Field Instruction. Any registered training organisation UETTDRCJ21A Lay ESI electrical cables. Before commencing work:

Similar documents
All Dielectric Self Supporting (ADSS) Fiber Optic Cable Installation

Cable installation guidelines

Aerial Cable Installation Best Practices

Identification - electrical services

Tab 10 - The NESC and Underground Applications. Restricted Siemens Industry, Inc All rights reserved.

Preparing a home for TransACT fibre-to-the-premise (FTTP) services

Underground Installation of Optical Fiber Cable by Pulling

High Voltage Cables kv. Handling and Operating Instructions

Triax TechInfo. Installing and pulling Fibre Optic cables

INSTRUCTION DE SÉCURITÉ SAFETY INSTRUCTION Mandatory as defined in SAPOCO/42 FIRE PREVENTION FOR CABLES, CABLE TRAYS AND CONDUITS

APPLICATION OF POWER SWITCHING FOR ALTERNATIVE LAND CABLE PROTECTION BETWEEN CABLE LANDING STATION AND BEACH MAN HOLE IN SUBMARINE NETWORKS

3M Scotchcast Mine and Portable Cable Splice and Jacket Repair Kit M-40

Installation of Optical Fiber

Identification of LV Cables

Medium Voltage 12/20 (24)kV NF C cable system. Xavier Brosse Luanda May 2009

IndyGo Facility Upgrades Project 35671EE

Track Work Authority ANWT 306. Applicability. Publication Requirement. Document Status NSW SMS. External Only October 2015.

DISCLAIMER. This document is current at the date of downloading. Hunter Water may update this document at any time.

VITALink Taped Splice Straight Through Crimp

FIBER OPTIC CABLE PULLING

All Dielectric Self Supporting (ADSS) Fiber Optic Cable Installation

SPECIAL SPECIFICATION 6559 Telecommunication Cable

Network Safeworking Rules and Procedures

SPECIAL SPECIFICATION 8540 Telecommunication Cable

ELECTRICAL SAFETY INSPECTION REPORT. MTM Garments Ltd.

Power cable accessories catalogue

CHAPTER 14 WIRING SIGNALS AND LIGHTING FIELD GUIDE Wiring Requirements WIRING

2178-L/S Series Fiber Optic Splice Case with Gasket

SCREEN WINCH SYSTEM INSTALLATION MANUAL FOR SCREENS FROM 300 cm. UP TO 450 cm. of width

Support Frame STB Technical Instruction Manual

SUMITOMO PRODUCT SPECIFICATION. FutureFLEX. TCxxMSOS-2 HIGH PERFORMANCE OSP TUBE CABLE SERIES WITH GALVANIZED STEEL INTERLOCKED ARMORING

OCC Installation Round Messenger Guidelines Excerpt from Optical Cable Corporation s INSTALLATION GUIDE

Aerial Installation Guidelines for Fiber Optic Cable

TELECOMMUNICATIONS V S WATER UTILITIES NATURE STRIP CONGESTION. Leigh Trevaskis. Riverina Water County Council

SECTION MEDIUM VOLTAGE CABLE INSTALLATION. 1. Section Underground Ducts and Manholes.

Instrumentation Cables

TruePlate Structural Plate

ACADEMIC SUCCESS CENTER THE COLLEGE AT BROCKPORT STATE UNIVERSITY OF NEW YORK PROJECT NO

TRANSMISSION ENGINEERING STANDARD TES-P , Rev. 0 TABLE OF CONTENTS 1.0 SCOPE 2.0 CABLES SPLICES

SCREEN WINCH SYSTEM INSTALLATION MANUAL FOR SCREENS UP TO 300 cm. of width

SUMITOMO PRODUCT SPECIFICATION. FutureFLEX. TCxxMSOS DIELECTRIC HIGH PERFORMANCE OSP TUBE CABLE SERIES

SCREEN WINCH SYSTEM INSTALLATION MANUAL FOR SCREENS UP TO 300 cm. of width

SUMITOMO PRODUCT SPECIFICATION. FutureFLEX. TCxxTOX / TOD DIELECTRIC OSP TUBE CABLE SERIES

Australian/New Zealand Standard

INTERNATIONAL TELECOMMUNICATION UNION DIGITAL SECTIONS AND DIGITAL LINE SYSTEMS DEFINITION OF TERMS RELEVANT TO OPTICAL FIBRE SUBMARINE CABLE SYSTEMS

Instructions. Cable with Armor F CAUTION. October Rev A

Laying of cables and lines in electrical installations and data networks

OCC Installation Figure 8 Guidelines Excerpt from Optical Cable Corporation s INSTALLATION GUIDE

ELECTRICAL SAFETY FOLLOW UP INSPECTION REPORT (8th) Factory Name Address Factory ID

Cables: Positive Identification and Spiking. Approval: EO Production Revision: A

Installation Operation Maintenance

TFT-150R-G. Tape Shield Cable (page 2) Suggested Installation Equipment (not supplied with kit) Wire Shield Cable (page 7)

Draft for Public Comment

ELECTRICAL INCIDENT REPORT BUSHFIRE NEAR 22 NUKKLGUP LOOP YALLINGUP WESTERN AUSTRALIA 5 JANUARY Report prepared by: EnergySafety WA EIS

OCC Installation Conduit Guidelines Excerpt from Optical Cable Corporation s INSTALLATION GUIDE

ELECTRICAL SAFETY INSPECTION REPORT

POLICY & APPLICATION GUIDE FOR 11kV POLYMERIC CABLES

(1) These Regulations may be called PEMRA Standards for Cable Television Regulations 2003.

SWA Cable BS6724 Steel Wire Armoured LSZH Eland Product Group A9L

220KV EHV NETWORK AT RELIANCE JAMNAGAR REFINERY COMPLEX

Newsletter

SECTION [ ] [02730] WAX-COATED DECOMPOSED GRANITE SURFACING

SJOF-BS604B. Fiber Optic Splice Closure User Manual Rev.1

Cambria County Association for the Blind and Handicapped 175 Industrial Park Road Ebensburg, PA Prepared for: Prepared by:

SUMITOMO PRODUCT SPECIFICATION. FutureFLEX. TCxxTOX-2 OSP TUBE CABLE SERIES WITH GALVANIZED STEEL INTERLOCKED ARMORING

3 Cleaning. 4 Technical data

Signalling Cable Equivalent Sizes

Cable Installation Tips

Bharat Heavy Electricals Limited HIGH PRESSURE BOILER PLANT, TIRUCHIRAPPALLI CONTROLS AND INSTRUMENTATION/FB

Public Works Division Lighting District Fiber Optic Specifications April 2009

PEM1124ENG ENGLISH. STK TERMINATION KIT FOR PLASTIC CABLE WITHOUT ARMOURING 1 kv STKR TERMINATION KIT FOR PLASTIC CABLE WITH ARMOURING 1 kv

Contact Details. British Transport Police: (24 hours) Crimestoppers: In association with:

Fiberglass - Technical Data

3 Foam Sealed Closure 2" (50 mm) with Compound Compression

Photovoltaic Module Installation Manual (IEC)

Photovoltaic Module Installation Manual (IEC)

Category 3 Non-Cab Operated Crane Safety Rev-04 Instructor Guide Revisions

CLP s first 400kV XLPE cable application

Flygt Submersible Motor Cables

3M Better Buried Compound Compression Closure System

PTS RABKA TRADE AND PRODUCTION COMPANY

MESP TECHNICAL SPECIFICATION FOR ELECTRIC CABLE 400mm 2 ALUMINIUM CONDUCTOR 1.9kV XLPE INSULATED WITHOUT METALLIC SCREEN

Mediacom Upgrade/Splicing Procedures (based on original document from Corporate dated 4/16/98)

SWA Cable - BS5467 Steel Wire Armoured PVC Eland Product Group A9S

Selecting the correct cable type for Outside Plant Application

INSTALLATION INSTRUCTIONS FOR

LANH39 SQA Unit Code H52S 04 Install hard-standing sub-layers

GUIDELINES FOR CABLE LAYING (PEM ELECTRICAL)

3M Better Buried Closures

LEGEND POWER SYSTEMS

Trends and Challenges of HV Cable Systems

Student Services & Classroom Addition

Design and Manufacture of Video Pipeline Inspection Systems A Full Service Company

Guide for installers. METTLER TOLEDO MultiRange System solution analog Ex1. Hazardous area. Safe area

SUMITOMO PRODUCT SPECIFICATION. FutureFLEX. TCxxTP2-1 PLENUM RATED TUBE CABLE SERIES (NFPA 262) WITH GALVANIZED STEEL INTERLOCKED ARMORING

Installation instructions Roxtec RM ES B

2011 The Practicalities of Fibre Deployment Colin Kirkpatrick

ATTACHMENT 2: SPECIFICATION FOR SEWER CCTV VIDEO INSPECTION

Sample Test Project. District / Zonal Skill Competitions. Skill- Electrical Installation. Category: Construction and Building Technology

PKK PKK CHARACTERISTICS. Dimensions. Travel. Travel speed. Acceleration. Temperature. Special versions APPLICATION AREAS. PLE max.

Transcription:

6.10 Cable Installation Purpose This field instruction outlines the minimum cable installation requirements for all Horizon Power Workers, including Workers operating, servicing, and/ or maintaining (MPS) Micro Power Systems electrical equipment (inclusive of all generating methodologies) for the following activities; laying cable pulling cable bedding cable backfilling cable trenches Note: This work practice must be read in conjunction with the following: Main Roads Western Australia - Utility Providers Code of Practice for Western Australia (1 February 2010) Underground Distribution Schemes Manual (UDS) Underground Cable Installation Manual (UCIM) Familiarity with the above manuals is essential for personnel undertaking cable laying activities on behalf of Horizon Power. Safety Before commencement of work, a risk assessment must be carried out using the Risk Analysis Procedure (OSH-3.6-1-02), to identify and document the hazards and risks associated with the task and ensure appropriate control measures are implemented. It is important that, appropriate control measures must be identified, documented and implemented in order to control hazards to As Low as Reasonable Practicable (ALARP). Authorisation Personnel performing cable installation work on Horizon Power worksites must conform to field instruction 1.3 Construction site access minimum requirements. The person in charge of cable installation at the worksite must, in addition to the above, have a Cable Layer authorisation. In order to achieve this authority, personnel must have attended and passed: Any registered training organisation UETTDRCJ21A Lay ESI electrical cables. Before commencing work: Ensure that all personnel comply with the minimum personal protective equipment (PPE) requirements when handling, loading, excavating, laying or pulling cables (see FI 2.6 Worksite Clothing / PPE Requirements) CS# 2245301 FI 6.10 Cable Installation Page 1 of 10

Conduct a risk assessment and job briefing to consider the following: shoring excavations confined spaces vehicle and pedestrian traffic management using machinery (for pulling cable) work near other underground and overhead services stability of any structure near excavations public safety additional PPE requirements Note: Livestock behind fences must be kept secure. Private property must not be damaged. Services must not be damaged. If trees in the road verge must be pruned, the pruned limbs must be sealed and left in a reasonable condition. Instruction Planning All work planning must take place before excavation begins. The following must be notified at least five days before work commences: Main Roads WA Railway services Local shires Councils and affected public Use the Dial before You Dig service to obtain information from all utilities about the location of existing underground services within the proposed area of work. When planning to install new cable, the following site access requirements and limitations must be considered: Environmental impact Private property or utilities (gas, telecom, rail, etc.). Other Horizon Power services (overhead, underground). CS# 2245301 FI 6.10 Cable Installation Page 2 of 10

For more information go to: Main Roads Western Australia - Utility Providers Code of Practice for Western Australia (1 February 2010) AS 4799-2000 Installation of underground utility services and pipelines within railway boundaries Note: Pavement or any constructed portions of any road reserve must not be broken to any extent without prior approval. For more on this, see the Underground Cable Installation Manual (UCIM), Section 16.4 Restoration of Surface: http://dm.horizonpower.com.au/otcs/llisapi.dll/properties/4723007 Excavation and Directional Drilling The requirements for excavation and directional drilling are covered in FI 6.4 Excavation Work and Directional Drilling, and the Underground Cable Installation Manual (UCIM) http://dm.horizonpower.com.au/otcs/llisapi.dll/properties/4723007 Ploughing Ploughing technology allows cables to be ploughed into the ground with an envelope of clean backfill sand. Ploughing equipment has the capability of installing cables in the following arrangements: o o Three single core cables (not twisted) in flat or trefoil (triangular) formation. As a minimum, cores must be transposed at every drum change. Triplex (twisted) The cable configuration must be surrounded with clean sand that is free of rocks and other hard formations: o o o 150 mm underneath the cable 50 mm on either side of the cable 300 mm above the cable Lay orange marker tape over the clean sand, as described in the Marking the ploughed cable route section, below. Fill the trench and compact to ground level with remaining material (ensure that stones and rocks have been removed) CS# 2245301 FI 6.10 Cable Installation Page 3 of 10

Marking the ploughed cable route Permanent above-ground cable markers must be installed along a cable route as described in Table 1 below. Table 1 Cable Marking Requirements Alignment category Description Marker tape required? (300 mm above cables) Above ground cable markers required? A Cable within the standard 0-500 mm alignment Install cable at a depth of 850 mm. Use orange marker tape above cable. Yes No B Cable within the 2.4 3.0 m alignment Install cable at a depth of 850 mm. Use orange marker tape above cable. Yes No C Cable outside road reserve (in remote area where there are no other services or infrastructure in the vicinity) Install cable at a depth of 1200 mm. Use orange marker tape above cables and above ground cable markers. Yes Yes When markers are required (per Table 1, above), they must be placed: on either side of the road at the crossing point wherever a cable crosses a boundary (e.g. road reserve property boundary, etc) and as close as possible to the cable installation For cables in paddocks and open spaces: place markers so that the impact or damage to agriculture (including livestock) is kept to a minimum place markers at the boundaries if a cable has to cross a paddock Markers should also be placed: to signify a change in direction of the cable route so that adjacent markers are visible from each other at a maximum distance of 150 m apart Cable Alignments If cables are placed on alignment marker tape must be placed above the clean sand. The marker tape must be wide enough to cover the cables. If cables are placed off alignment (outside the 0-500 mm alignment or the 2.4-3.0 m alignment) prior approval from Horizon Power and any other affected utilities must be obtained. CS# 2245301 FI 6.10 Cable Installation Page 4 of 10

If cable is out of the nominal 0-500 mm or 2.4-3.0 m alignment use heavy duty ducts to provide mechanical protection. If off alignment cables are buried direct cable cover slabs must be placed on top of 75 mm clean sand above the cable so that they overlap the width of the cables. This is followed by a further layer of clean sand to a depth of 300 mm above the cable and then marker tape. Note: For more information, see: Main Roads Western Australia - Utility Providers Code of Practice for Western Australia (1 February 2010). Underground Cable Installation Manual (UCIM), Section 10 Cables on and off Alignment Underground Distribution Schemes (UDS) Manual, Section 5 General Design Policies Handling Cable Drums Cable drums and cable are easily damaged through poor handling. Drums must be carefully loaded and handled using either: A forklift (with tines long enough to reach under both drum flanges) A crane (use spindles through the drum centre holes in conjunction with crane slings, lifting beams or spreader bars to prevent side pressure on the drum flanges) Never drop cable drums off a vehicle. The rolling of cable drums must be kept to a minimum. On delivery, visually inspect the cable drum for damage. Ensure that the cable end seals are intact. Cables must be returned to the supplier if the armouring, serving or sheath is: damaged corroded Positioning the drum Align the drum in the direction of the cable pull. Suitably mount the drum on purpose-built jacks, trailer or stands (a stable base must be provided for the drum during pulling). Spool the cable off the top of the drum. Check the drum flanges and remove any protrusions such as nails and splinters that could pierce the cable sheath. Ensure that the cable does not rub against the drum flange. Ensure that the drum is level and rotates freely and evenly. CS# 2245301 FI 6.10 Cable Installation Page 5 of 10

Provide adequate barricading around the drum to prevent unauthorised access. Note: Cable may be pulled off the bottom of the drum if there are space restrictions. Ensure that the reason for doing this is recorded on the risk assessment. Laying Cable Laying or pulling cable into trenches or ducts presents a risk of damage to the outer sheath of the cable. Also, bending a cable beyond a certain limit can damage the insulation which may result in shortened life or faults (see the cable manufacturer s instructions for minimum bend radii). Ensure that there is someone monitoring the drum during the pull to prevent overrun (two-way communications must be in place). When pulling cables, cable rollers must be used as they will: provide protection from abrasion assist with pulling cable around corners reduce friction and pulling tension In all instances, cables that are being drawn into place must be kept clear of abrasive surfaces by suitable means (e.g. rollers) to prevent any damage to the cable sheath. The cable must be placed in the trench without sustaining abrasion damage and without allowing rocks, etc. to fall into the trench and onto the cable. During cable installation, ensure that no twists, knots or kinks are formed. If the cable is being flaked directly into its final position in the trench and is not being pulled (i.e. the drum is moving) then rollers, etc. are not necessary. The cable must still be laid onto the required 150 mm of clean sand bedding (see the Bedding cable section, below). Pulling cable through ducts The cable outer sheath must not be damaged when pulling cables through ducts. A flared or belled entry must be used at the entry end of ducts during pulling to prevent damage to cable. For more information, see Underground Cable Installation Manual (UCIM), Section 13 Conduits http://dm.horizonpower.com.au/otcs/llisapi.dll/properties/4723007 Note: When pulling cable into a duct: It is recommended that personnel use specialised conduit rollers or flutes. Use a suitable lubricant to reduce friction between the cable and the duct. CS# 2245301 FI 6.10 Cable Installation Page 6 of 10

CS# 2245301 FI 6.10 Cable Installation Page 7 of 10

Pulling Tension Pulling tension must be regulated according to the size and type of cable. See the cable manufacturer s instructions for maximum pulling tensions. Pulling tensions can be limited using: breakaway swivel rated to the cable (pulling fuse) pre-set winch tension rated to the cable dynamometer (must be monitored) force gauge (must be monitored) Pulling speed must be limited to avoid drum overruns and damage to the cable. Pulling Methods When using power winches, there are four methods of attaching cable to the winch rope. The most suitable depends on the following: type of cable size length construction Armour pulling Uses the armour wires extended beyond the end of the cable and formed into a pulling eye. Stocking pulling Common for cables up to 33 kv. Care must be taken to not apply too much tension and stretch the cable sheath. Nose pulling For long cables and large cross section cables. Uses pulling eyes attached to the cable conductors. Used when stocking pulling exceeds sheath strength. Bond pulling Cable is lashed to steel wire rope to distribute pulling tension throughout its length (bonded). This method is only used when end pulling tensions for the cable are exceeded. Bend Radii Use rollers to reduce friction and provide an adequate bend radius when pulling cable around corners. Trenches must be wide enough to allow for the minimum installing bend radius (see the cable manufacturer s instructions for minimum bend radii). Cable sealing Cable that is not going to be terminated immediately must be re-sealed if the seal is damaged after pulling and/or removing any pulling eyes. Bedding cable The minimum cover for cables is 850 mm. This will ensure that a depth of 750 mm at the joints is maintained. CS# 2245301 FI 6.10 Cable Installation Page 8 of 10

The cable configuration must be surrounded with clean sand that is free of rocks and other hard formations: 150 mm underneath the cable 50 mm on either side of the cable 300 mm above the cable For cables vertically above one another, the sand filling between them must be 200 mm and the top cable must be covered with a further 300 mm of soft sand. Backfilling When backfilling a cable trench, ensure that: the backfill material is free of stones, rocks and paving material rubbish, pipe or cable off-cuts are not buried in the trench the backfilled material is compacted in layers to the same density as the surrounding soil the backfill is the same level as the original, unexcavated land all surplus spoil is removed from site Surface restoration Any pavement or constructed surfaces that are damaged during excavation must be restored in accordance with the Restoration and Reinstatement Specification for Local Governments in Western Australia (see the References section, below). Restoration of surface includes restoration of footpath of all type of materials (e.g. bitumen, brick paving, liquid limestone) Where cement footpath slabs have been removed to allow cable trench excavation, they must be reinstated in accordance with the local council's requirements. All damage to private property must be repaired (within reason) to the landowner s satisfaction, this may include: trees (limbs cut, sealed and debris removed) fences and walls (protected from damage) structures (protected from damage) paving (restored back to former condition) reticulation systems (repaired) underground services (repaired) For more on this, see Underground Cable Installation Manual (UCIM), Section 16 Reinstatement, and Section 17 Damage to Property http://dm.horizonpower.com.au/otcs/llisapi.dll/properties/4723007 CS# 2245301 FI 6.10 Cable Installation Page 9 of 10

References Occupational Safety & Heath Act 1984 Occupational Safety & Health Regulations 1996 SHMS OSH-3.6-1-02 Job Risk Analysis (JRA) Procedure SHMS OSH-3.6-1-26 Personal Protective Equipment 1.3 Construction Site Access Minimum Requirements 2.5 Other Personal Protective Equipment 2.6 Worksite Clothing / Personal Protective Equipment Requirements 2.23 Job Hazard and Risk Management (JRA) 6.1 Working Adjacent to Gas Mains 6.4 Excavation Work and Directional Drilling Section 9 of the Horizonpower s Instruction Manual Environmental UETTDRCJ21A Lay ESI electrical cables - Registered RTO Training AS 4799-2000 (Installation of underground utility services and pipelines within railway boundaries) Main Roads Western Australia - Utility Providers Code of Practice for Western Australia (1 February 2010) Restoration and Reinstatement Specification for Local Governments in Western Australia https://www.mainroads.wa.gov.au/documents/local_restoration_spec.rcnd08% 5E23177131.PDF Underground Cable Installation Manual http://dm.horizonpower.com.au/otcs/llisapi.dll/properties/4723007 Underground Distribution Schemes (UDS) Manual CS# 2245301 FI 6.10 Cable Installation Page 10 of 10