ELECTRICAL INCIDENT REPORT BUSHFIRE NEAR 22 NUKKLGUP LOOP YALLINGUP WESTERN AUSTRALIA 5 JANUARY Report prepared by: EnergySafety WA EIS

Similar documents
220KV EHV NETWORK AT RELIANCE JAMNAGAR REFINERY COMPLEX

PEM1126ENG ENGLISH STPKR. TERMINATION KIT FOR PAPER CABLE WITH LEAD SHEATH 1 kv INSTALLATION INSTRUCTION

Identification - electrical services

Assembly Instructions

TRF STEP-DOWN TRANSFORMER USER MANUAL

PEM1124ENG ENGLISH. STK TERMINATION KIT FOR PLASTIC CABLE WITHOUT ARMOURING 1 kv STKR TERMINATION KIT FOR PLASTIC CABLE WITH ARMOURING 1 kv

Part 4 High Voltage Overhead DISTRIBUTION CONSTRUCTION STANDARDS HANDBOOK

Cable installation guidelines

TRANSMISSION ENGINEERING STANDARD TES-P , Rev. 0 TABLE OF CONTENTS 1.0 SCOPE 2.0 CABLES SPLICES

2179-CD Series Fiber Optic Splice Closure. Installation Instructions

Continuous Currents. When inspectors see a photovoltaic (PV) power system. through Curious Cables. by John Wiles

EG4015. Digital Generator Governor Controller User Manual

SURGE PROTECTIVE DEVICES

3M Sensored Termination (15 kv) QX-T15I-vi1-E

Flygt Submersible Motor Cables

Operating instructions

LED Driver Linear / area fixed output

I r A Protection against direct contact Finger and back of hand proof to VDE 0106 Part 100

I r A Protection against direct contact Finger and back of hand proof to VDE 0106 Part 100

Instructions. Cable with Armor F CAUTION. October Rev A

Description Set value in neutral conductor is synchronous with set value Ir of main pole. R.m.s. value measurement and thermal memory CSA 100

SECTION MEDIUM VOLTAGE CABLE INSTALLATION. 1. Section Underground Ducts and Manholes.

Protective function Systems, cable, selectivity and generator protection. i 2 t constant function: switchable. I r A

Using Ultrasound and Infrared Technologies for Metal-Clad Switchgear Inspections

Installation Guide VL-MV10. Model No.

I r A Protection against direct contact Finger and back of hand proof to VDE 0106 Part 100

Quick Term III. 3M Cold Shrink 3 Core Indoor Termination. 3.3 kv mm 2

Protective function Systems, cable, selectivity and generator protection. i 2 t constant function: switchable. I r A

Cambria County Association for the Blind and Handicapped 175 Industrial Park Road Ebensburg, PA Prepared for: Prepared by:

Instructions for Use P.154-UP (9/4) P.155-UP (9/8) P.150-UP-12 (9/12) P.150-UP-16 (9/16)

LED Driver Compact fixed output

I r A I i = I n x. Protection against direct contact Finger and back of hand proof to VDE 0106 Part 100

Mediacom Upgrade/Splicing Procedures (based on original document from Corporate dated 4/16/98)

Aging test: integrated vs. non-integrated splices shield continuity systems.

PHASED OUT. LED control gear Compact fixed output. Driver LC 40W 900mA fixc C SNC China Domestic ESSENCE series

LED control gear Compact fixed output

Medium Voltage 12/20 (24)kV NF C cable system. Xavier Brosse Luanda May 2009

MESP TECHNICAL SPECIFICATION FOR ELECTRIC CABLE 400mm 2 ALUMINIUM CONDUCTOR 1.9kV XLPE INSULATED WITHOUT METALLIC SCREEN

LED Driver Compact fixed output

Protection against direct contact Finger and back of hand proof to VDE 0106 Part 100

HARTING Ethernet cabling cables and connectors, 4 wire

LEGEND POWER SYSTEMS

Trusted TMR I/O SmartSlot Slot Cables

INSTRUCTION DE SÉCURITÉ SAFETY INSTRUCTION Mandatory as defined in SAPOCO/42 FIRE PREVENTION FOR CABLES, CABLE TRAYS AND CONDUITS


Slot-type Photomicrosensor with connector or pre-wired models (Non-modulated) *1. configuration. Dark-ON/Light-ON

LED Driver Compact dimming

Failure Report. elbow near termination on bend. live-front

HID control gear Electronic. PCIS, PCS outdoor FOX B011 PCI outdoor. Ordering data. Circuit power1. tc/ta for 60,000 h For luminaires with 1 lamp

Pivot Power RJ45 Modular Plug Connectors

HVDC cable accessories

LED MODULES READYLINE DL

Power and Control T YPE BY RAVI GANATR November/December IAEI NEWS

Fully ly Automaticti. Motorised Satellite t TV System. User s manual REV

0.4 mm Pitch, Horizontal mating, Board- to-fine Coaxial Cable Connectors

CONSTRUCTION SPECIFICATION FOR TRAFFIC SIGNAL EQUIPMENT

IGNITION TRANSFORMER FOR BURNERS

Series CT7N Bimetallic Overload Relays

AS09..S 3-pole Contactors - Spring Terminals

MIKRO POWER FACTOR CORRECTION COMPONENTS

Metal Theft Taskforce Identification Booklet. Version 2

Coastal Carolina University RE-BID WILLIAMS BRICE RENOVATION AND REPAIR October 19, 2018 Construction Documents

User Manual CC DC 24 V 5A. Universal Control Unit UC-1-E. General Information SET. Universal Control Unit UC-1 Of Central Lubrication PAUSE CONTACT

Installation and User Guide 458/CTR8 8-Channel Ballast Controller Module

ECONOMICAL 36 kv CABLE SYSTEM FOR THE BELGIAN NETWORK

OPERATOR MANUAL OSD351 FIBRE OPTIC CCTV TRANSMITTER CARD

Sections 1. Application Equipment 2. Cable Preparation 3. Assembly 4. Termination Procedure 5. Inspection 6. Repair 7.

POLICY & APPLICATION GUIDE FOR 11kV POLYMERIC CABLES

ELECTRICAL SAFETY INSPECTION REPORT. MTM Garments Ltd.

Description Set value in neutral conductor is synchronous with set value Ir of main pole. CSA 100. conductor. I r A 50-63

Immersion Pumps HCT (High Chem) sealless

OPERATOR MANUAL OSD553 TRIPLE VIDEO FIBRE OPTIC RECEIVER

Figure 1: Device components

SECTION COMMUNICATIONS HORIZONTAL CABLING

LINK-RAY TM MODULATORS FOR CONSTANT- VOLTAGE. LinkRay Modulators 12 V / 24 V Constant-voltage Applications MODULATORS

Instructions for Use P.160-AP-8 (13/8) P.160-CP-8 (13/8) P.160-CP-12 (13/12) P.160-CP-16 (13/16)

TERMINATIONS AND JOINTS FOR XLPE-INSULATED kv MEDIUM VOLTAGE CABLES

Bharat Heavy Electricals Limited HIGH PRESSURE BOILER PLANT, TIRUCHIRAPPALLI CONTROLS AND INSTRUMENTATION/FB

ALM-6813/6812 INSTALLATION AND PROGRAMMING MANUAL

High Voltage Cable Splicing Training

Student Services & Classroom Addition

Owners SW-LCD 2.0 Manual & Specifications

Safety Codes Council Conference Banff C Panel Discussion

Metal Theft Taskforce Identification Booklet

Siam Pacific Electric Wire & Cable Co., Ltd.

Gel-sealed in-line fiber optic closure

Special Specification 6293 Adaptive Traffic Signal Control System

ACTIVE IF SPLITTER/COMBINER UHP-IFS

FOREST SHUTTLE S / L / M RECEIVER

UMN_ User Manual Antenna Simplex. TECHNO-MEDIA srl Via IV Novembre 92, Bollate (MB) tel

ELECTRICAL. DATA AND INDEX Not all complements shown A shown for reference. Index A leads B, CW (from shaft end) TERMINAL CONNECTIONS COM VCC CASE

INSTRUCTION AND MAINTENANCE VIDEO MOTORE PROJECTION SCREEN

ELECTRICAL SAFETY INSPECTION REPORT

MS2540 Current Loop Receiver with RS485 Communication

ZIG-POEPRO-70A. HDBaseT HDMI Extender

Weekly Time Switch. Rated time Time setting range Time division 24 hrs x 7 days 00:00 to 23:59 1min

Coaxial Cable Feedline Choke Kit - 50 Ω

28 & 32 & 40 & 55 & 65 & 84-INCH TFT-LCD 4K MONITOR

SWA Cable BS6724 Steel Wire Armoured LSZH Eland Product Group A9L

Cable Trouble. The Transit. R. G. Call University of Iowa. Volume 11 Article

Transcription:

ELECTRICAL INCIDENT REPORT BUSHFIRE NEAR 22 NUKKLGUP LOOP YALLINGUP WESTERN AUSTRALIA 5 JANUARY 2015 Report prepared by: EnergySafety WA EIS2015-0009 12 June 2015

TABLE OF CONTENTS 1. SUMMARY... 3 2. EXAMINATION... 5 2.1 Site Inspection... 5 2.2 Evidence Removed from Site for Examination... 5 3. INVESTIGATION... 9 3.1 Power Line Circuit Protection... 9 3.2 Works Performed by Western Power at or Near 22 Nukklgup Loop, Yallingup.... 9 3.3 Witness... 9 3.3.1 Resident... 9 3.4 Ownership of Equipment... 10 3.5 Pole (S997755)... 10 3.6 Pole Top Switch... 10 3.7 Cable Termination Head and Underground Cable... 10 4. WEATHER... 12 4.1 Cape Naturaliste, Western Australia Daily Weather Observations... 12 5. WESTERN POWER S INVESTIGATION REPORT... 13 6. CONCLUSION... 14 2

1. SUMMARY At 21:06 hours on 5 January 2015 Western Power notified EnergySafety that a bushfire at 22 Nukklgup Loop, Yallingup had damaged a house and vehicle. The fire started around 16:49 hours at 22 Nukklgup Loop, Yallingup near the corner of Gunyulgup Drive and Koorabin Drive. It moved rapidly in an easterly direction, up a grassed incline, to a house located on the property (Figure 1). DFES, with the aid of a witness account, were able to identify the area of fire origin was at the base of a Western Power pole number S997755 located within the road reserve in Gunyulgup Drive, Yallingup. The pole supported a 22kV underground to overhead pole-top cable head. Western Power pole (S997755) House lost in fire Direction of fire travel Figure 1 - The satellite image shows the area of fire origin and the bushfire s direction as it travelled east towards the house. EnergySafety s investigation found that a 22kV pole-top Cable Termination Head assembly on Western Power pole number S997755, for an overhead aerial conductor to underground cable arrangement, had failed as a result of the paper insulation on the lead cable failing. 3

This failure resulted in a short circuit and explosion taking place between the whitephase conductor and earthed cable screening and support framework. This caused hot molten metal fragments from the conductor and cable head termination assembly to fall to the ground and ignite the dry grass at the base of the pole. No other conclusion is supported by the available evidence. The fire burnt approximately 7 hectares of grass and pastoral land and resulted in the destruction of one house, its contents and a motor vehicle parked in the garage. 4

2. EXAMINATION EnergySafety investigator Patrick Roberts arrived at 22 Nukklgup Loop, Yallingup at 10:30 hours on 6 January 2015. Senior Inspector Roberts is a designated Inspector (Electricity) under the Energy Coordination Act 1994. The Inspection and investigation was conducted under the authority of s. 14 of this Act. At approximately 11:00 hours, Western Power investigators Brenden Lee and Andrew Shaw arrived on site and directed Inspector Roberts to the Cable Head Termination near the top of a Western Power pole (S997755). DFES personnel advised EnergySafety that the area of fire origin was on the ground at the base of the Western Power pole (S997755). 2.1 Site Inspection At the fire origin, EnergySafety s inspector found: A Western Power concrete pole. A pole top switch was installed on the pole and two 22kV overhead aerial to underground Cable Termination Heads (Figures 2 & 3). There were visible signs of arcing on the metal bracket on the northern-most side of the power pole adjacent to the crutch area of the Cable Termination Head (Figure 4). There were visible signs of damage to the insulation on the conductors at the Cable Termination Head (Figure 4). 2.2 Evidence Removed from Site for Examination The Cable Head Termination was taken from site by Western Power and provided to EnergySafety for evidence storage, examination and analysis. 5

Figure 2 - Photograph taken by EnergySafety on 6 January 2015 of the base of the pole and fire origin looking in the direction of fire travel towards the house. 6

Figure 3 - Photograph taken by EnergySafety on 6 January 2015 of the pole and cable head termination as it was found during the initial site inspection. The cable termination head that failed is to the left of the photograph. 7

Blackening due to Arc Fault Figure - 4 Photograph taken by EnergySafety on 6 January 2015 of the cable termination head at the pole top showing blackening indicating an arc fault. 8

3. INVESTIGATION 3.1 Power Line Circuit Protection On 5 January 2015 at 16:49 hours Western Power s protection (Recloser) on the BSN 537.0 Busselton 22kV overhead feeder operated (tripped), reclosed and then locked out as a result of the Cable Head Termination fault downstream of the Recloser. This is consistent with a witness account who heard two consecutive loud bangs coming from the area of the Western Power pole (S997755) in Gunyulgup Drive, Yallingup. At 17:23 hours, after confirming there were no additional faults in the area, in accordance with their standard procedures, Western Power s Network Operations Control Centre remotely reclosed the Recloser. The Recloser operated again, when reclosed and Western Power then dispatched an operative to investigate. On arrival, he was made aware of the bushfire by DFES personnel. 3.2 Works Performed by Western Power at or Near 22 Nukklgup Loop, Yallingup. Western Power and its contractors attended the property at Nukklgup Loop, Yallingup on the following occasions: The Pole was installed on 4 April 1995; and The section of cable where the Cable Termination Head was located was installed on 25 June 1995. 3.3 Witness 3.3.1 Resident The Resident at 22 Nukklgup Loop Yallingup, was on the outside deck on the Northern side of the house when the bushfire started on 5 January 2015. She heard two loud bangs coming from the direction of the Western Power pole number S997755 in Gunyulgup Drive, Yallingup. She then saw smoke and flames coming from the ground at the base of the power pole. Relevant extracts of her statement are as follows: It was the afternoon of Monday, 5 January 2015 and I was out on the deck on the Northern side of the house. I heard a loud bang, it sounded like gunfire. Less than a minute after that I heard another loud bang that sounded the same as the first. I remember looking to my left and seeing a bit of smoke coming from the top of some very tall trees to the west. I then bent down to look under the trees where I had seen the smoke and saw a small fire had started around the bottom of a power pole. 9

3.4 Ownership of Equipment The pole (S997755), pole top switch, Cable Termination Head, underground cables and overhead power line are the property of Western Power. 3.5 Pole (S997755) The concrete pole was inspected and found in good order and is not considered to have contributed to the incident. 3.6 Pole Top Switch The pole top switch was found in the open position when EnergySafety s investigator attended the incident site. It was concluded that the pole top switch had been operated post incident and did not contribute to the cause of the bushfire. 3.7 Cable Termination Head and Underground Cable The Cable Termination Head provides for the separation of the individual phase conductors away from the outer lead sheath of the cable to facilitate a connection to the overhead aerial conductors. The underground cable running up the pole is a 22kV oil-impregnated paper insulated cable which is fully screened, lead-covered and wire-armoured, commonly referred as Paper Insulated Lead-Covered-Steel-Wire-Armoured (PILCSWA) cable. The method of terminating the cable on the pole is by way of a high-voltage stressedcontrolled-polymer heat shrink termination. On 6 January 2015, the cable was cut away from the Cable Termination Head, at approximately 150mm below the steel wire armour anchor to the support ring by Western Power. The Cable Termination Head was then removed from site and provided to EnergySafety for examination and analysis (Figure 5). Figure 5 - Photograph taken by EnergySafety of the cable termination head on 15 January 2015 at Western Power's Office, Wellington Street, Perth. 10

On 15 January 2015 an examination of the removed Cable Head Termination was undertaken by EnergySafety and Western Power at Western Power s headquarters at 363 Wellington Street, Perth. A visual inspection of the Cable Termination Head found that it had very little pollution build up. There was a 16mm hole in the middle white phase conductor approximately 60mm above the Cable Head Termination crutch and arc damage to the heat shrink layer material (Figure 6). The outer sheath of the damaged white-phase conductor was removed to assess the integrity of the conductor insulation. It was determined that the paper insulation on the conductor had failed causing a short circuit to the earthed cable screening and support framework of the Cable Head Termination. The examination found that the cable termination was constructed in accordance with Western Power s design requirements. No fault was found with the construction methods or the workmanship involved. The Cable Termination Head support frame was found in good condition. It had signs of electrical arcing marks on the vertical section of the frame, opposite the white-phase conductor. The examination found the Cable Termination Head failed due to the failure of the cable insulation. The cause of the cable insulation failure could not be determined by the examination. Figure 6 Photograph taken by EnergySafety on 15 January 2015 of the damage caused to the centre white phase conductor and heat shrink at the crutch of the Cable Termination Head. 11

4. WEATHER The following weather details were provided by the Bureau of Meteorology for 5 January 2015. 4.1 Cape Naturaliste, Western Australia Daily Weather Observations Overall Temperature Max Wind Gust Min Max Direction Speed Time Rain 18.3 o C 35.0 o C SE 44 km/h 00:11hrs Nil Temperature At 9am Wind Direction Speed Relative Humidity 26.9 o C ESE 26km/h 38% Temperature At 3pm Wind Direction Speed Relative Humidity 33.4 o C SW 17km/h 34% 12

5. WESTERN POWER S INVESTIGATION REPORT Western Power conducted a separate investigation into the cable head failure and concluded that: The termination assembly was examined and found to be in good condition. The arcing damage was consistent with a failure of the paper insulation layers. The visible damage to the white-phase conductor is a result of the initial failure and arcing damage on the support frame. This is consistent with the Recloser protection data indicating that a failure occurred between the white-phase and earth. There was no evidence of defective materials or poor workmanship in the cable termination. The cable termination had failed as a result of the cable s paper insulation failure. After the cable termination had been stripped, on inspection the cable s paper insulation appeared to be in good condition. The cause of the cable insulation failure could not be conclusively determined by the investigation. No evidence of wildlife or malicious third party involvement could be found. 13

6. CONCLUSION EnergySafety s investigation found that at approximately 1649 Hours on 5 January 2015, a 22kV Cable Head Termination on a Western Power concrete pole failed as a result of the cable s paper insulation failure. This failure resulted in a short circuit and explosion taking place between the whitephase conductor and the earthed cable screening and support framework of the Cable Head Termination. This caused hot molten metal fragments from the conductor and Cable Head Termination assembly to fall to the ground and ignite the dry grass at the base of the pole which started the bushfire. 14