FEL TEST PLAN WORKSHEET

Similar documents
High-Power Setup Procedure

LCLS-II Injector Tuning Procedures. F. Zhou (SLAC) & F. Sannibale (LBNL) 2/6/2017

5 MeV Mott Polarization Measurement Procedure--DRAFT

JLab 10kW FEL Driver Beam Diagnostics

P. Emma, et al. LCLS Operations Lectures

Jefferson Lab Experience with Beam Halo, Beam Loss, etc.

Hall-B Beamline Commissioning Plan for CLAS12

RUNNING EXPERIENCE OF FZD SRF PHOTOINJECTOR

30 GHz Power Production / Beam Line

Requirements for the Beam Abort Magnet and Dump

Beam Losses During LCLS Injector Phase-1 1 Operation

Tutorial: Trak design of an electron injector for a coupled-cavity linear accelerator

PEP II Design Outline

An Operational Diagnostic Complement for Positrons at CEBAF/JLab

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

Design Studies For The LCLS 120 Hz RF Gun Injector

Present Status and Future Upgrade of KEKB Injector Linac

The PEFP 20-MeV Proton Linear Accelerator

The basic parameters of the pre-injector are listed in the Table below. 100 MeV

New Filling Pattern for SLS-FEMTO

Performance of a DC GaAs photocathode gun for the Jefferson lab FEL

The Elettra Storage Ring and Top-Up Operation

Linac 4 Instrumentation K.Hanke CERN

LHC Beam Instrumentation Further Discussion

Summary of the 1 st Beam Line Review Meeting Injector ( )

TESLA FEL-Report

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

TWO BUNCHES WITH NS-SEPARATION WITH LCLS*

4.4 Injector Linear Accelerator

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

Status of Elettra, top-up and other upgrades

Development of BPM Electronics at the JLAB FEL

Polarized Source Development Run Results

Future Performance of the LCLS

DARK CURRENT IN SUPERCONDUCTING RF PHOTOINJECTORS MEASUREMENTS AND MITIGATION

Status of SOLARIS Arkadiusz Kisiel

G0 Laser Status Parity Controls Injector Diagnostics

North Damping Ring RF

Availability and Reliability Issues for the ILC

Digital BPMs and Orbit Feedback Systems

Basic rules for the design of RF Controls in High Intensity Proton Linacs. Particularities of proton linacs wrt electron linacs

First Results and Future of the Photo Injector Test Facility at DESY Zeuthen PITZ. introduction first measurements future schedule

Activities on FEL Development and Application at Kyoto University

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY

STATUS AND COMMISSIONING RESULTS OF THE R&D ERL AT BNL*

TITLE PAGE. Title of paper: PUSH-PULL FEL, A NEW ERL CONCEPT Author: Andrew Hutton. Author Affiliation: Jefferson Lab. Requested Proceedings:

RF Design of the LCLS Gun C.Limborg, Z.Li, L.Xiao, J.F. Schmerge, D.Dowell, S.Gierman, E.Bong, S.Gilevich February 9, 2005

beam dump from P2 losses this morning

Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi)

SUMMARY OF THE ILC R&D AND DESIGN

High Rep Rate Guns: FZD Superconducting RF Photogun

COMMISSIONING SCENARIOS FOR THE J-PARC ACCELERATOR COMPLEX

Studies on an S-band bunching system with hybrid buncher

THE NEXT LINEAR COLLIDER TEST ACCELERATOR: STATUS AND RESULTS * Abstract

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting

BEAMAGE 3.0 KEY FEATURES BEAM DIAGNOSTICS PRELIMINARY AVAILABLE MODEL MAIN FUNCTIONS. CMOS Beam Profiling Camera

The FLASH objective: SASE between 60 and 13 nm

Electro-Optic Beam Deflectors

PROJECT DESCRIPTION. Longitudinal phase space monitors for the ILC injectors and bunch compressors

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

OPERATIONAL EXPERIENCE WITH CIRCULATING BEAM

ISOMET. Compensation look-up-table (LUT) and How to Generate. Isomet: Contents:

An Overview of Beam Diagnostic and Control Systems for AREAL Linac

HIGH POWER BEAM DUMP AND TARGET / ACCELERATOR INTERFACE PROCEDURES *

Screen investigations for low energetic electron beams at PITZ

Operational Experience with Jefferson Lab ERL/FEL Machine Protection System (MPS) Kevin Jordan & the FEL Team October 18, 2011

High Brightness Injector Development and ERL Planning at Cornell. Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems

Accelerator Instrumentation RD. Monday, July 14, 2003 Marc Ross

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

Development of beam-collision feedback systems for future lepton colliders. John Adams Institute for Accelerator Science, Oxford University

Extraction/Separator Setup. Michael Spata Operations Stay Treat July 16, 2015

The Distortion Magnifier

Summary report on synchronization, diagnostics and instrumentation

A Facility for Accelerator Physics and Test Beam Experiments

Parity Quality Beam (PQB) Study

EPJ Web of Conferences 95,

Current status of XFEL/SPring-8 project and SCSS test accelerator

DESIGN OF 1.2-GEV SCL AS NEW INJECTOR FOR THE BNL AGS*

Tolerances on Magnetic Misalignments in SESAME Storage Ring

Week 0: PPS Certification and Processing. Mon Feb 11 Tue Feb 12 Wed Feb 13 Thu Feb 14 Fri Feb 15 Sat Feb 16 Sun Feb 17

RF considerations for SwissFEL

Dark current and multipacting trajectories simulations for the RF Photo Gun at PITZ

Status of CTF3. G.Geschonke CERN, AB

Report on the LCLS Injector Technical Review

Suggested ILC Beam Parameter Range Rev. 2/28/05 Tor Raubenheimer

PRESENT STATUS OF J-PARC

Compact, e-beam based mm-and THzwave light sources

CLIC Feasibility Demonstration at CTF3

1. General principles for injection of beam into the LHC

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

JEFFERSON LAB, A STATUS REPORT*

Detailed Design Report

INFN School on Electron Accelerators. RF Power Sources and Distribution

Upgrading LHC Luminosity

Beam Position Monitor Developments at PSI

BCM Calibration for E Abstract

Electrical and Electronic Laboratory Faculty of Engineering Chulalongkorn University. Cathode-Ray Oscilloscope (CRO)

TTF / VUV-FEL. Schedule 2005 and Project Management Issues. Schedule 2005 Project Organisation Budget & Controlling

Interface Practices Subcommittee SCTE STANDARD SCTE Measurement Procedure for Noise Power Ratio

Transcription:

FEL TEST PLAN WORKSHEET PROGRAM DEPUTY APPROVAL FEL Exp Coordinator Signoff: Date: PI Reviewer Signoff: Date: Expiration Date (max. 90 days from approval): Presentation Required? yes no COMPLETION INFORMATION Completion Date: Crew Chief/PI Signoff: Comments (partial completion, etc.): NOTE: Information addressing the appropriate content of each of the following sections can be found in Section 2.0 of the Test Plan Instructions. Test Plan Title: Author(s): R. Legg, D. Douglas, D. Kehne, P. Piot, C. Bohn (Rev. 4) Date Submitted: Aug. 4, 1997 Revision Number: Brief Purpose of Test To set the injector orbit and beam parameters to the nominal values described in the modeling for the machine. Anticipated Benefits Beam Conditions Required Complete all of the following tables, entering a value or an X in the appropriate spaces: Beam Type/Current (enter value) Beam Type Beam Off Pulsed (std. current = 1 µa) a CW Beam Current a.the standard current for pulsed beam operation is 1 µa. If your test requires pulsed beam current >1 µa, then specify the required current and provide a brief explanation next to the specified current. X Beam Energy (select one) Beam Off 350 kev 10 MeV 42 MeV X Energy Recovery dump File name: inj_setup_rev4 FEL_testplantempl 97.07.24 Page 1 of 9

Beam Termination Point (select one) Inj Dump ER Dump Straight Ahead Dump Other (specify) X Type of Test (select one) Invasive (disrupts beam delivery) X Non-invasive (does not disrupt beam delivery) Time Required 16 hours (2 shifts) Preferred Time of Test swing and owl shift Staff Required to Execute the Test (including contact info) R. Legg, (w,p) 7592 (h) 877-1028 Controlled Access Requirements none planned. Hardware and/or Software Changes Required NOTE: If software changes are part of the test plan, include the name of the application, the old revision level, the new revision level, and if applicable, whether or not it is possible to roll back to the old revision level (are there hardware limitations, etc.). Setup Procedure 1. PSS setup 2. FSD clear 3. Magnets at nominal 4. Beam parameters setup mode. a. 10 usec pulse width b. Micropulse Frequency 2.339 MHz c. 60 Hz D. < 1 pc/bunch d. Viewer limited beam mode 5. Turn-On Checklist inj_setup_rev4 Page 2 of 9

Test Procedure COARSE INJECTOR SETUP 1. With the buncher rf off, steer the beam onto the viewer ITV0F02. 2. Center low current beam in solenoid, MFF0F01, using the Picomotors. 3. Turn the buncher rf ON. Center the beam in the buncher by varying the buncher phase between +/-30 degrees while watching the beam motion on the viewer, ITV0F02. Steer the beam entering the buncher using correctors MBH0F01H and V until the beam on the downstream viewer doesn t move as the phase is changed. 4. At this point, beam should be low and to the right on viewer ITV0F02 (Figure 1). If not, put it there using MBH0F01H and V. beam spot Figure 1: Sweet spot on ITV0F02 5. Turn off the beam. Turn the cryounit on and tune it using AUTOTUNE. Set the gradient in the first cavity to 11 MV/m and the second cavity to 9 MV/m. 6. Turn On the beam. Retract the viewer, ITV0F02, set the field in the quads MQJ0F03 and MQJ0F04 to 0 G-cm, increase the laser pulse width to 100 usec and transient phase the buncher according to the Transient phasing procedure. 7. Transient Phase the cryounit using the transient phasing procedure to put it on crest. If no beam response is seen on the GASK signal, steer the beam around through the unit using the corrector pair, MBH0F01BH and V until a response is seen or beam is seen on viewer ITV0F04. If no response is seen after finding the beam on the viewer so the beam is going through the unit, slowly adjust the drive laser attenuator to increase the peak current until a response is seen on the GASK or until the average beam current exceeds 1 microamps (use the lightbox harp as the diagnostic, the amplitude of the beam will be about 450 pa). Repeat for the second cavity in the cryounit. 8. Once the cavities are rough phased, reset the drive laser attenuator to its original value. 9. Steer the beam to the viewer ITV0F04 using the corrector pair MBH0F01BH and V. 10. Center the beam in the cryounit using the corrector pair MBH0F01BH and V. inj_setup_rev4 Page 3 of 9

To determine if the beam is centered, adjust the PSET by +/-30 degrees while watching the beam on viewer ITV0F04. If the beam is centered, it will only focus and de-focus on the viewer. If the beam is steered so strongly that it moves off the viewer, use corrector pair MBH0F04H and V to bring it back on viewer ITV0F04. 11. Re-energize the quads MQJ0F03 and MQJ0F04 to their original settings and put them back on their hysteresis loop. Subtract 27.5 degrees from the phase of the second cavity in the cryounit. 12. Thread the beam to the 10 MeV dump using steps 4.0 and 5.0 of the IR FEL Injection Line Setup Procedure. 13. Set the pulse control to 1 khz, 4.68 MHz, 50 microseconds. Cycle light box harp and record the amplitude and sigma of the pulse. Adjust the drive laser attenuator until the amplitude is about 6300 picoamps with a sigma of about 0.128 inches, see Fig. 2. This sets the charge per bunch to 60 pc and the average current to 14 ua. Cross calibrate the measurement with the intercepted current in the injector dump. 14. After checking the charge per bunch, reset the pulse rep rate to 60 Hz. Figure 2 CORRECTION OF SKEW COUPLING 1. Check all viewscreens (ITV0F02, 4 and 6, ITV0G01, and, if at all possible, change injection dipole string to look at ITV0F01). A nastily coupled beam looks like Figure 3, where the beam spot is a diagonal stripe. 2. Set the gradiant integral of MSQ0F03 (downstream of the unit) to the nominal value required to correct the HOM coupler-driven skew quad of the second cavity of the unit. This is nominally ~8.6 gauss, but may vary slightly depending on energy gain (assumed to be 5 MeV) and phase (assumed to be on crest). 3. Verify improvement in coupling on all viewers - diagonal stripes should be more upright. inj_setup_rev4 Page 4 of 9

Figure 3: Skew-coupled beam spot 4. Set skew quad MSQ0F02 (upstream of the unit) to remove HOM coupler driven coupling of first cavity of unit and to correct for error coupling from MFF0F02. Nominally, the cavity should give small effects, but the solenoid can be nasty and the effect depends on where the beam goes through the lens and what the lens is set to. As a best bet, pick a viewer showing residual coupling (not removed by Step 2), and try to dial it out. 5. Verify all signs of coupling are gone on all viewers. 6. If remnant coupling remains, iterate as follows: a. minimize coupling effects with MSQ0F03 b. minimize coupling effects with MSQ0F02 c. iterate Steps 6a and 6b to convergence, frustration, or exhaustion (pick one). NOTE: this procedure should be repeated after each resteering upstream of/through the unit, each change of MFF0F02, and/or and each change of unit RF parameters (e.g. energy/phase). FINE INJECTOR SETUP 1. Make a multislit measurement of the beam emittance after the unit. Make a hardcopy of the measurement. This is the baseline measurement. 2. Make a bunchlength measurement using the Happek device, if available. Record the measurement. 3. Set the field in quads MQG0G01 and MQG0G02 to 0 G. Make a measurement of the beam width (sigma X) at the dump viewer ITV0G01. The dispersion is 1.6 m at this location. The momentum spread of the beam is sigma X in meters divided by 1.6 meters. SETTING THE PHASE AND GRADIENT OF THE BUNCHER 1. The phase is set by measuring the eccentricity of the beam shape versus buncher phase. inj_setup_rev4 Page 5 of 9

a. To measure the beam s eccentricity, insert the viewer ITV0F04. b. Bring up the emittance measurement program from the FELMAIN screen. Take an average of 6 images and record sigma X and sigma Y as the buncher phase is adjusted. c. Fill in the table below: Table 1: Degrees from Nominal phase Initial Phase = -5-2 0 2 5 sigma X sigma Y 2. Set the buncher phase to a value which corresponds to an eccentricity of 1. The simulations show alpha changing from 1 to -2.5 for -/+5 degrees, so if the change is small call in the PI listed in the call in section, because something is wrong. 3. The buncher gradient is set by minimizing the momentum spread at the viewer ITV0G01. The sensitivity at this viewer from simulations is roughly a 3 mm increase in momentum spread for a 10% change in buncher gradient. The overall beam width on the viewer should be about 1 cm if the cryounit is close to nominal settings. Using the beam sigma function from the frame grabber, set the buncher gradient to minimize the beam sigma. 4. As a final test of the buncher phase, insert viewer ITV0G01 and record the beam centroid. Turn the buncher rf OFF and take a second beam centroid reading off the viewer. If the beam centroid moves on the viewer by more than 1 mm, then the beam properties don t match the beam momentum and the cryounit is off the nominal setup. Set the buncher phase to a value which doesn t move the beam on the viewer when the buncher is turned on and off, and then proceed to set up the cryounit. CRESTING THE CRYOUNIT 1. The first cavity of the cryounit operates on crest at 11 MV/m nominal gradient. The phase is set by measuring and plotting alpha X (alpha is measure of how much the beam is diverging or converging) versus cavity phase. a. To measure alpha X at the multislit, insert the multislit and the viewer. b. Bring up the emittance measurement program (?). inj_setup_rev4 Page 6 of 9

c. Fill in the table below: Table 2: Degrees from Nominal phase Initial Phase = -5-2 0 2 5 Alpha X 2. Set the cavity phase to a value for alpha of 0.3. This sets the cavity to the phase with the proper beam properties. 3. Record the phase of the second cavity in the cryounit. Zero Pos On the BPMs in the line into the dump to keep track of the launch angles. 4. Add 27.5 degrees to the phase of the second cavity in the unit. Set the gradient in the second cavity of the unit to 8 MV/m. This should put the cavity on crest and at the right momentum for the transport to the viewer. a. If the beam is on viewer ITV0G01, crest the cavity using the viewer. Higher energy is to the right (?) on the viewer and the sensitivity on the viewer is about 7 mm per degree. Zero Pos On the BPMs in the line into the dump to keep track of the launch angles. b. If the beam is NOT on the viewer, insert the viewer ITV0F05, and look for the beam there. The dispersion there is only 0.5 m (2mm/degree), so this checks for a course error in momentum. Check that the second cavity in the cryounit is close to crest on this viewer, and has not been inadvertently set to -55 degrees. Once the cavity is within 1 degree of crest, adjust the GSET on the second cavity to bring the beam to the center of the viewer. Once beam is centered at ITV0F05, retract the viewer and check for the beam on ITV0G01. Fine tune the launch to the dump viewer by adjusting the GSET of the second cavity while watching the Relative BPM spikes for the BPMs in the line into the dump. Once the beam is on viewer ITV0G01, go to step a. above. 5. Record the PSET and PMES of the second cavity in the cryounit when it is on crest. 6. Before subtracting 27.5 degrees to the second cavity in the unit to return its phase to the original value, crest the first cavity in the quarter cryounit using the dump viewer. Maximum energy corresponds to crest for the cavity. 7. Record the PSET and PMES of the first cavity in the cryounit when it is on crest. Call the on-call PI listed in this testplan if this value does not agree with the value in Table 1 within +/-1 degree. CALIBRATE THE GSETS OF THE CRYOUNIT CAVITIES 1. With the cryounit cavities still on crest, fill in the table below to obtain calibra- inj_setup_rev4 Page 7 of 9

tion data on the cryounit GSET s (couplers). The idea behind this technique is that the couplers have a linear error and an offset. By taking a sufficent number of measurements, the linear equations can be solved for the coefficients. 2. Record the setting of the rotational polarizer, then use it to attenuate the drive laser and reduce the charge per bunch until a the peak intercepted current on the lightbox harp is less than 80 pa. Increase the pulse width to 250 usec. 3. To fill out the table, Table 3: p, MeV/c MDU0F01, Bdl, G-cm GSET, nom. Cavity 1 Cavity 2 GSET, actual GMES GSET, nom. GSET, actual GMES ITV0F06, centroid pos. 7 8.103E3 7 7 7 8.103E3 9 5 8 9.260E3 7 9 8 9.260E3 11 5 9 1.042E4 9 9 9 1.042E4 11 7 a. set the dipole to the indicated Bdl and cycle it through hysteresis twice. b. set the GSET s for the cavities to the indicated values. If changing the GSET of cavity 1, re-crest cavity 2 after the gradients are changed. c. If the beam appears on the viewer, great, record the GSET s and GMES s and the beam centroid position on the viewer. If not (more likely), adjust the GSET for the second cavity until the beam appears on the viewer and record the actual GSET used and GMES and the beam centroid position. 4. Reset the dipole to its initial Bdl setting and cycle it through the hysteresis loop twice. 5. Set the phase of cavity 2 to -27.5 degrees off crest. 6. Set the GSET of cavity 1 to 11 MV/m and adjust the GSET of cavity 2 to bring the beam to the center of the BPM IPM0G01. 7. Reduce the pulse width to 50 usec and reset the rotational polarizer to its original value. Backout Procedure 1. Check the phase setting on the buncher again by re-measuring the alpha X of the beam at the multislit. It should be about 0.3. inj_setup_rev4 Page 8 of 9

a. Check that the phase of the buncher is close to zero crossing by inserting the viewer, ITV0F06, and turning the rf to the buncher OFF. The beam should get broader on the viewer, but the centroid should not move more than +/- 1mm. b. If either of these test fails, go back to the section SETTING THE PHASE AND GRADIENT OF THE BUNCHER above. The problem probably indicates the unit was not set properly when the buncher setup was done. 2. Make measurements of the beam momentum, dp/p, emittance, alpha and beta. Test Results Calculate the coefficients for the cryounit cavites couplers. ax1+b+cy1+d = Z1 ax2+b+xy2+d = Z2 : : inj_setup_rev4 Page 9 of 9