NERC Reliability Standard PRC-024 Generator Frequency and Voltage Protective Relay Settings

Similar documents
A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

Notes Generator Verification SDT Project

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

VAR Generator Operation for Maintaining Network Voltage Schedules

Standard Development Timeline

Standard IRO Reliability Coordination Responsibilities and Authorities

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

Definitions. Common Corridor:

10/13/2011 Planning Coordination Committee. Standards

BAL Real Power Balancing Control Performance Standard Background Document

Phase 2 of System Protection Coordination (Requirement revisions to PRC ) Hydro Québec TransÉnergie

BAL Real Power Balancing Control Performance Standard Background Document

Primary Frequency Response Ancillary Service Market Designs

0.1. Outage Management Process Summary

Toronto Hydro - Electric System

Unofficial Comment Form Project Establish and Communicate System Operating Limits (SOL and SOL Exceedance Definitions)

I. History of Time Error Correction and Reduced Reliance On Manual TEC Today

Simulation of DFIG and FSIG wind farms in. MATLAB SimPowerSystems. Industrial Electrical Engineering and Automation.

Form C: Type Test Verification Report

BE1-81O/U Frequency Protection. Washington State University Hands-On Relay School.

Form C: Type Test Verification Report

GC0100/101/102 Code Administrator Consultation Responses. Rob Wilson. Grid Code Panel 8 th Feb 2018

Expert Workgroup on Fast Fault Current Injection stage 1 Terms of Reference

Frequency Response Initiative Generator Event Survey. NERC Resources Subcommittee North American Generator Forum December 8, 2016

WESTERN ELECTRICITY COORDINATING COUNCIL. WECC Interchange Tool Overview

Instruction manual. DALI Gateway art Installation manual

Improved Synchronization System for Thermal Power Station

ECEN 667 Power System Stability Lecture 5: Transient Stability Intro

BPA s Network Open Season

Medium and High Voltage Circuit Breakers Characteristic Time Quantities of the Circuit Breaker with Applications

Electronic M.O.P Card. Instruction Manual Model D

Real Time Monitoring for SMART Grid Initiatives Synchronized Measurement & Analysis in Real Time SMART program by

Understanding VFD Allen Bradley Power Flex 4M Variable Frequency Drive. nfi

Primex Wireless, Inc. July, Wells Street Lake Geneva, WI

Hornsdale 2 Wind Farm. FCAS Capability Test Plan

SEMI F47 Compliance Certificate KEPCO Low-Power Power Supplies EPRI PEAC Corporation PQ Star sm Test Program. Certification Date: July 23, 2003

BE3-GPR GENERATOR PROTECTIVE RELAY

-Technical Specifications-

REFURBISHMENT OF SECONDARY SYSTEMS IN HIGH VOLTAGE SUBSTATIONS LESSONS LEARNED IN VENEZUELA

medlab One Channel ECG OEM Module EG 01000

Dynamic Performance Requirements for Phasor Meausrement Units

THE ASTRO LINE SERIES GEMINI 5200 INSTRUCTION MANUAL

FINAL REPORT LOAD SHEDDING IN TASMANIA ON 20 DECEMBER 2016 REVIEWABLE OPERATING INCIDENT REPORT FOR THE NATIONAL ELECTRICITY MARKET

Understanding the Limitations of Replaying Relay-Created COMTRADE Event Files Through Microprocessor-Based Relays

HYL-080D1750G358. Constant current LED driver DALI Dimmable. LED Driver. Product description. Benefits. Interfaces.

Self Excited Automatic Voltage Regulator For Generator Compatible with Marathon SE350* Operation Manual

CEA Standard. Standard Definition TV Analog Component Video Interface CEA D R-2012

english SGC inverter series hf transformer input voltage up to 800 V touch screen built-in data loggers

Frequency Response and Standard background Overview of BAL-003-1

RFIs AND RESPONSES; ANSWERS ARE IN RED.

Grid feeding monitoring according to VDE-AR-N 4105 and BDEW CM-UFD.M31

Mitigation of Cascading Outages and Prevention of Blackouts:System-Wide Corrective Control

ENA Engineering Recommendation G83 Issue

South Australian Energy Transformation

SPECIAL SPECIFICATION :1 Video (De) Mux with Data Channel

TriLIN Program Utility TPU_ TriLIN Programming Manual

Term Sheet Reflecting the Agreement of the ACCESS Committee Regarding In-Flight Entertainment November 21, 2016

Transient Stability Events & Actions

ENGINEERING COMMITTEE

CITY OF ISSAQUAH CABLE COMMISSION

EA350. Generator Automatic Voltage Regulator Operation Manual

SECTION MEDIUM VOLTAGE CABLE INSTALLATION. 1. Section Underground Ducts and Manholes.

Henkel Installation Handbook LINEGUARD 2001

American National Standard for Lamp Ballasts High Frequency Fluorescent Lamp Ballasts

ELIGIBLE INTERMITTENT RESOURCES PROTOCOL

Soft starter, 66 A, V AC, Us= 24 V DC, with control unit, Frame size N. Function Soft starter for three-phase loads, with control unit

multi-function meters

Annexes to Realisation Agreement

Automatic Under-Frequency Load Shedding (AUFLS) Technical Report

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 872 LIGHT EMITTING DIODE TRAFFIC SIGNAL LAMP UNITS JULY 19, 2002

HYL-035D0850G103. Constant current LED driver DALI Dimmable. LED Driver. Product description. Benefits. Interfaces.

Industriefunkuhren. Technical Manual. IRIG-B Generator-Module for analogue / digital Signals of Type: IRIG-B / IEEE C / AFNOR NF S87-500

DATA SHEET. Synchronisers, FAS-113DG ANSI code 25

Recommended Land Pattern: [mm]

EC456 Power System Protection Lab #1 Overcurrent Protection Relay

Series CT7N Bimetallic Overload Relays

AGENDA Cable TV Commission

OPERATING MANUAL. DMX / DSI / DALI Dekoder 3004B-H Mk2

SINAMICS G130 / G150. Line harmonics filter. Operating Instructions 05/2010 SINAMICS

Recommended Land Pattern: [mm]

FCPM-6000RC. Mini-Circuits P.O. Box , Brooklyn, NY (718)

Load Frequency Control Structure for Ireland and Northern Ireland

FCP Project Summary report

Operating Instructions 07/2007 Edition. SINAMICS G130/G150 Line harmonics filter. sinamics

LED MODULES READYLINE DL

User Manual CC DC 24 V 5A. Universal Control Unit UC-1-E. General Information SET. Universal Control Unit UC-1 Of Central Lubrication PAUSE CONTACT

Catalogue Ignitors and power switches for HID

EA63-7D. Generator Automatic Voltage Regulator Operation Manual. Self Excited Automatic Voltage Regulator

Model Number Structure

DLP200M 2 Relay Module for Heating and Cooling Plants

Passive DVI Extenders Over single Cat5/6/7 AT-DVI60SRS

Special Specification 6293 Adaptive Traffic Signal Control System

CURRENT INJECTION RELAY TESTER CR-100. ( Code P60212 (770081) ) INSTRUCTIONS MANUAL ( M / 05A ) (c) CIRCUTOR S.A.

This Chapter does not apply to applications and decisions on, development on land reserved in corridor maps.

Children cannot always recognize potential hazards properly. This 5.1 system is not designed for operation in a heavy industry environment.

ICTE TLR 5 Investigation Report Flowgate (West Memphis Xmfr 161/500kv ftlo San Souci Shelby 500kv) TLR Level 5: June 20, 2011 Report Issued:

ALTERNATIVE BROADCAST INSPECTION PROGRAM

NVLAP LAB CODE:

NVLAP LAB CODE:

For applications from 0.25 to 5 HP, the MD60 is a simple AC Microdrive that can be panel mounted as well as wall or machine mounted.

Transcription:

NERC Reliability Standard PRC-024 024-1 Generator Frequency and Voltage Protective Relay Settings Rick Terrill Luminant Power Generation Compliance NERC Standards Drafting Team Member

Reliability Standard PRC-024-1 Title: Generator Frequency and Voltage Protective Relay Settings Purpose: Ensure that generator frequency and voltage protective relays 1 are set to support transmission system stability during voltage and frequency excursions. 1 Includes voltage and frequency protective functions for discrete relays, multi-function protective devices, voltage regulators, etc.

PRC-024-1 Technical Requirements R1: Frequency Relay Setting R2: Voltage Relay Setting R3: Relay Setting Changes R4: Written Request for Settings R5: Existing Unit Exceptions R6: Questions on Limitations

Applicability GENERATOR OWNERS WITH INSTALLED VOLTAGE or FREQUENCY PROTECTIVE RELAYS and UNITS > 20 MVA or EACH UNIT WHERE PLANT TOTAL MVA > 75 MVA

Effective Dates 1 ST Day of 1 ST Calendar Quarter After Applicable Regulatory Approval YEAR 1 YEAR 2 YEAR 3 33% of GO units compliant 66% of GO units compliant 100% of GO units compliant

R1: Frequency Relay Setting Comparison of Turbine Capability to PRC-024 Criteria 64 63 62 FREQUENCY (Hz) NO TRIP ZONE No Trip Zone 0.1 1 10 100 1000 10000 Time (sec) 65 64 63 62 61 60 59 Turb A Turb B Turb C Turb D Turb E PRC-024 58 57 61 OFF NOMINAL FREQUENCY CAPABILITY CURVE 60 59 58 57 56 55 Frequency (Hz) NOTE: Times shown are relay setting times, not elapsed times. 56 55 0.01 0.1 1 10 100 1000 10000 TIME (sec)

Requirement R1 and Measure M1 R1. Each Generator Owner shall set installed generator frequency protective relaying not to trip during the following frequencyrelated operating conditions unless the Generator Owner s unit has an exception in accordance with Requirement R5: (Violation Risk Factors: High - Units 500 MVA; Medium - Units >100 MVA and <500 MVA; Lower - Units 100 MVA) (Time Horizon Operations Planning) R1.1 When operating within a frequency range of 59.5 Hz to 60.5 Hz, inclusive. R1.2 During the off-normal frequency excursions specified in PRC-024-1 Attachment 1. R1.3 Instantaneous underfrequency relay trip setting shall be set no higher than 57.8 Hz. R1.4 Instantaneous overfrequency relay trip settings shall be set no lower than 62.2 Hz. M1. Each Generator Owner shall have evidence such as setting sheets, calibration sheets, or other documentation, that generator frequency protective relays have been set in accordance with Requirement R1.

R2: Voltage Relay Setting Voltage Ride-Through Time Duration Curves 1.4 1.3 1.2 1.1 1.0 0.9 NO TRIP ZONE POI Voltage (PU) 0.8 Overlay? 0.7 0.6 0.5 0.4 0.3 0.2 NOTE: Times shown are relay setting times, not elapsed times. 0.1 0.0-1.0 0.0 1.0 2.0 3.0 4.0 Time (seconds) High Voltage Duration Low Voltage Duration

Requirement R2 and Measure M2 R2. Each Generator Owner shall set installed generator over and under voltage (including volts per hertz relays evaluated at nominal frequency) protective relays not to trip during the steady-state and voltage-related operating conditions as follows unless the Generator Owner s unit has an exception in accordance with Requirement R5 of this standard: (Violation Risk Factors: High - Units 500 MVA; Medium - Units >100 MVA and <500 MVA; Lower - Units 100 MVA) (Time Horizon Operations Planning) R2.1 When operating within 95% to 105% of rated generator terminal voltage. R2.2 During the transient voltage excursions measured at the point of interconnection to the Bulk Electric System as specified in PRC- 024-1 Attachment 2. The following generator protective relaying settings are acceptable: R2.2.1 For three-phase transmission system Zone 1 faults with Normal Clearing, relaying may be set based on actual fault clearing times, but not greater than 9 cycles. R2.2.2 Relaying may be set to meet a shorter voltage ride through duration curve as specified by the Transmission Planner based on the location specific voltage recovery characteristics. R2.2.3 Relaying may be set to trip a generator after fault initiation if this action is intended as part of a special protection scheme (SPS) or remedial action scheme (RAS). R2.2.4 Relaying may be set to trip a generator if clearing a system fault necessitates disconnecting the generator. M2. Each Generator Owner shall have evidence such as setting sheets, voltage-time curves, calibration sheets, coordination plots or dynamic simulation studies, that generator voltage protective relays have been set in accordance with Requirement R2.

R3: Relay Setting Changes GO changes settings of Frequency or Voltage Relays in R1 or R2 30 DAY MAX GO provides settings to RC, PC, TP, & TOP

Requirement R3 and Measure M3 R3. Each Generator Owner shall provide to the Reliability Coordinators, Planning Coordinators, Transmission Operators and Transmission Planners (that monitor or model the associated unit) its generator protection trip settings as specified by Requirement R1 and Requirement R2 within 30 calendar days of any change to those trip settings. M3. Each Generator Owner shall have evidence such as dated e-mails, mail receipts or other documentation that generator protective relay settings changes have been communicated to the entities listed in Requirement R3. (Violation Risk Factor Lower) (Time Horizon Operations Planning)

R4: Written Request for Settings RC, PC, TP, or TOP request settings of Frequency or Voltage Relays in R1 or R2 30 DAY MAX GO provides settings to RC, PC, TP, & TOP

Requirement R4 and Measure M4 R4.Each Generator Owner shall provide its affected Reliability Coordinator, Planning Coordinator, Transmission Operator and Transmission Planner (that monitor or model the associated unit), its generator protection trip settings as specified by Requirement R1 and Requirement R2 within 30 calendar days of a written request for the data. M4.Each Generator Owner shall have evidence such as dated e-mails, mail receipts, request received or other documentation that generator protective relay settings have been communicated to the entities listed in Requirement R4. (Violation Risk Factor Lower) (Time Horizon Operations Planning)

R5: Existing Unit Exceptions Manufacturer Limits Warranty Related Insurance Agreements Engineering Analysis Other? GO discovers equipment limitation 30 DAY MAX GO provides documentation to RC, PC, TP, & TOP

Requirement R5 and Measure M5 R5. If an existing generator unit 2 cannot meet either Requirement R1 or Requirement R2 due to equipment limitations, such as manufacturer warranty requirements or limitations that endangers the equipment according to published manufacturer instructions, (Protection System excluded), the Generator Owner of that unit shall provide documentation of the equipment limitation(s) to the Reliability Coordinators, Planning Coordinators, Transmission Operators and Transmission Planners that monitor or model the associated unit, within 30 days of identifying the equipment limitation. The exception for the equipment limitation shall expire coincident with either of the following conditions: The equipment causing the limitation is replaced with equipment that removes the technical limitation. The equipment causing the limitation is modified or upgraded resulting in an increase of generator nameplate capacity rating greater than 10%. M5. Each Generator Owner of existing generators that are unable to comply with Requirements R1 or R2 due to equipment limitations (Protection System excluded) shall have evidence such as warranty agreements, insurance agreements, manufacturers documented limitations, engineering analysis or other documentation that explains the equipment limitation of the unit(s). (Violation Risk Factor Medium Units >100MVA Lower Units 100 MVA) (Time Horizon Operations Planning) 2 Including generators under construction, generators with an executed interconnection agreement or Power Purchase Agreement, or generators with an executed equipment purchase contract and scheduled delivery within 2 years of the effective date of the standard.

R6: Questions on Limitations GO receives written communication from RC, PC, TP, or TOP 90 DAY MAX GO provides written response to RC, PC, TP, & TOP

Requirement R6 and Measure M6 R6. The Generator Owner shall provide a written response within 90 calendar days of receipt of written comments from the Reliability Coordinators, Planning Coordinators, Transmission Operators or Transmission Planners (that monitor or model the associated unit) regarding the equipment limitation. The response shall indicate whether a change will be made to the equipment limitation or if no change will be made to the equipment limitation, the reason why. M6.Each Generator Owner shall have evidence such as dated copy, e- mail receipts or other evidence that it provided a written response to a commenting entity within 90 calendar days of receipt of comments. (Violation Risk Factor Lower) (Time Horizon Operations Planning)

Documentation Examples Relay Setting: Setting Sheets, Calculation Sheets, Voltage vs. Time curves, Frequency vs. Time curves, Coordination Plot, Dynamic Simulation Studies Other?

Documentation Examples Other Communication Dated emails Mail receipts Other?

Coordination with UFLS GV SDT Chair is member of UFLS SDT Generator Frequency Relay Setting precedes UFLS Setting

Reference The Technical Justification for the New WECC Voltage Ride-Through (VRT) Standard, A White Paper Developed by the Wind Generation Task Force (WGTF) June 13, 2007

Issues Relay setting vs. Unit Performance 9 cycles Duration curve vs. No Trip Envelope Technology neutral and forward looking Synchronous and non-synchronous generators

Question & Answer