Beam Loss Detection for MPS at FRIB

Similar documents
Linac 4 Instrumentation K.Hanke CERN

Jefferson Lab Experience with Beam Halo, Beam Loss, etc.

Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi)

The PEFP 20-MeV Proton Linear Accelerator

Welcome and FRIB Project Status. FRIB Highlights and Plan Ahead

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

Proton Engineering Frontier Project

The ESS Accelerator. For Norwegian Industry and Research. Oslo, 24 Sept Håkan Danared Deputy Head Accelerator Division Group Leader Beam Physics

Design of the linear accelerator for the MYRRHA project

OPERATIONAL EXPERIENCE AT J-PARC

A SQUID-BASED BEAM CURRENT MONITOR FOR FAIR / CRYRING

Workshop on Accelerator Operations August 6-10, 2012 Glen D. Johns Accelerator Operations Manager

DARK CURRENT IN SUPERCONDUCTING RF PHOTOINJECTORS MEASUREMENTS AND MITIGATION

DESIGN OF 1.2-GEV SCL AS NEW INJECTOR FOR THE BNL AGS*

Digital BPMs and Orbit Feedback Systems

5 Project Costs and Schedule

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

LHC Beam Instrumentation Further Discussion

COMMISSIONING SCENARIOS FOR THE J-PARC ACCELERATOR COMPLEX

Low Level RF for PIP-II. Jonathan Edelen LLRF 2017 Workshop (Barcelona) 16 Oct 2017

Beam instrumentation at the 1-MW proton J-PARC RCS

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

HIGH POWER BEAM DUMP AND TARGET / ACCELERATOR INTERFACE PROCEDURES *

LIGHT PROTON THERAPY PROJECT

TWO BUNCHES WITH NS-SEPARATION WITH LCLS*

The Construction Status of CSNS Linac

RUNNING EXPERIENCE OF FZD SRF PHOTOINJECTOR

Preparations for Installation, Testing and Commissioning based on Experience at CERN, SNS and Siemens

Hall-B Beamline Commissioning Plan for CLAS12

ESS: The Machine. Bucharest, 24 April Håkan Danared Deputy Head Accelerator Division. H. Danared Industry & Partner Days Bucharest Page 1

A Fifteen Year Perspective on the Design and Performance of the SNS Accelerator

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY

Undulator Protection for FLASH and for the European XFEL

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

The FAIR plinac RF Systems

ABORT DIAGNOSTICS AND ANALYSIS DURING KEKB OPERATION

The Beam Test Facility at the SNS

RF plans for ESS. Morten Jensen. ESLS-RF 2013 Berlin

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

Radiation Safety System for Stanford Synchrotron Radiation Laboratory*

RF Upgrades & Experience At JLab. Rick Nelson

The Elettra Storage Ring and Top-Up Operation

Particle Beam Production - A Synchrotron-Based System - Prof. Dr. Thomas Haberer Scientific-technical Director Heidelberg Iontherapy Center

Dark current and multipacting trajectories simulations for the RF Photo Gun at PITZ

RADIATION SAFETY SYSTEM OF THE B-FACTORY AT THE STANFORD LINEAR ACCELERATOR CENTER

High Rep Rate Guns: FZD Superconducting RF Photogun

INFN School on Electron Accelerators. RF Power Sources and Distribution

arxiv: v1 [physics.ins-det] 1 Nov 2015

ILC-LNF TECHNICAL NOTE

SRS and ERLP developments. Andrew moss

Upgrading LHC Luminosity

High Brightness Injector Development and ERL Planning at Cornell. Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics

LLRF at SSRF. Yubin Zhao

Upgrade of CEBAF to 12 GeV

Beam Losses During LCLS Injector Phase-1 1 Operation

Detailed Design Report

Electron linac photo-fission driver for rare isotope program at TRIUMF

Recent APS Storage Ring Instrumentation Developments. Glenn Decker Advanced Photon Source Beam Diagnostics March 1, 2010

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

Commissioning the TAMUTRAP RFQ cooler/buncher. E. Bennett, R. Burch, B. Fenker, M. Mehlman, D. Melconian, and P.D. Shidling

CERN S PROTON SYNCHROTRON COMPLEX OPERATION TEAMS AND DIAGNOSTICS APPLICATIONS

A HIGH-POWER SUPERCONDUCTING H - LINAC (SPL) AT CERN

PRESENT STATUS OF J-PARC

North Damping Ring RF

BEAM DYNAMICS AND EXPERIMENT OF CPHS LINAC *

SUMMARY OF THE ILC R&D AND DESIGN

BEAM DIAGNOSTICS IN THE CNAO INJECTION LINES COMMISSIONING

Photo cathode RF gun -

Current status of XFEL/SPring-8 project and SCSS test accelerator

The sc cw-linac project TASCA2012, S. Mickat, LINAC

Simulations on Beam Monitor Systems for Longitudinal Feedback Schemes at FLASH.

New Filling Pattern for SLS-FEMTO

Beamline improvement during g2p experiment. Pengjia Zhu

SPEAR 3: Operations Update and Impact of Top-Off Injection

Polarized Source Development Run Results

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

HIGH-INTENSITY PROTON BEAMS AT CERN AND THE SPL STUDY

Development of New Carbon Therapy Facility and Future Plan of HIMAC

ARIEL e-linac Machine Protection System Requirements

Summary report on synchronization, diagnostics and instrumentation

Bunch-by-bunch feedback and LLRF at ELSA

Parity Quality Beam (PQB) Study

Technology Challenges for SRF Guns as ERL Sources in View of Rossendorf work

P. Adamson, Fermi National Accelerator Laboratory, Batavia, IL 60510, USA. Abstract

CEBAF Accelerator Update. Michael Tiefenback CASA Accelerator Physics Experimental Liaison June 14, 2017

III. Proton-therapytherapy. Rome SB - 3/5 1

The 2011 LHC Run - Lessons in Beam Diagnostics

Progress of Beam Instrumentation in J-PARC Linac

THE OPERATION EXPERIENCE AT KOMAC*

A Cathode Development Cornell Cultera This scope includes all labor and purchases required produce photocathodes required by CBETA.

DOSE DELIVERY SYSTEM OF THE VARIAN PROBEAM SYSTEM WITH CONTINUOUS BEAM

30 GHz Power Production / Beam Line

Proceedings of the 1997 Workshop on RF Superconductivity, Abano Terme (Padova), Italy

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems

Status of the SNS Linac: An Overview N. Holtkamp for the SNS Collaboration ORNL, Oak Ridge, TN 37830, USA

Karin Rathsman, Håkan Danared and Rihua Zeng. Report from RF Power Source Workshop

Challenges in Accelerator Beam Instrumentation

PEP II Design Outline

The FLASH objective: SASE between 60 and 13 nm

The basic parameters of the pre-injector are listed in the Table below. 100 MeV

Transcription:

Beam Loss Detection for MPS at FRIB Zhengzheng Liu Beam Diagnostics Physicist This material is based upon work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC0000661. Michigan State University designs and establishes FRIB as a DOE Office of Science National User Facility in support of the mission of the Office of Nuclear Physics.

Beam loss induced damage Outline Layered requirement for beam loss detection Diagnostic devices for beam loss detection Radiation detectors Differential beam current monitor (DBCM) Differential beam position monitor (DBPM) Halo monitor ring (HMR) Differential current monitoring for MPS Early-operation / commissioning planning of loss detection Beam loss monitoring system for commissioning Slide 2

Fast Beam Loss Induces Thermal Damage Deposited Energy Matters! LS1 LS2 LS3 20 MeV/u 8.4 pma 40 kw 35 ms 1.4 J 149 MeV/u 8.4 pma 297 kw 60 ms 17.8 J The worst case (uranium beam ~20MeV/u): may damage a SS bellow in less than 40 µs Slide 3

Errant Beam Loss Induces SRF Degradation Example: Errant beam mitigation at SNS* Errant beam: off-energy beam generated and transported to the downstream Errant beam hits cavity surface, desorbs gas/particulates, increases possibilities of arcing/discharge and leads to degradation e.g. two coupler windows leaks in 6c and 20d presumably from 2009 Historically most degradation has been recovered by thermal cycling of cryomodules MPS detects errant condition from SNS RF system or BLM and trigger MPS in 15µs <10% of BLM trips were due to ion source/lebt Most ion sources induces BLM trips during the first week of new source installation >90% of BLM trips were due to warm LINAC RF faults Adequate BLM and shorter beam stop time is wanted to reduce the degradation Odd beam from front end Quote from S. Kim s talk on 3/3/2014 cryomodule workshop Slide 4

Activation from 1 W/m Slow Losses Is Much Lower Than the Hand-on Maintenance Limit The ratios of dose rates from heavy-ion beams to the dose rate from the proton beam are very nearly the same as the ratios of the produced neutrons* Scale the residual dose rate for heavy ions relative to the 1 W/m, 1GeV proton beam loss. In the case of slow losses, FRIB ions produce low activations Ion (Specific Energy in MeV/u) Prompt Neutron Fluxes from 1 W/m loss relative to that from proton beam [%] Residual Dose Rate [mrem/h] H (1000) 100.0 98.9 238 U (200) 1.5 1.5 18 O (300) 12.2 12.1 * R. Ronningen Studies of limits on uncontrolled heavy-ion beam losses for allowing hands-on maintenance Slide 5

Slow Beam Loss Adds Cryogenic Load The present slow loss detection criterion has been set to 1 W/m, corresponding to 10-5 ~ 10-6 fractional power loss per meter An average 1 W/m beam loss adds ~250 W heat load to the cryoplant, which is 10% of the total 2 K design load The design margin for cryoplant heat load is limited, ~100% Will the SRF cavity experience long-term degradation from the lowlevel chronic beam loss? The current slow loss threshold will not trigger FPS trips. It is an optional detection criteria for commissioning/tuning Slide 6

Multi-Layer Detection Requirement for FPS The criterion for fast beam loss MPS is to mitigate the beam energy deposition for each event Adopt a lost beam energy limit, based on damage thresholds 20 kw x 35 µs = 1.4 J Example design detection/mitigation schema for Fast MPS (FPS) Threshold of full current Beam detection time (ms) Beam mitigation time (ms) Maximum beam energy loss 1 100% 15 35 20 kw x 100% x 35 ms = 1.4 J 2 10% 330 350 20 kw x 10% x 350 ms = 1.4 J 2 1% 3480 3500 20 kw x 1% x 3500 ms = 1.4 J Beam current from ion source fluctuates on order ~10% over tens of ms Monitoring at fluctuation thresholds below ~10% will require feed-forward from the injector current monitoring system Slide 7

Radiation Detectors Traditional Radiation Detectors include Ion Chamber and Neutron Detector. However, they are not sufficient for FRIB superconducting linac segments because Cavity X-ray background can be several rad/hr Radiation cross talk from LS3 overshadows LS1 and LS2 Radiation detectors are still useful at high power deposition areas and for tuning purpose Gamma intensity from LS3 decreases to 7.5% for a line loss and 0.6% for a point loss, it is still larger than LS1 loss signal. Neutron radiation is more penetrating than gamma and therefore its cross talk effect is even worse. Slide 8

Design Example of DBCM (Bergoz BCM) Example: LS1 differential currents Current difference measurements are performed in <10 µs with a current resolution better than 4 µa (~1% of full beam current) Beamline Segment LEBT 1.3 RFQ 0.7 MEBT 0.7 LS1 2.4 FS1 1.4 LS2 1.2 FS2 0.3 LS3 and BDS 0.9 Time of flight (µs) Slide 9

Differential Current Monitoring by BPM Pair Experiment was set up at ReA3 with Fermilab BPM receivers Measures second harmonic 161 MHz 81 db gain pre-amp; 1.32 db cable loss Effective BW ~37kHz (ԏ~4.3µs) For 37 khz, the calculated intensity RMS resolution (std) is 126 na From experiment, the RMS intensity resolution (std) for single BPM is measured as 67-106 na for 204800 samples, assuming beam is at the center. The differential intensity resolution is ~140 na FRIB BPM intensity resolution is comparable with ReA3 BPM, and it features fast evaluation (~15µs) However, the BPM resolution is very sensitive to beam position and beam velocity. Calibration is necessary FRIB BPM intensity resolution rms bunch lgth beta MeV/u rms deg mm rfq out 0.03275 0.5 2.7 0.9 ls1 in 0.03275 0.5 1.8 0.6 ls1 out 0.18647 16.63 0.9 1.7 ls2 out 0.50624 148.63 0.6 3.1 ls3 out 0.56985 202.06 4.7 27.7 target 0.56985 202.06 7.5 44.2 na-rms 323 322 763 2023 2306 2355 Linear and Polynomial fit for BPM intensity Slide 10

Halo Monitor Ring (HMR) The halo ring monitor is a niobium ring designed to intercept ions in the halo of the beam that are likely to be lost farther downstream It has high sensitivity (~0.1nA) for integrated small signal and fast response time (~10 µs) for large signal Drawback: Its aperture is hard to determine by simulation. Have to use large aperture and may skip 1 st phase commissioning to avoid possible limitation HMR measurement at NSCL with 18 O 3+ at 11 MeV/u Slide 11

Beam Pipe Temperature Sensor Inside Cryomodule There are two hot spots of potential beam loss inside the cryomodule, the drift space before and after solenoid We consider a localized slow loss on beam pipe, 0.05 W on a 1cm 2 spot, the resulted rising time at the hot spot is ~2 seconds / 0.1 K. After 10 second, the temperature is 5 K Slide 12

Differential Current Monitoring for FPS Charge Stripper Beam Current Monitoring based on ACCTs Beam Current Monitoring based on BPMs Differential current monitoring is mainly for large beam losses Current from ion source fluctuates at 10% in a time scale of tens of ms, hence the differential current monitoring is less effective for small losses BPM and BCM differential current measurement should be cross-calibrated Slide 13

Beam Inhibit Devices for Machine Protection MPS trips trigger beam abort within 35 µs Ion sources» Removal of extraction HV ceases beam production LEBT E-bends» Removal of HV prevents low energy beam to further acceleration downstream. After abort up to 10 µs of beam remains in pipe CW operation continuously generates beam Downstream BID may be required to further limit unplanned beam energy deposition Front End Ion sources E-bends RFQ Slide 14

Commissioning Approach For initial pulsed beam (50 eµa, 50 µs, <1 Hz) Total lost beam energy deposition is below damage threshold May not require FPS in this mode For initial, low power CW beam (<340 ena K 17+, 344 W full power) Requires beam mitigation in ~50 ms Conductive thermal flux may alleviate the energy deposition limit Fast beam loss monitoring could be performed by differential beam current measurements Demonstrate FPS beam mitigation at fastest time scales Slow loss beam monitoring will be calibrated and commissioned Demonstrate detection limits, response time, crosstalk Slide 15

Operations Approach Fast protection systems will be commissioned at necessary response times Slow loss MPS can serve any mode once it has been established Beam loss thresholds and faults will require study for various operating modes and ion species Low power CW operation (mode O2) may require dedicated Faraday cups in warm sections to calibrate beam current monitors Dynamic Ramping is a mode of special interest Quickly evolving pulse length and duty cycle over time scale of seconds Data acquisition may require reconfiguration from gated to continuous mode Slide 16

Beam Loss Monitoring Network for Commissioning Slow response time Beam Pipe Commissioning segment by segment Temperature Sensor 2 K/4 K header heater PS current Novel techniques? Si/CVD diamond detectors LHe ionization detectors Ion chambers Neutron detectors Slide 17