Minutes of Meeting ENTSO-E Drafting Team on RfG DSO Technical Expert Group. Participants Name Affiliation present excused

Similar documents
Connection requirements for generators to distribution grid C10/11 CENELEC. 26 Oct 2016 Elia WG Belgian Grid

GC0100/101/102 Code Administrator Consultation Responses. Rob Wilson. Grid Code Panel 8 th Feb 2018

1. EXPERT MEETING EXPERT MEETING EXPERT MEETING Feedback from the meeting attendees...

Summary of Meeting and Actions

VAR Generator Operation for Maintaining Network Voltage Schedules

Expert Workgroup on Fast Fault Current Injection stage 1 Terms of Reference

10/13/2011 Planning Coordination Committee. Standards

Grid Code Modification Register. March 2018

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

NERC Reliability Standard PRC-024 Generator Frequency and Voltage Protective Relay Settings

Load Frequency Control Structure for Ireland and Northern Ireland

Frequency changes during large system disturbances workgroup, phase 2 (GC0079)

REFURBISHMENT OF SECONDARY SYSTEMS IN HIGH VOLTAGE SUBSTATIONS LESSONS LEARNED IN VENEZUELA

Grid Code Review Panel Meeting

Definitions. Common Corridor:

Form C: Type Test Verification Report

Form C: Type Test Verification Report

Notes Generator Verification SDT Project

Flicker Caused by Operation of Industrial Technology

Gamma instabus. Technical product information

Annexes to Realisation Agreement

Toronto Hydro - Electric System

english SGC inverter series hf transformer input voltage up to 800 V touch screen built-in data loggers

Item Topic Lead Action Documents

Stage 05: Draft Final Modification Report

Simulation of DFIG and FSIG wind farms in. MATLAB SimPowerSystems. Industrial Electrical Engineering and Automation.

AMERICAN NATIONAL STANDARD

SERIES H: AUDIOVISUAL AND MULTIMEDIA SYSTEMS Infrastructure of audiovisual services Coding of moving video

Specification. NGTS Issue 1 October 1993

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

HARMONIZATION OF SYNOPTIC BLOCK DIAGRAMS ON THE CONTROL PANELS OF MV SWITCHGEAR AND CONTROLGEAR

Q&A OVERVIEW REPORT Q&A OVERVIEW HOLLANDSE KUST (ZUID) Date: 15 December V November 2017 V December 2017

Conformity assessment procedures for Radio & Telecommunication Terminal Equipment Scheme

FCP Project Summary report

Interface Practices Subcommittee SCTE STANDARD SCTE Composite Distortion Measurements (CSO & CTB)

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

Policy on the syndication of BBC on-demand content

MEETING REPORT. Electro-Magnetic Compatibility (EMC) Directive 2004/108/EC 22 st Working Party in Brussels, 28 th of May :00 14:00

2018 TEST CASE: LEGAL ONLINE OFFERS OF FILM EXECUTIVE SUMMARY

SEMI F47 Compliance Certificate KEPCO Low-Power Power Supplies EPRI PEAC Corporation PQ Star sm Test Program. Certification Date: July 23, 2003

AMERICAN NATIONAL STANDARD

Official Journal of the European Union L 82/3 DECISIONS COMMISSION

Confirmed Action Notes of the DG Technical Forum meeting. April Held at ENA commencing 10:30 Attendees:

These restrictions, also called Network Constraints, are characterized by:

Best Practice Regulatory Frameworks for Mobile TV. forum

The Three-Phase Inverter Not Only for Your Home...

ITU-T Y.4552/Y.2078 (02/2016) Application support models of the Internet of things

HYL-080D1750G358. Constant current LED driver DALI Dimmable. LED Driver. Product description. Benefits. Interfaces.

Delivery, installation, commissioning and warranty of multi-channel Programmable High Voltage Supply System

SINAMICS G130 / G150. Line harmonics filter. Operating Instructions 05/2010 SINAMICS

ENGINEERING COMMITTEE Energy Management Subcommittee SCTE STANDARD SCTE

Frequency Response Initiative Generator Event Survey. NERC Resources Subcommittee North American Generator Forum December 8, 2016

NOTIFICATION OF A PROPOSAL TO ISSUE A CERTIFICATION MEMORANDUM

Drop Passives: Splitters, Couplers and Power Inserters

COMMISSION OF THE EUROPEAN COMMUNITIES COMMISSION STAFF WORKING DOCUMENT. Accompanying document to the

MINUTES OF THE JOINT GRID CODE REVIEW PANEL MEETING. Held at the Clarion Hotel, IFSC, Dublin. On 27 January 2010 at 1 pm

Dynamic Performance Requirements for Phasor Meausrement Units

Applying to carry BBC content and services: a partners guide to process

SINAMICS G130. dv/dt filter plus Voltage Peak Limiter. Operating Instructions 03/2013 SINAMICS

SMPTE STANDARD Gb/s Signal/Data Serial Interface. Proposed SMPTE Standard for Television SMPTE 424M Date: < > TP Rev 0

Summary Project Specification Consultation Report

Experiences of CESC in Smart Grid Initiatives LT Network Automation. Anjan Mitra / Arka Ghosh

Modular operating rooms Sundsvall Regional Hospital

Generator protection relay

V9A01 Solution Specification V0.1

AMERICAN NATIONAL STANDARD

Operation of offshore wind power plants connected with HVDC

FINAL TECHNICAL REPORT. I, the undersigned, representing the beneficiary of the Grant Decision/Agreement number,

16 th Annual PQSynergy International Conference and Exhibition 2016

Maschinenfabrik Reinhausen Germany Power Quality

Operating Instructions 07/2007 Edition. SINAMICS G130/G150 Line harmonics filter. sinamics

Real Time Monitoring for SMART Grid Initiatives Synchronized Measurement & Analysis in Real Time SMART program by

Unofficial Comment Form Project Establish and Communicate System Operating Limits (SOL and SOL Exceedance Definitions)

South Australian Energy Transformation

WP2 European Product Analysis, Task 2.1 Determining energy efficiency criteria, D 2.1 Periodic Criteria Papers (first set)

medlab One Channel ECG OEM Module EG 01000

COMMITTEE - O. Fr. 16th Session - H9-3. DISTINCTION BETWEEN OPTICAL FIBRE CABLES OF HEADINGS AND (Item IX.

Type Approval Certificate

Colour Matching Technology

SIM 5 series Lamp Kit

REDFISH TECHNOLOGIES

3 Resolution of the Board of Supervisors, acting as responsible agency with respect to

HYL-035D0850G103. Constant current LED driver DALI Dimmable. LED Driver. Product description. Benefits. Interfaces.

USER MANUAL. KW-11T Wireless High Definition Transmitter. KW-11R Wireless High Definition Receiver MODELS: P/N: Rev 9

Cotton Boll Weevil Control Act

Test Report. Measurement of Low Power Consumption of Electric and Electronic Appliances. Tested by (name + signature)...

640 kv extruded HVDC cable system

GRIDCON POCOM POCOS POCOL MeDIUM VOLTAGe COMPeNSATION SySTeMS IN CABINeT DeSIGN. POWeR QUALITy

Magnecraft Power Relays

CEN, CENELEC, ESMIG, Eurelectric and ORGALIME joint workshop. Electromagnetic Interference in the Cenelec-A band

OT 100/ /700 P5

ENGINEERING COMMITTEE Interface Practices Subcommittee AMERICAN NATIONAL STANDARD ANSI/SCTE

ENGINEERING COMMITTEE

GV2P05. Main. Device short name. Device application

Digital Input Modules for Compact FieldPoint

The BBC s Draft Distribution Policy. Consultation Document

Remote Voltage Detector - JET (RVD) Medium and High Voltage kV AC

KACO-display. Wireless Solar Monitoring System. Operating Instructions KACO-display. full of energy...

Designing for the Internet of Things with Cadence PSpice A/D Technology

ITU-T Y Functional framework and capabilities of the Internet of things

Transcription:

Date: 17 April 2012 Time: 10h30 17h00 Place: ENTSO-E premises, Brussels Minutes of Meeting ENTSO-E Drafting Team on RfG DSO Technical Expert Group Participants Name Affiliation present excused DT RfG Hans Abele Transnet X Luis Coronado REE X Anders Danell SVK X Torsten Haase 50Hz X Edwin Haesen ENTSO-E X Jako Kilter Elering X Sergio Martinez Villanueva REE X Mark Norton EirGrid X Ramūnas Ponelis Litgrid X Ralph Pfeiffer Amprion X Thibault Prevost RTE X Jerzy Rychlak PSE X Rosen Ulinski ESO X Helge Urdal National Grid X Mario Valente Terna X Wilhelm Winter Tennet X DSO TEG Pierre Andersson E.ON Elnät Sverige AB (Eurelectric DSO) X Pilar Barrera Bewag Netz (Eurelectric DSO) X Alberto Cerretti Enel Distribuzione (Eurelectric DSO / EDSO-SG) X Florian Chapalain EDSO-SG X Falk Engelmann VKU (CEDEC) X Bruno Gouverneur Synergrid (Eurelectric DSO) PM AM Tony Hearne ESB (Eurelectric DSO) X Mike Kay ENWL (Geode) X Riccardo Lama Enel Distribuzione (Eurelectric DSO) X Mika Loukkalahti Helen Sahköverkko Oy (Eurelectric DSO) X Johan Lundqvist Svenskenergi (Geode) X Marc Malbrancke Inter-Regies (CEDEC) AM PM Pavla Mandatova Eurelectric DSO X Javier Meco Endesa (EDSO-SG) X Jacques Merley ERDF (Eurelectric DSO) X Viktoria Neimane Vattenfall R&D (Eurelectric DSO) X Joachim Nilges RWE (Eurelectric DSO) X Piotr Ordyna Tauron (EDSO-SG) X Allan Norsk Jensen DEA (Eurelectric DSO) X Jesus Peco Iberdrola (EDSO-SG) X Herman Poelman Alliander (CEDEC / EDSO-SG) X Graeme Vincent Scottish Power (Eurelectric DSO) X Jarmo Saarinen Fortum Oyj (Eurelectric DSO) X Walter Schaffer Salzburgnetz (CEDEC) X Bilal Simsek TEDAS (Eurelectric DSO) X Siegfried Wanzek E.ON-Energie (Eurelectric DSO) X

1. Agenda 10h30 12h30 : overview of responses on DSO survey 13h30 16h00 : evolution RfG 16h00 17h00 : ON / certification A working draft version of the RfG code was sent to all DSO TEG participants on Friday 13 April 2012. This document is considered work in progress still and is intended as guidance for discussion on how to progress with the code. No additional proposals are made for the agenda. The agenda is approved. 2. Overview of responses on DSO survey A survey was sent to all DSO TEG members on how 19 requirements of the NC RfG draft relate to the present applicable distribution grid codes in the working domain of the members. The relation as assessed by the DSO TEG members is expressed as either: Presently not covered in the distribution grid code; Covered by the distribution grid code; Resulting in a minor deviation with the distribution grid code; Resulting in a significant deviation with the distribution grid code. The 19 requirements included in the survey are: Frequency ranges Rate of change of frequency withstand capability Limited frequency sensitive mode (over-frequency) Active power controllability and control range Limited frequency sensitive mode (under-frequency) Frequency sensitive mode Simulation models Torsional stress Black start capability Voltage ranges Maximum power reduction at under-frequency Reactive power capability at maximum active power (synch) Reactive power capability below maximum active power (synch) Reactive power capability at maximum active power (PPM) Reactive power capability below maximum active power (PPM) Fault-ride-trough capability (synch - type B and C) Fault-ride-through capability (synch - type D) Fault-ride-through capability (PPM - type B and C) Fault-ride-through capability (PPM - type D) Only six responses 1 were received prior to the meeting relating to distribution grid codes from Austria 1 A response covering most applicable distribution grid codes in France and the Irish synchronous area were sent after the meeting.

Belgium Germany Great Britain (covering regional difference between England/Wales and Scotland) Italy The responses are discussed in the meeting for clarification. All agree that the outcome is shared among the DSO TEG members. Austria Response covers 60 to 70% of DSOs in Austria. Main focus is on FRT requirements for type D. Austria does not have an FRT requirement in its distribution grid code. DSOs use contracts based on capacity threshold only. With the implementation of the NC RfG a different situation will exist when connecting a 20MW wind park depending on the connection voltage as it can be type B or D (if at or above 110kV). Question is raised if there can be more flexibility in FRT requirements at national level. The DT notes there is considerable flexibility at national level to define an FRT curve (by selecting 8 parameters) based on the local grid situation. Belgium: Response covers all Belgian DSOs. Survey only filled in for connections below 30kV, so only type A and B requirements are addressed. Germany Evaluation of the draft RfG code requirements to existing rules is different as the classification by capacity used in the RfG code is not directly comparable with classification by voltage level used in Germany in the Transmission Code and Grid Connection rules. Taking this in consideration some requirements in the draft NC RfG are less stringent compared to present, recently established requirements. These are as such considered significant deviations from present practices. The DSO TEG assesses that a risk exists this could re-open difficult discussions at national level. The DSO TEG proposes to provide sufficient cover in the code that a less stringent requirement in the RfG code stemming from the absence of the voltage classification is no argument to reconsider requirements at national level. Great Britain One distribution grid code covers all of GB with slight regional differences. These present regional differences result in a different impact of the type D FRT requirements if the RfG draft was to be applied. Italy It is noted that the Italian NRA recently approved changes in the distribution code by implementing several requirements of the draft RfG. A different impact is envisaged for FRT when implementing it on LV or MV connected units. MV FRT requirements take the operation of MV circuit breakers in distribution automation into account. Retrofitting is foreseen for all MV plants for the beginning of 2013 for other requirement than FRT. It would be difficult to ask for an additional retrofit based on RfG requirements. Type C and D is connected to transmission. Even if a generator connected to the distribution side of a substation, it has to comply with the transmission code. The DSO TEG notes that also in Germany a new wave of retrofit (after the 50.2Hz retrofit) is not reasonable. The DT stresses the common understanding in this topic. The NC RfG is considered to be forward looking.

Discussion on relation between the survey and justification for significant deviations of the NC RfG with present standards and requirements: The question on what is the reference for significant deviations is still unanswered. The DSO TEG assumes a cost assessment will be asked for anyway when setting the national implementation. Were CBAs performed to come to the present distribution grid code requirements? No, not a formal CBA, but the DSO TEG considers the established development process for a grid connection rule/ standard in co-operation between TSOs/ DSOs, grid users and manufacturers to be an inherent nonexplicit CBA. The DSO TEG expects that if a CBA is made, this covers different technical alternatives, e.g. based on the voltage level of connection. Clarification is asked on whether the definition of Maximum Capacity refers to installed or contractual capacity? The DSO TEG agrees with the present definition of contractual capacity. This definition does still allow for national variances. The DSO TEG asks for a clear definition of and relation with standards, e.g. for testing testing to avoid an unclear relation between the functional requirements in the RfG being more general per definition and standards including provisions for testing. The DT considers it not up to the code to relate to variances in existing standards. In addition the draft code focuses on the connection point whereas many existing standards consider the unit terminals. The DSO TEG notes that people will interpret the type B to C threshold at their convenience to end up in a desired category. Also, at present many contracts and connection rules relate to requirements of a facility, not a single unit or module at the Connection Point. 3. Evolution RfG Main topics proposed for discussion: Derogations Definition Generating Unit vs Power Generating Facility Operational Notification The DSO TEG notes that they did not have sufficient time to review the latest working draft and are still working on a common opinion. Definition of Power Generating Module and Connection Point Some issues for clarification are raised by the DSO TEG: Several modules with the same connection point Multiple connection points of a facility at different voltage levels Connection to a Closed Distribution Network (CDN), or in general the notion of private lines between Power Generating Modules and the public grid. Clarification: Multiple Power Generating Modules inside a Power Generating Facility may have multiple Connection Points with different voltages. This type of situation exists already For wind parks the definition of PPM allows the aggregation of wind turbine generators to be considered one module. A single or a number of DFIG unit(s) is considered a PPM as it is non-synchronously connected. Asynchronous generators are covered by the definition of a PPM as its definition does not require a power electronic interface.

In case of multiple synchronous PGMs, all have to comply individually with RfG requirements. In case these have a single controller, it has to be analyzed whether the installations are indivisible. The DSO TEG agrees with this concept, but considers practical situations at distribution level where other interpretations may be possible. The DSO TEG states that mentioning a CDN in the definition of a Connection Point creates confusion as it should refer only to a transmission or distribution network. The DT agrees to include a definition of CDN in line with that of the 3 rd Package. The present draft gives the owner of a CDN the same responsibilities in the context of this code as a Network Operator (e.g. for compliance monitoring and enforcement). The DSO TEG does not give an agreement or disagreement on this approach since it is considered to be not clear whether all Network Operator responsibilities can be covered by 3 rd parties. Some DSO TEG members argue that the 3rd package defines CDN obligatory in relation with consumption., so that private lines mentioned above would not be covered by the code and responsibility at the connection point to the public grid remains unclear. Reactive power capabilities The present reactive power capability requirement of a type C generator refers to the HV side of a step up transformer. The DSO TEG proposes to formulate the requirement based on the majority of existing situations rather than the exception. It is noted that where a wind farm power station connects at a distribution nominal voltage which is the same as that of wind farm internal collector network, for example 20kV, there will be no stepup transformer at the Connection Point, resulting to a possible interpretation that the present requirement would apply at the LV/20kV transformer at a turbine base. The DT will redraf the clause, referring to the Connection Point, allowing an exception to be defined by the Relevant Network Operator in accordance with Art 4(3). If a PGF owner owns a long connection line with the connection point at the far side, this poses no problem. If not, the code will give the right to request compensation from the owner of the line. Fault Ride Through requirements The latest working draft uses a curve with parameters to be defined instead of a shaded area, in order to avoid misinterpretations. Embedded generation in an industrial site The DSO TEG considers steam storage to be a reasonable option for CHPs which would not justify an exemption from the code. The DT clarifies that an exemption is only allowed for some requirements. The DSO TEG has a concern on local political influence of CHP owners to which DSOs have to respond and asks for exemptions prescribed in the code to be as limited as possible. Voltage Control System, parameters and settings for type D synchronous generators Requirements are much less prescriptive in the code and are to be agreed bilaterally. Maximum active power reduction for under-frequency A figure is added for clarification. The relaxation is shifted from type C to type A. Protection settings The DSO TEG notes that the draft code often states the Relevant Network Operator has to come to an agreement with the PGF owner. At present, protection settings are often prescribed by the DSO as stated in the national law. The DSO TEG asks for this practice to be continued considering the mass market for distribution connected generators. The DT argues that this agreement is set to avoid liability claims in case a protection action has detrimental results. The DT also notes that protection at the connection point is of relevance for this code which should of

course not be in contradiction with the protection at the generator terminals. Also, protection devices and settings are explicitly mentioned in ACER s framework guidelines on electricity grid connections. The DT will consider redrafting Art 9.6 to allow for national law to give the Relevant Network Operator the possibility to prescribe protection settings. 4. Operational notification (see presentation) A proposal for revising the Title in RfG on Operational Notification is presented and discussed by means of main principles and open questions to the DSO TEG. This will be used as guidance to revise the relevant Articles in the code. All agree on the proposed principle for type A PGM certification. The proposed process follows existing practice if a standard exists to perform the tests on. The DSO TEG proposes to avoid confusion for type C modules and replace PGM certificate by PGM declaration so it does not imply self-certification by CE marking. Questions for feedback: Do the proposals adequately respond to DSO concerns? The key issue for the DSO TEG is who is an authorized certifier. Do the proposals deliver an acceptable way forward in terms of the difference of opinion between DSOs and manufacturers about need for independent certification, particularly for Type A? The DSO TEG agrees with the proposal but notes that functional standards at EU level are missing for LV units. The only existing directives are the LV directive and EMF directive which are non-functional and not relevant for certification of the requirements in the RfG code. For this reason it is at present legally not possible to have certification for protection. It is noted that a standard can exist at national level or System Operator level. If required could a CBA be provided by the DSO EG to defend use of independent certification for LV installations? The DSO TEG agrees to support a CBA on this given that a standard for 3d party certification exists. The DSO TEG asks what will be the consequence in case such standard is not available when the code enters into force? As a default, self-certification will be allowed for the time being. Does the proposal go too far by allowing Type B to be treated in the same way? What are the main risks? The DSO TEG proposes to align the operational notification of type B modules with that of type C to be in line with today s practices. The DT notes that this will include on-site testing for type B modules. The DSO TEG proposes to lower the intensity of the process for type B modules. The DSO TEG proposes to have the Relevant Network Operator / national rules set a threshold for factory versus on-site testing and certification. For type C is the single stage process fit for purpose between on the one hand providing assurance of compliance and on the other hand delivering cost effectiveness? The DSO TEG agrees on this. End of meeting