20/07 Revised Draft for Review GWR 2 9/26/07 Revised Study GWR 3 10/9/07 Added comments Section 3.ii GWR 4 10/12/07 ICT Review JDL JH Entergy Transmission Business Page 1 of 8

AECI AFC AMRN ATC ICT EES MVA MW OASIS OATT SOCO TSR TTC Acronyms Used in this Study Associate Electric Cooperatives, Incorporated Allowable Flowgate Capacity Ameren Corporation Control Area Available Transfer Capability Independent Coordinator of Transmission Entergy Control Area Mega-Volt Amp Mega-Watt Online Access and Same-time Information System Open Access Transmission Tariff Southern Company Control Area Transmission Service Request Total Transfer Capability Entergy Transmission Business Page 2 of 8

Table of Contents Section Title Link to Page 1. EXECUTIVE SUMMARY...4 2. SAFETY AWARENESS...5 3. SCOPE SUMMARY...5 I. Contract Path Allocation Modification... 5 II. New Madrid Substation... 6 4. SCOPE DETAILS...6 5. COSTS...7 6. SCHEDULE...7 7. ATTACHMENTS...7 A. Location Drawings... 7 B. One Line Drawings... 7 Entergy Transmission Business Page 3 of 8

1. EXECUTIVE SUMMARY Mid American Energy (Customer) submitted a transmission service request for long term firm point to point service for 103 MW from Ameren Control Area (AMRN) to Southern Company Control Area (SOCO). The time period for this transfer is from 1/1/2008 until 1/1/2009. The direction of the transaction is AMRN to SOCO. This facility study identifies substations that must be upgraded in order to mitigate undesirable system conditions. This facility study is a unique study in that it impacts not only Entergy, but also Ameren and AECI. Entergy cannot determine the final list of upgrades until a solution for increasing the AMRN-AECI-EES contract path is finalized between the three parties. No additional studies were performed to determine any other facilities required for this Transmission Service Request to be available. Entergy is willing to jointly work with the affected systems to determine the final solutions for granting this service, but any additional studies Entergy performs at this time would not provide much in the way of useful results. Under Entergy s Independent Coordinator of Transmission which became effective on November 17, 2006, Entergy will recover these costs based on the Attachment T to our OATT. The ICT has not classified any upgrades, but will evaluate any future solutions. Pending the results of AECI s Affected System Study and coordination between AMRN-AECI-EES, any changes will need to be reviewed by the AMRN- AECI-EES contract path parties. The single connection between Entergy and AMEREM is the 500 kv line connecting Entergy s Dell Substation and AECI s New Madrid Substation. The limiting element for power flow on this line is the transformation capability at the New Madrid substation. The transformation limit is 1500 MVA. This interface capability has been split on an equal basis with 500 MVA to AMEREN, 500 MVA to AECI and 500 MVA to Entergy. Since the original TSR was queued, the methodology for allocating the Ameren/Entergy, & the AECI/Entergy contract path limits was modified. (See OASIS posting at: http://oasis.e-terrasolutions.com/documents/ees/amrnaeciinterfaces.pdf). Entergy allocates its 500 MVA share to transmission service customers on a first come first served basis. This allows AMEREN to have a possible contract limit on this interface of 500 MVA to 1000 MVA depending on the timing of the requests received. The exact amount available to AMEREN is a dynamic amount that can only be provide by the ICT due to competing requests and rollover rights that may or may not be confirmed. Entergy Transmission Business Page 4 of 8

2. SAFETY AWARENESS Safety is a priority with Entergy. Safety will be designed into substations and lines. The designs will be done with the utmost safety for personnel in mind for construction, operation and maintenance of the equipment. Should the work contained within this Facility Study be approved, a detailed Safety Plan will be formulated and incorporated within the project plan. All employees working directly or indirectly for Entergy shall adhere to all rules and regulations outlined within the Entergy Safety manual. Entergy requires safety to be the highest priority for all projects. All Entergy and Contract employees must follow all applicable safe work procedures. 3. SCOPE SUMMARY I. Contract Path Allocation Modification The existing 500 kv transformers at the New Madrid substation limit the interface capability to 1500 MW. Each of the parties connected to this interface split capacity on an equal basis with 500 MW allocated to Ameren, 500 MW allocated to AECI and 500 MW allocated to Entergy. Previous Allocation Summary One third of the 1500 MW thermal capability of the New Madrid interface is allocated to each party (500+500+500) One half of the resulting 500 MW Entergy portion is made available to the AMRN path and the other half to AECI path The New Madrid interface is the only tie to AMRN so the AMRN interface limit = 1/3(New Madrid thermal limit) + ½(Entergy s third) = 500 MW+ ½(500) MW = 750 MW AECI has additional ties to Entergy. The thermal limit of those ties is 805 MW. The AECI interface limit = 805 MW + 750 MW= 1555 MW Total Interface Limit on AECI path and Ameren Path = 750 + 1555 = 2305 Beginning September 2007, Entergy modified the split allocation and allocated its 500 MW share on a first come first served basis. This will allow Ameren path to have a contract limit on this interface of up to 1000 MW and the AECI path up to 1805 MW, depending on the timing of the requests received. This change of the contract interface will allow more efficient use of available transmission service. Revised Allocation Summary The 500MW Entergy portion will be made available on a first come first serve basis New AMRN interface limit = 500 MW + 500 MW (if available) Entergy Transmission Business Page 5 of 8

AMRN s 1/3(New Madrid interface) + Entergy s 1/3(New Madrid interface) New TTC = 1000 MW New AECI interface limit = 805 MW+ 500 MW+ 500 MW (if available) AECI tie lines + AECI s 1/3(NM-Dell) + Entergy s 1/3(NM-Dell) New TTC = 1805 MW A new North Interface Limit Flowgate (NIFL_TieCap) will ensure that the total simultaneous transfers across the AMRN and AECI interfaces do not exceed the existing limit. The total North Interface Limit will remain unchanged at 2305 MW, and the total transactions across both paths will be limited to 2305 MW. The Facility Study has identified one transmission constraint, but cannot determine the final list of upgrades until a solution for increasing the AMRN-AECI-EES contract path is finalized between the contract path participants. The constraint can be addressed in the following manner: II. New Madrid Substation An increase in the contract limit on this interface will require the installation of additional transformer capacity at the AECI New Madrid Substation. To grant the transmission service, the EHV auto-transformers at New Madrid must either be upgraded to allow the full 3000 amp capacity across the Ameren contract path or additional EHV transformer capacity must be installed. Feedback from Siemens has indicated that the current delivery time for large EHV auto-transformers is 26 months if ordered from Brazil and 48 months if ordered from Germany. These lead times are consistent with recent Entergy experience. It will be necessary to coordinate with AECI for the Affected System Study. 4. SCOPE DETAILS Required Transmission Upgrades I. New Madrid Substation This substation is owned by AECI. The ICT has notified AECI that they are an affected system from this facility study. AECI will determine the required transmission upgrades needed to accommodate this request from an Affected System study. This information is included to provide a complete scope of work; however, this work will be done by other entities. Upgrade to allow the full 3000 amp capacity across the Ameren contract path or additional EHV transformer capacity must be installed. Yet any changes on the affected party s side will need to be reviewed by the AMRN-AECI- EES contract path parties. Entergy Transmission Business Page 6 of 8

5. COSTS The ICT has no upgrades to review since Entergy cannot determine the final list of upgrades until a solution for increasing the contract path is finalized. The cost estimate for work at the New Madrid substation should be provided by AECI. Should upgrades be needed on the Entergy system resulting from AECI s completed Affected System Study, the ICT will then make a determination of the upgrades. For more information on cost responsibility for Base Plan and Supplemental Upgrades, see Attachment T to Entergy s OATT. 6. SCHEDULE Software changes have been implemented to make Entergy s 500 MW portion of the contract path capacity of the New Madrid Dell 500 kv line available to the market on a first come, first served basis. A detailed schedule will be prepared subsequent to customer approval. The line upgrades are dependent on obtaining outages for the line work. If outages cannot be obtained or must be sequenced due to seasonal requirements, additional time will be required to complete the upgrades. 7. ATTACHMENTS Description A. Location Drawings Page Dell New Madrid Area A-1 B. One Line Drawings Description Page Dell Substation Sheet 1 B-1 Dell Substation Sheet 2 B-2 Entergy Transmission Business Page 7 of 8

Dell New Madrid 500 kv Line Segment Line #866 A-1 Arkansas Missouri Border 9.4 Miles 3/B 954 MCM ACSR Entergy Transmission Business Page 8 of 8