Extraction/Separator Setup. Michael Spata Operations Stay Treat July 16, 2015

Similar documents
Hall-B Beamline Commissioning Plan for CLAS12

Upgrade of CEBAF to 12 GeV

PEP II Design Outline

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

A Cathode Development Cornell Cultera This scope includes all labor and purchases required produce photocathodes required by CBETA.

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

A Facility for Accelerator Physics and Test Beam Experiments

New Filling Pattern for SLS-FEMTO

An Operational Diagnostic Complement for Positrons at CEBAF/JLab

JLab 10kW FEL Driver Beam Diagnostics

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY

Status of SOLARIS Arkadiusz Kisiel

High-Power Setup Procedure

TITLE PAGE. Title of paper: PUSH-PULL FEL, A NEW ERL CONCEPT Author: Andrew Hutton. Author Affiliation: Jefferson Lab. Requested Proceedings:

BBU threshold current study for 6 GeV beam in 12 GeV beamline setup

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems

FINAL DESIGN OF ILC RTML EXTRACTION LINE FOR SINGLE STAGE BUNCH COMPRESSOR

TWO BUNCHES WITH NS-SEPARATION WITH LCLS*

Requirements for the Beam Abort Magnet and Dump

Next Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack

PEP II STATUS AND PLANS *

AREAL- Phase 1. B. Grigoryan on behalf of AREAL team

SPEAR 3: Operations Update and Impact of Top-Off Injection

Synchrotron Light Facility. Operation of ALBA RF. Angela Salom on behalf of RF team: Francis Perez, Bea Bravo and Jesus Ocampo

30 GHz Power Production / Beam Line

5 MeV Mott Polarization Measurement Procedure--DRAFT

Development of beam-collision feedback systems for future lepton colliders. John Adams Institute for Accelerator Science, Oxford University

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

Spear3 RF System Sam Park 11/06/2003. Spear3 RF System. High Power Components Operation and Control. RF Requirement.

Detailed Design Report

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

The FAIR plinac RF Systems

RF Upgrades & Experience At JLab. Rick Nelson

Digital BPMs and Orbit Feedback Systems

9th ESLS RF Meeting September ALBA RF System. F. Perez. RF System 1/20

CEBAF Accelerator Update. Michael Tiefenback CASA Accelerator Physics Experimental Liaison June 14, 2017

Advanced Photon Source - Upgrades and Improvements

P. Emma, et al. LCLS Operations Lectures

The PEFP 20-MeV Proton Linear Accelerator

North Damping Ring RF

CBETA Quarterly Report 7

. SLAC-P~ December 1995

Top-Up Experience at SPEAR3

LLRF at SSRF. Yubin Zhao

Accelerator Instrumentation RD. Monday, July 14, 2003 Marc Ross

ILC Damping Ring Lattice Status Report. Louis Emery and Aimin Xiao Argonne National Laboratory Presented at KEK workshop Dec 18th, 2007

ANKA Status Report. N.Smale, on behalf of all ANKA colleagues, Directors : A.-S. Müller, C Heske, T Baumbach.

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

SRS and ERLP developments. Andrew moss

SUMMARY OF THE ILC R&D AND DESIGN

High Brightness Injector Development and ERL Planning at Cornell. Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics

Operating Experience and Reliability Improvements on the 5 kw CW Klystron at Jefferson Lab

1. General principles for injection of beam into the LHC

The ESS Accelerator. For Norwegian Industry and Research. Oslo, 24 Sept Håkan Danared Deputy Head Accelerator Division Group Leader Beam Physics

Scavenger Extraction. Karen Goldsmith Shawn Alverson

COMMISSIONING SCENARIOS FOR THE J-PARC ACCELERATOR COMPLEX

Summary of CBETA Independent Cost Reviews. R. Michnoff January 19, 2017

RF Power Generation II

CEBAF 12GeV Commissioning: Status and Plans

Jae-Young Choi On behalf of PLS-II Linac team

XFEL High Power RF System Recent Developments

Beam Losses During LCLS Injector Phase-1 1 Operation

PEP II Status and Plans

OPERATIONAL EXPERIENCE WITH CIRCULATING BEAM

The Elettra Storage Ring and Top-Up Operation

The Beam Test Facility at the SNS

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

Studies on an S-band bunching system with hybrid buncher

RF Power Upgrade at Jefferson Lab

Friday 05/03/ :00 13:00 : Establishing reference orbit golden Jorg Wenninger. Problems Wrong polarity on MCBXH3.L8 Polarity flag changed in DB

Present Status and Future Upgrade of KEKB Injector Linac

SABER A Facility for Accelerator Physics and Test Beam Experiments Roger Erickson SABER Workshop March 15, 2006

A HIGH POWER LONG PULSE HIGH EFFICIENCY MULTI BEAM KLYSTRON

K800 RF AMPLIFIER TUBE UPGRADE

CLIC Feasibility Demonstration at CTF3

ANKA RF System - Upgrade Strategies

Improvements to Siemens Eclipse PET Cyclotron Penning Ion Source

STATUS OF THE SwissFEL C-BAND LINAC

Status of Elettra, top-up and other upgrades

KEKB INJECTOR LINAC AND UPGRADE FOR SUPERKEKB

A Fifteen Year Perspective on the Design and Performance of the SNS Accelerator

AARHUS UNIVERSITET November, ASTRID2 Status. Heine Dølrath Thomsen on behalf of the ASTRID2 Team

Proton Engineering Frontier Project

FEL TEST PLAN WORKSHEET

Electron Bypass Line (EBL) Design Electrons to A-line bypassing LCLS T. Fieguth, R. Arnold

beam dump from P2 losses this morning

Status of CTF3. G.Geschonke CERN, AB

Bunch-by-bunch feedback and LLRF at ELSA

Availability and Reliability Issues for the ILC

X-ray BPM-Based Feedback System at the APS Storage Ring. O. Singh, L. Erwin, G. Decker, R. Laird and F. Lenkszus

EPJ Web of Conferences 95,

2008 JINST 3 S LHC Machine THE CERN LARGE HADRON COLLIDER: ACCELERATOR AND EXPERIMENTS. Lyndon Evans 1 and Philip Bryant (editors) 2

Summary of the 1 st Beam Line Review Meeting Injector ( )

Precision measurements of beam current, position and phase for an e+e- linear collider

CONSTRUCTION AND COMMISSIONING OF BEPCII

4.4 Injector Linear Accelerator

PEP-II Disassembly Technical Systems

Equipment Installation, Planning, Layout, organisation and updates

Recent APS Storage Ring Instrumentation Developments. Glenn Decker Advanced Photon Source Beam Diagnostics March 1, 2010

TRIUMF CYCLOTRON MAIN MAGNET POWER SUPPLY REPLACEMENT

Transcription:

Extraction/Separator Setup Michael Spata Operations Stay Treat July 16, 2015

Accelerator Overview

Extraction System Design settings for magnets and RF Separators come from CED All beamlines have been commissioned 750 MHz system needs to be recommissioned Pass 1 Pass 2 Pass 3 Pass 4 Pass 5 Extraction Elevation View West Arc Beamlines

Combiner RF Components 20 kv High Voltage Power Supply LLRF Controls RF Amplifier 10 kw (IOT) Coupler Splitter Forward Power Reflected Power Splitter Splitter Transmitted Power Phase Shifters Circulators Existing HV Deck Cavity Cavity Cavity Cavity Transmitted Power Beam-based determination of high power phase shifter settings and cavity shunt impedance RF IOT Layout

Transmitted Power Combiner Resonance Control LLRF Controls 20 kv High Voltage Power Supply RF Amplifier 10 kw (IOT) Forward Power Resonance control system to maintain cavity frequency independent of input power Coupler Splitter Reflected Power Splitter Splitter LCW Supply Phase Shifters Heater Circulators LCW Supply Mixing Valve Cavity Cavity Cavity Cavity Rack Space for 5 Heaters Transmitted Power

Resonance Control System Resonance control system under development for 750 MHz cavities One-button start-up software package will be provided to turn on the system

E03 Girder Aperture Beam separation at the E03 girder is sufficiently large to challenge the available aperture. The 6 GeV machine had less than 4 mm of clearance with the two beams on the nominal trajectory. Redesigned the E03 quad girders to accommodate the two beams. Need to correct for the nonlinearity of the BPM at large position offset. BPM shifted by half the beam separation. Beam separation on first and second pass is 2.524 cm. Beam separation on third through fifth pass is 3.192 cm. Need to correct for non-linearities Offset Rectangular Beamline Extracted and Recirculated Beams

Beam Position Monitor X X XROT k X X Y Y YROT k Y Y X XROT cos(45 ) YROT sin(45 ) Y YROT cos(45 ) XROT sin(45 )

Beam Position Monitor X X XROT k X X Y Y YROT k Y Y X XROT cos(45 ) YROT sin(45 ) Y YROT cos(45 ) XROT sin(45 )

BPM Non-Linearity

Poisson Model of BPM Electrode

BPM Nonlinearity Correction Difference/Sum Method

BPM Nonlinearity Correction Difference/Sum Method Correction to 100 microns

Lambertson Elevation Control Down beam of the Lambertson magnet the beamline elevation for hall A is 2.2 cm above Hall B. The Hall C beamline is 2.2 cm below Hall B. The original 6 GeV layout used transport channel correctors and quad kicks to change the elevation of the beam and set that pass to the proper Hall. This technique often resulted in aperture limitations. The new layout uses dedicated correctors at 2T09, 4T09, 6T09, 8T09 and AT04 to control the beam elevation at the entrance of the Lambertson magnet Transport Recombiner

Lambertson Elevation Control First pass uses a single BC corrector on a 10 Amp trim. Second pass uses two BC magnets on 10 Amp trims for the nominally doubled beam energy. Third pass uses a CB corrector which is a new design used in the Reinjection Chicane. Its powered by a 20 Amp trim. Fourth Pass uses two BD magnets on 12 Amp trims. Fifth pass uses a BD magnet on a 10 Amp trim. The 1C and 3C vertical correctors take the vertical pitch out of the beam and set the final elevation. They have been upgraded to 12 Amp trims. Ideal Corrector Settings

8T09/AT09 Viewer Beam trajectories through ZA magnets different than YR magnets Viewer frame machined for new 12 GeV elevations New frame will be installed during this downtime

Extraction Procedure RF Separator procedure being modified to include magnetic transport through Extraction dipoles, into BSY recombiner and through to Hall A,B,C dumplets. Excerpt from test plan steps for inclusion in procedure.. Find quad center for 6S10, 6E01, 6E02, 6E03 and 6A01 BPMs and update SOF values. Run tune beam to the 6R dump and let the extraction and arc orbit locks reach their targets. Record value of IPM6E03.XPOS. Insert 6E02 viewer and document image of recirculated beam. Remove viewer and let orbit locks converge. Change MBC6S10H to move the beam from +5.5 mm to -11.0 mm at 6E02. Insert 6E02 viewer and document image of recirculated beam. Adjust MYA6T01/MYA6T01A to tune beam to mirror-symmetric position at 6E03 recorded in step 3 above. Adjust MXSEP6T (MYR6T02) to get beam to zero horizontal position at IPM6T00A. Adjust MJG6T03 to get beam to zero horizontal position at IPM6T00B. Adjust MJH6T04 to zero entrance into 6T region. Thread beam through 6T beamline to the IPM6T06 BPM. Adjust MXB6T01/MXB6T02 step dipole to optimize transport along IPM6T07, IPM6T08 and IPM6T09 girders. Insert Lambertson viewer and adjust MXU6T04 to center the beam on the Hall B aperture. Remove viewer and thread tune beam to the Hall B dumplet. Adjust MCB6T09V to center the beam on the Hall A aperture or Hall C aperture. Record values for each.

Extraction System Status Pass 1 Pass 2 Pass 3 Pass 4 Pass 5 Extraction Elevation View West Arc Beamlines What remains to be done Recommission 750 MHz cavities Measure shunt impedance for each cavity Find high power phase shifter settings Checkout new 8T09/AT09 viewer Build and commission the resonance control system Complete and checkout one button start-up for 750 MHz cavities Implement non-linear correction for BPMs Finalize procedure with Anna and give it to Tom

Thanks Questions?

Existing Horizontal RF Separation (500 MHz)

Halls A,B,C 5 th Pass Vertical Separation (500 MHz) To Halls A,B,C B Beam A C B Accelerator Frequency 1500 MHz A A B C A B C A B C A B C A B C A RF Separator Cavity 500 MHz

5 th Pass Horizontal RF Separation (750 MHz)