SPEAR 3: Operations Update and Impact of Top-Off Injection

Similar documents
Top-Up Experience at SPEAR3

New Filling Pattern for SLS-FEMTO

The Elettra Storage Ring and Top-Up Operation

Digital BPMs and Orbit Feedback Systems

PEP II Design Outline

Status of SOLARIS Arkadiusz Kisiel

P. Emma, et al. LCLS Operations Lectures

Status of Elettra, top-up and other upgrades

Operational Status of PF-Ring and PF-AR after the Earthquake

COMMISSIONING RESULTS OF BEAM DIAGNOSTICS FOR THE PETRA III LIGHT SOURCE

Requirements for the Beam Abort Magnet and Dump

LHC Beam Instrumentation Further Discussion

TWO BUNCHES WITH NS-SEPARATION WITH LCLS*

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

North Damping Ring RF

Production of quasi-monochromatic MeV photon in a synchrotron radiation facility

Advanced Photon Source - Upgrades and Improvements

Fast Orbit Feedback at the SLS. Outline

First Simultaneous Top-up Operation of Three Different Rings in KEK Injector Linac

Status and Plans for PEP-II

Characterizing Transverse Beam Dynamics at the APS Storage Ring Using a Dual-Sweep Streak Camera

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

LCLS Injector Technical Review

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

INTRODUCTION. SLAC-PUB-8414 March 2000

Development of an Abort Gap Monitor for High-Energy Proton Rings *

Current status of XFEL/SPring-8 project and SCSS test accelerator

Present Status and Future Upgrade of KEKB Injector Linac

Detailed Design Report

Mechanical aspects, FEA validation and geometry optimization

Summary of the 1 st Beam Line Review Meeting Injector ( )

RF considerations for SwissFEL

FIRST SIMULTANEOUS TOP-UP OPERATION OF THREE DIFFERENT RINGS IN KEK INJECTOR LINAC

The basic parameters of the pre-injector are listed in the Table below. 100 MeV

2008 JINST 3 S LHC Machine THE CERN LARGE HADRON COLLIDER: ACCELERATOR AND EXPERIMENTS. Lyndon Evans 1 and Philip Bryant (editors) 2

COMMISSIONING OF THE ALBA FAST ORBIT FEEDBACK SYSTEM

SUMMARY OF THE ILC R&D AND DESIGN

Recent APS Storage Ring Instrumentation Developments. Glenn Decker Advanced Photon Source Beam Diagnostics March 1, 2010

Program Risks Risk Analysis Fallback Plans for the. John T. Seeman DOE PEP-II Operations Review April 26, 2006

Upgrading LHC Luminosity

PEP-II STATUS REPORT *

Photo cathode RF gun -

Design Studies For The LCLS 120 Hz RF Gun Injector

Hall-B Beamline Commissioning Plan for CLAS12

Summer / Fall 2004 Downtime AEG Preparation Work

Accelerator Systems of the TPS

A Facility for Accelerator Physics and Test Beam Experiments

ILC Damping Ring Lattice Status Report. Louis Emery and Aimin Xiao Argonne National Laboratory Presented at KEK workshop Dec 18th, 2007

ANKA Status Report. N.Smale, on behalf of all ANKA colleagues, Directors : A.-S. Müller, C Heske, T Baumbach.

Phase (deg) Phase (deg) Positive feedback, 317 ma. Negative feedback, 330 ma. jan2898/1638: beam pseudospectrum around 770*frev.

ANKA Status Report. N.Smale, A.-S. Müller, E. Huttel, M.Schuh Slides courtesy of A.-S. Müller and C.Heske.

ALBA. Libera Workshop 16 A. Olmos

Electron Bypass Line (EBL) Design Electrons to A-line bypassing LCLS T. Fieguth, R. Arnold

Radiation Safety System for Stanford Synchrotron Radiation Laboratory*

OPERATIONAL EXPERIENCE AT J-PARC

EPJ Web of Conferences 95,

EUROFEL-Report-2007-DS EUROPEAN FEL Design Study

Monthly Progress Report Stanford Synchrotron Radiation Laboratory

PEP II STATUS AND PLANS *

ANKA RF System - Upgrade Strategies

Status of CTF3. G.Geschonke CERN, AB

Control of Intra-Bunch Vertical Motion in the SPS with GHz Bandwidth Feedback

Bunch-by-bunch feedback and LLRF at ELSA

PEP-I1 RF Feedback System Simulation

An Overview of Beam Diagnostic and Control Systems for AREAL Linac

CERN S PROTON SYNCHROTRON COMPLEX OPERATION TEAMS AND DIAGNOSTICS APPLICATIONS

Diagnostics Development in SRRC

CONSTRUCTION AND COMMISSIONING OF BEPCII

PEP-II longitudinal feedback and the low groupdelay. Dmitry Teytelman

Tolerances on Magnetic Misalignments in SESAME Storage Ring

CLIC Feasibility Demonstration at CTF3

Simulations on Beam Monitor Systems for Longitudinal Feedback Schemes at FLASH.

P. Adamson, Fermi National Accelerator Laboratory, Batavia, IL 60510, USA. Abstract

Future Performance of the LCLS

AARHUS UNIVERSITET November, ASTRID2 Status. Heine Dølrath Thomsen on behalf of the ASTRID2 Team

5 Project Costs and Schedule

STATUS OF THE INTERNATIONAL LINEAR COLLIDER

TOP-UP OPERATION IN LIGHT SOURCES

Report on the LCLS Injector Technical Review

PROJECT DESCRIPTION. Longitudinal phase space monitors for the ILC injectors and bunch compressors

CEBAF Accelerator Update. Michael Tiefenback CASA Accelerator Physics Experimental Liaison June 14, 2017

FINAL DESIGN OF ILC RTML EXTRACTION LINE FOR SINGLE STAGE BUNCH COMPRESSOR

COMMISSIONING SCENARIOS FOR THE J-PARC ACCELERATOR COMPLEX

Linac 4 Instrumentation K.Hanke CERN

Status of the X-ray FEL control system at SPring-8

ABORT DIAGNOSTICS AND ANALYSIS DURING KEKB OPERATION

30 GHz Power Production / Beam Line

beam dump from P2 losses this morning

Introduction to Synchrotron Radiation and Storage Ring Light Sources.

4.4 Injector Linear Accelerator

Week 0: PPS Certification and Processing. Mon Feb 11 Tue Feb 12 Wed Feb 13 Thu Feb 14 Fri Feb 15 Sat Feb 16 Sun Feb 17

1. General principles for injection of beam into the LHC

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

PEP-II Status and Outlook

An Operational Diagnostic Complement for Positrons at CEBAF/JLab

MULTI-BUNCH INSTABILITY DIAGNOSTICS VIA DIGITAL FEEDBACK SYSTEMS AT PEP-II, DAæNE, ALS and SPEAR

Linac-Beam Characterizations at 600 MeV Using Optical Transition Radiation Diagnostics *

Precision measurements of beam current, position and phase for an e+e- linear collider

X-ray BPM-Based Feedback System at the APS Storage Ring. O. Singh, L. Erwin, G. Decker, R. Laird and F. Lenkszus

Transcription:

SPEAR 3: Operations Update and Impact of Top-Off Injection R. Hettel for the SSRL ASD 2005 SSRL Users Meeting October 18, 2005

SPEAR 3 Operations Update and Development Plans Highlights of 2005 SPEAR 3 user run Machine performance Accelerator development plans Timing modes and short bunches 500 ma operation Top-off operation possibilities

SPEAR 3 Safety Stand-down and Restart Validation Sept 04: SPEAR start-up for user run to begin Oct 18 Oct 11: Type A electrical accident at SLAC Oct 12: Accelerators shut down Oct 12 - Jan: Staff training and preparations for restart (e.g circuit breaker analysis, safety procedure revisions, etc) Jan 10-13: Restart validation review Jan 18: SSRL accelerator restart Feb 3: First beam lines opened

95.0% user beam uptime 2005 User Run Highlights

2005 User Run Highlights cont. First 500 ma operation June 20, 2005

2005 SPEAR3 Performance Lifetime ~60 h lifetime @ 100 ma ~0.1% horizontal-vertical coupling ~10-20 µm vertical beam size lifetime could be greater if coupling increased reduced lifetime when BL5 EPU in intermediate state reason undetermined; will resume study with new BL5 vacuum chamber in 2006

2005 SPEAR3 Performance Orbit Stability Slow orbit feedback ~0.2 µm orbit motion glitches : ID gap changes, trestle traffic stored current X rms Y rms 24 hours

2005 SPEAR3 Orbit Stability - cont. BPM processor temperature dependence adding photon BPMs to feedback adding air conditioning for BPM electronics in 2006 e- BPM processor temp BL 6 photon BPM 20 µm

SPEAR 3 Circumference Changes - RF Frequency Feedback RF frequency (green) changes ~30 Hz twice daily from lunar tide 2 o C (9 o C pk-pk outside diurnal temperature over 4 days shown in violet) RF frequency (green) changes by 1 khz for a 2 o C tunnel temperature variation (red) over 1 month period

0.00040 Floor Alignment Monument Elevation Changes 0.00030 0.00020 0.00010 0.00000-0.00010 400 µm -0.00020-0.00030-0.00040 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 June 2003 - July 2003 Nov 2003 - July 2003 Sep 2004 - July 2003

Floor Motion Study - Hydrostatic Level System (G. Gassner - SLAC) Tunnel floor moves diurnally and seasonally HLS to be extended in tunnel and onto experimental floor X

Orbit Stability in 1-200 Hz BW red = noise floor x rms = 3.7 μm y rms = 2.2 μm

Orbit Stability in 1-200 Hz BW - Photon BPMs electron BPM photon BPM noise spectra for different beam lines vary beam line monitor systems introduce additional noise photon BPM performance must be characterized and understood before adding to feedback BL 2 pbpm BL 5 pbpm

SPEAR 3 Development Orbit Monitoring and Stability Turn-turn digital BPM processing non-linear beam dynamics fast tune measurement More BPMs for BL 12 "Fast" orbit feedback (<50 Hz) Air conditioned BPM processing stations HLS system for motion studies of floor, accelerator and beam line components

SPEAR 3 Development SLM and Pinhole Camera window #3 UV/visible synchrotron light monitor: Jan 2006 transverse beam size, emittance and bunch length measurements bunch-bunch stability studies Cassegrain mirrors Bldg. 120 Control Room M1, M2 mirrors window #2 window #1 M0 mirror Improvements to X-ray pinhole camera (BL 2) electron clearing magnets absorber X-ray pinhole image 50 X 150 µm RMS @ 1% coupling 0.1% coupling expected

4.8 m matching straight 3 m standard straight SPEAR3 Development - Double-Waist Chicane Optics (BL 12, BL 13) 7.6 meters 2.2 m 2.2 m BL12 in-vac undulator ~5.5 mm gap RF BL13 EPU 10 mm gap

Double-Waist Chicane Beamline 9 on other side of wall DRIFT SPOOLS 7.33 m Y X GATE VALVE Z, e- beam SUPPORTS ENTRANCE MASK UPBEAM MATCHING CELL

Double-Waist Chicane Optics Tracking and Frequency Map Analysis with IDs Baseline optics Chicane optics

FY 2006 Double-Waist Chicane Optics Commissioning install quadrupole triplet and temporary beam chamber, no chicane install new power supplies to allow independent control of matching straight section quads and triplet commission, characterize and optimize chicane optics with beam FY 2007 install chicane magnets, chicane vacuum chambers, BL 12, in-vacuum undulator install additional quadrupole and chicane magnet power supplies commission, characterize optimize chicane lattice with undulator

SPEAR 3 Development Timing Mode Studies 781 ns 586 ns 195 ns normal fill 279 bunches 0.36 ma/bunch/100 ma 100 ns 100 ns "camshaft" fill 5-20 ma 200 ns 200 ns 200 ns 181 ns 4-7 bunches fill 140 ma max, ~2 h lifetime (unless increase vert beam size) ~20 ma/bunch # bunches limited by HOM heating in chamber bellows

SPEAR 3 Timing Mode Studies - cont. Tested timing fill patterns at 100 ma: ~25 ma/bunch maximum 7 or more 20 ma bunches; lifetime = 2 hours without increasing vertical beam size Camshaft bunch lifetime = (50, 6, 2) hours for (0.36, 5, 20) ma camshaft bunch Bunch purity: need 10-6?

SPEAR 3 Bunch Length Reduction? Nominal bunch length = 17 ps rms (5 mm) @ 1mA/bunch Bunch length increases with current/bunch:

SPEAR 3 Bunch Length Reduction? -cont. Equilibrium short bunch schemes: Low momentum compaction lattice need to calculate attainable bunch length probably low current Harmonic RF cavity factor of ~2 decrease expensive Non-equilibrium manipulations (not likely to be implemented): Transient RF phase modulation (on for few msec, off for few 10s msec) Transverse kick with betatron oscillations (similar transient to above) - W. Guo Transverse zero-cross kick + unkick (very expensive) - S. Zholents

First 500 ma - June 20, 2005 BL6 opened with 500 ma - July 19 No serious chamber heating Lifetime = 14 hours at 500 ma, IDs closed Multi-bunch stability achieved RF feedback loops tuned to damp longitudinal instabilities Sextupole magnet strengths increased to damp transverse instabilities (13% lifetime hit) Some ion instabilities observed No immediate need for multibunch feedback SPEAR 3 500 ma Operation

SPEAR 3 500 ma Operation - Fill Scenarios delivery time = 8 hrs t fill = ~6-7 min ΔI/I = 35% delivery time = 6 hrs t fill = ~4-5 min ΔI/I = 30% delivery time = 4 hrs t fill = ~3-4 min ΔI/I = 22% delivery time = 2 hrs t fill = ~1.5-2 min ΔI/I = 12% Assume fill rate = 50-60 ma/min (after injector improvements), 7 A-h VQ

SPEAR 3 500 ma Operation - Top-Off Injection Inject with beam line stoppers open Reduce thermal transient on beam line optics to improve stability Choose optimum beam delivery time (hours to seconds) Maintain high beam current constancy SPEAR3 Injection Times @ 60 ma/min SPEAR3 Injection Times @ 60 ma/min 6 3 12 6 5 2.5 10 5 delivery time (hours) 4 3 2 1 2 1.5 1 0.5 fill time (min) delivery time (min) 8 6 4 2 4 3 2 1 fill time (sec) 0 0 5 10 15 20 25 30 delta I/I (%) delivery time fill time 0 0 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 delta I/I (%) delivery time fill time 0

Radiation safety SPEAR 3 Top-Off Injection - Issues other labs successful in injecting with BL stoppers open existing BL shielding sufficient? existing SPEAR and Injector shielding sufficient for higher average current? Efficient injector and injection into SPEAR improvements to gun, linac and booster stability, reliability improvements to BTS injection line

SPEAR 3 Top-Off Injection Issues for Users Interruption to user experiment and data acquisition What is desired current constancy? (30%? 10%? 1%? What is tolerable fill interruption time? 0.1% other?) depends on current constancy factor and charge/shot from injector charge/shot for single bunch may be limited to 10-20% of bunch current to avoid detector and other component transients? bunch train filling only possible with new booster RF system What is tolerable minimum beam delivery time? depends on current constancy factor and beam lifetime lifetime can be increased with vertical beam size and/or bunch length Can user data acquisition be gated, synchronized or filtered to avoid injection transient effects? H injection kicker transient = ~10 ms (~0.1 ms with feedback)

Top-Off Injection at Other Labs APS inject every 120 sec, single bunch (0.5 ma/shot; accumulator ring) 0.5% current stability (lifetime = 7 h @ 100 ma) SPring-8 inject every 1-5 min 0.1% current stability (lifetime = 27 h @ 100 ma) ESRF no top-off; inject with shutters open lifetime = 75 h @ 200 ma (9 h @ 90 ma, 16-bunch) SLS inject every 2-4 min (0.1-0.5 ma/shot, single bunch) 0.1% current stability (lifetime = 3-4 h @ 400 ma) ALS (planned) inject every 30 sec, train of 10 bunches (1.5 ma/shot) 0.3% current stability (lifetime = 3 h @ 500 ma) 5 M$

FY 2006 SPEAR 3 Top-Off Injection - Plan Continue injector studies to improve reliability, reproducibility and fill rate Rebuild BTS transport line to remove several vacuum windows Conduct radiation safety study for injection with beam line stoppers open Plan (and conduct) tests of injection transients on beam line data acquisition Work with users to identify top-off issues and tolerable modes FY 2007 Inject with beam line stoppers open (delivery time = hours) Define current constancy goal and acceptable user interruption period and frequency Continue injector development to achieve top-off goals FY 2008.. Implement accelerator upgrades to achieve top-off goals

SPEAR 3 - Summary of Plans for 2006 Improve orbit stability faster orbit feedback more BPMs, air-conditioned BPM processors HLS machine and beam line component stability studies (Noise Abatement Team) Commission and characterize double-waist chicane optics Commission UV/Visible SLM and measure bunch parameters Conduct beam dynamics studies for BL 12 and BL 13 EPU Carry out top-off study plan Continue injector improvements (including rebuild BTS) Strive to deliver the best beam possible to users