Agenda Meeting name CUSC Modifications Panel Meeting number 204 Date of meeting 31 March 2017 Time 10:00 14:00 Location Teleconference Number National Grid House, Warwick 0808 2389819, Participant Code 81833258# Item Topic Lead Action Documents 1 Introductions/Apologies for Absence Chair 2 Minutes of the Panel meetings held on 24 February 2017 All Agree 3 Review of Actions Minute 5604: HC to ensure that the lessons learnt exercise carried out by CMP262 Workgroup to be shared at a future Panel meeting. Minute 5757: to discuss the process of appointing external consultants and funding requirements for Workgroups with National Grid and to report back to the Panel and also to investigate if generic analysis could be identified and collected to better understand what the impact on consumers is so that it can be utilised for current and future modifications. Minute 5767: Run a lesson learnt on CMP264/CMP265 following January 2017 Panel meeting. Minute 6100: NH to get a view on the funding process within Ofgem and to HC NH/
produce one pager slide, indicating where in the licence the Proposer or National Grid is required to complete analysis. Minute 6020: Panel to provide feedback to regarding Joint Code Administrator Forward Work Plan report. Minute 6079: GG to address the issue of modifications being raised by parties following their proposals being rejected as WACMs by Workgroups at GSG. Minute 6110: to review and issue the updated Terms of Reference for CMP271/274 timetable which will be capture the updated timetable as per JA s query. Minute 6114: NH to clarify from an Ofgem perspective whether and if required what further analysis is needed to progress CMP250. Minute 6135: to send out draft CMP276 Terms of Reference to the Panel utilising CMP271/274 and the additional comments from AP. Then Panel members to review and provide any additional points back to the Code Administrator. Minute 6136: to review the Workgroup membership and provide an update at the next Panel meeting for CMP271, CMP274 and CMP276. Minute 6138: to request a legal view on the Pending Modifications definition in the CUSC. Minute 6148: AW agreed to check whether the Requirements for Generators work would impact the CUSC exhibits. Minute 6153: NH to clarify the timeline for CMP251 and if a further consultation will be required on CMP261. All GG NH NH Complete Page 2 of 6
Minute 6157: to get a view on what would happen if a non CUSC Party raised a modification and whether 8.12 would still be applicable. Minute 6159a: agreed to come back to March or April CUSC Panel, to gain views from Panel members on the options for a joint Independent Panel Chair appointment process. Minute 6159b: AW to review whether National Grid will take a view on a joint Panel Chair and the clarification of whether the Code Administrator is acting as a representative for National Grid. Minute 6163: AW to take an action to clarify when Transmission Owners are required to review their Modification Application fees. AW also to send James Abrahams details to GG. 4 New CUSC Modification Proposals CMP277 Special License Condition 4J SM Proposal Attached (late paper) & Presentation CMP278 BSIS 2017 Housekeeping SM Proposal Attached (late paper) & Presentation 5 Workgroups/Standing Groups & Review of Plan on a Page Review of CUSC Modifications Plan on a Page Presentation CMP250 Stabilising BSUoS with at least a twelve month Page 3 of 6
notice period. CMP261 Ensuring the TNUoS paid by Generators in GB in Charging Year 2015/16 is in compliance with the 2.5/MWh annual average limit set in EU Regulation 838/2010 Part B (3). CMP268 Recognition of sharing by Conventional Carbon plant of Not-Shared Year-Round circuit CMP271 Improving the cost reflectivity of demand transmission charges And CMP274 Winter TNUoS Time of Use Tariff (TToUT) for Demand TNUoS CMP275 Transmission generator benefits in the provision of ancillary and balancing services levelling the playing field. CMP276 Socialising TO costs associated with "green policies" Governance Standing Group GG Transmission Charging Methodologies Forum CUSC Issues Standing Group 6 European Code Development NH GG Page 4 of 6
Joint European Stakeholder Group 7 Authority Decisions as of 23 March 2017 NH 8 on Industry Codes/General Industry s relevant to the CUSC General All 9 AOB All 10 Notification of Future Meetings: Monthly CUSC Panel Meetings for 2017 (10:00 to 14:00): Meeting No 205: 28 April 2017 at National Grid House, Warwick Meeting No 206: 26 May 2017 at National Grid House, Warwick Meeting No 207: 30 June 2017 at National Grid House, Warwick Meeting No 208: 28 July 2017 at National Grid House, Warwick Meeting No 209: 25 August 2017 at National Grid House, Warwick Meeting No 210: 29 September 2017 at National Grid House, Warwick Meeting No 211: 27 October 2017 at National Grid House, Warwick Meeting No 212: 24 November 2017 at National Grid House, Warwick Meeting No 213: 15 December 2017 at National Grid House, Warwick Attendees Name Initials Position Mike Toms MT Panel Chair John Martin Code Administrator Lurrentia Walker LW Panel Secretary (alternate) Nikki Jamieson National Grid Panel Member Garth Graham GG Users Panel Member Simon Lord SL Users Panel Member Cem Suleyman CS Users Panel Member James Anderson JA Users Panel Member Paul Mott PM Users Panel Member Kyle Martin (dial-in) KM Users Panel Member Paul Jones PJ Users Panel Member Nicholas Rubin NR ELEXON Andy Pace AP Consumers Panel Member Nadir Hafeez (dial-in) NH Authority Representative Stephen McAllister SM CMP277/CMP278 Proposer (National Grid) Peter Bolitho PB Waters Wye (Observer and Representing the below) Page 5 of 6
Calon Energy Eggborough Power Limited VPI Immingham Intergen Apologies Name Initials Position Heena Chauhan HC Panel Secretary Page 6 of 6