AltaLink Management Ltd.

Similar documents
Alberta Electric System Operator

PARTICIPANT INVOLVEMENT PROGRAM (PIP)

SUMMARY REPORT. Consultation Summary Report. January 2016

TELECOMMUNICATIONS V S WATER UTILITIES NATURE STRIP CONGESTION. Leigh Trevaskis. Riverina Water County Council

Marc Richter Vice President Regulatory Services. June 3, 2015 CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION. By Electronic Delivery

3 Resolution of the Board of Supervisors, acting as responsible agency with respect to

BEFORE THE NEW JERSEY BOARD OF PUBLIC UTILITIES

ORDER NO * * * * * * * * * On December 21, 2018, the Maryland Public Service Commission

(1) These Regulations may be called PEMRA Standards for Cable Television Regulations 2003.

Staff Report: CenturyLink Cable Franchise

MTS FiON. for Multiple Dwelling Units (MDUs) Brownfield

Request for Proposals Fiber Optic Network Backbone Upgrades

Licensing & Regulation #379

REFURBISHMENT OF SECONDARY SYSTEMS IN HIGH VOLTAGE SUBSTATIONS LESSONS LEARNED IN VENEZUELA

COST SHARING POLICY FOR COMCAST CABLE SYSTEM CONSTRUCTION FOR STREETS WHICH DO NOT MEET MINIMUM DENSITY REQUIREMENTS

OECD COMMUNICATIONS OUTLOOK 2001 Broadcasting Section

Load Frequency Control Structure for Ireland and Northern Ireland

Based on our maintenance efforts, during the second quarter of 2018, Comcast s plant was 99.9% reliable.

VAR Generator Operation for Maintaining Network Voltage Schedules

BILOXI PUBLIC SCHOOL DISTRICT. Biloxi Junior High School

BPA s Network Open Season

Definitions. Common Corridor:

ILF Scotland Transition Fund

FIBRE TO THE HOME - FTTH - FAQs

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS DIVISION OF PUBLIC UTILITIES AND CARRIERS

Verizon NY Section 2 Network Services Issue C, December, 2001

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

Property No

Village of Glenview Appearance Commission

City of Kingston Report to Committee of Adjustment Report Number COA

AREA CODE EXHAUST AND RELIEF. Questions and Answers

LOW-BUDGET INDEPENDENT FEATURE FILM ASSISTANCE PROGRAM GUIDELINES FOR

1. Entries must be received or post-marked no later than 5:00 p.m., NOVEMBER 25, Faxed, or late entries will not be accepted.

January 11, Re: Notice of Ex parte presentation in MB Docket No.07-57

Broadcasting Decision CRTC and Broadcasting Orders CRTC , , , , and

FACILITIES STUDY MID AMERICAN TRANSMISSION SERVICE REQUESTS. OASIS Revision: 4

The Telecommunications Act Chap. 47:31

Official Journal of the European Union L 117/95

Cambria County Association for the Blind and Handicapped 175 Industrial Park Road Ebensburg, PA Prepared for: Prepared by:

Selecting the correct cable type for Outside Plant Application

10/13/2011 Planning Coordination Committee. Standards

VERIZON MARYLAND INC.

GOVERNMENT GAZETTE OF THE REPUBLIC OF NAMIBIA. N$4.00 WINDHOEK - 11 July 2014 No. 5507

WISCONSIN LEGISLATIVE COUNCIL INFORMATION MEMORANDUM

ELIGIBLE INTERMITTENT RESOURCES PROTOCOL

1. EXPERT MEETING EXPERT MEETING EXPERT MEETING Feedback from the meeting attendees...

APPLICATION AND EFFECTIVENESS OF THE SEA DIRECTIVE (DIRECTIVE 2001/42/EC) 1. Legal framework CZECH REPUBLIC LEGAL AND ORGANISATIONAL ARRANGEMENTS 1

This Chapter does not apply to applications and decisions on, development on land reserved in corridor maps.

*** no equipment put on roofs or buildings. Dish must be put in ground 3 feet from building to allow for mowing. ***

A Discussion with Neighborhood Representatives RPI 3/13/2017-1

REPORT TO THE PLANNING COMMISSION

OECD COMMUNICATIONS OUTLOOK 2001 Broadcasting Section

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona USA

APPLICATION OF POWER SWITCHING FOR ALTERNATIVE LAND CABLE PROTECTION BETWEEN CABLE LANDING STATION AND BEACH MAN HOLE IN SUBMARINE NETWORKS

A. The Cable Operator shall provide Subscribers a toll-free or local telephone number for installation, service, and complaint calls.

Preparing a home for TransACT fibre-to-the-premise (FTTP) services

About the Presenter. Robert C. May III Partner Telecom Law Firm, PC

SOUTHWESTERN BELL TELEPHONE COMPANY TARIFF F.C.C. NO. 73 1st Revised Page 9-1 Cancels Original Page 9-1

May 26 th, Lynelle Briggs AO Chair Planning and Assessment Commission

AES standard for audio connectors - Modified XLR-3 Connector for Digital Audio. Preview only

WIRELESS PLANNING MEMORANDUM

Tab 10 - The NESC and Underground Applications. Restricted Siemens Industry, Inc All rights reserved.

Broadcasting Decision CRTC

Broadcasting Public Notice CRTC

Property No

Ofcom's proposed guidance on regional production and regional programming

Appendix 1: Background Information Document

Plan for Generic Information Collection Activity: Submission for. National Transportation Safety Board (NTSB).

COMMUNICATIONS OUTLOOK 1999

Recovering and Relaying Cables

AREMA 2015 ANNUAL CONFERENCE. NYSDOT / Amtrak. Hudson Line Improvement Program. David W. Emerich, PE CHA. Minneapolis, MN October 4-7, 2015

Policy on the syndication of BBC on-demand content

Class B digital device part 15 of the FCC rules

Toronto Hydro - Electric System

APPENDIX D TECHNOLOGY. This Appendix describes the technologies included in the assessment

Canada-Japan Literary Awards Step 1. Step 2. Step 3. Deadline. Further Information GUIDELINES AND NOMINATION FORM

DESIGN!!GUIDELINES!!!!!

The MTS FiON Network. for Multiple Dwelling Units (MDUs) Greenfield/Brownfield Renovations

Annex J: Outline for Bhutan DTV Road Map

Digital Switchover Management of Transition Coverage Issues Statement

LUPA Proposed Final Programmatic Agreement November 20, 2015

RECOGNITION OF PRIOR LEARNING CANDIDATE APPLICATION FORM UEE30811 CERTIFICATE III IN ELECTROTECHNOLOGY - ELECTRICIAN

Saskatchewan History. Authors Guidelines for New Submissions

Planning Commission Staff Report Street Vacation Hearing Date: December 11, 2013

Note for Applicants on Coverage of Forth Valley Local Television

47 USC 534. NB: This unofficial compilation of the U.S. Code is current as of Jan. 4, 2012 (see

GENERAL SERVICES TARIFF P.S.C.-D.C.-No. 203 Verizon Washington, DC Inc. Section 26 1st Revised Page 1 Cancels Original Page 1 CALL ROUTING SERVICE

CITY POLICY SUPERSEDES: NEW CORPORATE BILLINGS AND CHEQUES - FORMS

Young Choir of the Year Postal Entry Form

Independent TV: Content Regulation and the Communications Bill 2002

The proposed UCC guidelines cover the operation of TVWS in the frequency range MHz based on Dynamic Spectrum Allocation (DSA) technique.

LUVERNE PUBLIC ACCESS POLICIES AND PROCEDURES

Property No

CHAPTER 98: CABLE TELEVISION Tampering with city cable system prohibited Fees

CHARLOTTE MECKLENBURG PUBLIC ACCESS CORPORATION

Broadcasting Decision CRTC

Introduction of digital TV in Bosnia and Herzegovina - Support for Public Broadcasting System

REDFISH TECHNOLOGIES

British Columbia Utilities Commission (BCUC) British Columbia Hydro and Power Authority (BC Hydro)

Date. James W. Davis, PhD James W. Davis Consultant Inc.

Transcription:

Decision 21317-D01-2016 Central Alberta Underground Fibre Optic Build July 12, 2016

Alberta Utilities Commission Decision 21317-D01-2016 Central Alberta Underground Fibre Optic Build Proceeding 21317 Application 21317-A001 July 12, 2016 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary, Alberta T2P 3L8 Telephone: 403-592-8845 Fax: 403-592-4406 Website: www.auc.ab.ca

Alberta Utilities Commission Calgary, Alberta Decision 21317-D01-2016 Proceeding 21317 Central Alberta Underground Fibre Optic Build Application 21317-A001 1 Decision summary 1. In this decision, the Alberta Utilities Commission must decide whether to approve an application by (AltaLink) to construct and operate an underground fibre optic cable in central Alberta. For the reasons outlined in this decision, the Commission finds that approval of the proposed development is in the public interest, having regard to the social and economic effects of the project and its effect on the environment. Pursuant to sections 14 and 15 of the Hydro and Electric Energy Act, the Commission approves the application and grants AltaLink a permit to construct and a licence to operate the underground fibre optic cable. 2 Introduction 2. On February 8, 2016, AltaLink applied to the Commission pursuant to sections 14 and 15 of the Hydro and Electric Energy Act for approval to construct and operate an underground fibre optic cable from the Sunnybrook 510S Substation to the Ellerslie 89S Substation (the project). AltaLink requested the fibre optic cable be designated as Central Alberta Underground Fibre Optic Cable 0012F (the fibre optic cable). The application was filed as Application 21317-A001 and assigned Proceeding 21317. 3. The Sunnybrook 510S Substation is located in the southwest quarter of Section 36, Township 50, Range 3, west of the Fifth Meridian, in Warburg, Alberta. The Ellerslie 89S Substation is located in the northwest quarter of Section 27, Township 51, Range 24, west of the Fourth Meridian, in the city of Edmonton. The following map illustrates the location of the proposed fibre optic cable: NORTH R.3 627 770 R.1W.5M. 16 STONY PLAIN SUNNY BROOK 510S SUBSTATION R.27 SPRUCE GROVE STONY PLAIN NO. 135 SASK ATCH EWAN 16A 60 R. DEVON CITY OF EDMONTON ELLERSLIE 89S 14 SUBSTATION BEAUMONT 2 R.24W.4M. T.53 T.50 LEDUC PROPOSED UNDERGROUND FIBRE OPTIC LINE N.T.S. Decision 21317-D01-2016 (July 12, 2016) 1

4. The Commission issued a notice of application to all potentially directly and adversely affected stakeholders on February 29, 2016. The Gunn Métis Local 55 (Gunn Métis) submitted a statement of intent to participate (SIP) and an application to file confidential information with the Commission to supplement its SIP. No other person responded to the notice of application. 5. The AUC denied the Gunn Métis request for confidentiality on April 19, 2016, 1 but granted the deadline of April 25, 2016, for the Gunn Métis to file any additional information in support of its SIP. 6. The Gunn Métis did not to file any additional information and, on May 6, 2016, the AUC ruled that the Gunn Métis had failed to demonstrate how the rights it was asserting may have been directly and adversely affected by the Commission s decision on the fibre optic cable and therefore it did not have standing to trigger a hearing into AltaLink s application. 2 7. The AUC also reissued the notice of application to a list of new stakeholders identified by AltaLink but no new submissions were received by the May 24, 2016, submission deadline. 8. The Commission considers the close of record for this proceeding to be May 6, 2016. 3 Discussion 9. AltaLink explained that its Western Alberta Transmission Line and ATCO Electric s Eastern Alberta Transmission Line projects are each strung with an optical ground wire creating two significant north-south fibre optic cable links. It stated that these links represented the initial portions of a province-wide utility-owned fibre optic cable ring, built to enhance transmission system reliability. AltaLink stated that an east-west gap exists that could be connected with the proposed new fibre optic cable. AltaLink stated that the project would increase the security, speed and reliability of AltaLink s current telecommunications network. 10. In addition, AltaLink explained that the Alberta Interconnected Electric System is currently experiencing issues with fault protection on the existing 500-kV Transmission Line 1209L. It stated that the project would allow protection on the transmission line to be converted to direct fibre. 11. The project would consist of: a. 71 kilometres of one 72 single-mode fibre optic cable between AltaLink s Sunnybrook 510S Substation and Ellerslie 9089R Radio Site, utilizing: i. AltaLink s existing easement on private land ii. highways 770 and 627 government road allowance iii. Winterburn Road (215th Street) road allowance within the city of Edmonton 1 2 Exhibit 21317-X0024, Ruling on Confidentiality Motion, April 19, 2016. Exhibit 21317-X0034, Ruling on Standing, May 6, 2016. 2 Decision 21317-D01-2016 (July 12, 2016)

iv. AltaLink s existing 1043L and 909L/1045L and 909L/1044L transmission line rights-of-way within the city of Edmonton v. portions of the Edmonton Transportation/Utility Corridor (TUC) including AltaLink s existing 1209L and 1202L rights-of-way b. 0.4 kilometres of two 48 single-mode fibre optic cables between AltaLink s Ellerslie 9089R Radio Site and Ellerslie 89S Substation in two existing conduits 12. AltaLink stated that the project would provide faster, more secure and reliable communications between the termination points of AltaLink s Sunnybrook 510S Substation and Ellerslie 89S Substation. It explained that this would support faster fault-clearing time between the Genesee electrical generation area and the city of Edmonton. 13. AltaLink explained that the project may also provide communication tie-in points with the proposed Harry Smith 367S Substation and the existing Acheson 305S Substation. These tie-ins would provide the same benefits to reliability, security and speed as with the Sunnybrook 510S and Ellerslie 89S substations. 14. AltaLink stated that the project is part of AltaLink s capital replacement and upgrade programs. As such, there was no direction letter or needs identification document from the Alberta Electric System Operator for the project. 15. AltaLink stated that public notification was provided to all stakeholders, including occupants, residents and landowners, local First Nations, agencies, industrial interest holders and oil and gas companies within 100 metres from the edge of the road allowance, existing transmission rights-of-way and new utility easements in accordance with Rule 007: Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments. AltaLink also consulted with the landowners on whose land the fibre optic cable work was proposed. AltaLink submitted that 295 landowners, nine agencies, eight industrial interest holders, and 15 oil and gas companies were notified by mail. 16. AltaLink determined that a six-metre right-of-way would be necessary due to an approximate construction equipment width of four metres plus a one-metre buffer on either side to allow for slight deviations and additional equipment access for construction on private land. Where AltaLink proposed to construct within the TUC, it explained that there would be sections where it would be limited to a four-metre right-of-way width due to obstacles and other facilities in the area. 17. AltaLink stated that some of the rights-of-way it required were located on privately owned lands. It explained that it would make all reasonable efforts to secure the land rights required through negotiation with landowners. If it was unable to obtain the needed land rights through negotiation, AltaLink stated that it would apply to the Surface Rights Board for rights-of-entry orders under the Surface Rights Act. 18. AltaLink stated that it proposed the fibre optic cable route that represented a low-impact location for the project and viable route from a technical and constructability standpoint. AltaLink stated that in its route determination process, it considered routes that utilized or Decision 21317-D01-2016 (July 12, 2016) 3

paralleled existing infrastructure, minimized line length and costs, and included feedback from key government agencies and landowners. 19. AltaLink stated that approaches, water bodies, roads and other infrastructure crossings would be directionally drilled to minimize surface disturbance and inconvenience to residential accesses. 20. AltaLink stated that the post-construction land maintenance and weed control of lands on which the fibre optic cable would be installed would be the responsibility of the landowner. Where the fibre optic cable would be located in road allowances in Parkland County, Leduc County, the city of Edmonton, and in the TUC, vegetation management and maintenance would be the responsibility of the appropriate agency. Where AltaLink has a right-of-way easement with a landowner on cultivated lands, AltaLink would not have vegetation management obligations post construction. Where AltaLink has right-of-way easement with a landowner on uncultivated land, generally, AltaLink would follow the obligation in the negotiated right-of-way easement agreement with the landowner. 21. AltaLink submitted an Environmental Specifications and Requirements (ESR) document for the project. In the ESR, AltaLink stated that the project would comply with the Environmental Protection Guidelines for Transmission Lines (R&R/11-03). All activities related to the project would comply with all applicable legislation; regulations and guidelines applicable to transmission line and substation construction, and all project activity would occur within the rights-of-way and approved project work sites. 22. AltaLink submitted that the cost of the project would be $6,658,000 (within +20 per cent/-10 per cent accuracy) allocated as capital maintenance. 4 Findings 23. AltaLink conducted a complete participant involvement program and there are no outstanding public or industry objections from parties granted standing or concerns associated with the construction or operation of the underground fibre optic cable. 24. The Commission finds that the application meets the information requirements stipulated in Rule 007. The Commission also finds that the participant involvement program completed by AltaLink meets the requirements of Rule 007. 25. The Commission is satisfied that the application sufficiently addresses AltaLink s intent to increase the reliability of AltaLink s telecommunications network by connecting, through the fibre optic cable, the Western Alberta Transmission Line to the Eastern Alberta Transmission Line. The Commission finds that the proposed enhancement to AltaLink s communication capability will enhance transmission system reliability. 26. The Commission is satisfied that the environmental aspects of the project have been reasonably assessed by AltaLink. The Commission accepts that impacts to wildlife and the environment would be minimized by virtue of the fact that the underground fibre optic cable will generally be buried in existing road allowances, previously disturbed areas within existing rights-of-way, and the Edmonton TUC. The Commission further finds that the additional 4 Decision 21317-D01-2016 (July 12, 2016)

mitigation measures proposed by AltaLink in the ESR and adherence to environmental legislation and environmental regulatory requirements will also effectively minimize the impacts of the project. 27. The Commission finds, given its underground nature, the project will have limited adverse social effects. The Commission observes in this respect that it received only one objection to the project from the Gunn Métis. The Commission considers this lack of objections to the project to be evidence of the project s limited impact to neighbouring landowners. 28. Having considered the social, economic and environmental effects of the proposed project, the Commission finds that approval of AltaLink s application to construct and operate the fibre optic cable is in the public interest pursuant to Section 17 of the Alberta Utilities Commission Act. Therefore, the Commission approves the project as proposed by AltaLink. 5 Decision 29. Pursuant to sections 14, 15 and 19 of the Hydro and Electric Energy Act, the Commission approves Application 21317-A001 and grants AltaLink a permit to construct and a licence to operate the Central Alberta Underground Fibre Optic Cable 0012F as set out in Appendix 1 Telecommunications Facilities Permit and Licence 21317-D02-2016 July 12, 2016. Appendix 1 will be distributed separately. Dated on July 12, 2016. Alberta Utilities Commission (original signed by) Tudor Beattie, QC Commission Member Decision 21317-D01-2016 (July 12, 2016) 5