Expert Workgroup on Fast Fault Current Injection stage 1 Terms of Reference

Similar documents
Grid Code Modification Register. March 2018

GC0100/101/102 Code Administrator Consultation Responses. Rob Wilson. Grid Code Panel 8 th Feb 2018

Mitigation of Cascading Outages and Prevention of Blackouts:System-Wide Corrective Control

Stage 05: Draft Final Modification Report

Item Topic Lead Action Documents

Simulation of DFIG and FSIG wind farms in. MATLAB SimPowerSystems. Industrial Electrical Engineering and Automation.

South Australian Energy Transformation

Minutes. Meeting name Meeting number 80. Grid Code Review Panel. Date of meeting 20 July 2016 Time Location

NERC Reliability Standard PRC-024 Generator Frequency and Voltage Protective Relay Settings

Grid Code Review Panel Meeting

Summary of Meeting and Actions

Real Time Monitoring for SMART Grid Initiatives Synchronized Measurement & Analysis in Real Time SMART program by

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

1. EXPERT MEETING EXPERT MEETING EXPERT MEETING Feedback from the meeting attendees...

, Participant Code # Item Topic Lead Action Documents

Digital Switchover Management of Transition Coverage Issues Statement

Grid Code Review Panel. Multi Unit BMUs Update

RCOA Mandatory Contestability for Phase 1 Customers. 16 December 2016

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

Research on Control Strategy of Complex Systems through VSC-HVDC Grid Parallel Device

Appendix C.4 Assistant Deputy Ministers Project Review Committee Terms of Reference

Hornsdale 2 Wind Farm. FCAS Capability Test Plan

Form C: Type Test Verification Report

Form C: Type Test Verification Report

FCP Project Summary report

PEP-I1 RF Feedback System Simulation

PERFORMANCE ANALYSIS OF DFIG WIND TURBINES WITH CROWBAR PROTECTION UNDER SHOR CIRCUIT

Annexes to Realisation Agreement

Name Initials Position

Operation of offshore wind power plants connected with HVDC

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

May 26 th, Lynelle Briggs AO Chair Planning and Assessment Commission

Licence for the transmission of digital terrestrial television multiplex service

700 MHz clearance programme timescale review. Review of progress, risks and readiness

BBC Response to Glasgow 2014 Commonwealth Games Draft Spectrum Plan

REQUEST FOR PROPOSALS AND TERMS OF REFERENCE

Connection requirements for generators to distribution grid C10/11 CENELEC. 26 Oct 2016 Elia WG Belgian Grid

REFURBISHMENT OF SECONDARY SYSTEMS IN HIGH VOLTAGE SUBSTATIONS LESSONS LEARNED IN VENEZUELA

American National Standard for Electric Lamps - Fluorescent Lamps - Guide for Electrical Measures

Class B digital device part 15 of the FCC rules

BPA s Network Open Season

American National Standard for Lamp Ballasts High Frequency Fluorescent Lamp Ballasts

Why You Need a Nathan Or How to Avoid the Pitfalls of Synchrophasor Integration

MATE3 Owner s Manual Addendum

ITU-T Y Functional framework and capabilities of the Internet of things

TEN TRANSFERABLE LESSONS FROM THE UK S DIGITAL TV SWITCHOVER PROGRAMME

GEO-Netcast White Paper Final Draft 9 December Improving access to data, products and services through GEOSS

Toronto Hydro - Electric System

16 th Annual PQSynergy International Conference and Exhibition 2016

ENA Engineering Recommendation G83 Issue

The Art of Low-Cost IoT Solutions

640 kv extruded HVDC cable system

Frequency changes during large system disturbances workgroup, phase 2 (GC0079)

About... D 3 Technology TM.

Timing Modules. Connect Frequency Control Timing Modules

640 kv XLPE HVDC cable system

6.3 DRIVERS OF CONSUMER ADOPTION

March 14, Gentlemen;

Advanced Coding and Modulation Schemes for Broadband Satellite Services. Commercial Requirements

Operating Instructions 07/2007 Edition. SINAMICS G130/G150 Line harmonics filter. sinamics

Signalling Cable Equivalent Sizes

Synchronization Issues During Encoder / Decoder Tests

PRELIMINARY Sunny Boy 240-US

Fieldbus Testing with Online Physical Layer Diagnostics

DIGITAL TELEVISION: MAINTENANCE OF ANALOGUE TRANSMISSION IN REMOTE AREAS PAPER E

VAR Generator Operation for Maintaining Network Voltage Schedules

Inter-Area Oscillation Damping by PDCI Modulation from PMU Feedback

4 Channel Video over Fiber With Ethernet

Dynamic Performance Requirements for Phasor Meausrement Units

Specification. NGTS Issue 1 October 1993

DIGITAL INSTRUMENTS S.R.L. SPM-ETH (Synchro Phasor Meter over ETH)

Alberta Electric System Operator

SMPTE STANDARD Gb/s Signal/Data Serial Interface. Proposed SMPTE Standard for Television SMPTE 424M Date: < > TP Rev 0

BNCE TV07: Power Impacts of Quick Start Standby Functionality in Televisions

Official Journal L 191, 23/07/2009 P

OUR CONSULTATION PROCESS WITH YOU

Case analysis: An IoT energy monitoring system for a PV connected residence

Zero Crossover Dynamic Power Synchronization Technology Overview

K800 RF AMPLIFIER TUBE UPGRADE

Broadcasting Ordinance (Chapter 562)

Recovering and Relaying Cables

Removal of Decaying DC Component in Current Signal Using a ovel Estimation Algorithm

Broadcasting Order CRTC

Industriefunkuhren. Technical Manual. OEM Sync-Module FE1000 (IRIG-B) ENGLISH

Policy on the syndication of BBC on-demand content

Experiment 7: Bit Error Rate (BER) Measurement in the Noisy Channel

GCC Interconnection Grid: Operational Studies for the GCC Interconnection with United Arab Emirates (UAE) N. AL-SHAHRANI GCCIA Saudi Arabia

6Harmonics. 6Harmonics Inc. is pleased to submit the enclosed comments to Industry Canada s Gazette Notice SMSE

Text with EEA relevance. Official Journal L 036, 05/02/2009 P

10/13/2011 Planning Coordination Committee. Standards

Notes Generator Verification SDT Project

A Unique Power Supply for the PEP II Klystron at SLAC*

Definitions. Common Corridor:

I. History of Time Error Correction and Reduced Reliance On Manual TEC Today

Guest Editor Pack. Guest Editor Guidelines for Special Issues using the online submission system

Load Frequency Control Structure for Ireland and Northern Ireland

BER MEASUREMENT IN THE NOISY CHANNEL

APQ Series Type C Power Factor Correction Banks

WHEN a fault occurs on power systems, not only are the

CENELEC GUIDE 13 FAQ. Frequently Asked Questions on the Frankfurt Agreement. Edition 1,

Transcription:

Expert Workgroup on Fast Fault Current Injection stage 1 Terms of Reference Governance 1. The need case to establish a Next Steps Expert Technical Workgroup Supporting Fast Fault Current Injection (FFCI) and associated control including Virtual Synchronous Machine (VSM) approaches was agreed at the 12th January 2017 Grid Code Development Forum (GCDF) following presentation of the proposal. 2. The work will be divided into two stages: stage 1 workgroup shall work in accordance with the Terms of Reference and shall be responsible for preparing a draft Grid Code Modification Proposal(s) in accordance with the timetable set by the chair. 3. Stage 2 Workgroup will work under the Grid Code Review Panel (GCRP) governance once the modification proposal(s) is approved by GCRP to proceed. Background In 2017, National Grid consulted on its proposals for Fast Fault Current Injection and Fault Ride Through (GC0100) as part of the implementation of the RfG and HVDC European Network Codes. As part of this consultation, National Grid proposed three options which included:- Option 1 Option 2 Option 3 the requirement for enhanced converter control performance similar to that of a Synchronous machine, for implementation by 2021 the so called Virtual Synchronous Machine (VSM), the use of currently available converter control technology with a ceiling current of 1.25pu The use of currently available converter control technology with a ceiling current of 1.0pu. In preparation for this work, National Grid had run numerous studies which were documented as part of this consultation. This consultation is available from the following link:- https://www.nationalgrid.com/sites/default/files/documents/final%20workgroup%20c onsultation_0.pdf As part of the consultation, National Grid advised that they would be happy with any of the above options, but if either option 2 or 3 were selected, they would wish to set

up an expert group to look at enhanced converter control strategies similar to the VSM but in addition to market based solutions, including the use of synchronous compensators. The reason for this is two-fold. Firstly, based on National Grid s Future Energy Scenario s (FES) and the System Operability Framework (SOF), there is a rapid decline in the volume of transmission connected Synchronous Generation which results in concerns over issues such as declining synchronising torque, falling levels of inertia, low short circuit levels, depressed retained voltage profiles under fault conditions, ability for generation connected to healthy circuits under fault conditions to name but a few. Secondly, the majority of converter based technologies use a control strategy based on a phase locked loop (PLL) which have number of shortcomings from a System perspective. There is increasing concern over the use of the Phase Locked Loop (PLL) as a converter control strategy and this issue has been documented in the SOF. https://www.nationalgrid.com/sites/default/files/documents/phase%20locked%20loop %20FINAL.pdf Furthermore, many converter strategies inject current into the network unlike synchronous generators which largely behave as voltage source behind impedance. As a consequence, they don t contribute to reducing negative and zero sequence imbalance or help with harmonics. Current sources have also been shown to be less stable in models and real applications. Following the consultation, there was an overwhelming response for Option 3, largely as this option is already technically available in today s market. As a result, and in line with the GC0100 consultation, National Grid is therefore proposing to set up an expert group to examine and address these issues. Stage 1 Workgroup Scope: This stage will:- 1) Evaluate option 1 of GC0100, enhanced converter control performance similar to that of a Synchronous machine 2) Review international practice (including VSM) of advanced converter control strategies 3) Understand the technical feasibility and costs of such developments 4) Comprise of national and international experts who have knowledge and experience of such technologies including manufacturers 5) Develop a clear specification for converter performance post 1 January 2021 6) Understand the application of such technologies to both small installations (less than 1MW) up to the largest installations which could be in the GW range.

7) Seek to develop a cost for the development and application of the above options from the smallest to largest plants. 8) Develop a draft Grid Code modification proposal to be proceeded in stage 2 In addition, the following specific areas will also be examined:- Fault Ride Through Active power recovery Fast Fault Current Injection Low Voltage Blocking Voltage and Reactive Power Voltage stability Provision of active power over a range of system voltage changes Angular Stability Voltage and Frequency ranges Inertial response to combined frequency and voltage disturbances Reactive current delivery during and after a fault in addition the phase relationship with the System. Transient voltage and excitation control Emergency and Restoration Ensuring that the required performance as described above does not adversely impact the performance of the system over a range of conditions such as islanding, Low Frequency Demand Disconnection or the ability to deliver a viable Black Start Strategy. Scenarios Examination and studies conducted under System Operating conditions, both normal and abnormal against typical demand and generation scenarios in the early 2020 s. Stage 1 of the workgroup will not consider:- 1. Options for implementation ahead of 1 st Jan 2021 other than to clarify any requirements that are unclear as part of option 3 proposed under GC0100. 2. Modifications to existing Frequency, Voltage and Angular stability requirements or ranges. 3. Specification for multi-terminal offshore HVDC systems or for users connected to remote end HVDC- systems. 4. Market framework, market impact, cost benefit or commercial optimisation matters, nor any other matters as reserved for the Stage 2 of the work group (see below), but rather seek to provide the technical considerations.

5. Specific project designs, clarifications or advice which will continue to be managed across the period of review under existing processes between Users and National Grid within established code frameworks. Workgroup Membership Stage 1 is specifically aimed at examining technical solutions and will therefore comprise an expert group who have national and international experience in technical and converter based control. In particular, technical experts from manufacturers, utilities, developers, research organisations, consultants and trade associations would be welcome to join. NGET will appoint a chair who shall act impartially and independently. NGET will also provide a technical secretary resource for the Workgroup who will handle administrative arrangements such as venue, agenda and recording actions and meeting notes. The chair and the secretary may appoint alternates to attend a meeting in their place. NGET shall ensure as far as possible that an appropriate cross-section of relevant experience interests and expertise is able to be represented on the workgroup. Workgroup Meetings The Workgroup will meet in person, but may decide to hold meetings by teleconference with agreement of the chair and a majority of the membership. An agenda and any supporting material for the meeting will be issued to the Workgroup members as required to allow Workgroup members to consider these items prior to the meeting. The frequency of the workgroup meetings shall be defined as necessary by the Workgroup chair to meet the scope and objectives. It is estimated that the workgroup will have 3 meetings and conclude in 6 months. Deliverables The Workgroup will provide updates to the GCRP as appropriate and on conclusion will present a report and Grid Code modification proposal as appropriate, which includes Detail the findings of the Group; Draft, prioritise and recommend changes to the Grid Code and associated documents in order to implement the findings of the Group; and Highlight any consequential changes which are or may be required.

Appendix 1 Indicative Scope Stage 2 (for information) Once the draft Grid Code modification produced in stage 1 is approved by GCRP to proceed, Stage 2 workgroup will be established under normal GCRP governance to take forward the modification. The indicative works include:- 1) Convene a cost benefit analysis to identify the most economic and efficient solution which is fit for operating the system in the 2020 s. This shall include but not be limited to:- a. The application of VSM type technologies installed on all Generation, HVDC equipment and Storage technologies b. The need or otherwise for fault ride through and VSM type technology for plant below 1MW c. The implications and costs to the system if the specifications identified in stage 1 applied only to plant of 1MW and above d. The use of market based solutions adjusting the plant mix to ensure the requirements of the SQSS can be satisfied or the partial use of VSM type technology with various levels of de-rating permitted. e. The use of synchronous compensation equipment or de-clutched Generation f. The balance and costs between equipment installed by Generators, HVDC System Owners or Storage Owners and Network Licensees g. Consider the balance between reserve holding, inertial response and operation of the Low Frequency Demand Disconnection Scheme. 2) Ensure the Cost Benefit Analysis at least uses the same scenarios developed under Phase 1 to understand the total costs of operating the system in the 2020 s under both normal and abnormal conditions. 3) Determine the overall most economic and efficient result, either via technical solutions, market arrangements or a combination of the two. The scenarios developed in Stage 1 will be used in this process but this would not preclude additional scenarios being used in Stage 2.