Report from the Mini-peer Review of the Tracker GTRC6 Problem, Root Cause, Tests & planned GTRC7 Resolution.

Similar documents
GLAST Large Area Telescope:

GLAST Large Area Telescope:

Glast beam test at CERN

LAT PROJECT DOCUMENT CHANGE NOTICE (DCN) SHEET 1 OF 1

GLAST Large Area Telescope:

GLAST Large Area Telescope: LAT Planning Meeting

TKK S ASIC-PIIRIEN SUUNNITTELU

Gamma-ray Large Area Space Telescope (GLAST) Large Area Telescope (LAT) Anticoincidence Detector (ACD) Subsystem Photomultiplier Tube Review

Results on 0.7% X0 thick Pixel Modules for the ATLAS Detector.

LAT I&T Peer Review, 2003

ATLAS Pixel Subsystem and Simulation

CGEM-IT project update

GLAST Large Area Telescope:

Design, Realization and Test of a DAQ chain for ALICE ITS Experiment. S. Antinori, D. Falchieri, A. Gabrielli, E. Gandolfi

RTPC 12 Simulation. Jixie Zhang Aug 2014

Adding Analog and Mixed Signal Concerns to a Digital VLSI Course

Testing and Characterization of the MPA Pixel Readout ASIC for the Upgrade of the CMS Outer Tracker at the High Luminosity LHC

GLAST Large Area Telescope:

Accredited Standards Committee C63

Trigger Report. Wesley H. Smith CMS Trigger Project Manager Report to Steering Committee February 23, 2004

Data Pattern Generator DG2020A Data Sheet

Agilent 86120B, 86120C, 86122A Multi-Wavelength Meters Technical Specifications

VLSI Chip Design Project TSEK06

EE141-Fall 2010 Digital Integrated Circuits. Announcements. Homework #8 due next Tuesday. Project Phase 3 plan due this Sat.

Particle Test Peer Review

ATLAS Group LPNHE. ATLAS upgrade activities. Biennale du LPNHE Tirrenia (Pise)

THE WaveDAQ SYSTEM FOR THE MEG II UPGRADE

The Silicon Pixel Detector (SPD) for the ALICE Experiment

New Serial Link Simulation Process, 6 Gbps SAS Case Study

Sharif University of Technology. SoC: Introduction

Solutions to Embedded System Design Challenges Part II

Paul Dauncey For the CALICE-UK electronics group. A. Baird, D. Bowerman, P. Dauncey, R. Halsall, M. Postranecky, M.Warren, O.

Scan. This is a sample of the first 15 pages of the Scan chapter.

The ATLAS Tile Calorimeter, its performance with pp collisions and its upgrades for high luminosity LHC

FPGA Laboratory Assignment 4. Due Date: 06/11/2012

Achieving Faster Time to Tapeout with In-Design, Signoff-Quality Metal Fill

Clock - key to synchronous systems. Topic 7. Clocking Strategies in VLSI Systems. Latch vs Flip-Flop. Clock for timing synchronization

Clock - key to synchronous systems. Lecture 7. Clocking Strategies in VLSI Systems. Latch vs Flip-Flop. Clock for timing synchronization

The Alice Silicon Pixel Detector (SPD) Peter Chochula for the Alice Pixel Collaboration

First LHC Beams in ATLAS. Peter Krieger University of Toronto On behalf of the ATLAS Collaboration

First evaluation of the prototype 19-modules camera for the Large Size Telescope of the CTA

Status of GEM-based Digital Hadron Calorimetry

Lecture 17: Introduction to Design For Testability (DFT) & Manufacturing Test

itop (barrel PID) and endcap KLM G. Varner Jan-2011 Trigger/DAQ in Beijing

Prospect and Plan for IRS3B Readout

UNIT IV CMOS TESTING. EC2354_Unit IV 1

EE141-Fall 2010 Digital Integrated Circuits. Announcements. Synchronous Timing. Latch Parameters. Class Material. Homework #8 due next Tuesday

Commissioning of the ATLAS Transition Radiation Tracker (TRT)

HAPD and Electronics Updates

CMS Upgrade Activities

Minutes of the ALICE Technical Board, November 14 th, The draft minutes of the October 2013 TF meeting were approved without any changes.

Atlas Pixel Replacement/Upgrade. Measurements on 3D sensors

Abstract. Keywords INTRODUCTION. Electron beam has been increasingly used for defect inspection in IC chip

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

Random Access Scan. Veeraraghavan Ramamurthy Dept. of Electrical and Computer Engineering Auburn University, Auburn, AL

nmos transistor Basics of VLSI Design and Test Solution: CMOS pmos transistor CMOS Inverter First-Order DC Analysis CMOS Inverter: Transient Response

Update on DAQ for 12 GeV Hall C

A Transaction-Oriented UVM-based Library for Verification of Analog Behavior

Innovative Fast Timing Design

Dick Loveless. 20 November 2008 SLHC Workshop. Dick Loveless SLHC Workshop 20 Nov

Outline. GEM R&D and assembly facilities at UVa. Cosmic test results. Update on the cm 2 GEM prototype

Electronics for Satellite Experiments. Electronics for Satellite Experiments

Sources of Error in Time Interval Measurements

SWITCH: Microcontroller Touch-switch Design & Test (Part 2)

Risk Risk Title Severity (1-10) Probability (0-100%) I FPGA Area II Timing III Input Distortion IV Synchronization 9 60

Highly Accelerated Stress Screening of the Atlas Liquid Argon Calorimeter Front End Boards

Verification of HBM through Direct Probing on MicroBumps

Review of the CMS muon detector system

Status of readout electronic design in MOST1

THE DESIGN OF CSNS INSTRUMENT CONTROL

At-speed Testing of SOC ICs

Testing Digital Systems II

ST2225A. LED Display Driver. Version : A.025 Issue Date : 2001/11/26 File Name Total Pages : 12. : SP-ST2225A-A.025.doc


2.6 Reset Design Strategy

Electronics procurements

Front End Electronics

2.1. Log on to the TUMI system (you cannot proceed further until this is done).

. The vertical pull-in range is approximately 10 Hz at fv = 60 Hz.

A FOUR GAIN READOUT INTEGRATED CIRCUIT : FRIC 96_1

Why FPGAs? FPGA Overview. Why FPGAs?

Silicon PhotoMultiplier Kits

A Briefing on IEEE Standard Test Access Port And Boundary-Scan Architecture ( AKA JTAG )

Application Note AN-708 Vibration Measurements with the Vibration Synchronization Module

Beam Loss Detection for MPS at FRIB

VLSI Technology used in Auto-Scan Delay Testing Design For Bench Mark Circuits

Failure Analysis Technology for Advanced Devices

AIDA Advanced European Infrastructures for Detectors at Accelerators. Milestone Report. Pixel gas read-out progress

A Serializer ASIC at 5 Gbps for Detector Front-end Electronics Readout

Welcome and FRIB Project Status. FRIB Highlights and Plan Ahead

Status of the CUORE Electronics and the LHCb RICH Upgrade photodetector chain

RX40_V1_0 Measurement Report F.Faccio

ELEC 4609 IC DESIGN TERM PROJECT: DYNAMIC PRSG v1.2

Unit V Design for Testability

Timing EECS141 EE141. EE141-Fall 2011 Digital Integrated Circuits. Pipelining. Administrative Stuff. Last Lecture. Latch-Based Clocking.

System IC Design: Timing Issues and DFT. Hung-Chih Chiang

Global Trigger Trigger meeting 27.Sept 00 A.Taurok

Commissioning and Initial Performance of the Belle II itop PID Subdetector

Avoiding False Pass or False Fail

MULTIPLE TPS REHOST FROM GENRAD 2235 TO S9100

Transcription:

Document # Date Effective Page 1 of 7 LAT-TD-02668-01 November 25, 2003 Author(s) Supersedes Hartmut Sadrozinski LAT TECHNICAL PROCEDURE, GUIDELINE Subsystem/Office Document Title Report from the Mini-peer Review of the Tracker GTRC6 Problem, Root Cause, Tests & planned GTRC7 Resolution. Report from the Mini-peer Review of the Tracker GTRC6 Problem, Root Cause, Tests & planned GTRC7 Resolution.

LAT-TD-02668-01 [Report from the Mini-peer Review of the Tracker GTRC6 Problem] Page 2 of 7 CHANGE HISTORY LOG Revision Effective Date Description of Changes

LAT-TD-02668-01 [Report from the Mini-peer Review of the Tracker GTRC6 Problem] Page 3 of 7 A mini-peer Review of the Tracker GTRC6 Problem, Root Cause, Tests & planned GTRC7 Resolution was held on Friday, 14 Nov 2003 at 1pm Pacific Time in the GLAST III conference room, (Bldg 234) at SLAC. The charge is given in Appendix A, the committee and other attendees in Appendix B, and the agenda in Appendix C. Materials submitted are at htttp://scipp.ucsc.edu/~hartmut/glast/gtrc. The committee was impressed by the cooperation of the TKR and ELEX groups and the time spent on the review, given the many other pressing duties. Following are findings and conclusions related to the charge, followed by a list of recommendations. A Findings: a. GTRC6 Problem During the TKR MCM and mini-tower testing, two problems were found: A logical error in the handling of the time-over-threshold (which is used to estimate the charge deposited in the SSDs). This error occurs when the trailing edge of the TOT coincides with the raising edge of a consecutive pulse, and leads to a time out. A race condition in the inter-chip communications of the GTRCs, which severely limits the operational range in frequency and/or voltage. The TOT problem has been verified in VHDL and on bare die, after the test program was modified. It showed up in mini-tower testing with a random source in fairly large data sets. The data taken with the mini-tower seem to confirm the findings, but need confirmation. Recommendation 1, 2. The timing problem, including observed delays etc., is understood and has been corrected on 6 GTRC6 ICs with Focused Ion Beam (FIB) surgery, after which the GTRC6 worked well. Conclusion to Point #1 of Charge: The root causes for the two GTRC6 issues have been identified. b. GTRC7 Resolution The TKR and ELEX group have submitted ASICs with the following changes: GTRC6B: fix the timing problem without re-route. GTRC7: fix timing problem, AND change TOT logic, complete reroute. GTCC1_TOT1 TEM ASIC containing the TOT logic. The GTRC6B has minimal risk, because the existing GTRC layout will be used with only two local modifications, which have been proven to work after FIB surgery on 6 of the current devices. These modifications restored frequency and voltage margins, but will not run with TOT enabled.

LAT-TD-02668-01 [Report from the Mini-peer Review of the Tracker GTRC6 Problem] Page 4 of 7 GTRC7 will restore frequency and voltage margins, and will run with TOT enabled. The corrected TOT code has been run successfully in the TEM FPGA attached to the mini-tower with 1M triggers at 300 Hz without showing time-out errors to the on-line system. (However off-line analysis of the data collected is yet to be done). The modified GLAST Tracker Cable-Controller ASIC GTCC1_TOT1 would replace the ordinary GTCC1 residing in the TEM and would be able to run the TOT code in conjunction with the GTRC6B. Operation within the frequency and power budget should be possible with either the GTRC7 + GTCC1 combination or the GTRC6B + GTCC1_TOT1 combination. c. Design, Layout and Testing Conclusion to Point #2 of Charge: The design solutions are appropriate. The LAT TKR readout controller ASIC GTRC was designed, simulated, laid out by the SLAC LAT electronics group. The testing is done in the LAT TKR group, mainly at UCSC, both on probe card and on MCM, and on the mini-tkr tower at INFN Pisa and at SLAC, with support from the LAT I&T group. The test vectors used by the designer during design verification are different from those used in the testing. High rate testing with random realistically long pulses, which could help identifying further problems with the GTRC, has not been performed yet. Recommendations 3, 4, 5, 6, 7, 8, 9 Conclusion to Point #3 of Charge: Past GTRC6 testing could have benefited from better coordination of design, layout and testing, and from realistic system tests including high rate random triggering. This should be lessons learned for future GTRC6 and GTRC7 testing. d. Additional observations The TKR and ELEX systems assume the same supply voltage both at the TEM power supply and at the TKR ASIC pad. This does not take into account the voltage drop on cables and polyswitches. Series protection resistors have been inserted in the lines to protect the system from a local fault, for example in a damaged ASIC. The efficacy of this protection has not been verified experimentally. The design and verification tools should be upgraded. Recommendations 10, 11, 12 B Recommendations 1. Resolve GTRC6 Mini-Tower test results (no TOT timeout observed in Van de Graaf tests during 24 hrs of operation at 15 30 Hz trigger rate). Estimate the expected rate of TOT overlaps and compare with observed time-out rate during cosmic ray running (about one in 10 3-10 4 triggers at 10 Hz trigger rate).

LAT-TD-02668-01 [Report from the Mini-peer Review of the Tracker GTRC6 Problem] Page 5 of 7 2. Test GTRC7 VHDL code in FPGA with a long TREQ (GTFE pulse) and many TACK. The length of the TREQ should be longer than the longest pulse you expect from heavy ions in the space. 3. Improve handling of Test Vectors for GTRC6 & GTRC7: Designer should propose test vectors to be included in testing. Designer should verify the % of coverage in VHDL 4. Provide more complete documentation of GTRC describe the different states of the state machine. 5. Perform high rate triggering tests with single tray and radioactive source. 6. Continue system tests with multiple tray/multiple MCM using TEM, preferable with ELEX/DAQ group involvement. A high rate test of the entire mini-tower should be performed ASAP to look for potential additional system errors. 7. Continue to perform coordinated, but independent tests with the present mini-tower (at SLAC) and the new mini-tower (at INFN) 8. Test results vs. specifications: Provide a matrix comparing specifications described in LAT-SS- 00152-02 and the test results. 9. Produce new schedule for GTRC / MCM production and testing, taking in account possible holiday downtime of foundry. 10. Review requirements for normal / worst cases operations (temperature, voltage, frequency) together with ELEX group. 11. Perform tests of interplay of Polyswitches and protection resistors. 12. For future ASIC programs at SLAC improve robustness of ASIC development flow - e.g., improved digital simulation tools, more sophisticated libraries. - test vectors should be generated from simulations and the coverage of the test vectors should be assessed to ascertain that all critical functions have been tested.

LAT-TD-02668-01 [Report from the Mini-peer Review of the Tracker GTRC6 Problem] Page 6 of 7 APPENDIX A Charge to Committee (as understood by the chair): 1. Review if the root cause for these issues has been identified 2. Review if the design solution is appropriate 3. Review the completed and planned test & simulation verification activities 4. Identify any recommendations for future verification activities 5. Add any other insights and recommendations APPENDIX B Committee: Hartmut Sadrozinski - chair Neil Johnson - Cal Subsystem Manager (by phone) Helmuth Spieler - LBNL Off Project Support Lou Fetter - GSFC Consultant Elliott Bloom - LAT I&T Test Manager Jim Martin LAT IPO In Attendance: Robert Johnson TKR Subsystem Manager Gunther Haller Elex-DAQ Subsystem Manager Sandro Brez TKR Subsystem, INFN (by phone) Luca Latronico TKR Subsystem, INFN (by phone) Hiro Tajima TKR Subsystem (by phone) Mutsumi Sugizaki TKR Subsystem Mike Huffer Elex Subsystem Diether Freytag Elex subsystem Oren Milgrome Elex subsystem Eduardo Do Couto e Silva I&T Rick Claus I&T Peter Michelson - LAT IPO Lowell Klaisner - LAT IPO Dick Horn System Engineering (by phone) Nick Virmani LAT Parts Engineer (by phone) Andy Lankford UCI Off Project Support (by phone)

LAT-TD-02668-01 [Report from the Mini-peer Review of the Tracker GTRC6 Problem] Page 7 of 7 APPENDIX C Agenda: A. Specifications, Functions of GTRC R. Johnson 5 min B. Design (including methodology) G. Haller et al. 15 min C. Testing of GTRC6 a. Wafer Testing R. Johnson et al. 10min b. MCM Testing at UCSC R. Johnson et al. 10 min c. Testing at SLAC n.a. 10 min d. Testing at INFN L. Latronico 15 min e. Mini-tower testing at SLAC H. Tajima/E. do Couto10 min D. GTRC6 Problem & Design changes in GTRC7 R. Johnson/ G. Haller 20min E. Discussion on points 1-2 of the charge Committee 15min F. Plan for further Tests GTRC6 R. Johnson at al. 20 min G. Test Plan for GTRC7 R. Johnson/ G. Haller 20 min H. Discussion on points 3-4 of the charge Committee 15min I. Discussion on points 5 of the charge Committee 15min J. Committee Discussions Committee only 20 min K. Close-out 10 min