Beam systems without failures what can be done?

Similar documents
LHC Machine check out

beam dump from P2 losses this morning

WHAT WE WILL DO FOR BEAM PREPARATION IN 2009 : BEAM INTERLOCKS

The 2011 LHC Run - Lessons in Beam Diagnostics

LHC_MD292: TCDQ-TCT retraction and losses during asynchronous beam dump

1. General principles for injection of beam into the LHC

LHC COMMISSIONING PLANS

MACHINE PROTECTION WORKSHOP REVISITED OPEN ISSUES, PROGRESS AND DECISIONS ON MAJOR TOPICS

LHC Nominal injection sequence

LHC Beam Instrumentation Further Discussion

REVIEW OF LHC OPERATION

INITIAL BEAM COMMISSIOMING OF INJECTION AND BEAM DUMP

Status and Plans for PEP-II

Session 07 - What did we learn with beam in 2008? LHC Performance Workshop Chamonix Rhodri Jones on behalf of BE/BI & all our collaborators

S67: PRE-CYCLE & RAMP

PICS IN THE INJECTOR COMPLEX WHAT ARE WE TALKING ABOUT?

Injectors. Injectors ready

2008 JINST 3 S LHC Machine THE CERN LARGE HADRON COLLIDER: ACCELERATOR AND EXPERIMENTS. Lyndon Evans 1 and Philip Bryant (editors) 2

Friday 05/03/ :00 13:00 : Establishing reference orbit golden Jorg Wenninger. Problems Wrong polarity on MCBXH3.L8 Polarity flag changed in DB

ABORT DIAGNOSTICS AND ANALYSIS DURING KEKB OPERATION

What can be learned from HERA Experience for ILC Availability

RF upgrade program in LHC injectors and LHC machine

Full IEFC workshop Feb.

Procedures for the Commissioning of the Beam Interlock System for the CNGS and SPS-LHC Transfer Lines

ANKA RF System - Upgrade Strategies

RF PERFORMANCE AND OPERATIONAL ISSUES

Detailed Design Report

Bunch-by-bunch feedback and LLRF at ELSA

Spear3 RF System Sam Park 11/06/2003. Spear3 RF System. High Power Components Operation and Control. RF Requirement.

SUMMARY OF SESSION 4 - UPGRADE SCENARIO 2

18 GHz, 2.2 kw KLYSTRON GENERATOR GKP 24KP 18GHz WR62 3x400V

LESSONS LEARNT FROM BEAM COMMISSIONING AND EARLY BEAM OPERATION OF THE BEAM LOSS MONITORS (INCLUDING OUTLOOK TO 5 TEV)

Program Risks Risk Analysis Fallback Plans for the. John T. Seeman DOE PEP-II Operations Review April 26, 2006

14 GHz, 2.2 kw KLYSTRON GENERATOR GKP 22KP 14GHz WR62 3x400V

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

FILLING SCHEMES AND E-CLOUD CONSTRAINTS FOR 2017

arxiv: v1 [physics.acc-ph] 9 Aug 2016

Availability and Reliability Issues for the ILC

Equipment Installation, Planning, Layout, organisation and updates

PEP II Design Outline

A Fast Magnet Current Change Monitor for Machine Protection in HERA and the LHC

Linac3 experience for LHC ion runs

The Elettra Storage Ring and Top-Up Operation

New Filling Pattern for SLS-FEMTO

PEP-II Status. U. Wienands, PEP-II Run Coordinator for the PEP-II team

LLRF at SSRF. Yubin Zhao

SPEAR 3: Operations Update and Impact of Top-Off Injection

Beam Loss Detection for MPS at FRIB

Commissioning of the ATLAS Transition Radiation Tracker (TRT)

TECHNICAL SPECIFICATION Multi-beam S-band Klystron type BT267

Development of an Abort Gap Monitor for High-Energy Proton Rings *

Synchrotron Light Facility. Operation of ALBA RF. Angela Salom on behalf of RF team: Francis Perez, Bea Bravo and Jesus Ocampo

Proceedings of the 1997 Workshop on RF Superconductivity, Abano Terme (Padova), Italy

THE ARCHITECTURE, DESIGN AND REALISATION OF THE LHC BEAM INTERLOCK SYSTEM

Accelerator Instrumentation RD. Monday, July 14, 2003 Marc Ross

North Damping Ring RF

LEP Status and Performance in 2000

High Power Cyclotrons

Top-Up Experience at SPEAR3

PEP-II Overview & Ramp Down Plan. J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007

The LEP Superconducting RF System

Suggested ILC Beam Parameter Range Rev. 2/28/05 Tor Raubenheimer

5 Project Costs and Schedule

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY

OPERATIONAL EXPERIENCE WITH CIRCULATING BEAM

Status of SOLARIS Arkadiusz Kisiel

PEP-I1 RF Feedback System Simulation

Commissioning of the CNGS Extraction in SPS LSS4

Current status of XFEL/SPring-8 project and SCSS test accelerator

1:1 and 1:2 Redundant Low-Noise Ka-Band Block Converter Systems

Progress in Finite State Machine Developments at FLASH. Olaf Hensler MCS

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

Scavenger Extraction. Karen Goldsmith Shawn Alverson

KEKB Accelerator Physics Report

LIGHT PROTON THERAPY PROJECT

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

OPERATIONAL EXPERIENCE AT J-PARC

Status of Elettra, top-up and other upgrades

Review of Diamond SR RF Operation and Upgrades

Control of Intra-Bunch Vertical Motion in the SPS with GHz Bandwidth Feedback

The ESRF Radio-frequency Data Logging System for Failure Analysis

A Facility for Accelerator Physics and Test Beam Experiments

P. Adamson, Fermi National Accelerator Laboratory, Batavia, IL 60510, USA. Abstract

ANKA Status Report. N.Smale, A.-S. Müller, E. Huttel, M.Schuh Slides courtesy of A.-S. Müller and C.Heske.

RF2TTC and QPLL behavior during interruption or switch of the RF-BC source

Failure Modes, Effects and Diagnostic Analysis

Operating Experience and Reliability Improvements on the 5 kw CW Klystron at Jefferson Lab

CLIC Feasibility Demonstration at CTF3

Present Status and Future Upgrade of KEKB Injector Linac

Andrei Seryi, Toshiaki Tauchi. December 15-18, 2008

Commissioning the TAMUTRAP RFQ cooler/buncher. E. Bennett, R. Burch, B. Fenker, M. Mehlman, D. Melconian, and P.D. Shidling

CLEX (CLIC Experimental Area)

Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi)

Summary of CBETA Independent Cost Reviews. R. Michnoff January 19, 2017

Digital BPMs and Orbit Feedback Systems

LEP OPERATION AND PERFORMANCE WITH ELECTRON-POSITRON COLLISIONS AT 209 GEV

National Park Service Photo. Utah 400 Series 1. Digital Routing Switcher.

EPJ Web of Conferences 95,

Transcription:

Acknowledgements: T.Baer, C.Bracco, G.Bregliozzi, G.Lanza, L.Ponce, S.Redaelli, A.Butterworth Beam systems without failures what can be done? After LS1 Session 07-09 th February 2012 M.Solfaroli/J.Uythoven

Outline Beam dumps analysis Per system: Failures Possible improvements Operation beyond 5 TeV Conclusions 2

Analysis methodology All dumps of 2010/2011 runs analyzed: Powering (PIC, cryo, QPS, EL, ) dumps excluded MD periods excluded Sorted by energy: 450 GeV (only those with at least 300 bunches in 1 beam) Ramp Dumps screened and classified Given the scope of the investigation, the outcome is not designed to determine the success or failure of systems, but rather to establish a way for yet a better performance 3

BDs @450 Gev (Intensity B1/2 > 3E10 13 p) 2010 (2 events) 2011 (38 events) Beam dump cause LOSSES (injection region) BLM (failure of a processing card) Beam dump cause LOSSES 11 EXCURSION 10 VAC 8 RF 3 LBDS + KICKERS 2 MPS 1 SW 1 OPERATIONAL 1 UFO 1 4

BDs @RAMP 2010 (40 events) 2011 (15 events) Beam dump cause EXCURSION 9 OPERATIONAL 8 COLL 6 SW 4 RF 3 LBDS + KICKERS 3 LOSSES 2 MPS 2 VAC 1 FEEDBACK 1 UFO 1 5 Beam dump cause RF 6 EXCURSION 2 UFO 2 EXP 1 COLL 1 LBDS + KICKERS 1 VAC 1 FEEDBACK 1

BDs @ 2010 (107 events) 2011 (107 events) Beam dump cause OPERATIONAL 17 LBDS+KICKERS 13 UFO 12 LOSSES 11 COLL 11 EXCURSION 10 FEEDBACK 8 NON-STANDARD OP 7 EXP 5 BLM 5 SW 4 ACCESS 2 RF 2 6 Beam dump cause RF 28 VAC 14 UFO 14 SW 8 LOSSES 7 COLL 7 LBDS + KICKERS 6 NON STANDARD OP 6 EXP 5 FEEDBACK 3 EXCURSION 3 ACCESS 2 MPS 2 OPERATIONAL 2

General considerations At 450 GeV (I B1/B2 > 3E10 13 p): Only 2 dumps in 2010 Excursion the most important Losses are also significant but almost all at injection regions during injection; improvements are foreseen (see C.Bracco s talk): During ramp: Moving/adding TCDIs in the transfer lines to reduce showers in injection region (LS1) BLM sunglasses Possibly increasing BLM thresholds at injection SPS MSE ripple reduction SPS MKE4 beam position with respect to the waveform delayed (possible intervention on the magnet (out of specification) during LS1) Situation strongly improved from 2010 (40 dumps) to 2011 (15 dumps) 40 % of dumps is due to RF At : Number of dumps in 2010 and 2011 is surprisingly equal (107 events) For 2011 RF is the major source of dumps with 26 % Vacuum is also important with 13 % of dumps 13 % of dumps due UFOs 7

Energy Problem Possible improvement 450 GeV Cavity trip - 2 times Allow for smaller beam intensities 450 GeV HOM on line too high temperature Allow for smaller beam intensities RAMP 2 cavities lost (arc detected) Solved during 2011 RAMP Interlock on total voltage - RAMP Bad settings left in - 2 times Solved RAMP Reboot of LBDS-RF front-end - RAMP Klystron current error Solved during 2011 RF main coupler interlock (arc) 6 times Solved during 2011 New total voltage interlock triggered - Trip of ACS module due to a faulty power supply 3 times Solved during 2011 RF beam dumps - 2011 One of the temperature sensors for a HOM indicated too high temperature 3 times Allow for smaller beam intensities Cavity trip 4 times Allow for smaller beam intensities M1B2 cavity trip (sick cavity) 5 times Problem will be solved in LS1 Vacuum power supply problem on a Klystron 2 times Klystron filament current low fault 2 times - Cavity quench Allow for smaller beam intensities PLC problem - 8

RF beam dumps - 2011 On June 17 th 2011 all RF interlocks connected to the BIS Protect RF equipment from power coming from the beam Required if beam current above half nominal (1400 x 1.1e11p+) Since then, 25 beam dumps caused by RF, above injection 9/25 were connected to the RF interlock for high beam intensity 7/9 where with high beam intensity (proton operation) 2/9 where with low beam intensity (ion operation) and fill could have been saved After LS1 could again separate RF Interlock from the BIS If beam current below half nominal (1400 x 1.1e11 p+) some RF interlocks don t dump the beam Needs reliable Safe RF beam intensity measurement From BPM already used for set-up beam flag From BCTs (need redundancy, unbunched beam to be treated) Will not save any high intensity proton fills Reason for 50 % of 2011 RF trips should be solved, another 20 % will be solved during LS1 (see E.Jensen s talk) 9

VAC beam dumps - 2011 Energy Problem Possible improvement 450 GeV Dump due to e-cloud ( Vacuum spike in P4 during scrubbing ) No problems if operating at 50 ns, scrubbing if 25 ns 450 GeV Vacuum spike dumps in IP2 and IP8 7 times RAMP Vacuum spike dumps in IP2 and IP8 Vacuum spike dumps in IP2 and IP8 9 times Vacuum interlock in IR4 3 times Instabilities on BGI HV led to a spark and beam dump due to vacuum The origin of spikes are VAMTF vacuum modules (LMC 9-16/11/2011) (see V.Baglin s talk). The problem could appear again during 2012 run. The VAMTF will be re-designed for LS1! The 3 dumps appeared in a row and no problem was seen afterwards. X-rays performed, nothing abnormal was found To be scheduled It seems that the MCP in B1V detector aged and failed - 10

VAC beam dumps - 2011 RF fingers problem: For IP2/8 a completely new design will be installed during LS1 Pressure spike could become an issue at higher energy and beam current Vacuum interlock threshold can be risen locally where the problem appears if too much BLM will dump e-cloud: A good scrubbing (20 h / 2 weeks, see G.Rumolo/G.Arduini talk) is needed to operate the machine at 25 ns (before or after the LS1) BGIs: In a sense it was operational error, as it was known that this kind of operation can be dangerous not to do it It seems that the MCP in B1V detector aged and failed. Nothing can be done, except trying to minimize the ageing 11

VAC after LS1 M.Jimenez 12

LBDS + kickers beam dumps Energy Problem Possible improvement 450 GeV MKI erratic - 450 GeV MKI erratic - RAMP Power supply of MKD generator M faulty Internal LBDS trigger: dump issued by the tracking system (BETS), following an unexplained increase in the generator voltage strength on the dilution kicker MKBH Energy tracking verification error Power supply instability fixed Power supply instability fixed Power supply instability fixed Self trigger of LBDS B1.Vacuum pump in dump line of B1 off Vacuum pump replaced MKD: instability on the main power supply Power supply instability fixed Internal LBDS trigger. Dump issued by the tracking system (BETS), following an unexplained increase in the generator voltage strength on the dilution kicker MKBH Internal trigger of LBDS: dilution kicker MKBH-B.B2 power supply problem Power supply instability fixed Power supply instability fixed 13

LBDS + kickers beam dumps MKI erratics clearly need to dump the beam, as well as for LBDS MKD erratics (did not occur in 2011) Most LBDS failures were due to instabilities in the power converters of the MKD and MKB generators Over Christmas all MKD and MKB power converters have been sent to the manufacturer and have been repaired for a known weakness. This should improve tracking performance. If problem not solved, MKB generators tracking window could be enlarged (alarms to be installed, useful to know if a generators starts to lose stability) Vacuum interlocks on MKB: pumps were replaced during Christmas break should be better now. Not possible to enlarge the limits due to danger of magnet flashover 14

COLLIMATORS beam dumps Energy Problem Possible improvement RAMP Collimator temperature interlock triggered beam dump for TCTVB.4R2. Adapted threshold Collimator position interlock from both TCTs beam 1 at IP1. It looks like all of a sudden wrong measurement of position. It seems to be a SEU tbc Collimators IP5 interlock. TCL.5R5.B1, TCTH.4R5.B2, TCTVA.4R5.B2 are off. Analysis showed that it was a power supply failure, unlikely to be an SEU SEU mitigation ongoing SEU PRS problem in for TCTH.4L1.B1 and TCTVA.4L1.B1 of IR1, need to exchange RS power supply Collimator power supply problem in IP1 TCTVA and TCTH in 4R1.B2. Communication lost The measured gap exceeded the beta* limits for several collimators in IP1 and IP5. Beam dumped due to a problem with the new TCT beta* functions. The tighter function have a problem of interpolation in conjunction with the granularity of the beta* info (10 cm only) Environment interlock on collimators in point 7 B1. Apparently collimator jaw becoming too hot SEU mitigation ongoing SEU mitigation ongoing Spurious setting problem (SOLVED) Adapted threshold Collimator environment (temperature) dump, point 2 TCTVB_4R2TTRU Adapted threshold 15

COLLIMATORS beam dumps 2011 run After LS1 No structural problem encountered Some dumps due to temperature reading: the thresholds have been increased and the whole monitoring system is being improved Few SEU observed, new shielding should reduce this effect by a factor 10 (for the same radiation level) A new PXI chassis with increased redundancy being developed to increase availability it will be installed during LS1 Although the system has been designed to be resistant, integrated radiation could become an issue, affecting equipment lifetime Collimator position limits will be tighter (as defined to be a fraction of sigma), but the reliability of the system is not expected to be affected 16

OPERATIONAL beam dumps The number of operational mistakes has been reduced from 25 in 2010 to 3 in 2011, thanks to: An extensive work on establishment of solid operational procedures A big effort to improve SW tools Increased knowledge of systems and beam behavior 17

OPERATIONAL beam dumps 3 dumps in 2011 due to: 1. New SIS interlock on RF voltage dumped the beam when the RF was switched off for asynch dump test for RPs. Forgot to mask it. 2. During end-of-fill the collimators were moved close to the beam in order to understand if close settings could increase the impedance and create instabilities. This was a preparation for the beta=1m operation. Things worked well, but when driving the TCSG in IR6 close to the beam, the SIS dumped since the distance between TCSG and TCDQ became too large. Beam dump clean. 3. A clear OP mistake with the tune FB switched on with too little signal. The beam 1 trajectory is growing over ~1000 turns to 0.4 mm rms. Number 1, 2 are operational mistakes but due to non-standard operation 18

UFOs UFO s global number is dominated by MKI UFOs (limiting on Q4 and D2). Some improvements by increasing BLM thresholds in selected sectors (see T.Baer s talk) are ongoing but more studies will be done during 2012 run Dumps by arc UFOs are expected to dominate the statistics after LS1 as their number increases with E faster than the MKI UFOs one. A new strategy is under discussion to increase BLM threshold (see A.Verweij s talk) 19

More System Energy Reason for dump Tune feedback did not get its function FEEDBACK Tune FB dragged the tune of B2 H onto the resonance (1/3) OFB became unstable in IR2 squeeze RAMP Problems with OFB during ramp Door in Pt4 opened ACCESS A door was left open and seen as such after many days of beam operation BLM BLM crate problem leading to loss of communication MPS 450 GeV Glitch on Beam Permit Loop A Identical to previous dump, again a glitch on BPL B2/A Communication problems SW Problem CMW library release Equipment SW bugs Not easy to identify systematic sources of problem (if any), but problems should be addressed as: Even 1 dump less can make a difference Secondary sources of dumps can become primary if not treated 20

Conclusions The dump causes treated in this talk are a minor part (see M.Zerlauth s talk) of the total, the gain is minimum, but still important!! Large improvement between 2010 and 2011 (it will not be easy to continue on this line after LS1, but we will try to do so!!) Largest improvement on discipline and operational procedures RF is dumping most. 50 % of 2011 dumps should have been solved and 20 % more during LS1. However, dumps with high beam currents will be very difficult to improve on. VACUUM has no fundamental problem UFOs might become an issue after LS1 WHAT ABOUT integrated radiation (equipment lifetime)? WHAT ABOUT ageing? 21

22