Status of Elettra, top-up and other upgrades

Similar documents
The Elettra Storage Ring and Top-Up Operation

PEP II Design Outline

Status of SOLARIS Arkadiusz Kisiel

Digital BPMs and Orbit Feedback Systems

SPEAR 3: Operations Update and Impact of Top-Off Injection

New Filling Pattern for SLS-FEMTO

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems

PEP II STATUS AND PLANS *

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

Top-Up Experience at SPEAR3

ANKA Status Report. N.Smale, A.-S. Müller, E. Huttel, M.Schuh Slides courtesy of A.-S. Müller and C.Heske.

Accelerator Systems of the TPS

Detailed Design Report

4.4 Injector Linear Accelerator

30 GHz Power Production / Beam Line

RF considerations for SwissFEL

Present Status and Future Upgrade of KEKB Injector Linac

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting

Status of RF Power and Acceleration of the MAX IV - LINAC

Current status of XFEL/SPring-8 project and SCSS test accelerator

A Facility for Accelerator Physics and Test Beam Experiments

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY

ANKA RF System - Upgrade Strategies

ANKA Status Report. N.Smale, on behalf of all ANKA colleagues, Directors : A.-S. Müller, C Heske, T Baumbach.

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

KARA and FLUTE RF Overview/status

COMMISSIONING RESULTS OF BEAM DIAGNOSTICS FOR THE PETRA III LIGHT SOURCE

SUMMARY OF THE ILC R&D AND DESIGN

Upgrading LHC Luminosity

LHC Beam Instrumentation Further Discussion

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

Introduction to Synchrotron Radiation and Storage Ring Light Sources.

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

Operational Status of PF-Ring and PF-AR after the Earthquake

The basic parameters of the pre-injector are listed in the Table below. 100 MeV

CLIC Feasibility Demonstration at CTF3

News from HZB / BESSY Wolfgang Anders at ESLS-RF Meeting September 2010 Trieste

CLEX (CLIC Experimental Area)

CONSTRUCTION AND COMMISSIONING OF BEPCII

Production of quasi-monochromatic MeV photon in a synchrotron radiation facility

COMMISSIONING OF THE ALBA FAST ORBIT FEEDBACK SYSTEM

LLRF at SSRF. Yubin Zhao

Summary of the 1 st Beam Line Review Meeting Injector ( )

Future Performance of the LCLS

OPERATIONAL EXPERIENCE AT J-PARC

North Damping Ring RF

LEP OPERATION AND PERFORMANCE WITH ELECTRON-POSITRON COLLISIONS AT 209 GEV

STATUS OF THE INTERNATIONAL LINEAR COLLIDER

First Simultaneous Top-up Operation of Three Different Rings in KEK Injector Linac

P. Emma, et al. LCLS Operations Lectures

Activities on FEL Development and Application at Kyoto University

Accelerator Instrumentation RD. Monday, July 14, 2003 Marc Ross

Focus of efforts. ILC 2010, Mar/27/10 A. Seryi, BDS: 2

LEP Status and Performance in 2000

Photo cathode RF gun -

The PEFP 20-MeV Proton Linear Accelerator

An Overview of Beam Diagnostic and Control Systems for AREAL Linac

Recent APS Storage Ring Instrumentation Developments. Glenn Decker Advanced Photon Source Beam Diagnostics March 1, 2010

CEBAF Accelerator Update. Michael Tiefenback CASA Accelerator Physics Experimental Liaison June 14, 2017

2008 JINST 3 S LHC Machine THE CERN LARGE HADRON COLLIDER: ACCELERATOR AND EXPERIMENTS. Lyndon Evans 1 and Philip Bryant (editors) 2

INFN School on Electron Accelerators. RF Power Sources and Distribution

Jae-Young Choi On behalf of PLS-II Linac team

NSLS2 Diagnostic System Commissioning and Measurements

PEP II Status and Plans

Screen investigations for low energetic electron beams at PITZ

A HIGH POWER LONG PULSE HIGH EFFICIENCY MULTI BEAM KLYSTRON

Status of CTF3. G.Geschonke CERN, AB

DESIGN OF 1.2-GEV SCL AS NEW INJECTOR FOR THE BNL AGS*

THE NEXT LINEAR COLLIDER TEST ACCELERATOR: STATUS AND RESULTS * Abstract

Proton Engineering Frontier Project

Tolerances on Magnetic Misalignments in SESAME Storage Ring

Design and Simulation of High Power RF Modulated Triode Electron Gun. A. Poursaleh

Operational experience with the SOLEIL LINAC and Status of the ThomX LINAC project

Development of an Abort Gap Monitor for High-Energy Proton Rings *

Requirements for the Beam Abort Magnet and Dump

Linac 4 Instrumentation K.Hanke CERN

A Fifteen Year Perspective on the Design and Performance of the SNS Accelerator

LCLS Injector Technical Review

RF plans for ESS. Morten Jensen. ESLS-RF 2013 Berlin

SRS and ERLP developments. Andrew moss

COMMISSIONING SCENARIOS FOR THE J-PARC ACCELERATOR COMPLEX

EUROFEL-Report-2007-DS EUROPEAN FEL Design Study

Status and Plans for PEP-II

PEP-II STATUS REPORT *

Compact, e-beam based mm-and THzwave light sources

Suggested ILC Beam Parameter Range Rev. 2/28/05 Tor Raubenheimer

High Brightness Injector Development and ERL Planning at Cornell. Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics

KEKB Accelerator Physics Report

NSLS-II RF Systems James Rose, Radio Frequency Group Leader PAC 2011

SLAC ILC Accelerator R&D Program

Fast Orbit Feedback at the SLS. Outline

Spear3 RF System Sam Park 11/06/2003. Spear3 RF System. High Power Components Operation and Control. RF Requirement.

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

TWO BUNCHES WITH NS-SEPARATION WITH LCLS*

Availability and Reliability Issues for the ILC

Characterizing Transverse Beam Dynamics at the APS Storage Ring Using a Dual-Sweep Streak Camera

P. Adamson, Fermi National Accelerator Laboratory, Batavia, IL 60510, USA. Abstract

TITLE PAGE. Title of paper: PUSH-PULL FEL, A NEW ERL CONCEPT Author: Andrew Hutton. Author Affiliation: Jefferson Lab. Requested Proceedings:

PEP-II Status. U. Wienands, PEP-II Run Coordinator for the PEP-II team

Soft x-ray optical diagnostics, concepts and issues for NGLS

Transcription:

Status of Elettra, top-up and other upgrades Emanuel Karantzoulis ELETTRA / Trieste, Italy / 2010 November 25-26

Past and Present Configurations 1994-2007 From 2008 No full energy injection Full energy injection

2008 and 2010: transition years 1994-2007 Elettra ramping Since 2008 Full energy injection Decay mode, 2 GeV (340mA) and 2.4 GeV (140) SRFEL at 1 GeV. Top-up at 2 GeV (300mA) & 2.4 GeV (150 ma) Since May 2010 Elettra in top-up

26 beam lines of which major upgrades XRD1 SuperESCA SR-FEL (2 GeV, currently 1.8 GeV and 130 nm) 2 under construction Microflurescence XRD2

Modes of operation 2 GeV multibunch / hybrid / very small demand for single bunch 2.4 GeV multibunch / hybrid 1-1.8 GeV SR-FEL single, 4-bunch 0.8-1.0 GeV 4 bunch, CSR also for pump-probe experiments 5000 hours/year for users. For 2011 total 6560 hours 11 ID sections with PM wiggler, PM undulators: planar, APPLE II, canted, short; electromagnetic (circular polarization) and a superconducting wiggler. Also many bending beam lines including one for Mammography and one IR (THz) Allow the users to change gaps but not beam position/angle (we set it).

How operate 24 hours per day 7 days a week for periods from 4 to 8 weeks with 1 to 2 weeks shutdown Group of 14 operators, shift in pair, 3 shifts per day Elettra runs as a project (ODAC) that enters vertically to the matrixed structure of ST. Uses 104 persons for 28.8 man years, has 28 task leaders corresponding to the subsystems while 19 of them have dedicated budget; for 2010 the budget for functioning of the complex was 620 k

Elettra s new injector 2005 project funded 2007 autumn connection with SR 2008 Finished on time (3 March 2008 for user shifts already programmed since 2007) and within budget Difficulties with the booster main PSs Stability Reproducibility

100 MeV pre-injector Performs well, still margin for improvement especially on the klystron discharges (almost one per day and many false ) Spare gun and modulator constructed (redundancy) Effort on water/ambient temp stability Linac made of a thermionic gun, cathode Th306 Thales, a 500 MHz pre bunching cavity, an S-band 3 GHz bunching structure and two LIL (CERN) 5 m accelerating sections of about 50 MeV each providing thus 10 MeV /m The sections are powered by a 3 GHz 45 MW pulsed Thales 2132A S band klystron using a MDK modulator

Booster Faced problems mainly due to big PSs (also their controls); hard work of about 1 year, main problems fixed Acceptable operations established. Booster operates at full cycle (2.5 GeV ) and up to 3 Hz Full energy injection to Elettra at any energy and any filling (multibunch, single bunch,few bunch) up to 2.4 Hz rep. rate with efficiencies up to 100% RF system taken from Elettra (RF9) 500 MHz 60 kw (TV klystron ) and a 5-cell PETRA type cavity. Power transmission via coaxial line.

Elettra Availability Availability on scheduled user beam time storms 100% downtime inj. preparation uptime 1.5 5.4 2.4 1.1 4.4 2.2 2 4.48 1.76 3.7 5.7 2.7 4.07 2.6 1.4 3.8 1.2 1.5 3.173 0.727 90% 2.3 90.7 92.3 91.76 88.3 90.63 93.6 94.6 80% 2004 2005 2006 2007 2008 2009 2010

Other 3HC 30 25 20 15 10 5 0 Systems Failures in % of User Downtime 2010 Instrumentation Magnets/Pulsed Magnets General inj/setup/delays Radio Frequency High Level Software Controls & feedbacks Control Access Interlocks Insertion Devices Pre-injector Instability Water/Air Compr/Condiz Electricity Storms/big-interruptions Miss-handling Beamlines Power Supplies Vacuum Components

Mean time between beam losses FF excl storms hours 80 70 60 50 40 30 20 10 0 117 118 119 120 121 122 123 124 125 126 127 128 129 run

Top Up Implementation to the machine achieved within one year (2009) Radioprotection measurements finished as scheduled by end of March 2010. However due to 2 low gap chamber installation during the April shutdown some more controls were required in May. On May 10, top-up operations for users was implemented at 2.0 GeV. On May 24, top-up operations for users was implemented at 2.4 GeV

Operating in top-up Fixed current mode (1mA) every 6 min at 2 GeV, 20 min at 2.4 GeV in about 20 pulses at 2 Hz Total current loss budget 10 (5 at 2.4 GeV ) ma /hour. This allows efficienciesin the range 100 60% otherwise blocks top up for the rest of the hour Each beam line is interlocked with dosimeters; above a certain radiation level the beam line is blocked for 4 hours Fast dcct already installed will allow bunch to bunch fill for hybrid operations refilling also the single bunch.

Top-up controller Although at the beginning only 20% of user time was programmed, immediately users wanted top-up at 100%

Gating Provided via internet, upon request we provide additional interface boards. In general few beam lines make use of it. Sometimes certain beam lines (in fast measurements ) can get disturbed by the kick of the injection system during top up. Usually either the disturbance is marginal or by adjusting the kickers becomes marginal. Some beam lines however like the IR always use gating.

Systems stability during top-up > 90% homogeneity within 1 ma in 56 hours

e-bpm system ambient temperature effects No top up, current decay from 330 to 260 ma slow drift of horizontal beam position in the middle of ID9 of about 7 um in 5 hours Oscillations are due to the Libera e-bpm electronics being affected by ambient temperature oscillations in the Service Area (± 2 deg) due to a fault on the air conditioning system. Top up at 300 ma no drift, peak to peak 1.5 um

Long term stability Horizontal from 16/9/2010 00:00 to 20/9/2010 06:00 4 μm for 102 hours vertical 1.5 μm

Longest run in top-up Beam current 180 hours non stop

Ongoing projects Installed 2 low gap (9 mm ) chambers New Undulator (KYMA) for SuperESCA Ambient temp stabilization Air cooling of hot points Realignment BBA 8 th corrector Photon bpm

Re-Alignment A complete realignment is underway. The strategy has been defined and the work is programmed in 3 phases, June and September (survey / bpm tests) and November December (alignment). The second semester of the Elettra user program has been modified accordingly. Important elements are that more network points will be set, survey will include the bpms and data from BBA will also be used. old 6672 h tot 5000 h user New Tot 6256 h User 4720 h

BBA A beam based alignment project has been approved. All 108 quads will be shunted with modules. Already the prototype is working and expect to have all modules installed and functioning by the shutdown November / December 2010 Automatic measuring algorithm in simulations, use local bumps module A. Carniel

8th corrector/section In the phase of constructing the magnets Design by D. Castronovo

BPM cooling 24 hottest bpms (after dipoles) will be air-cooled with a fan system dangerous for vacuum leak With a fan the temp drops between 40 and 50 deg G. Loda and R. Geometrante

Conclusions Elettra updates to keep up with the most recent sources Top up at both 2 and 2.4 GeV is now the regular mode of operations and it has been indeed a long way i.e. from lacking a full energy injector to top-up A big effort towards reproducibility and stabilization is currently under way Near future: Upgrade to 2.5 GeV, get Long. FB functional, install skew elements etc. Many thanks to all members of the Elettra team (ODAC project )

Machine Parameters Beam energy [GeV] 2 2.4 Storage ring circumference [m] 259.2 Beam height in experimental area [m] 1.3 Number of achromats 12 Length of Insertion Device (ID) straight sections [m] 6(4.8 utilizabile per ID's) Number of straight sections of use for ID's 11 Number of bending magnet source points 12 Beta [m] Betax Dispersion [m] Beam revolution frequency [MHz] 1.157 Number of circulating electron bunches 1-432 Time between bunches [ns] 864-2 Tunes: horizontal/vertical 14.3/8.2 Natural emittance [nm-rad] 7 9.7 Energy lost per turn without ID's [kev] 255.7 533 Maximum energy lost per turn with ID's [kev] (all) 315 618.5 Critical energy [kev] 3.2 5.5 Bending magnet field [T] 1.2 1.45 Betay Path length [m] Q1S1Q2Q3 QF SF SD QDSD SFQF Q3Q2S1Q1 Geometrical emittance coupling % 1% Spurious dispersion (at the centre of IDs): horizontal (rms max/min) [cm] 6/2. Spurious dispersion (at the centre of IDs): vertical (rms max/min) [cm] 2/0.5 Operation mode multibunch One refill per day (09:30) of duration (incl. ramping etc.) [min] 30 Injection energy [GeV] 0.75 / 0.9 / 1 Injected current [ma] 320 140 Machine dominated by the Touschek effect Energy spread (rms) % 0.08 0.12 Lifetime [hours] 8.5 26 Bunch length (1 σ) [mm] & 5.4 7 Beam dimensions (1 σ) & ID source point - horizontal/vertical [µm] 241/15 283/16 Bending magnet source point - horizontal/vertical [µm] 139/28 197/30 Beam divergence (1 σ) & ID source point - horizontal/vertical [µrad] 29/6. 35/8. Bending magnet source point - horizontal/vertical [µrad] 263/9 370/13 &: The values shown (taking into account the energy spread) are averages, obtained from a consideration of different angle and position values of the spurious dispersion and can very by ±10%

Booster Magnet lattice FODO with missing magnets Maximum energy 2.5 GeV Injection energy 100 MeV RF frequency 499.654 MHz Circumference 118.8 m Revolution period 396 ns Harmonic number 198 Equilibrium emittance (2.5 GeV) Normal Emittance Optic Low Emittance Optic 226 nm.rad 166 nm.rad r.m.s. energy spread (2.5 GeV) 7.18 10-4 Energy loss per turn (2.5 GeV) 388 kev Damping times (h,v,l) (2.5 GeV) 5.1, 5.1, 2.6 ms Betatron tunes Q x, Q y 5.39, 3.42 6.8, 2.85 Natural chromaticities ξ x, ξ y -6.6, -4.7-11.1, -5.2 Momentum compaction factor 0.0443 0.0308 Maximum β x, β y, D x 10.8, 13.8, 1.621 m Peak effective RF voltage (available 1.1MV) 15.0, 17.2, 1.683 m 0.84 MV (τ q ~1 s) 0.73 MV (τ q ~1 s)