TTF2 (TESLA Test Facility, Phase 2) VUV FEL (Vacuum-Ultraviolet Free-Electron Laser)

Similar documents
TTF / VUV-FEL. Schedule 2005 and Project Management Issues. Schedule 2005 Project Organisation Budget & Controlling

Summary of the 1 st Beam Line Review Meeting Injector ( )

Review Meeting on on the TESLA Test Facility Phase 2 Summary Hans Weise for the Meeting Participants. Hans Weise

Photoinjector Laser Operation and Cathode Performance

P. Emma, et al. LCLS Operations Lectures

TESLA FEL-Report

The FLASH objective: SASE between 60 and 13 nm

The X-Ray FEL at DESY

Beam Instrumentation for X-ray FELs

Current status of XFEL/SPring-8 project and SCSS test accelerator

Nick Walker DESY MAC

First Results and Future of the Photo Injector Test Facility at DESY Zeuthen PITZ. introduction first measurements future schedule

5 Project Costs and Schedule

Future Performance of the LCLS

30 GHz Power Production / Beam Line

Lasing with Long Bunch Trains

RF considerations for SwissFEL

The basic parameters of the pre-injector are listed in the Table below. 100 MeV

Status of CTF3. G.Geschonke CERN, AB

EUROFEL-Report-2007-DS EUROPEAN FEL Design Study

LCLS Injector Technical Review

STATUS OF THE EUROPEAN XFEL

Digital BPMs and Orbit Feedback Systems

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

4.4 Injector Linear Accelerator

Status of the X-ray FEL control system at SPring-8

SPEAR 3: Operations Update and Impact of Top-Off Injection

Beam Losses During LCLS Injector Phase-1 1 Operation

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

Summary of recent photocathode studies

Linac 4 Instrumentation K.Hanke CERN

CLIC Feasibility Demonstration at CTF3

Accelerator Instrumentation RD. Monday, July 14, 2003 Marc Ross

RUNNING EXPERIENCE OF FZD SRF PHOTOINJECTOR

Beam Instrumentation for CTF3 and CLIC

Summary report on synchronization, diagnostics and instrumentation

BUNCH-COMPRESSOR TRANSVERSE PROFILE MONITORS OF THE SwissFEL INJECTOR TEST FACILITY

Intra-train Longitudinal Feedback for Beam Stabilization at FLASH

STATUS OF THE EUROPEAN XFEL CONSTRUCTING THE 17.5 GEV SUPERCONDUCTING LINEAR ACCELERATOR

SIMULTANEOUS OPERATION OF THREE LASER SYSTEMS AT THE FLASH PHOTOINJECTOR

LHC Beam Instrumentation Further Discussion

Focus of efforts. ILC 2010, Mar/27/10 A. Seryi, BDS: 2

Photo cathode RF gun -

TWO BUNCHES WITH NS-SEPARATION WITH LCLS*

PROJECT DESCRIPTION. Longitudinal phase space monitors for the ILC injectors and bunch compressors

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi)

Linac-Beam Characterizations at 600 MeV Using Optical Transition Radiation Diagnostics *

INFN School on Electron Accelerators. RF Power Sources and Distribution

High Rep Rate Guns: FZD Superconducting RF Photogun

Cathode Studies at FLASH: CW and Pulsed QE measurements

Upgrading LHC Luminosity

Undulator Protection for FLASH and for the European XFEL

AREAL- Phase 1. B. Grigoryan on behalf of AREAL team

Design Studies For The LCLS 120 Hz RF Gun Injector

COMMISSIONING RESULTS OF BEAM DIAGNOSTICS FOR THE PETRA III LIGHT SOURCE

LLRF at SSRF. Yubin Zhao

SABER A Facility for Accelerator Physics and Test Beam Experiments Roger Erickson SABER Workshop March 15, 2006

Status of SOLARIS Arkadiusz Kisiel

Simulations on Beam Monitor Systems for Longitudinal Feedback Schemes at FLASH.

The Elettra Storage Ring and Top-Up Operation

SLAC ILC Accelerator R&D Program

Technical Document 1 attached to the European XFEL Convention

Photocathodes FLASH: Quantum Efficiency (QE)

A Facility for Accelerator Physics and Test Beam Experiments

Results of recent photocathode studies at FLASH. S. Lederer, S. Schreiber DESY. L. Monaco, D. Sertore, P. Michelato INFN Milano LASA

The PEFP 20-MeV Proton Linear Accelerator

STATUS REPORT ON THE COMMISSIONING OF THE JAPANESE XFEL AT SPRING-8

SUMMARY OF THE ILC R&D AND DESIGN

PEP II Design Outline

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY

TITLE PAGE. Title of paper: PUSH-PULL FEL, A NEW ERL CONCEPT Author: Andrew Hutton. Author Affiliation: Jefferson Lab. Requested Proceedings:

Andrei Seryi, Toshiaki Tauchi. December 15-18, 2008

Status of JRA-SRF in CARE

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems

Detailed Design Report

sflash First Seeding at FLASH On behalf of the sflash team Jörn Bödewadt Hamburg University

Screen investigations for low energetic electron beams at PITZ

DARK CURRENT IN SUPERCONDUCTING RF PHOTOINJECTORS MEASUREMENTS AND MITIGATION

Availability and Reliability Issues for the ILC

Compact, e-beam based mm-and THzwave light sources

Status of Elettra, top-up and other upgrades

Research and Development on Superconducting Radio-Frequency Technology for Electron Linear Accelerators. Deliverable

Report on the LCLS Injector Technical Review

Hall-B Beamline Commissioning Plan for CLAS12

Top-Up Experience at SPEAR3

An Overview of Beam Diagnostic and Control Systems for AREAL Linac

Requirements for the Beam Abort Magnet and Dump

Characterizing Transverse Beam Dynamics at the APS Storage Ring Using a Dual-Sweep Streak Camera

LCLS Linac Technical Design Review Diagnostics and Controls

KARA and FLUTE RF Overview/status

THE NEXT LINEAR COLLIDER TEST ACCELERATOR: STATUS AND RESULTS * Abstract

Towards an X-Band Power Source at CERN and a European Structure Test Facility

Status of RF Power and Acceleration of the MAX IV - LINAC

CERN S PROTON SYNCHROTRON COMPLEX OPERATION TEAMS AND DIAGNOSTICS APPLICATIONS

CLIC Feasibility Demonstration at CTF3

New Filling Pattern for SLS-FEMTO

High QE Photocathodes lifetime and dark current investigation

PITZ Introduction to the Video System

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

Transcription:

DESY MAC Meeting 9. Nov. 2004 TTF2 (TESLA Test Facility, Phase 2) VUV FEL (Vacuum-Ultraviolet Free-Electron Laser) Overview and Status Jörg Rossbach 1

Overview BC 3 BC 2 Injector 3 LOLA 260 m 2

TTF External Contributions to Installation and Operation Installation Operation DESY Coord. Cathodes Accel.Modules INFN Milano Cathodes INFN Milano Schreiber RF Gun / Cryogenics RF Modulators FNAL Freq.Tuner BPMs / HOM Studies CE Saclay Lange Nölle / Baboi Freq.Tuner BPMs CE Saclay Transverse deflecting cavity LOLA SLAC Schlarb Klose Transverse deflecting cavity LOLA SLAC OTR Diagnostics INFN Frascati Honkavaara OTR Diagnostics INFN Frascati Gun Laser MBI Schreiber Gun Laser MBI LLRF Warsaw Univ. Ayvazyan Simrock Ctrls YerPhi Ayvazyan Rehlich Ctrls ITEP Moscow Univ. Rehlich 3 additional manpower RF Protvino Choroba

New Partners 2 Helmholtz Virtual Research Centers : 1. Electron guns 2. Advanced beam diagnostics EU Infrastructure Programme: 1. EUROFEL 2. CARE 3. Synchrotron Radiation I3 Several more under progress 4

VUV FEL beam parameters VUV FEL @ 6 nm (1 GeV) Normalized emittance from injector (1 nc) Norm. emittance at undulator entrance Beam size in undulator Bunch length (rms) Peak current Long. emittance σ E σ l 1.2 mrad mm 2 mrad mm 65 µm 150 fs 2500 A 40 mm kev 5

TTF2 Time Structure Repetition rate Macro-pulse <I> within pulse train max. 9 ma Duty cycle ~ 0.8% 100ms I 800µs macro-pulse I peak ~ 2.5 ka t Bunch I 1.0-0.111µs bunch spacing t Slice I 2-5 ka 1 nc 100 fs ~ ps Slice ~ e.g. 10 fs t Without 3 rd harm. cav. 6

The TTF with its VUV FEL is a new type of FEL radiation user facility an FEL research machine a test-bed for s.c. linac technology a prototype for the European XFEL Consequence: TTF needs several stages for electron beam manipulation and full control of beam parameters during all of these stages. flexible optics lattice, thus many quadrupole magnets and power supplies lots of beam diagnostics high density of special components Machine characteristics VUV FEL is not suited to estimate XFEL or ILC costs&efforts just by scaling length or beam energy! 7

Priorities and Milestones Due to unexpected financial restrictions some major cost driving components needed to be delayed. necessary to re-define priorities. Decision: delay power supplies cabling long bunch train issues Milestones: 1: Injector commissioning up to ACC2 2: Complete vacuum system 3: FEL commissioning at ~30nm wavelength with single bunch 4: Full bunch train operation 8

TTF2 Schedule of the last year 11 2004 now 6 2004 1 2004 9 2003 commissioning complete accelerator end shutdown survey of components and final alignment installation of remaining components (diagnostics,cables,container,ps,interlock,photon beamline) commissioning injector survey of magnets end vacuum installation installation of injector installation of gun start vacuum installation incl. module processing incl. module installation & all magnets 9

Overview and Status Progress since June 2003: Machine completely installed, vacuum closed Injector commissioned up to ACC2; emittance ok for 30 nm Commissioning of entire machine started 1. Sept. 2004 Accumulated delay of ~ 3 months w.r.t. June 2003 TTF2 installation schedule contained ~ 450 topics Talk by M. Körfer 10

Injector General concept: 1. Full performance test of gun components at PITZ/Zeuthen Zeuthen 2. Installation at TTF Present TTF gun: First emittance measurement (vert( vert.) at ~100 MeV,, no compression 1 0.5 Laser spot on cathode: σx = 0.51 ± 0.02 mm 0 3 11 2 x,mm 1 3 2 1 y,mm σy = 0.62 ± 0.02 mm Test at PITZ: ε = 1.7 π mm mrad downstream BC2: ε 3 π mm mrad Compression by BC2 cleary observed No quantitative measurement yet

Injector Improvement plans: 1. Transversely homogenous laser spot on cathode 2. Longitudinal flat top profile 3. Increase electric field on cathode First test at PITZ: 1 0.5 σx = 0.57 ± 0.02 mm 0 3 2 x,mm 1 3 ε x = 1.9 π mm mrad ε y = 1.3 π mm mrad 2 σy = 0.58 ± 0.02 mm 1 y,mm Talk by M. Krassilnikov 12

Tunnel layout: Concept and Experience Intention: tunnel design prototyping TESLA tunnel 32 Container Experience: + cabling is less time consuming + short cable length - bad cable tray access below walkway - time consuming cabling beside the containers -For TTF2: container more expensive than standard racks Conclusion for TESLA & XFEL: different tunnel layout; Conclusion for ILC: tbd 13 tbd; ; experience and numbers available

Mechanical Design Tools: Full 3D representation 14

Vacuum All vacuum chambers particle free installed using local clean rooms BC 3 BC 2 15

Electron beam diagnostics Charge Monitors Toroids: : available + Screens OTR s installed & commissioned + BPMs all BPMs installed and cabled + but only 20 Read out Electronics available Problem: delivery of milled rf-housing and availability of rf connectors -- connectors -- BPMs at Strategic Positions : -- - Injector: Full Instrumentation - BC3: 2 BPMs Up- and Downstream - LOLA: 2 BPMs - Bypass Line: 2 BPMs - Dump Line: 1 BPM... and much more beam diagnostics talk by Dirk Noelle New Generation of BPM Electronics available by End of 2004 16

Schedules Task Milestone Milestone (as of 19. 8. 2003) Milestone (rev. Jan 2004) Milestone (9. 11. 2004) Commissioning of accelerating modules ACC 3,4,5 incl. proof of max. gradient Modules commissioned 1.9.2003 15. 9.2003 15.9.2003 Vacuum system entire machine Vacuum closed xx. 1. 2004 Commissioning injector up to ACC2 incl. commissioning modules ACC1 and ACC2 First beam up to ACC2 15. 3. 2004 12. 2. 2004 mid of Febr. 2004 21. 4. 2004 29. 4. 2004 Installation of remaining components Commissioning entire machine, except for collimator and undulator Commissioning of collimator and undulator beamline all installations completed First beam through bypass into dump First beam through undulator into dump 14. 5. 2004 14. 6. 2004 26. 8. 2004 1. 9. 2004 (except PS & BPMs) 16. 9. 2004 end of 10.2004 30. 9. 2004 end of 11. 2004 Commissioning photon diagnostics in the tunnel Beam intensity and spectrum of spontaneous radiation 1. 8. 2004 end of 12. 2004 17

Schedules Major reasons for delay w.r.t. schedule of August 2003: Magnetic shielding of ACC1 cavities re-fabricated 2 times More time needed for installation beyond vacuum (e.g. cabling, container), partially due to conflicts with HERA priority 4 weeks 4 weeks Severe delay of PSs: : late order due to financial restrictions + company went bankrupt no beam through bypass before end of Oct. 04 4 weeks 18

Allocation of responsibilities: Hardware work packages (almost unchanged since 2001): 19 Zuständigkeiten TTF2 Kryogenik Magnete Umbau, Einbau, Montage Kollimator allg. Kollimator Vakuum Diagnostik Bunch compressor 3 allg. Bunch compressor 3 Vakuum Zwischen-und Ersatzbeaml. Bypass Undulator Vermessung Uebersichtszeichnungen Spektrometer+Dump Injektor III allg. Injektor III Vakuum RF gun + laser TESLA Module Undul.kammer + Zwischenst. Kontrollen Wasser und Strom RF Versorgung Feedback Cavities Koppler Magnet-Netzger Netzgerätete Koordination Vakuum Kabel Gestelle Personen-Interlock Technisches Interlock Photonen-Diagnose bernd.petersen@desy.de, bernward.krause@desy.de, burghard.sparr@desy.de, markus.koerfer@desy.de cornelius.martens@desy.de dirk.noelle@desy.de, frank.stulle@desy.de mike.seidel@desy.de hans-peter.wedekind@desy.de harder@ifh.de, joachim.pflueger@desy.de, johannes.prenting@desy.de, josef.gonschior@desy.de, michael.schmitz@desy.de, klaus.floettmann@desy.de, annette.brenger@desy.de siegfried.schreiber@desy.de bernd.petersen petersen@desy.de, ulrich.hahn@desy.de kay.rehlich@desy.de jens-peter.jensen@desy.de stefan.choroba@desy.de klaus.balewski@desy.de, dieter.proch@desy.de wolf-dietrich.moeller@desy.de hans-joerg.eckoldt@desy.de Kirsten.Zapfe@desy.de juergen.liebing@desy.de gabriele.weichert@desy.de dietrich.ramert@desy.de martin.staack@desy.de josef.feldhaus@desy.de

TTF / VUV-FEL Organigramm TESLA Collaboration Board DESY Directorate DESY TTF / VUV-FEL Coordination Board Chair: M Division Leader D. Trines Co-Chair: FS Division Leader J. Schneider Members: Project leader FEL technology J. Rossbach Project leader LINAC technology H. Weise Project leader photons J. Feldhaus FEL concepts M. Yurkov TESLA TEST Facility R&D coordinator C. Pagani Representative of V3 (PoF related issues) U. Wolframm DESY TTF / VUV-FEL Project Group Chair: Project leader FEL technology J. Rossbach Co-Chair: Project leader LINAC technology H. Weise Project leader photons J. Feldhaus Members: - people responsible for the individual work packages - members of the Coordination Board New International Collaborators 20 DESY technical/administrative groups Groups from TESLA Collaboration

TTF / VUV-FEL Commissioning VUV FEL responsibilities for commissioning procedures (13-August August-2004) Gun Operation llrf (FSM) llrf (closed loop) phase stability laser / RF water regulation; rf tune gun technical interlock gun dark current meas. laser beam line laser laser server laser controls streak camera laser cathode production Faraday cups toroids BPM collimator phase scan energy, energy spread beam based alignment bucking coil field envelope matching study effect of laser mirror wakefield effects quantum efficiency phase charge studies Ayvazyan Kotthaus Simrock Carneiro Schreiber Han Klose Schreiber Petrosyan Rehlich Schreiber Sertore Carneiro / Nölle Nölle Nölle Flöttmann Sertore Schlarb Krassilnikov Flöttmann Flöttmann Miltchev Kim Schreiber Sertore TTF Linac ACC1 ACC5 llrf Ayvazyan phase calibration Ayvazyan set-up nominal optics Castro magnets Castro OTR screens Honkavaara toroids Nölle BPMs Nölle wire scanners Werner beam loss detection Pugachov dark current transmission Flöttmann spot size and shapehonkavaara check envelope matching (inj( inj.) Flöttmann emittance measurement with screens Honkavaara bunch compressor 2 Kim beam with compression Limberg bunch length monitoring (pyro( pyro) Schlarb measurement beam energy Castro energy spread Schlarb compensate dispersion Golubeva streak camera (TOSY) Grimm IR interferometer Grimm velocity bunching Carneiro time-of of-flight flight (TOF) Kollewe measure phase stability Simrock final state machine LLRF Brandt establish golden orbit Castro module operation Kostin HOM studies Baboi Electron Beam Downstream of Linac ACC7 section: LOLA Ross / Klose LOLA Kicker Schlarb / Obier electro-optical optical sampling (EOS) Steffen timing meas. By EOS (TEO) Schlarb bunch compress. Meas.by CDR Schlarb dto.. By IR interferometer Grimm collimator Körfer orbit feedback Balewski establish bypass operation Castro beam diagnostics bypass Nölle undulator: beam losses in undulator Körfer / Pugatchov electron orbit / beam based alignm. Faatz wire scanners Sachwitz electron spectrometer / beam dump Schmitz Photon Beam Diagnostics intensity and spatial distribution MCP detectors HASYLAB systems spectral distribution dipole radiation, timing w/ respect to pump-probe probe laser FEL photon beam transfer Yurkov Treusch Tiedke Plönjes Tiedke 21

Summary Machine completely installed, vacuum closed Injector commissioned up to ACC2; emittance ok Commissioning of entire machine started 1. Sept. 2004 Electron beam through bypass on beam dump 22