LSD Review December 2012 Schedule, Re-Baseline, & Resource Analysis

Similar documents
12GeV CEBAF Commissioning

6MSD Weekly Scheduling Meeting. 1:30, MCC Conference Room

6MSD Weekly Scheduling Meeting. 1:30, MCC Conference Room

Upgrade of CEBAF to 12 GeV

Monthly Progress Report Stanford Synchrotron Radiation Laboratory

LSD Bi-Weekly Resource Planning Meeting Agenda 25 July 2012

CEBAF 12GeV Commissioning: Status and Plans

CEBAF Accelerator Update. Michael Tiefenback CASA Accelerator Physics Experimental Liaison June 14, 2017

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

A Cathode Development Cornell Cultera This scope includes all labor and purchases required produce photocathodes required by CBETA.

Next Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack

Beam Losses During LCLS Injector Phase-1 1 Operation

Availability and Reliability Issues for the ILC

6MSD Weekly Scheduling Meeting. 1:30, MCC Conference Room

P. Emma, et al. LCLS Operations Lectures

AREAL- Phase 1. B. Grigoryan on behalf of AREAL team

PEP-II Overview & Ramp Down Plan. J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007

Capability Improvements: Polarized Photoinjector*

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

SPEAR 3: Operations Update and Impact of Top-Off Injection

CBETA Quarterly Report 7

RF considerations for SwissFEL

Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi)

Present Status and Future Upgrade of KEKB Injector Linac

Welcome and FRIB Project Status. FRIB Highlights and Plan Ahead

30 GHz Power Production / Beam Line

5 Project Costs and Schedule

Workshop on Accelerator Operations August 6-10, 2012 Glen D. Johns Accelerator Operations Manager

Trigger Cost & Schedule

RF Power Upgrade at Jefferson Lab

The LEP Superconducting RF System

RF Upgrades & Experience At JLab. Rick Nelson

The Construction Status of CSNS Linac

Suggested ILC Beam Parameter Range Rev. 2/28/05 Tor Raubenheimer

ESS Linac WP8 Radio Frequency Systems and Test Facilities

Andrei Seryi, Toshiaki Tauchi. December 15-18, 2008

Deliverable 2.17 Periodic WP2 Progress Report 3

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

Status of the Jefferson Lab Polarized Beam Physics Program and Preparations for Upcoming Parity Experiments

Status of the SNS Linac: An Overview N. Holtkamp for the SNS Collaboration ORNL, Oak Ridge, TN 37830, USA

Energy Upgrade Options for the LCLS-I Linac

BBU threshold current study for 6 GeV beam in 12 GeV beamline setup

The Elettra Storage Ring and Top-Up Operation

CLIC Feasibility Demonstration at CTF3

The PEFP 20-MeV Proton Linear Accelerator

Status of the FAIR Project. Jürgen Henschel FAIR Project Leader / Technical Director GSI & FAIR

Focus of efforts. ILC 2010, Mar/27/10 A. Seryi, BDS: 2

TABLE OF CONTENTS. Page. A. Project Summary 1. Technical Progress 3 2. Cost Reporting 5

A Facility for Accelerator Physics and Test Beam Experiments

Status of KEK X-band Test Facility and its future plans

The SPEAR 3 Upgrade Project Close-out Report April 2004

TTF / VUV-FEL. Schedule 2005 and Project Management Issues. Schedule 2005 Project Organisation Budget & Controlling

WBS Trigger. Wesley Smith, U. Wisconsin CMS Trigger Project Manager. DOE/NSF Review April 11, 2000

TITLE PAGE. Title of paper: PUSH-PULL FEL, A NEW ERL CONCEPT Author: Andrew Hutton. Author Affiliation: Jefferson Lab. Requested Proceedings:

ILC-LNF TECHNICAL NOTE

HD Review March 30, 2011 Franz Klein

News from HZB / BESSY Wolfgang Anders at ESLS-RF Meeting September 2010 Trieste

PEP-II Disassembly Technical Systems

J/NLC Progress on R1 and R2 Issues. Chris Adolphsen

LLRF at SSRF. Yubin Zhao

Hall-B Beamline Commissioning Plan for CLAS12

Mosaic 1.1 Progress Report April, 2010

Equipment Installation, Planning, Layout, organisation and updates

CLEX (CLIC Experimental Area)

RF Power Klystrons & 20 Year Look. R. Nelson 7/15/15

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems

Operating Experience and Reliability Improvements on the 5 kw CW Klystron at Jefferson Lab

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

Library. Summary Report

An Operational Diagnostic Complement for Positrons at CEBAF/JLab

Grid Code Modification Register. March 2018

SRS and ERLP developments. Andrew moss

PICS IN THE INJECTOR COMPLEX WHAT ARE WE TALKING ABOUT?

Jefferson Lab Experience with Beam Halo, Beam Loss, etc.

What can be learned from HERA Experience for ILC Availability

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

THE JLAB 12 GEV ENERGY UPGRADE OF CEBAF *

Status of the X-ray FEL control system at SPring-8

SUMMARY OF THE ILC R&D AND DESIGN

ANKA Status Report. N.Smale, A.-S. Müller, E. Huttel, M.Schuh Slides courtesy of A.-S. Müller and C.Heske.

Week 0: PPS Certification and Processing. Mon Feb 11 Tue Feb 12 Wed Feb 13 Thu Feb 14 Fri Feb 15 Sat Feb 16 Sun Feb 17

Budget and Schedule. Alcator C Mod. DoE Review Co-Operative Agreement Renewal May 13-14, 2003

Status of RF Power and Acceleration of the MAX IV - LINAC

LLRF World Wide. LLRF Lecture Part6 S. Simrock, Z. Geng DESY, Hamburg, Germany

US CMS Endcap Muon. Regional CSC Trigger System WBS 3.1.1

Towards an X-Band Power Source at CERN and a European Structure Test Facility

Program Risks Risk Analysis Fallback Plans for the. John T. Seeman DOE PEP-II Operations Review April 26, 2006

Thoughts on Project Standard in Japan

ESS Linac WP8 Radio Frequency Systems and Test Facilities

EUROFEL-Report-2007-DS EUROPEAN FEL Design Study

Status of JRA-SRF in CARE

Summary of CBETA Independent Cost Reviews. R. Michnoff January 19, 2017

The European Spallation Source

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY

Jae-Young Choi On behalf of PLS-II Linac team

Status of Elettra, top-up and other upgrades

RELIABILITY REASON FOR A COMMERCIAL INADVERTENT-INTERCHANGE SETTLEMENT STANDARD.

Proton Engineering Frontier Project

First Simultaneous Top-up Operation of Three Different Rings in KEK Injector Linac

Transcription:

LSD Review December 2012 Schedule, Re-Baseline, & Resource Analysis Dianne Napier

Outline Part II Review Charges Addressed in this Presentation: Issues raised in Part I Review Report adequately addressed Consider whether the new baseline is achievable Re-Baseline Effort Changes Implemented Upcoming Changes Schedule Overview Critical Path Resource Analysis

Part II Review Charges Issues raised in Part I Review Report adequately addressed The team needs to go through all the talks presented and update the overall plan to: Reflect ALL items discussed Ensure that the different schedules (shutdown work, project, planning for commissioning ops, etc.) are all synchronized Ensure the interconnects and resource overloads that may arise are captured in an overall plan There was the impression that there are disconnects at a significant level including the dates for 1 st Beam to the different halls. Consider whether the new baseline is achievable Are the resources adequate? Are the critical elements and dates understood and well defined?

Re- Baseline Changes - Overview LSD - CR # Title Timeframe Float (Days) Budgeted Labor (Hours) Delta (BL from Oct) 07 12GeV Hall C Inst. Sch. Through July 2015 291 62,891 +0.02% 08 12GeV CRs (Hall B (008) & Acc ETC (003) Various Various Various Various 09 12GeV Acc Beam Transport Through Sept 2013 33 28,010 +16% 11 Hall A Schedule Update Through Feb 2014 384 5,281-52% (HA labor) 12 6GeV Acc Maint. Through Jan 2014 236 18,182 +16% 13 CM & RF Re-Commissioning Through Sept 2013 17 1,272 +100% 14 0L04 Project (RF Zone) Through Sept 2013 18 3,634 +100% 15 Flood Recovery (Acc, Physics, FML) Various Various Various +100% 16 Dogleg Upgrade Through May 2014 30 1,610 +100% 17 11GeV Separator Through March 2014 94 6,416 +100% 19 12GeV Hall B Inst. Sch Sept 2010 - March 2015 376 156,740 +100% 20 High Power Beam Dump (A&C) Through May 2014 580 546 +100% 18 Bubble Chamber Test (Injector) March July 2013 35 1,144 +100%

Re- Baseline Changes End of November Progress of existing schedule in new baseline End Of Oct Re-Baseline # Activities ~2300 ~3100 # Budgeted Labor Hours 339,172 579,693 LSD CR-07: 12GeV Hall C Installation Schedule & Beamline Work Changes/Action Items from Review held in Oct 2012, Labor estimates, missing line items LSD CR-08: 12GeV CRs (008 and 003 12GeV Hall B push out dates, Accelerator ETC (labor estimate increases))

Re- Baseline Changes LSD CR-09: 12GeV Accelerator Beam Transport (re-sequencing) Removal of logic to correct for sequencing of work actually being done Increase of 16% in labor hours LSD CR-11: Hall A Schedule Update Change in experiment reduction in work, re-plan for activities behind schedule LSD CR-12: 6GeV Accelerator Maintenance 2013 activities had placeholder for Feb 2013 schedule updated for some of the activities. Correlated AWP with existing maintenance list (HCO activities with labor added)

Re-Baseline Changes LSD CR-13: CM Re-commissioning plan & RF maintenance/repair Re-commission cryomodules for CEBAF with associated RF for each zone Starting Jan 2013 through end of down (Sept 2013) LSD CR-14: 0L04 Project (RF) R100 is installed in 0L04 and will be using 8K klystrons with the newer 12GeV style LLRF hardware and a modified HPA/CPS. Procurement, installation/testing (May July 2013); new klystrons replacement Oct 2013) LSD CR-15: Flood Recovery (Acc, Physics, FML) List of flood recovery items in the accelerator, physics halls, and FML activities

Re- Baseline Changes LSD CR-16: Dogleg Upgrade Project Design and procurement (for magnet mods, power supplies) FY13 Installation and testing/commissioning FY14 during UIM down LSD CR-17: 11GeV Separator Project Design, procurement, installation (tunnel) FY13. Installation upstairs (through April 2014) LSD CR-19: 12GeV Hall B Installation Schedule (partial) Review held 14 Nov 2012 Integrated detailed activities planned from Nov through April 2013 (S&A supported activities, forward carriage mods, installation of subway addition to existing spaceframe, start pre-cabling of electronic crates on forward carriage)

Re- Baseline Changes LSD CR-20: High Power Beam Dump (A&C) Design and procurement FY13 AWP implemented Bottoms-up in progress for Jan LSD CR-18: Bubble Chamber Injector Test Installation in April 2013 in the 5MeV region of the injector, commissioning & test during Summer 2013 (3 weeks of data) Requires lockup of Inj and Nlinac High level schedule implemented detailed bottoms up required with resource provider review

Upcoming Changes Under Review for January Implementation LSD CR-10: 12GeV Hall D Schedule Update LSD CR-xx: Detailed High Power Beam Dump Schedule LSD CR-xx: Detailed Bubble Chamber Test LSD CR-xx: If TLA schedule slips further in January will include in the schedule LSD CR-xx: UIM 4-6 month down (Summer 2014)

Schedule - Overview Activity ID Activity Name Start Finish Total Float 1.20M.1 MILESTONES 005m Start Accelerator Installation Shutdown 18-May-12 015m PSS Certs - Accelerator 04-Jan-13 * 28.00d 085m Complete HAll C 6GeV Deinstallation 29-Jan-13 * 13.00d 090m Start Hall C 12GeV Installation 20-Feb-13* 0.00d 075m Start Hall B12GeV Installation 06-Mar-13 * -16.77d 070m Complete Hall B 6GeV Deinstallation 06-March-13-16.77d 020m End of Accelerator Installation Shutdown 18-Sep-13* 0.00d 025m PSS Full Lock Up/Function Test 19-Sept-13 91.00d 030m CEBAF Lock-up Begin Restoration 19-Sept-13 91.00d 035m Hot Check Out - Start 19-Sept-13 91.00d 040m Hot Check Out - Complete 24-Oct-13 65.00d 045m Beam To Hall A Start (12GeV Activity) 06-Feb-14 * 0.00d 052m 3-Pass Beam To Hall A Comp. (12GeV milestone) 03-Mar-14* 206.00d 055m Beam To Hall D Start (12GeV milestone) 12-Jun-14 * 135.00d 060m Beam To Hall D Complete (12GeV milestone) 02-Jul-14 * 120.00d 065m 12GeV CD-4A ( Approve Accelerator Completion & Start of Operations) 30-Dec-14* 0.00d 070m 2-08 Halls A, B & C Equipment Installation Completed (12GeV milestone) - Oct-15 (Re- Baseline Date) 0.00d 080m Beam To Hall B (12GeV milestone) 4/28/2015 356.00d 095m Beam To Hall C (12GeV milestone) 8/26/2015 273.00d

Schedule Overview (cont.) Activity ID Activity Name Start Finish 1.20M.2.1/2 ESR MILESTONES & CHL #1 &2 MILESTONES Total Float 12022036 Performance Mapping Complete (of warm compressors) 03-Dec-12 948.00d 12022041 4K Coldbox Cooldown 03-Dec-12 948.00d 12022017 Hall D Refrigerator Ready for Solenoid Cooldown 17-Dec-12 * 457.00d 12022015 CHL #1 Shutdown Maintenance Complete 20-Dec-12 31.00d 12022020 CHL #1 & N/S Linacs Cooldown Start 02-Jan-13 * 28.00d 12022021 CHL #1& N/S Linacs Cooldown Complete (14days of lag from start of cooldown) 22-Jan-13 28.00d 12022031 CHL Individual Runs & (Firing Up) 14-Feb-13 * 902.00d 12021002 CHL 1 Cooldown - Hall C Start 15-Mar-13 * 132.00d 12022026 CHL #2 Fully Operational 01-May-13* 848.00d 12021001 Cryo Plant Summer Configuration Start 06-May-13 * 95.00d 12022046 2K Coldbox Re-Commissioning 03-Sep-13 * 763.00d 12021005 ESR Up - Start Cooldown 06-Sep-13 * 9.00d 12021003 CHL 1 Cooldown - Hall C Complete 06-Sep-13 * 9.00d 1.20M.4 TEST LAB DEMOLITION 1204055 VTA Start 10-Dec-12 * 35.00d 1204050 CMTF Complete 10-Dec-12* 35.00d 1204060 VTA Complete 24-Dec-12* 43.00d

High Level WBS w/ Re-baseline Changes (Noted in Blue) Activity ID Start Finish Total Float Orig Dur Budg Lbr LSD Rebaseline November 2012 Progress 08-Sep-09 01-Sept-15 268.00d 1483.00d 580539.27h 1.20M LSD MILESTONES 18-May-12 26-Aug-15 273.00d 811.00d 0.00h 1.3.1 CRYOMODULES 01-May-12 25-June-13 59.00d 287.00d 2078.37h 1.3.2 POWER SYSTEMS 01-Mar-11 27-June-14 207.00d 829.00d 31310.34h 1.3.3 CRYOGENICS 01-Jun-12 5-March-14 641.00d 434.00d 17112.00h 1.3.4 BEAM TRANSPORT 21-May-12 18-Sept-13 33.00d 334.00d 28010.76h 1.3.5 EXTRACTION 01-Nov-11 9-July-13 801.00d 416.00d 2664.60h 1.3.6 INSTRUMENTATION/CONTROLS/ SAFETY SYS 01-Nov-10 29-April-14 602.00d 863.00d 41908.73h 1.4.2 CONSTRUCTION HALL B 06-Sep-10 30-March-15 376.00d 1128.00d 156740.48h 1.4.3 CONSTRUCTION HALL C 08-Sep-09 30-July-15 291.00d 1460.00d 62891.16h 1.5 HALL D MAINTENANCE & UPGRADE 01-May-12 01-May-14 169.50d 496.50d 29175.63h 1.5.1.10 HALL D FLOOD RECOVERY 02-Jan-13 28-March-13 420.00d 60.00d 0.00h 1.6.1.1.3 BSY SERVICE BUILDING ADDITION 1.8.1.1 ACCELERATOR BEAM COMMISIONING 1.8.1.3 CONSTRUCTION CRYOMODULES ACCELERATOR PRE-OPS 02-Apr-12 17-Dec-12 463.00d 193.00d 144.00h 17-May-13 1-Sept-15 268.00d 569.00d 17264.00h 03-Dec-12 16-Aug-13 773.00d 175.00d 10269.02h

1.23.7 BUBBLE CHAMBER TEST INJECTOR 04-Mar-13 30-July-13 35.0d 105.0d 1144.00h High Level WBS w/ Re-baseline Changes (Noted in Blue) Activity ID Start Finish 1.23 ACCELERATOR MAINTENANCE AND UPGRADE Total Float Orig Dur Budg Lbr 18-May-12 30-May-14 580.00d 504.00d 125643.88h 1.23.1 MAINTENANCE ACTIVITIES 18-May-12 27-May-14 146.00d 501.00d 113366.28h 1.23.1.0 MAINTENANCE ACTIVITIES 18-May-12 16-Jan-14 236.00d 411.00d 16930.00h 1.23.1.1 MAINTENANCE TASKS (RSR AWP FY13) 01-Oct-12 30-Sept-13 7.00d 248.00d 83376.28h 1.23.1.2 CRYOMODULE SHUFFLE 24-May-12 23-Aug-13 17.00d 312.00d 1272.00h 1.23.1.3 11 GeV SEPARATOR 01-Aug-12 1-April-14 94.00d 411.00d 6416.00h 1.23.1.5 DOG LEG UPGRADE 03-Dec-12 27-May-14 30.00d 365.00d 1610.00h 1.23.1.6 0L04 03-Dec-12 1-Nov-13 18.00d 229.00d 3634.00h 1.23.2 PEPPo ACTIVITIES 21-May-12 27-Jul-12 DONE 47.00d 668.00h 1.23.3 WARM-UP ACTIVITIES 23-Aug-12 20-Dec-12 30.00d 83.00d 1344.00h 1.23.4 RECOMMISSION CRYOMODULES & RF 14-Jan-13 24-May-13 80.00d 93.00d 5320.00h 1.23.5 HIGH POWER BEAM DUMP 03-Dec-12 30-May-14 580.00d 368.00d 545.60h 1.23.6 ACC MAINTENANCE FLOOD RECOVERY 01-Oct-12 29-July-13 742.00d 204.00d 4400.00h

1.29 CRYOGENICS (WORK GROUP SCHEDULE-PARTIAL) 14-Sep-12 09-April-13 864.00d 138.00d 0.00h High Level WBS w/ Re-baseline Changes (Noted in Blue) Activity ID Start Finish Total Float Orig Dur Budg Lbr 1.24 HALLS A, B, C MAINTENANCE & UPGRADES 18-May-12 29-April-15 354.00d 730.00d 27210.50h 1.24.1 HALL A MAINTENANCE & UPGRADE 18-May-12 18-Feb-14 652.00d 432.00d 5281.00h 1.24.1.1 CONSTRUCTION HALL A 18-May-12 24-May-13 384.00d 253.00d 1176.00h 1.24.1.2 PROGRAM HALL A 18-May-12 18-Feb-14 652.00d 432.00d 4105.00h 1.24.1.3 HALL A FLOOD RECOVERY 02-Jan-13 28-March-13 212.00d 60.00d 0.00h 1.24.2 HALL B MAINTENANCE & UPGRADE 21-May-12 04-April-13 817.22d 211.00d 12399.50h 1.24.2.2 HALL B FLOOD RECOVERY 02-Jan-13 28-March-13 822.00d 60.00d 0.00h 1.24.3 HALL C MAINTENANCE & UPGRADE 21-May-12 29-April-15 354.00d 729.00d 9530.00h 1.24.3.15 POLARIMETRY and BEALINE MODIFICATIONS 30-Sep-12 29-April-15 354.00d 637.00d 3040.00h 1.24.3.16 HALL C FLOOD RECOVERY 02-Jan-13 28-March-13 827.00d 60.00d 0.00h 1.26 CONVENTIONAL FACILITIES MAINT. & UPGRADES 11-Jan-12 29-Oct-14 474.00d 680.00d 90.00h 1.26.18 FACILITIES FLOOD RECOVERY 01-Oct-12 29-Oct-14 2.00d 497.00d 0.00h 1.27 FEL MAINTENANCE & UPGRADE 27-Feb-12 03-Oct-13 740.00d 403.00d 26661.80h 1.28 ESH & Q 18-May-12 20-Dec-12 183.00d 150.00d 1364.00h

Schedule Critical Path (Float less than 22 days) NO CHANGE TO CP WITH RE-BASELINE EFFORT 12GeV CHL Hall D Transfer Line and Header (0 days float ) Fabrication & Installation of cryogenic transfer line & can for solenoid 1.8.1.3.3.2 Hall D Cryogenics Pre-Ops (Commission Solenoid Distribution can header Start Hall D Solenoid Cooldown (17 Dec constrained date) Hall C De-installation (+13 DAYS) Removal work (QWeak, SOS Dipole, Shield Hut, Concrete Floor, C-Can /Platform) Relative to end of de-installation (mid Feb 2013: (12GeV installation of SHMS rails then SHMS carriage fabrication end of April)) Hall B De-installation (-17 DAYS) Relative to end of de-installation goal of mid Feb 2013 On schedule to meet goal and will be updated in Dec progress

Schedule Resource Analysis Resources Critically Analyzed: S&A MSINST (installation, vacuum, mag meas) Safety Systems Group Elec Techs (I&C, RF, DC, Electricians) RadCon Techs Resource Charts available for all listed above, Cryo, SRF, Ops Software & Operators, Engineers, Hall Labor Physics Labor is not resource leveled in this effort See W. Akers presentation for Physics Labor Graphs Nomenclature: UF = Utilization Factor = total hours per day for each activity (# people available x 8 hours)

Schedule Resource Analysis Areas of Concern: S&A, Elec Techs (as of end of Oct) S&A group is fully utilized & current delays for Hall support are helping now, but concerns that this work will soon pile up Elec techs are fully utilized & new requests are being made Current Areas of Concern w/re-baselined Schedule (UF >1): S&A RF Elec Techs Important to Know: Resource data from re-baseline is not leveled & will be done in Jan 2013 Timeline Focus: Jan 2013 June 2013 Past resource leveling efforts say we CAN level this, identified scope contingency available if needed LSD schedule will re-baseline again in April 2013

Resource Utilization Analysis 2.5 2 1.5 1 utilization factor- Mech Inst, Mag Meas, Vac Techs Other scope (all but 12GeV Acc Beam Transport) (3 people) 6GeV Maint - placeholders 12GeV Hall C, HA Compt Polar & 11GeV Separator 0.5 0

Resource Utilization Analysis 4.5 4 3.5 3 2.5 2 1.5 1 0.5 0 6GeV Maint - placeholders utilization factor - SAF Elec Des, Eng, Tech (7 people)

Resource Utilization Analysis 2.5 2 1.5 utilization factor - icd elec tech (10 people) 6GeV Maint - placeholders 12GeV I&C & 11GeV Separator 1 0.5 0

Resource Utilization Analysis 2 1.5 utilization factor - dc elec tech (8 people) 12GeV Acc & 6GeV Maint. 1 0.5 0

Resource Utilization Analysis 2 1.5 1 0.5 0 12GeV Acc (RF), FEL, 11GeV Separator, High Power Beam Dumps utilization factor - rf elec tech (8 people) Needs smoothing 6GeV Maint. Placeholder, RF Recommissioning, 12GeV Acc (RF) & 11GeV Separator

Resource Utilization Analysis 2.5 2 12GeV Acc & HC utilization factor - mech align tech (6 people) 12GeV Acc & HA, B, C, D 1.5 1 0.5 0

Part II Review Charges - Summary Issues raised in Part I Review Report adequately addressed The team needs to go through all the talks presented and update the overall plan to: Reflect ALL items discussed Ensure that the different schedules (shutdown work, project, planning for commissioning ops, etc.) are all synchronized Ensure the interconnects and resource overloads that may arise are captured in an overall plan There was the impression that there are disconnects at a significant level including the dates for 1 st Beam to the different halls. Consider whether the new baseline is achievable Are the resources adequate? Yes - RF Techs to be reviewed & minor resource leveling still needed & planned for Jan 2013 Are the critical elements and dates understood and well defined? Yes & critical milestones implemented as well

Backup

Beam Delivery Dates (Hall A) 12GeV CD-4A 30-Dec-14 Requirements: Accelerator commissioned by transporting a 2 na electron beam at 2.2 GeV beam energy (1 pass) Accelerator Commissioning #1 (6 weeks) Oct Nov/Dec 2013 1 pass @ 2.2GeV/pass to 2R Dump 12GeV Hall A Beam Commissioning Comp. (2-09 milestone) Mar-14 Requirements: Beam energy of at least 6 GeV and at least 2 na average beam current Beam To Hall A Start Comm. (12GeV 1.8 Activity) Feb-14 Accelerator Commissioning #2 (13 weeks) Jan March 2014 3 pass to HA & 5 ½ pass through HD transport line to dump

Beam Delivery Dates (Hall D) Accelerator Commissioning #2 (13 weeks) Jan March 2014 3 pass to HA & 5 ½ pass through HD transport line to dump 2-12 Hall D Equipment Installation Comp. (12GeV Milestone) Jun-14 Beam To Hall D Start (12GeV Milestone) Early start Jun-14 Beam To Hall D Complete (12GeV Milestone) Early finish Jul-14 Hall D Commissioning Start (12GeV Cartoon Schedule) Oct-14 2-13 Hall D Beam Commissioning Completed (12GeV Milestone) Dec-14