Linac3 experience for LHC ion runs

Similar documents
2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

The PEFP 20-MeV Proton Linear Accelerator

Full IEFC workshop Feb.

Present Status and Future Upgrade of KEKB Injector Linac

SRS and ERLP developments. Andrew moss

AREAL- Phase 1. B. Grigoryan on behalf of AREAL team

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

Linac 4 Instrumentation K.Hanke CERN

CERN S PROTON SYNCHROTRON COMPLEX OPERATION TEAMS AND DIAGNOSTICS APPLICATIONS

Upgrading LHC Luminosity

Detailed Design Report

Equipment Installation, Planning, Layout, organisation and updates

RF Power Klystrons & 20 Year Look. R. Nelson 7/15/15

The Elettra Storage Ring and Top-Up Operation

RF considerations for SwissFEL

RF Upgrades & Experience At JLab. Rick Nelson

RF upgrade program in LHC injectors and LHC machine

Availability and Reliability Issues for the ILC

Preparations for Installation, Testing and Commissioning based on Experience at CERN, SNS and Siemens

Proton Engineering Frontier Project

What can be learned from HERA Experience for ILC Availability

EPJ Web of Conferences 95,

PRESENT STATUS OF J-PARC

LHC Beam Instrumentation Further Discussion

Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi)

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY

1. General principles for injection of beam into the LHC

RF plans for ESS. Morten Jensen. ESLS-RF 2013 Berlin

ESS Linac WP8 Radio Frequency Systems and Test Facilities

OPERATIONAL EXPERIENCE AT J-PARC

Commissioning the TAMUTRAP RFQ cooler/buncher. E. Bennett, R. Burch, B. Fenker, M. Mehlman, D. Melconian, and P.D. Shidling

Welcome and FRIB Project Status. FRIB Highlights and Plan Ahead

High Power Cyclotrons

LLRF at SSRF. Yubin Zhao

The Construction Status of CSNS Linac

CEBAF Accelerator Update. Michael Tiefenback CASA Accelerator Physics Experimental Liaison June 14, 2017

Spear3 RF System Sam Park 11/06/2003. Spear3 RF System. High Power Components Operation and Control. RF Requirement.

PICS IN THE INJECTOR COMPLEX WHAT ARE WE TALKING ABOUT?

PEP-II Overview & Ramp Down Plan. J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007

5 Project Costs and Schedule

The FAIR plinac RF Systems

ANKA RF System - Upgrade Strategies

beam dump from P2 losses this morning

Beam Loss Detection for MPS at FRIB

Synchrotron Light Facility. Operation of ALBA RF. Angela Salom on behalf of RF team: Francis Perez, Bea Bravo and Jesus Ocampo

New Filling Pattern for SLS-FEMTO

Jefferson Lab Experience with Beam Halo, Beam Loss, etc.

Karin Rathsman, Håkan Danared and Rihua Zeng. Report from RF Power Source Workshop

LHC Machine check out

Workshop on Accelerator Operations August 6-10, 2012 Glen D. Johns Accelerator Operations Manager

An Overview of Beam Diagnostic and Control Systems for AREAL Linac

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

SLS RF operation report 2003

THE OPERATION EXPERIENCE AT KOMAC*

4.4 Injector Linear Accelerator

Current status of XFEL/SPring-8 project and SCSS test accelerator

Particle Beam Production - A Synchrotron-Based System - Prof. Dr. Thomas Haberer Scientific-technical Director Heidelberg Iontherapy Center

DELIVERY RECORD. Location: Ibaraki, Japan

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

ANKA Status Report. N.Smale, on behalf of all ANKA colleagues, Directors : A.-S. Müller, C Heske, T Baumbach.

Beam systems without failures what can be done?

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

Session 07 - What did we learn with beam in 2008? LHC Performance Workshop Chamonix Rhodri Jones on behalf of BE/BI & all our collaborators

A New 4MW LHCD System for EAST

Upgrade of CEBAF to 12 GeV

Operating Experience and Reliability Improvements on the 5 kw CW Klystron at Jefferson Lab

A Fifteen Year Perspective on the Design and Performance of the SNS Accelerator

A HIGH POWER LONG PULSE HIGH EFFICIENCY MULTI BEAM KLYSTRON

The ESS Accelerator. For Norwegian Industry and Research. Oslo, 24 Sept Håkan Danared Deputy Head Accelerator Division Group Leader Beam Physics

The sc cw-linac project TASCA2012, S. Mickat, LINAC

Status of CTF3. G.Geschonke CERN, AB

RF Power Generation II

Next Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack

INFN School on Electron Accelerators. RF Power Sources and Distribution

Status and Plans for PEP-II

News from HZB / BESSY Wolfgang Anders at ESLS-RF Meeting September 2010 Trieste

High QE Photocathodes lifetime and dark current investigation

Program Risks Risk Analysis Fallback Plans for the. John T. Seeman DOE PEP-II Operations Review April 26, 2006

K800 RF AMPLIFIER TUBE UPGRADE

ANKA Status Report. N.Smale, A.-S. Müller, E. Huttel, M.Schuh Slides courtesy of A.-S. Müller and C.Heske.

The 2011 LHC Run - Lessons in Beam Diagnostics

Studies on an S-band bunching system with hybrid buncher

WHAT WE WILL DO FOR BEAM PREPARATION IN 2009 : BEAM INTERLOCKS

Jae-Young Choi On behalf of PLS-II Linac team

ABORT DIAGNOSTICS AND ANALYSIS DURING KEKB OPERATION

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

Low Level RF for PIP-II. Jonathan Edelen LLRF 2017 Workshop (Barcelona) 16 Oct 2017

North Damping Ring RF

SPS BPM system renovation. Roadmap & Milestones

45 MW, 22.8 GHz Second-Harmonic Multiplier for High-Gradient Tests*

Status of Elettra, top-up and other upgrades

The SPL at CERN. slhc. 1. Introduction 2. Description. 3. Status of the SPL study. - Stage 1: Linac4 - Stage 2: LP-SPL - Potential further stages

Status of RF Power and Acceleration of the MAX IV - LINAC

SPEAR 3: Operations Update and Impact of Top-Off Injection

S67: PRE-CYCLE & RAMP

Concept and R&D Plans for Project X

LCLS-II Injector Tuning Procedures. F. Zhou (SLAC) & F. Sannibale (LBNL) 2/6/2017

Design Studies For The LCLS 120 Hz RF Gun Injector

Klystron Lifetime Management System

A HIGH-POWER SUPERCONDUCTING H - LINAC (SPL) AT CERN

Transcription:

Linac3 experience for LHC ion runs G Bellodi for the Linac3 team Keywords: beam performance reliability set up time results of MDs remaining unknowns 1

A year in perspective Source removed: change of main insulators, fix nonconformity issues good exercise in retrospective! RF reference settings moved with insertion of new couplers Beam to LEIR <2 months to restart Source extraction system repair to cure high voltage breakdowns Source incident: LHC ion run program slightly re-organized as mitigation measure 2

October 29 th source repair in detail Monday late evening: one of the 1200 A solenoid coils in the source went into open circuit. Tuesday 30/10 : decision of full dismantling to install the spare coil. By the end of the day, the source was open on the support in the tunnel. TE-MSC made a rapid certification of the spare (which was untested for 10 years). Wednesday 31/10 : the (800 kg) magnetic circuit could be dismounted, rotated and opened. By the end of the afternoon TE-MSC could return the spare, and it was squeezed into the yoke. Thursday 01/11 : the magnetic circuit was remounted and connected to the cooling and power supplies. A fast measurement of the internal field was made and seen to be as expected. By the end of the day the source was pumping. Friday 02/11 morning : the vacuum was good enough, and the final reconnection and remounting of the shielding was made. In the afternoon, the source could be 3 restarted for conditioning.

AFT statistics from start of the LHC ion run (05/11 to 03/12) 27.8h total downtime Injectors downtime impact on LHC Fault time by system (LHC ion run) CPS LINAC3 SPS SPS (setup) LINAC3~13h (2% downtime) LEIR (setup) LINAC3 (setup) 0 5 10 15 204 25

Linac3 Power Amplifier Failures: 10 Nov: IGBT & trigger unit of Tank3 failed: 8 hrs downtime probably damaged IGBT of Tk2 and led to 20 Nov: IGBT & trigger unit of Tk2 & Tk3 failed: 7 hrs downtime failure of Tk2 caused failure of Tk3 system Consolidation of the common power supply with two new individual systems will prevent interaction 25 Nov: 100 MHz RFQ system ignitron unit failed - first failure to our knowledge At start-up of Tank1 amplifiers: contact issues both failures likely due to aging but latter difficult to manage Replacement of RFQ amplifier launched BUT missing financing for Tank1 amplifier HLRF Consolidation Financing of full consolidation should be made a priority! Replacement of small 2.5 kw amplifiers for buncher, debuncher and ramping cavities (in sync with LLRF cons.) Replacement of 350 kw Bertronix amplifiers for RFQ and IH-DTL Tank1 After initial market survey results, only 1 replacement 350 kw amplifier can be financed with the funding agreed Maintenance of Linac1 RF amplifiers foreseen for IH-DTL Tank2 & Tank3 1955 technology! TE-EPC replacement of PC (Tank2 and Tank3) planned for after LS2 5

Beam current performance extraction from 05/11 to 03/12/2018 <BCT05>~175 ua <BCT25>~30.6 ua source LEIR injection RF faults MD 30uA Oven refills 6

Source stability Choices leading to more reliable 2018 operation: P Zisopoulos old Thomson RF generator replaced with Sairem before start of operation only fresh Pb was used ( turnaround time after oven refill reduced to 8-9 hours) GHOST modules: two scripts produced and tested so far (P Zisopoulos) 1) Source HT extraction voltage optimization (scan in ±5V steps and maximize the beam current in BCT15 ) P Zisopoulos 2) Automatic ramping of the oven power at source restart after an oven refill 7

# Pb54+ ions Foils o After recurrent issues with ACF foils, new GSI-produced stripping foils of different thicknesses were procured and installed o Confirmed better quality and performance of GSI-produced foils (in terms of reproducibility from foil to foil, and results better matching expectations). o Possible hints of shorter lifetime. If confirmed, would need to schedule more frequent exchanges (every 2 weeks, alternating with oven refills?) Stock of 16 foils installed on 4 arms, a single arm exchange can be carried out in the shadow of an oven refill.) 3.0E+15 2.5E+15 2.0E+15 1.5E+15 74 ACF 100 ACF 75 ACF 95 GSI Foil history 1.0E+15 95 GSI 99 GSI 5.0E+14 0.0E+00 1/4/18 1/5/18 1/6/18 1/7/18 1/8/18 1/9/18 1/10/18 1/11/18 1/12/18 date 8

Pb 54+ ratio sigma - kev Dp/p % 30 25 20 15 10 5 GSI ACF 0 50 70 90 110 130 150 170 foil thickness - ug/cm2 0.3 0.2 0.1 0-0.1-0.2-0.3-0.4-0.5 50 70 90 110 130 150 170 foil thickness ug/cm2 ACF GSI 0.19 0.18 0.17 0.16 0.15 0.14 0.13 0.12 0.11 0.1 50 70 90 110 130 150 170 foil thickness ug/cm2 GSI ACF Foils characterization Mean energy and energy spread measurements in ITFS spectro line : clear correlation b/w beam energy and foil thickness CSD scans: Pb54+ production higher for thicker foils? 9

kev Foil degradation and energy drift Seen from Linac3 Foil degradation marked by increase in energy spread of the beam and shift towards lower beam average energies ( foil thickening effect??) 30 foil #1 20 10 0-10 -20 0 10 20 30 40 50 delta E sigma Seen by LEIR S Hirlander 03/12 Foil failure -30 # days of operation Monitoring by: Seen by LEIR - weekly measurements in Linac3 ITFS spectro line (dedicated and destructive) - running Schottky measurement of the injected beam energy in LEIR (transparent to operation, very powerful tool!) 10

Conclusions and lessons learnt After a 2017 beam availability near 99%, 2018 made for some rolling up of sleeves... Progress made towards better beam stability/performance: - replacement of source RF generator better reliability - oven refills with fresh Lead better stability, shorter recovery time - progress in the automatisation of source adjustments - installation of better performing GSI foils better stability - progress in understanding beam performance through systematic monitoring (e.g. foils degradation) RF remains a weak point: - HLRF consolidation during and after LS2 is critical & full funding for amplifier replacement should be made available - LLRF upgrade will bring more operational flexibility. Source incident availability of spares is critical as is expertise in dismantling/re-installing. A hot spare source (parallel Linac3 source stand?) is for the nice-to-nave list, but missing ABP manpower to work on it ( double wish for Father Xmas?) 11

Milestones 2019-2020 Wrap-up of MD data and documentation of Panos s GHOST scripts Preparation of ion source tests in 2020 Set milestones dates (end of March?) for : - final LLRF upgrade specifications - detailed planning of HW commissioning and beam startup in 2020 - GHOST release on a stable platform 12

Spare slides 13

AFT statistics from 17/04 (beam to LEIR) 14

LEIR injected intensity vs RF parameters Sensitivity studies were carried out to determine the stability margins required for the LLRF upgrade at Linac3, measuring variations in the beam intensity injected into LEIR as function of the individual RF cavities phase and amplitude settings. Sensitivity of LEIR to Tank1 settings R Scrivens EDMS 2038110 phase amplitude In order to control the most sensitive equipment, the amplitude should be reproducible to 0.1%, and the phase to 0.5 degrees 15

BCT25/BCT15 sigma - kev Dp/p % 30 25 20 15 10 5 GSI ACF 0 50 70 90 110 130 150 170 foil thickness - ug/cm2 0.3 0.2 0.1 0-0.1-0.2-0.3-0.4-0.5 50 70 90 110 130 150 170 foil thickness ug/cm2 ACF GSI 0.25 0.2 0.15 0.1 0.05 GSI 150 1_1 GSI 150 1_2 GSI 125 1_3 GSI 125 1_4 GSI 100 3_1 GSI 100 3_3 GSI 100 3_4 ACF 75 2_1 Foils characterization Mean energy and energy spread measurements in ITFS spectro line CSD scans 0 ACF 100 2_4 50 51 52 53 54 55 56 charge state 16