Next Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack

Similar documents
J/NLC Progress on R1 and R2 Issues. Chris Adolphsen

X-Band Klystron Development at

INFN School on Electron Accelerators. RF Power Sources and Distribution

THE NEXT LINEAR COLLIDER TEST ACCELERATOR: STATUS AND RESULTS * Abstract

RF considerations for SwissFEL

45 MW, 22.8 GHz Second-Harmonic Multiplier for High-Gradient Tests*

NLC - The Next Linear Collider Project NLC R&D. D. L. Burke. DOE Annual Program Review SLAC April 9-11, 2003

DEVELOPMENT OF X-BAND KLYSTRON TECHNOLOGY AT SLAC

US-ILC Waveguide Industrialization Study. Marc Ross, Chris Nantista and Chris Adolphsen

Detailed Design Report

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

Present Status and Future Upgrade of KEKB Injector Linac

Status of KEK X-band Test Facility and its future plans

RF Upgrades & Experience At JLab. Rick Nelson

CLIC Feasibility Demonstration at CTF3

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

Development of Multiple Beam Guns for High Power RF Sources for Accelerators and Colliders

L-Band RF R&D. SLAC DOE Review June 15 th, Chris Adolphsen SLAC

Towards an X-Band Power Source at CERN and a European Structure Test Facility

KLYSTRON GUN ARCING AND MODULATOR PROTECTION

DEVELOPMENT OF A 10 MW SHEET BEAM KLYSTRON FOR THE ILC*

High Power Solid State Modulator Development at SLAC. Craig Burkhart Power Conversion Department March 5, 2010

Evaluation of Performance, Reliability, and Risk for High Peak Power RF Sources from S-band through X-band for Advanced Accelerator Applications

Chapter 4. Rf System Design. 4.1 Introduction Historical Perspective NLC Rf System Overview

Pulses inside the pulse mode of operation at RF Gun

A New 4MW LHCD System for EAST

Design of a 50 MW Klystron at X-Band*

Status of CTF3. G.Geschonke CERN, AB

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

30 GHz Power Production / Beam Line

SRS and ERLP developments. Andrew moss

Pulsed Klystrons for Next Generation Neutron Sources Edward L. Eisen - CPI, Inc. Palo Alto, CA, USA

RF POWER GENERATION FOR FUTURE LINEAR COLLIDERS* 1. Introduction

KEKB INJECTOR LINAC AND UPGRADE FOR SUPERKEKB

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

Overview of the X-band R&D Program

WG2 Group Summary. Chris Adolphsen Terry Garvey Hitoshi Hayano

XFEL High Power RF System Recent Developments

RF Power Generation II

RF plans for ESS. Morten Jensen. ESLS-RF 2013 Berlin

P. Emma, et al. LCLS Operations Lectures

Linac upgrade plan using a C-band system for SuperKEKB

North Damping Ring RF

Current status of XFEL/SPring-8 project and SCSS test accelerator

ILC-LNF TECHNICAL NOTE

A HIGH POWER LONG PULSE HIGH EFFICIENCY MULTI BEAM KLYSTRON

RF Power Upgrade at Jefferson Lab

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

14 GHz, 2.2 kw KLYSTRON GENERATOR GKP 22KP 14GHz WR62 3x400V

18 GHz, 2.2 kw KLYSTRON GENERATOR GKP 24KP 18GHz WR62 3x400V

Solid State Modulators for X-Band Accelerators

Spear3 RF System Sam Park 11/06/2003. Spear3 RF System. High Power Components Operation and Control. RF Requirement.

NEW METHOD FOR KLYSTRON MODELING

RF Solutions for Science.

RF Power Klystrons & 20 Year Look. R. Nelson 7/15/15

AREAL- Phase 1. B. Grigoryan on behalf of AREAL team

Status of RF Power and Acceleration of the MAX IV - LINAC

Program Risks Risk Analysis Fallback Plans for the. John T. Seeman DOE PEP-II Operations Review April 26, 2006

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

The Construction Status of CSNS Linac

Modulator Overview System Design vs. Tunnel Topologies. Snowmass Workshop August 16, 2005 Ray Larsen for the SLAC ILC Group

PULSED POWER FOR FUTURE LINEAR ACCELERATORS

LSD Review December 2012 Schedule, Re-Baseline, & Resource Analysis

Overview of NLC/JLC Collaboration *

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

X-band Solid State Modulator Development. Craig Burkhart Power Conversion Department January 5, 2011

4.4 Injector Linear Accelerator

5 Project Costs and Schedule

SLAC X-band Technology R&D. Tor Raubenheimer DOE Briefing June 11 th, 2010

CERN EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH. A 50 Hz LOW-POWER SOLID-STATE KLYSTRON-MODULATOR

Commissioning the TAMUTRAP RFQ cooler/buncher. E. Bennett, R. Burch, B. Fenker, M. Mehlman, D. Melconian, and P.D. Shidling

Klystron Lifetime Management System

STATUS OF THE SwissFEL C-BAND LINAC

PEP II Design Outline

Upgrade of CEBAF to 12 GeV

Energy Upgrade Options for the LCLS-I Linac

THE X-BAND KLYSTRON PROGRAM AT SLAC'

SMTF Beta <1 Front End Linac Infrastructure and Plans

SPEAR 3: Operations Update and Impact of Top-Off Injection

The SLAC Polarized Electron Source *

PEP-II Overview & Ramp Down Plan. J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007

X-Band klystron development at the Stanford Linear Accelerator Center

Monthly Progress Report Stanford Synchrotron Radiation Laboratory

ANKA RF System - Upgrade Strategies

The basic parameters of the pre-injector are listed in the Table below. 100 MeV

DELIVERY RECORD. Location: Ibaraki, Japan

OF THIS DOCUMENT IS W8.MTO ^ SF6

Digital BPMs and Orbit Feedback Systems

High-power klystrons. The benchmark in scientific research. State-of-the-art RF sources for your accelerator

Design, Fabrication and Testing of Gun-Collector Test Module for 6 MW Peak, 24 kw Average Power, S-Band Klystron

The TESLA RF System. S. Choroba. for the TESLA Collaboration. DESY Notkestr. 85, D Hamburg, Germany

Upgrading LHC Luminosity

Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi)

DEPARTMENT OF ELECTRONICS AND COMMUNICATION ENGINEERING QUESTION BANK

ILC RF System R&D. Chris Adolphsen, SLAC. Section of 1.3 GHz SC Linac. June 29, 2007 PAC07 Talk FRYC01

The Elettra Storage Ring and Top-Up Operation

Karin Rathsman. Calculations on the RF Source and Distribution

Transcription:

The Four 50 MW XL4 X-band klystrons installed on the 8-Pack

The Demonstrate an NLC power source Two Phases: 8-Pack Phase-1 (current): Multi-moded SLED II power compression Produce NLC baseline power: 475 MW 400 ns. LC TRC R1 requirement for GLC/NLC: Demonstration of the SLED II pulse compression system RF power and energy handling capability at the design level. 8-Pack Phase-2 (2004): Use the SLED II system for a Linac sub-unit test: A full power demonstration of an RF feed to 4.8 m of high gradient structures on the NLCTA beamline. One of the LC TRC R2 requirement for GLC/NLC: A linac subunit test

The Phase 1&2 baseline goals NLC Baseline Phase 1 Phase 2 Klystrons @ power 2 @ 75 MW 4 @ 50 MW 4 @ 50 MW Pulse length 1.6 µs 1.6 µs 1.6 µs Klys. - SLED power transfer efficiency 95% 90% (1) 90% (1) SLED power multiplier 3.3 3.0-3.2 (2) 3.0-3.2 (2) Power at SLED output 475 MW 540-576 MW 540-576 MW Pulse length 400 ns 400 ns 400 ns SLED - structure power transfer efficiency 95% n/a 90% (1) Power at structures - total 450 MW 486-518 MW Structure gradient 65 MV/m 66-68 MV/m (3) Notes: 1) Phase 1 power handling inefficiency is due to liberal use of WR90 2) Phase 1 SLED power multiplier low due to potential mode conversion inefficiency 3) Eight 60 cm. S17 structures

Phase 1 Summer 03 m-sled Straight-up layout Four 50 MW XL4 klystrons allows SLED commissioning and full power operation. Milestone: 475 MW, 400ns at the load tree September 2003 Test capability: 540 MW, 400ns

8-Pack Phase 1 Status In End Station B. SLED line tubes are placed in position.

Current klystron layout for Modulator & LLRF commissioning Four 50 MW klystrons on modulator; HV checkout, RF checkout, ongoing. The modulator and LLRF systems are being exercised while the high power loads are being conditioned. 7 of 10 loads have been conditioned 2 more are on now.

8-Pack Phase 1 Status LLRF: The system for LLRF control is in and being used. The system for LLRF monitoring is being commissioned. Power from 2 klystrons combined and sent to alternate loads on the hybrid. ~80-100 MW combined 50 ns/div. System now in use for conditioning loads to 80 MW, 500 ns. See Steve Smith s talk

8-Pack Phase 1 Status Modulator: IGBT heating problems solved, modified di/dt protection circuit. The voltage pulse is made flat by delaying the turn-on of 19 driver cards. Flatness for 4 XL4s, 1.6 µs, at 400 kv, ± 0.7% 4/7/03 Now, energy recovery diodes are not fast enough to catch the extremely fast IGBT core reset transients, particularly on the delayed boards. LLNL designed and built an array of fast diodes that works best of all devices tried. Currently building enough arrays for all boards in the system, available this week. Also adding Metal Oxide Varistor (MOV) across diodes to protect them. Have successfully tested at 30 Hz with arrays, but currently running RF tests at 10 Hz to minimize failures until the new arrays are installed. With all boards equipped with arrays, hope to achieve 60 Hz operation. See Dick Cassel s talk

Klystrons: 8-Pack Phase 1 Status: Next Linear Collider Four XL4 klystrons are installed and connected to the modulator, each delivering ~50MW at 400 kv. These are sufficient to perform all high power tests, for 8-Pack phases 1 & 2. Klystron arcs (~10) have been observed, no harm to the klystron. KEK/Toshiba klystron PPM2, which achieved 70 MW @ 1.5 µs at KEK, is being tested at SLAC. Progress is slow, have had 75 MW @ 100 ns., 60MW @ 1.0 µs. KEK/Toshiba klystron PPM4 is being tested at KEK (@ 50 hz). It will be shipped to SLAC in July for further testing (@ 120 hz). See John Cornuelle s talk One of the LC TRC R2 requirement for GLC/NLC: A full test of a PPM klystron at 120 or 150 Hz. KEK PPM2 under test at SLAC

Klystrons: 8-Pack Phase 1 Status: SLAC PPM klystron, XP3-3, is being tested. Eliminate transverse magnetic fields. Re-defeat 11.7 GHz oscillation. Achieved saturation, 80MW, at 200 ns. >60% eff. Examining beam break-up at longer pulse lengths. The second unit, XP3-4, is in fabrication. Convert to an integral pole piece design. Re-optimize cavity tuning for max. RF power. XP3-4 on test 10/03 PPM klystron XP4 is finishing design. More robust design. Larger gun ceramic for lower gradients. Integral pole piece design as XP3-4. XP4-1 on test 2/04 XP4-2 on test 5/04 See John Cornuelle s talk XP3-3 under test at SLAC

8-Pack Phase 1 Status: High power RF system: All Straight-up configuration components are in fabrication (or ready). Critical Items: The Combiner, the Cross Potent*, Splitter all parts have been fabricated, the sub-assemblies brazed and cold tested, and are in the final brazing cycle. The couplers are completed. The SLED pump Tees are nearing completion. The load trees are being assembled *see later slide

8-Pack Phase 1 Status High power RF system: Combiner now complete, in cold test braze prep photo See Sami Tantawi s talk

8-Pack Phase 1 Status Multimoded couplers (3), complete, in cold test.

8-Pack Phase 1 Status Cross Potent body Power out SLED SLED Power in The cover to this port was dented (~.3 mm) when the Cross Potent slipped (~1 ) during QC. Repair is underway. Then ready for final braze.

8-Pack Phase 1 Status SLED Pump Tees, in final prep. & installation Installed for cold testing

8-Pack Phase 1 Status Splitter, being prepared for final braze

8-Pack Phase 1 Status Load tree under assembly

Project schedule overview Phase 1 Finish conditioning loads 7/15 (current configuration) SLED lines in cold testing now Cross potent ready 7/14 Cold testing / assembly in July & August Pump down system 8/8 Bake-out finished 9/4 475 MW 400 ns milestone 9/03

Phase 1 Project schedule Begin System Commissioning: 9/4 copy of schedule attached

The Phase 2 One of the LC TRC R2 requirement for GLC/NLC: A Linac subunit test 8-Pack Phase-2 goal: Use the SLED II system for a full power demonstration of an RF feed to 4.8 m of high gradient structures on the NLCTA beamline. Install eight 60 cm long high gradient RF structures Transmit the high power from the SLED II system to the beamline. Split the high power to the high gradient RF structures Gain experience with a GLC/NLC RF feed at full power and full rep. rate

Phase 2 8-Pack Layout Schematic of the power handling to the beamline From SLED Mechanical/vacuum system in design 6 db 4.8 db Overmoded 3 db WR90 3 db 3 db 3 db 3 db

Phase 2 8-Pack Layout System design underway Layout of power splitters TBD. Structure install copied from present scheme

Phase 2 8-Pack Layout System design, to be reviewed in July

Phase 2 8-Pack Layout Phase 2 RF parts list (not finalized) High power parts designed at SLAC, ready for fab. Power splitters in design at KEK WR90 parts on order with SLAC klystron dept. Build for complete system Design by Des Status Fab by Fab status 1.6 pump tee SLAC Complete SLAC First 6 started in June Pump Varian To be purchased 1.6 coupler SLAC Complete SLAC Complete, recycle from Phase 1 Mode stripper SLAC Complete SLAC Not started Quadrupus SLAC Complete SLAC Complete, recycle from Phase 1 Med power load SLAC Complete SLAC Kly Not started 1.6-2.93 taper SLAC Complete SLAC Not started 2.93 spool SLAC Lengths TBD SLAC Not started H-plane bend SLAC Complete SLAC 4 in Fab, bodies complete 6 db Splitter KEK Started tbd Not started 4.8 db Splitter KEK Started tbd Not started 3 db Splitter KEK Started KEK Not started WR90 45dB coupler SLAC Complete SLAC Kly Not started WR90 E-plane bend SLAC Complete SLAC Kly Not started WR90 spool SLAC Complete SLAC Kly Not started WR90 3dB splitter SLAC Complete SLAC Kly Started in May Magic tee SLAC Complete SLAC Kly Not started WR90 Input arm SLAC Complete SLAC Kly Not started WR90 H-plane bend SLAC Complete SLAC Kly Not started WR90 output arm SLAC Complete SLAC Kly Not started WR90 pump tee SLAC Complete SLAC Kly Not started Component total

Phase 2 8-Pack Layout Schematic of the power handling to the beamline From SLED 6 db 4.8 db Overmoded 3 db WR90 3 db 3 db 3 db 3 db

Phase 2 8-Pack Layout Simplified configuration for initial running. From SLED Motivation: get 8 structures powered as soon as possible. Upgrade as structures and power splitters become available. Overmoded From NLCTA station 1 From NLCTA station 2 300MW, 400 ns 3 db 3 db 3 db 3 db 3 db These structures could be located in stations 1 & 2.

Phase 2 schedule overview, from ISG-X 1 2 Commission Phase 1 3 4 Machine Backup Phase 1 components KEK 5 Braze Backup Phase 1 components SLAC 6 7 Phase 2 design complete ALL 8 Structure - RF system interface defined ALL 9 10 Fabricate 'Mode Stripper' SLAC 11 Fabricate High Power components SLAC 12 Fabricate before-structure WR90 components SLAC 13 Fabricate on-structure WR90 components SLAC 14 15 Install Hardware on roof 16 Install Hardware in tunnel 17 Install Structures 18 Goal: 4+2+2 structures powered 19 20 RF design of 6 db and 4.8 db splitters complete KEK 21 Mech. design of 6 db and 4.8 db splitters complete tbd 22 Machine 6 db and 4.8 db splitters tbd 23 Braze 6 db and 4.8 db splitters tbd FY04 24 Fab. distribution for 6 db and 4.8 db splitter install SLAC 25 8-Pack Phase 2 Fabrication and Installation Plan 2003 2004 July Aug Sept Oct Nov Dec Jan Feb Mar Coordinate with structure test schedule

ID Task Name Duration Start Finish Predecessors 1 8-Pack Parts Schedule 0 days 6/20/03 6/20/03 2 Cross Potent 66 days 4/4/03 7/14/03 3 fab 28 days 4/4/03 5/13/03 9 cold test 20 days 4/21/03 5/16/03 12 final assy. 42 days 5/7/03 7/14/03 13 rcv. jog converters (2) 0 days 5/7/03 5/7/03 79 14 rcv. c/r converters (4) 0 days 5/23/03 5/23/03 86 15 Determine how to braze 0 days 5/20/03 5/20/03 33 16 prepare fixturing 7 days 6/11/03 6/19/03 15 17 QC 2 days 6/9/03 6/10/03 18 repair 5 days 6/11/03 6/17/03 17 19 braze prep 5 days 6/18/03 6/24/03 18 20 braze 1 3 days 6/25/03 6/27/03 13,14,11,16,19 21 braze 2 3 days 7/7/03 7/9/03 20 22 cold test assy. 3 days 7/10/03 7/14/03 21 23 vacuum process 0 days 7/14/03 7/14/03 22 24 Splitter 54 days 4/11/03 6/26/03 25 fab parts 21 days 4/11/03 5/9/03 31 final assy. 40 days 5/1/03 6/26/03 32 rcv. c/r converters (3) (16989) 0 days 5/13/03 5/13/03 86FS-3 days 33 Determine how to braze 14 days 5/1/03 5/20/03 34 prepare fixturing 5 days 5/21/03 5/28/03 33 35 braze 1 3 days 6/16/03 6/18/03 32,30,27,34 36 braze 2 3 days 6/19/03 6/23/03 35 37 Cold test assy. 3 days 6/24/03 6/26/03 36 38 vacuum process 0 days 6/26/03 6/26/03 37 39 Combiner 60 days 4/3/03 6/26/03 40 fab. Body 39 days 4/11/03 6/5/03 47 final assy. 60 days 4/3/03 6/26/03 48 Shims -94 (17199) 1 day 4/3/03 4/3/03 49 rcv. c/r converters (1) 0 days 5/27/03 5/27/03 86 50 braze 3 days 6/17/03 6/19/03 48,46,49,33 51 Cold test assy. 5 days 6/20/03 6/26/03 50 52 vacuum process 0 days 6/26/03 6/26/03 51 53 1.6" MM couplers 55 days 4/3/03 6/19/03 54 Cold Test Part 12 days 4/3/03 4/18/03 57 Production Parts 47 days 4/3/03 6/9/03 66 final assy. 55 days 4/3/03 6/19/03 67 pins (17193) 1 day 4/3/03 4/3/03 68 braze coupler #1 5 days 6/2/03 6/6/03 61,67,63 69 braze coupler #2 3 days 6/10/03 6/12/03 62,67,65 70 Cold test assys. 5 days 6/13/03 6/19/03 69 71 vacuum process 0 days 6/19/03 6/19/03 70 72 Jog converters 25 days 4/3/03 5/7/03 80 Circ - Rect converters 38 days 4/3/03 5/27/03 87 6.725" SLED tubes 54 days 3/31/03 6/13/03 94 Large pump T 58 days 4/4/03 6/25/03 95 Redesign 1 day 4/4/03 4/4/03 96 Machine parts 26 days 4/22/03 5/28/03 97 Weld SS subassy 1 2 days 6/3/03 6/4/03 96 98 Weld SS subassy 2 2 days 6/3/03 6/4/03 96 99 Final weld 2 days 6/17/03 6/18/03 97,98 100 Final machine 5 days 6/19/03 6/25/03 99 101 vacuum process 0 days 6/25/03 6/25/03 100 102 SLED tuner drive 51 days 4/10/03 6/20/03 103 machine parts 32 days 4/10/03 5/23/03 104 assm. System 10 days 6/2/03 6/13/03 103 105 commission controls 5 days 6/16/03 6/20/03 104 June July August September 5/25 6/1 6/8 6/15 6/22 6/29 7/6 7/13 7/20 7/27 8/3 8/10 8/17 8/24 8/31 9/7 6/20/03 Phase 1 schedule 04-03 Page 1 THIS SCHEDULE CHANGES FREQUENTLY. CHECK THE DATE ON LINE #1 - DCS 6/20/03

ID Task Name Duration Start Finish Predecessors 106 Installation 81 days 5/7/03 9/4/03 107 splitter done 0 days 6/26/03 6/26/03 24 108 pump T done 0 days 6/25/03 6/25/03 94 109 cross potent done 0 days 7/14/03 7/14/03 2 110 couplers done 0 days 6/19/03 6/19/03 53 111 combiner done 0 days 6/26/03 6/26/03 39 112 SLED tuner drive done 0 days 6/20/03 6/20/03 102 113 load processing 44 days 5/7/03 7/15/03 114 process 4 loads 8 days 5/7/03 5/16/03 115 swap and bake 6 days 5/19/03 5/27/03 114 116 process 3 loads 6 days 6/2/03 6/9/03 115 117 swap 2 and bake 4 days 6/11/03 6/16/03 116 118 process 3 loads 4 days 6/17/03 6/20/03 117 119 swap and bake 6 days 6/23/03 7/7/03 118 120 process 2 loads and hybrids 6 days 7/8/03 7/15/03 119 121 SLED 48 days 5/12/03 7/24/03 122 install SLED tubes 17 days 5/12/03 6/16/03 90FS-3 days,93ff+1 123 cold test SLED tubes 7 days 6/17/03 6/25/03 122 124 Assemble full SLED (pump T's) 5 days 6/26/03 7/9/03 123,108,112 125 cold test SLED lines 3 days 7/10/03 7/14/03 124 126 cold test SLED with XP 3 days 7/22/03 7/24/03 125,128 127 combiner - cross potent 16 days 7/15/03 8/5/03 128 cold test cross potent - irises 5 days 7/15/03 7/21/03 109 129 mount combiner - cross potent 3 days 7/25/03 7/29/03 111,110,126 130 cold test 5 days 7/30/03 8/5/03 129,121 131 splitter - loads 22 days 6/11/03 7/17/03 132 mount 4 loads to a quadrupus 5 days 6/11/03 6/17/03 114 133 cold test 3 days 6/18/03 6/20/03 132 134 mount 4 loads to a quadrupus 5 days 6/23/03 6/27/03 118 135 cold test 3 days 7/7/03 7/9/03 134 136 mount splitter - loads 3 days 7/10/03 7/14/03 107,133,135 137 cold test 3 days 7/15/03 7/17/03 136 138 attach system together 3 days 8/6/03 8/8/03 121,127,131,110,137 139 cold test 5 days 8/11/03 8/15/03 138 140 bake system 14 days 8/18/03 9/4/03 141 wrap 5 days 8/18/03 8/22/03 139 142 ramp up (2 shifts) 1 day 8/25/03 8/25/03 141 143 bake (inc. 1 weekend) 5 days 8/26/03 9/1/03 142 144 ramp down (2 shifts) 1 day 9/2/03 9/2/03 143 145 unwrap/connect 2 days 9/3/03 9/4/03 144 146 Begin System Commissioning 0 days 9/4/03 9/4/03 106 June July August September 5/25 6/1 6/8 6/15 6/22 6/29 7/6 7/13 7/20 7/27 8/3 8/10 8/17 8/24 8/31 9/7 6/20/03 Phase 1 schedule 04-03 Page 2 THIS SCHEDULE CHANGES FREQUENTLY. CHECK THE DATE ON LINE #1 - DCS 6/20/03