OPERATIONAL EXPERIENCE WITH CIRCULATING BEAM

Similar documents
1. General principles for injection of beam into the LHC

Friday 05/03/ :00 13:00 : Establishing reference orbit golden Jorg Wenninger. Problems Wrong polarity on MCBXH3.L8 Polarity flag changed in DB

REVIEW OF LHC OPERATION

LHC COMMISSIONING PLANS

Session 07 - What did we learn with beam in 2008? LHC Performance Workshop Chamonix Rhodri Jones on behalf of BE/BI & all our collaborators

LHC Beam Instrumentation Further Discussion

beam dump from P2 losses this morning

LHC Nominal injection sequence

PEP II Design Outline

LHC_MD292: TCDQ-TCT retraction and losses during asynchronous beam dump

New Filling Pattern for SLS-FEMTO

2008 JINST 3 S LHC Machine THE CERN LARGE HADRON COLLIDER: ACCELERATOR AND EXPERIMENTS. Lyndon Evans 1 and Philip Bryant (editors) 2

WHAT WE WILL DO FOR BEAM PREPARATION IN 2009 : BEAM INTERLOCKS

LEP OPERATION AND PERFORMANCE WITH ELECTRON-POSITRON COLLISIONS AT 209 GEV

HIGH POWER BEAM DUMP AND TARGET / ACCELERATOR INTERFACE PROCEDURES *

OPERATIONAL EXPERIENCE AT J-PARC

The 2011 LHC Run - Lessons in Beam Diagnostics

LHC Machine check out

arxiv: v1 [physics.acc-ph] 9 Aug 2016

INITIAL BEAM COMMISSIOMING OF INJECTION AND BEAM DUMP

Digital BPMs and Orbit Feedback Systems

EPJ Web of Conferences 95,

First LHC Beams in ATLAS. Peter Krieger University of Toronto On behalf of the ATLAS Collaboration

Tolerances on Magnetic Misalignments in SESAME Storage Ring

LESSONS LEARNT FROM BEAM COMMISSIONING AND EARLY BEAM OPERATION OF THE BEAM LOSS MONITORS (INCLUDING OUTLOOK TO 5 TEV)

Precise Digital Integration of Fast Analogue Signals using a 12-bit Oscilloscope

Libera Hadron: demonstration at SPS (CERN)

Linac 4 Instrumentation K.Hanke CERN

Requirements for the Beam Abort Magnet and Dump

Commissioning of the CNGS Extraction in SPS LSS4

COMMISSIONING SCENARIOS FOR THE J-PARC ACCELERATOR COMPLEX

An Operational Diagnostic Complement for Positrons at CEBAF/JLab

Characterizing Transverse Beam Dynamics at the APS Storage Ring Using a Dual-Sweep Streak Camera

CERN S PROTON SYNCHROTRON COMPLEX OPERATION TEAMS AND DIAGNOSTICS APPLICATIONS

SPEAR 3: Operations Update and Impact of Top-Off Injection

30 GHz Power Production / Beam Line

Precision measurements of beam current, position and phase for an e+e- linear collider

COMMISSIONING OF THE ALBA FAST ORBIT FEEDBACK SYSTEM

Equipment Installation, Planning, Layout, organisation and updates

P. Emma, et al. LCLS Operations Lectures

arxiv: v1 [physics.ins-det] 1 Nov 2015

Mechanical aspects, FEA validation and geometry optimization

Commissioning the TAMUTRAP RFQ cooler/buncher. E. Bennett, R. Burch, B. Fenker, M. Mehlman, D. Melconian, and P.D. Shidling

ABORT DIAGNOSTICS AND ANALYSIS DURING KEKB OPERATION

LEP Status and Performance in 2000

Beam instrumentation at the 1-MW proton J-PARC RCS

TESLA FEL-Report

AARHUS UNIVERSITET November, ASTRID2 Status. Heine Dølrath Thomsen on behalf of the ASTRID2 Team

Status of SOLARIS Arkadiusz Kisiel

Control of Intra-Bunch Vertical Motion in the SPS with GHz Bandwidth Feedback

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems

A Facility for Accelerator Physics and Test Beam Experiments

Development of an Abort Gap Monitor for High-Energy Proton Rings *

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

Recent APS Storage Ring Instrumentation Developments. Glenn Decker Advanced Photon Source Beam Diagnostics March 1, 2010

The basic parameters of the pre-injector are listed in the Table below. 100 MeV

Top-Up Experience at SPEAR3

Design Studies For The LCLS 120 Hz RF Gun Injector

Hall-B Beamline Commissioning Plan for CLAS12

Screen investigations for low energetic electron beams at PITZ

COMMISSIONING RESULTS OF BEAM DIAGNOSTICS FOR THE PETRA III LIGHT SOURCE

Challenges in Accelerator Beam Instrumentation

CONSTRUCTION AND COMMISSIONING OF BEPCII

Proceedings of the 1997 Workshop on RF Superconductivity, Abano Terme (Padova), Italy

The Elettra Storage Ring and Top-Up Operation

FINAL DESIGN OF ILC RTML EXTRACTION LINE FOR SINGLE STAGE BUNCH COMPRESSOR

S67: PRE-CYCLE & RAMP

THE ARCHITECTURE, DESIGN AND REALISATION OF THE LHC BEAM INTERLOCK SYSTEM

Development of beam-collision feedback systems for future lepton colliders. John Adams Institute for Accelerator Science, Oxford University

TRANSVERSE DAMPING AND FAST INSTABILITIES

A Fast Magnet Current Change Monitor for Machine Protection in HERA and the LHC

Beam systems without failures what can be done?

arxiv:hep-ex/ v1 27 Nov 2003

An Overview of Beam Diagnostic and Control Systems for AREAL Linac

Phase (deg) Phase (deg) Positive feedback, 317 ma. Negative feedback, 330 ma. jan2898/1638: beam pseudospectrum around 770*frev.

The PEFP 20-MeV Proton Linear Accelerator

CLIC Feasibility Demonstration at CTF3

MACHINE PROTECTION WORKSHOP REVISITED OPEN ISSUES, PROGRESS AND DECISIONS ON MAJOR TOPICS

THE ANTIPROTON DECELERATOR (AD)

FEL TEST PLAN WORKSHEET

RF PERFORMANCE AND OPERATIONAL ISSUES

Electron Clouds in the SPS: progress in the analysis of cures/mitigations measures and potential schedule of implementation J.M.

ANKA Status Report. N.Smale, A.-S. Müller, E. Huttel, M.Schuh Slides courtesy of A.-S. Müller and C.Heske.

INTRODUCTION. SLAC-PUB-8414 March 2000

Fast Orbit Feedback at the SLS. Outline

FILLING SCHEMES AND E-CLOUD CONSTRAINTS FOR 2017

Extraction/Separator Setup. Michael Spata Operations Stay Treat July 16, 2015

PEP-II longitudinal feedback and the low groupdelay. Dmitry Teytelman

SUMMARY OF THE ILC R&D AND DESIGN

Advanced Photon Source - Upgrades and Improvements

The hybrid photon detectors for the LHCb-RICH counters

Preparations for Installation, Testing and Commissioning based on Experience at CERN, SNS and Siemens

P. Adamson, Fermi National Accelerator Laboratory, Batavia, IL 60510, USA. Abstract

LCLS-II Injector Tuning Procedures. F. Zhou (SLAC) & F. Sannibale (LBNL) 2/6/2017

Test beam data analysis for the CMS CASTOR calorimeter at the LHC

The FLASH objective: SASE between 60 and 13 nm

SUMMARY OF SESSION 4 - UPGRADE SCENARIO 2

Week 0: PPS Certification and Processing. Mon Feb 11 Tue Feb 12 Wed Feb 13 Thu Feb 14 Fri Feb 15 Sat Feb 16 Sun Feb 17

PRESENT STATUS OF J-PARC

Summary report on synchronization, diagnostics and instrumentation

Transcription:

OPERATIONAL EXPERIENCE WITH CIRCULATING BEAM S. Redaelli on behalf of the LHC beam commissioning team CERN, Geneva, Switzerland Abstract Following various injection tests, the full LHC beam commissioning started on September th. Within three days of beam operation, we established stable and captured circulating beam 2 and achieved circulating beam 1 for several turns. This was made possible by a thorough preparation of all the required accelerator systems, beam instrumentation and control software, which all achieved a remarkable performance during this initial phase with pilot beams. First beam measurements of the linear machine optics were carried out and showed that the machine is well under control. The operational experience with circulating beam, the performance of the various systems and the first detailed measurement results are reviewed. INTRODUCTION The experience with LHC circulating beam was limited to about three days of operation, from Sep. th to Sep. 12th. The effective beam time was about 40 hours that were efficiently used to close the first turn for both beams and to commission circulating, captured beam 2 with decent lifetime. This was done under the light of the cameras that brought additional stress to the operation crews but that provided CERN with a worldwide visibility. During the three days of beam commissioning, the initial beam tests of most of the critical LHC accelerator systems such as RF, beam dump, beam instrumentation, magnetic model, controls, machine protection and collimators were carried out. In addition, first measurements of orbit, linear optics, momentum, aperture, beta-beating, longitudinal dynamics, magnet polarities were also performed, providing first hints of the overall machine performance. These measurements were only possible for beam 2 (B2) because the operational experience of beam 1 (B1) was limited to the beam threading and to the first turn. Clearly the meticulous preparation of the injection tests that took place before Sep. th [1] played a key role in the overall success of this initial commissioning. In this paper, the operational experience with LHC circulating beam is discussed. After reviewing the commissioning strategy, the achieved milestones and the list of performed activities, the operation of the various systems tested during the beam commissioning period are presented. A first look at the overall machine performance is given and some conclusions are drawn. Focus is put on the aspects that were not treated in detail in companion contributions of these proceedings [2, 3, 4, 6, 5]. 198 MILESTONES OF CIRCULATING BEAM COMMISSIONING Commissioning strategy The beam commissioning was carried out with single pilot bunches of 2 4 9 protons. This ensured a safe operation throughout the commissioning of circulating beam. Contrary to what happened during the sector tests, no quench was induced during this phase. Sectors 23, 34 and 45 for B1 and sectors 78 and 67 for B2 were tested with beam during previous injection tests [1]. The rest of the machine was explored for the first time starting on the morning of Sep. th. Interleaved extractions from the SPS were possible and worked reliably throughout the beam tests. The beam threading started with B1 and con- Beam losses [gy/s] -3 09:33:43-3 09:40:43-3 09:47:43-3 09:57:31-3 :08:43-3 :12:13-3 :26:13 IP2 IP3 IP4 IP5 IP6 IP7 IP8 IP1 Beam on TCSG.4R6.B1 Beam on TCLA.D6R7.B1 Beam on TCTH.4L8.B1 All collimators open (lost on 2nd turn) Beam 1 direction > Beam on TDI.4L2 Beam on TCLA.A5R3.B1 Beam on TCTH.4L5.B1 0 5 15 20 25 Longitudinal position [km] Figure 1: Beam loss patterns along the ring during the various stages of the B1 commissioning. The injected beam was stopped in all the IP s where collimators are installed, and its tajectory was optimized before exploring the subsequent sector. Vertical dashed lines show the IP positions. The full system of about 4000 monitors is shown.

Figure 2: Illustrative view of the milestones of three days of LHC beam operation. The extracted intensity for beam 1 (green) and beam 2 (yellow) as measured in TI2 and Ti8 respectively are given as a function of time. The plots show (1) the BTV screen snapshots of the first turns of B1 and B2, (2) a typical YASP trajectory acquisition, (3) first longitudinal profile and tune measurements, (4) an example of response matrix measurements, (5) the mountain range plot of the first captured beam, (6) the first on-line beta-beat measurement and (7) examples of beam current and wire scanner measurements. tinued with B2 after having established the first turn for B1. Within one shift, the first turn was achieved for both beams. Then, the commissioning proceeded for B2. The operation was interrupted on Sep. 12th due to a number of unrelated hardware failures that culminated in the Sep. 19th accident, which eventually put an end to the 2008 beam commissioning. Whenever possible, the collimators in each insertion region (IR) were closed to stop the beam and give the possibility of optimizing the trajectory steering before sending the beam into next sector(s). This has been possible for all IRs except for IR4, where no collimator is installed. This sector-by-sector steering proved to be very effective because both beams went through all sectors at the first shot with small losses. This is illustrated in Fig. 1 where the beam losses measured for B1 at the collimators in the various IP s are shown (about 4000 monitors the 27 km). After steering adjustment on the TDI, the beam 1 was then stopped in IP3, on the tertiary collimator left of IP5, on the beam dump collimators in IP6, on the collimators in IP7, on the tertiary collimators left of IP8 and left of IP1 (the latter is not shown in Fig. 1) before finally closing the first turn. Similarly, B2 was stopped in IP7, IP6, IP5, IP3, IP2 and IP1 before closing the first turn. Correspondingly, all 199 the available screens (BTV s) in the various points (injection regions, IP3, IP4, IP6, and IP7) were also inserted in the beam path and used to witness the beam passage. The beam loss monitoring (BLM) and beam position monitoring (BPM) systems were deployed for day-1 and worked reliably in asynchronous mode. When the beams reached IP1 and IP5, several shots where intentionally lost on the tertiary collimators upstream of the IP in order to provide to ATLAS and CMS the first chance to acquire beam-induced events (ALICE and LHCb had extensively done the same during the sector tests). The full static magnetic model of the LHC based on Fi- DeL [5] was used to generate injection currents for all the circuits. A full machine re-cycle was performed after a 20 hour stop caused in the night of Sep. th by a failure of the quench protection system of the circuit RB.A34. Milestones and performed activities The main milestones and the activities performed during three days of beam operation, from Sep. th until Sep. 12th, are graphically illustrated in Fig. 2. The plot of the extracted beam intensities for beam 1 (green) and

Proceedings of Chamonix 2009 workshop on LHC Performance Figure 3: Snapshots of the beam screen (BTV) acquisitions that illustrate the very first turn of B1 (left) and B2 (right). These screens are located in the injection regions of either beam and could record the image of the injected beam as well as the image of the beam after one turn, 89 μs after. beam 2 (yellow) as a function of time, as measured at the end of TI2 and TI8, is used as a background to show highlights plots of the achievements of the first exciting LHC beam commissioning phase. The main milestones can be summarized as it follows: Threading and first turn closure for both beams during the morning shift on Sep. th. Circulating, un-captured beam (300+ turns) in the evening of Sep. th. Captured beam with good lifetime (first beam circulated for more than minutes) on Sep. 11th. Figure 4: First turn of B2 as measured with YASP (top) and closed-orbit calculated as average of the first 90 turns of B2, on the evening of Sep. th (bottom). In both cases, horizontal and vertical planes are given. OPERATIONAL EXPERIENCE OF ACCELERATOR SYSTEMS The BTV screen images of the first turns achieved for B1 (left) and B2 (right) are shown in Fig. 3. These acquisitions were taken at :26 and 15:00 of Sep. th, respectively. The Aluminum screens of the injection region were The following activities were performed as integral part of left into the beam during the beam threading and, after all the beam tests that led to the aforementioned milestones: the collimators were opened, they recorded the image of measurements of optics response matrix with single the injected beam and of the same beam after 1 turn, i.e. turn acquisitions (starting on the night of Sep. th); after 89 μs. It was possible to record up to 4 turns on these screens, as it is shown in the next Section for B1. Screen detailed optics and beta-beat measurements. were then removed from the beam path to proceed with the commissioning of asynchronous BPM acquisitions establishment of circulating beam, which relied of the meaand tune measurements with BBQ system (without surements from the BPM and BLM systems. and with chirp excitation); The BPM system worked remarkably well during this commissioning phase with pilot beam [6]. The system was beam commissioning of various RF measurements only available in asynchronous mode, with auto-triggered and of the hardware needed for the beam capture; acquisitions of first turn, injection turns (up to 120) and 1 Hz closed orbit data with circulating beams. The YASP initial commissioning of beam dump system [4]; program by J. Wenninger was used to handle all these ac initial commissioning of beam instrumentation (slow quisition types. An example of first turn YASP acquisition and fast beam current measurements, wire scanners) is given in Fig. 4 (top), where the very first turn of B2 is shown. An example of the average closed-orbit over 90 beam tests with the collimators around the ring. turns, as established on the evening of Set.th with uncaptured beam, is also shown. Clearly, all the above imply that the required controls layers One of the key ingredients for a rapid establishment of for settings, measurements and analysis were correspondcirculating B2 was the early commissioning of the BBQingly deployed successfully. The importance of the sector based tune measurement system [7] because it allowed the tests to achieve this is apparent. 200 Establishment of closed-orbit almost within tolerance in the afternoon of Sep. 12th.

Proceedings of Chamonix 2009 workshop on LHC Performance Figure 6: Longitudinal beam profile of the circulating, uncaptured B2. Each vertical line represent one turn. Courtesy of RF team. Figure 5: On-line tune application with the first tune measurement performed on the un-captured beam. The commissioning of the BBQ system was done in the early stage and was used to establishing circulating B2 [7]. observation that the tunes were close to a half-integer resonance. A few tune trims to change the working point were then sufficient to achieve several tens of turns and then start the beam lifetime optimization. A snapshot of the tune measurement application that show the first tune spectrum measured over about 200 turns is given in Fig. 5. The beam lifetime of the un-captured beam was then further improved Figure 7: Mountain range graphs of the circulating B2 with with additional tune and chromaticity trims. More than 300 RF off (left) and with RF on after adjustment of RF phase turns were established in the night of Sep. th. This is iland frequency (right). The beam capture was performed lustrated by the measurements of longitudinal beam profile on the evening of Sep. 13th. After capture, the circulatfrom the wall current monitors in IP4, see Fig. 6. Later on, ing beam was kept stably in the machine for -15 minafter beam capture, the BBQ tune measurements with chirp utes without special optimization of the transverse optics excitations were also successfully commissioned with the parameters. Courtesy of RF team. circulating beam. The initial commissioning of the Inject&Dump and of the Circulate&Dump operational modes was also perity of the machine alignment, aperture, magnetic model, formed. Beam dumps after up to about 4 seconds from the setting generation, etc. It is interesting to note that the beam injection were programmed and this operational mode was that first circulated in the LHC for several minutes also exmaintained during the subsequent commissioning phases, perienced the first real emergency beam dump, caused by until stable circulating beam was established. More details a fault in the RQD.81 circuit at about 22:45 on Sep. 11th. on the beam dump tests were presented in [4]. The beam dump worked as expected and the LBDS system successfully executed and passed the external postafter an interruption of the commissioning plan due to operation checks (XPOC). a failure of the quench protection system of the circuit The set-up of circulating beams is a pre-requisite for furrb.a34, beam tests continued in the evening of Sep. 11th with the initial commissioning of the RF instrumentation ther detailed beam tests of various systems. On Sep. 12th, the initial commissioning of additional beam instrumentain IP4 and with the beam capture. This phase was driven by the RF team in SR4. After switching ON the RF, the tion such as wire scanners (see an example of acquisition in Fig. 8) and slow and fast beam current monitors [6] was RF phase and frequency were adjusted and the beam capture was achieved. This is illustrated in Fig. 7, where the started. By using the 90 turn acquisition of the injection oscillations, it was also possible to have a first on-line mea mountain range plot of the longitudinal beam profile is shown with RF OFF (left) and with RF ON after tuning surements of horizontal and vertical beta-beating for B2. A snapshot of the application is given on Fig. 9. Last but not (right). When the programmed beam dump was removed, least, the last hours of beam operation were dedicated to the the first captured beam circulated in the machine for more optimization of the closed orbit, which was brought almost than ten minutes without further adjustment of transverse within tolerance with a limited number of corrections. optics parameters. This indicated a very good overall qual201

Signal amplitude [a.u.] 0.023 0.0225 0.022 0.0215 0.021 0.0205 0.02 0.0195 0.019 σ x = 2.36 mm σ y = 2.38 mm 0.0185-0 5 Wire position [ mm ] Figure 8: First vertical wire scanner measurement with captured beam (top, ingoing and outgoing scans) and Gaussian fits of the horizontal and vertical profiles (bottom). Amplitude [a.u.] 1 0.98 0.96 0.94 0.92 0.9 0.88 0.86 0.84 0.82 BTV data 1st turn 2nd turn 3rd turn 0.8-5 -2 1 4 7 x [ mm ] Figure : Profiles of the three first turns of B1 recorded on the Ti screen BTVSI-C5L2-B1 (top) and Gaussian fits of the projected horizontal profiles. Similar fits have been performed also for the vertical plane. The estimated beam size are approximately σ x =0.58 mm and σ y =0.33 mm. Figure 9: First on-line beta-beat measurement available on Sep. 12th. The 90-turn injection oscillations was sufficient for a estimate. Courtesy of R. Tomàs. OVERALL MACHINE PERFORMANCE After having had a look at the various systems available from the LHC control during the first days of beam commissioning, the main machine parameters from detailed measurements are reviewed. A quick look at beam 1 As already discussed, the commissioning of B1 was only limited to the threading around the ring and the closure of 202 the first turn. Beyond what was measured during the various sector tests [1], no detailed measurements were performed. In Fig. the profiles of the first tree turns of B1, as measured with the Titanium screen BTVSI-C5L2-B1 in IP2 are shown. The beam sizes for the projected beam profiles can be calculated with Gaussian fits, as shown for the horizontal plane in the bottom part of Fig.. The ratio σ x /σ y calculated from the nominal optics is 2.7 whereas from the fits one gets 2.5 (taking into account a factor 1.8-2 difference on the emittances, ɛ x 2ɛ x, as indicated by transfer line screen matching). Tune, coupling, chromaticity and beta-beat for beam 2 The integer tunes in both planes were measured with the trajectory data from the injection oscillations. The results are illustrated in Fig. 11. The nominal values were achieved in both planes without need of correction. The summary of the best estimates of linear optics parameters for beam 2 can be summarized as it follows (the two values quoted are from references [7] and [8], respectively): Tunes: Q x =0.3803 0.3015, Q y =0.3066 0.2441 (Nominal values: Q x =0.28, Q y =0.31).

Figure 11: Integer tunes calculated for B2 with YASP. The nominal values Q x =64and Q y =59were achieved. Coupling (closest tune approach): C =0.07 0.06 Figure 12: Best B2 closed-orbit as established on Friday 12th. The RMS orbit deviation excluding a few suspicious monitors is about 1.6 mm (horizontal) and 1.3 mm (vertical), compatible with the expected tolerance from beam dynamics. Faulty monitors (red) are disregarded for the RMS calculation. Chromaticity Q x Q y 30 units. The values of Q x and Q y listed above are calculated with the BBQ system on the circulating beam [7] or with Fourier analysis of the injection oscillations [8]. The difference between the tunes in the two planes are consistent with the coupling measurements. Throughout the days of beam tests it has not been possible to consistently reproduce tune measurements. This aspect is not fully understood. A possible problem with the reproducibility of trim quadrupole field [5] is being investigated. The coupling is within the range that can be corrected without requiring special injection optics with separated tunes. On the other hand, there was not the possibility to attempt coupling corrections. No dedicated tune measurements were carried out for different beam momenta. The quoted chromaticity estimates were inferred from preliminary measurements of synchrotron side bands around the tune peak [7]. Updated estimates of the beta-beat have been calculated off-line with a much improved statistic compared from the initial on-line estimates as in Fig. 9 [8, 3]. The horizontal beating is typically below 30% with isolated peaks up to 40%, to be compared with the tolerance of 20% [3]. This indicates that the optics is very well under control. For the vertical plane, errors up to 0% were measured. The analysis carried out in [3] has identified potential polarity errors that could explain this discrepancy. They will be corrected for the 2009 operation. Closed orbit and aperture for beam 2 The best reference closed-orbit, established after beam capture, is shown in Fig. 12. The horizontal RMS orbit was 1.6 mm and the vertical was 1.3 mm. This levels were achieved by using a limited number of correctors. The analysis of the residual orbit suggests that by using more correctors one could easily improved the RMS errors by a factor 3-5 [9]. Note that red bars in Fig. 12 indicate faulty monitors or monitors with known calibration errors that have been disregarded for the calculation of the RMS. Figure 13 shows the distribution of monitor readings for the first closed-orbit established for un-captured beam (top graphs, corresponding to the data of Fig. 4) as well as for the best orbit of Fig. 12 (bottom graphs). The distribution is 203 Figure 13: Distribution of horizontal (left graphs) and vertical (right) BPM readings for the first closed-orbit established on the night of Sep. th (top) and for the best closed-orbit achieved on Sep. 12th (bottom). The read lines indicate the ±4 mm LHC tolerance in the arcs. The horizontal orbit shows a negative offset of 1.2 mm, corresponding to an energy error of about 3. compared with the LHC arc tolerance of ±4 mm. It is seen that after corrections only a limited number of monitors exceeds the tolerances and the distributions are narrower. Note that the orbit in the insertion regions where the two beams share the same vacuum pipe were not optimized. It is also noted that the horizontal offset for the captured beam has an offset of about -1.2 mm due to the energy mismatch discussed in the next Section. It has not been possible to perform dedicated aperture measurements in the LHC ring after establishing the circulating beam. The aperture of only two arcs 23 for B1 and 78 for B2 was systematically measured during the sector tests by exciting free oscillations of the injected beam trajectory, with varying oscillation phases and amplitudes [1]. A machine aperture very close to nominal was measured.

Figure 14: Horizontal (top) and vertical (bottom) trajectories as measured for B2 during matrix response measurements, compared with the nominal mechanical aperture. All monitor readings are shown. CONCLUSIONS In this paper the operational experience with LHC circulating beam has been reviewed. The achieved milestones, the activities performed and of the tools available during three days of LHC beam commissioning have been reviewed. It has been shown that most of the key accelerator systems of the LHC have been deployed and have successfully been used during the Sep. th event, which was a great achievement for CERN in many respects. An impressive amount of useful information could be inferred from the limited beam commissioning experience, thanks to the availability from day-1 of a large number of sophisticated control applications and analysis tools. A selection of results from many beam based measurements have been presented. It is fair to conclude that, even though some localized problems have been identified, the overall machine performance was impressive. This indicates a remarkable good quality of machine alignment, magnetic model, magnets, settings management generation. These achievements were made possible by the great performance of the involved accelerator systems that preformed as expected during the initial tests with pilot beams. On the other hand, it is important to realise that the 2008 beam experience only covered a minor fraction of the commissioning steps required to achieve physics production at the LHC and the work ahead should not be underestimated. Figure 15: Sector-by-sector momentum error for B1 (blue) and B2 (red) as calculated from the first turn (FT) and from the closed-orbit (CO) measurements. CO estimates for B2 refer to the best achieved orbit as in Fig. 12. Courtesy of J. Wenninger. For the circulating B2, an attempt was made to estimate the available aperture by looking at all the different beam trajectories measured during the optics response matrix measurements. This is shown in Fig. 14. The phase coverage of these oscillations is not complete and hence these cannot be considered as systematic measurements. On the other hand, oscillations of about ± mm were routinely excited in the full ring without apparent beam loss problems. Radio-frequency settings and beam 2 momentum The LHC frequency was set to 400788963 Hz, i.e. 229 Hz higher than the nominal. This is consistent with the observed average energy error of about - units of the dipole field component, see Fig.15. The synchrotron frequency calculated from a peak detector Schottky spectrum [] is about 60 Hz to be compared with the expected 66 Hz. 204 ACKNOWLEDGMENTS As mentioned in the text, the good results presented here were only possible thanks to the work of many people that worked on the LHC during the last two decades. This contribution has been prepared on behalf of the LHC beam commissioning team. In particular, T. Bohl, M. Lamont, R. Steinhagen, R. Tomàs and J. Wenninger are specially thanked for having provided material for this paper and for the presentation. The many discussions with and inputs from G. Arduini, R. Bailey, E. Bravin, A. Butterworth, E. Ciapala, S. Fartoukh, M. Giovannozzi, R. Jones, W. Venturini and many others are also kindly acknowledged. The colleagues from OP and the shift crews of the LHC injection complex, which delivered reliably the required LHC beams during the beam tests, are also sincerely thanked. REFERENCES [1] M. Lamont et al., LHC-Performance-Note-001 (2008). [2] V. Kain, these proceedings. [3] R. Tomàs, these proceedings. [4] B. Goddard, these proceedings. [5] L. Bottura, these proceedings. [6] R. Jones, these proceedings. [7] R. Steinhagen et al., LHC-Performance-Note-007 (2009). [8] R. Tomàs et al., LHC-Performance-Note-008 (2009). [9] J. Wenninger, private communication. [] T. Bohl, private communication.