Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi)

Similar documents
The ESS Accelerator. For Norwegian Industry and Research. Oslo, 24 Sept Håkan Danared Deputy Head Accelerator Division Group Leader Beam Physics

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

The PEFP 20-MeV Proton Linear Accelerator

ESS: The Machine. Bucharest, 24 April Håkan Danared Deputy Head Accelerator Division. H. Danared Industry & Partner Days Bucharest Page 1

Workshop on Accelerator Operations August 6-10, 2012 Glen D. Johns Accelerator Operations Manager

Upgrading LHC Luminosity

The Construction Status of CSNS Linac

Beam Losses During LCLS Injector Phase-1 1 Operation

Proton Engineering Frontier Project

Beam Loss Detection for MPS at FRIB

Preparations for Installation, Testing and Commissioning based on Experience at CERN, SNS and Siemens

RF plans for ESS. Morten Jensen. ESLS-RF 2013 Berlin

Linac 4 Instrumentation K.Hanke CERN

PRESENT STATUS OF J-PARC

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

COMMISSIONING SCENARIOS FOR THE J-PARC ACCELERATOR COMPLEX

DELIVERY RECORD. Location: Ibaraki, Japan

P. Emma, et al. LCLS Operations Lectures

The FAIR plinac RF Systems

ESS Linac WP8 Radio Frequency Systems and Test Facilities

RF considerations for SwissFEL

Karin Rathsman, Håkan Danared and Rihua Zeng. Report from RF Power Source Workshop

Particle Beam Production - A Synchrotron-Based System - Prof. Dr. Thomas Haberer Scientific-technical Director Heidelberg Iontherapy Center

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

HIGH-INTENSITY PROTON BEAMS AT CERN AND THE SPL STUDY

OPERATIONAL EXPERIENCE AT J-PARC

CLIC Feasibility Demonstration at CTF3

A HIGH-POWER SUPERCONDUCTING H - LINAC (SPL) AT CERN

Low Level RF for PIP-II. Jonathan Edelen LLRF 2017 Workshop (Barcelona) 16 Oct 2017

Empirical Model For ESS Klystron Cathode Voltage

30 GHz Power Production / Beam Line

Design of the linear accelerator for the MYRRHA project

A Fifteen Year Perspective on the Design and Performance of the SNS Accelerator

Dark current and multipacting trajectories simulations for the RF Photo Gun at PITZ

APT Accelerator Technology

INFN School on Electron Accelerators. RF Power Sources and Distribution

PEP II Design Outline

ESS Linac WP8 Radio Frequency Systems and Test Facilities

BEAM DYNAMICS AND EXPERIMENT OF CPHS LINAC *

Basic rules for the design of RF Controls in High Intensity Proton Linacs. Particularities of proton linacs wrt electron linacs

Detailed Design Report

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

DESIGN OF 1.2-GEV SCL AS NEW INJECTOR FOR THE BNL AGS*

4.4 Injector Linear Accelerator

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY

Pulsed Klystrons for Next Generation Neutron Sources Edward L. Eisen - CPI, Inc. Palo Alto, CA, USA

The Elettra Storage Ring and Top-Up Operation

Digital BPMs and Orbit Feedback Systems

Concept and R&D Plans for Project X

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

J/NLC Progress on R1 and R2 Issues. Chris Adolphsen

New La'ce Import Status. Karin Rathsman

LIGHT PROTON THERAPY PROJECT

What can be learned from HERA Experience for ILC Availability

A New High Intensity Proton Source. The SCRF Proton Driver. (and more!) at Fermilab. July 15, Bill Foster SRF2005

Karin Rathsman. Calculations on the RF Source and Distribution

Status of the SNS Linac: An Overview N. Holtkamp for the SNS Collaboration ORNL, Oak Ridge, TN 37830, USA

The SPL at CERN. slhc. 1. Introduction 2. Description. 3. Status of the SPL study. - Stage 1: Linac4 - Stage 2: LP-SPL - Potential further stages

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting

SNS Target Imaging and Related Developments

THE OPERATION EXPERIENCE AT KOMAC*

Present Status and Future Upgrade of KEKB Injector Linac

Status of CTF3. G.Geschonke CERN, AB

TITLE PAGE. Title of paper: PUSH-PULL FEL, A NEW ERL CONCEPT Author: Andrew Hutton. Author Affiliation: Jefferson Lab. Requested Proceedings:

The Beam Test Facility at the SNS

HIGH POWER BEAM DUMP AND TARGET / ACCELERATOR INTERFACE PROCEDURES *

Status of the X-ray FEL control system at SPring-8

Status of RF Power and Acceleration of the MAX IV - LINAC

LCLS Injector Technical Review

The European Spallation Source

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

DISCLAIMER. Portions of this document may be illegible in electronic image products. Images are produced from the best available original document.

Towards an X-Band Power Source at CERN and a European Structure Test Facility

Hall-B Beamline Commissioning Plan for CLAS12

LLRF at SSRF. Yubin Zhao

The LEP Superconducting RF System

SRS and ERLP developments. Andrew moss

PEP-I1 RF Feedback System Simulation

Current status of XFEL/SPring-8 project and SCSS test accelerator

Suggested ILC Beam Parameter Range Rev. 2/28/05 Tor Raubenheimer

Status of SOLARIS Arkadiusz Kisiel

Welcome and FRIB Project Status. FRIB Highlights and Plan Ahead

Radiation Safety System for Stanford Synchrotron Radiation Laboratory*

BBU threshold current study for 6 GeV beam in 12 GeV beamline setup

Electron linac photo-fission driver for rare isotope program at TRIUMF

XFEL High Power RF System Recent Developments

PEP-II Overview & Ramp Down Plan. J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007

TOWARDS THE COMMISSIONING OF J-PARC

A HIGH POWER LONG PULSE HIGH EFFICIENCY MULTI BEAM KLYSTRON

G0 Laser Status Parity Controls Injector Diagnostics

Availability and Reliability Issues for the ILC

Studies on an S-band bunching system with hybrid buncher

Status of the FAIR Project. Jürgen Henschel FAIR Project Leader / Technical Director GSI & FAIR

CERN S PROTON SYNCHROTRON COMPLEX OPERATION TEAMS AND DIAGNOSTICS APPLICATIONS

SMTF Beta <1 Front End Linac Infrastructure and Plans

EPJ Web of Conferences 95,

Synchrotron Light Facility. Operation of ALBA RF. Angela Salom on behalf of RF team: Francis Perez, Bea Bravo and Jesus Ocampo

FINAL DESIGN OF ILC RTML EXTRACTION LINE FOR SINGLE STAGE BUNCH COMPRESSOR

FIRST SIMULTANEOUS TOP-UP OPERATION OF THREE DIFFERENT RINGS IN KEK INJECTOR LINAC

Linac3 experience for LHC ion runs

Transcription:

Commissioning of Accelerators Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi) www.europeanspallationsource.se 6 July, 2017

Contents General points Definition of Commissioning Adapting it to Accelerators Commissioning and Installation System Commissioning Moving to Initial Operations Commissioning of instruments Personal and moving experience Optimizing Commissioning 2

What is commissioning Commissioning: Process by which an equipment, facility, or plant (which is installed, or is complete or near completion) is tested to verify if it functions according to its design objectives or specifications. 3

Commissioning particle accelerators Unique systems in general. Most accelerators are based in individual design. Makes predicting the commissioning proces challeging Even ones based in previous design would be diferent enough to require specific commissioning In general is in multiple steps Injector then storage ring Different sections of the LINAC Could be in parallel to part of the installation 4

Beam Commissioning and Systems Commissionig could only start after installation is almost finish. Delays in the installation tend to reduce the avalaible time for commissioning Two main periods in the commissioning System Commissioning: Each individual system is tested, optimized, and verify to reach the nominal parameters, WITHOUT producing beam Beam Commissioning: Optimize the performance of the whole accelerator, detecting and mitigating the errors of the design, components and installating, and reaching the parameters required for Initial Operations. And Dry Runs to link the two stages 5

User s Instruments commissioning In a user facility (light source, spallation source, collider) the corresponding instrument scientist s need to commission their systems That could require a different set of parameters than operation Pressure in the accelerator commissioning to switch to instrument commissioning Both could run in paralel for a while 6

Moving to Operations Knowledge acquired during commissioning needs to be carried overt to operations Part of the commissioning is to document the information required for operations Having continuity in the team between commissioning and operations 7

Preparing for commissioning Beam time is expensive, so try always to use the beam Have a plan for the commissioning (and be prepare to modify it often) Define clear procedures to perform the basic tasks of the commissioning Test the software using virtual accelerator Train the commissioning team in the use of the most common tools before hand Simulate at least some of the procedures using a virtual accelerator Use tools like OpenXAL or MML Borrow, steal and copy from similar projects: reuse code, do not try to reinvent the wheel 8

Commissioning crew Composition of the team Try to involve the operators as soon as possible: Experience carried over to operations Operators vs experts Operators are in general more careful and methodic Experts should guide the commissioning Accelerator physicist involved in the majority of the task of Beam Commissioning In-house team vs external experts External experts could join for clear defined tasks 9

The Low Energy Beam Transport (LEBT) matches the beam to the RFQ input Proton source creates the beam Solenoid focuses the beam Iris controls the current Chopper and collimator controls the pulse length ACCT measures current Courtesy Oystein Midttun

Solenoid scan in the LEBT 11

ESS Commissioning ESS Timetable Commissioning steps Defining the procedures Simulations 12

Accelerator overview Tuning Dump Parameter Value Units Max energy 2 GeV Peak current 62.5 ma Repetition Rate 14 Hz Pulse length 2.86 ms Average Power 5 MW RF Frequency 352/704 MHz Maximum losses Species 1 W/m Proton Device Total Number RFQ 1 DTL tanks 5 Spokes Tanks 13 Spokes Cavities 26 Cryo tanks (M-β) 9 RF cavities (M-β) 36 Cryo tanks (H-β) 21 RF cavities (H-β) 84 Klystrons/IOTs 120 Modulators 30-60 13

Considerations about the commissioning ESS would operate with a long pulse (2.86 ms). High peak current: 62.5 ma-> space charge dominates at low energy Only 1.4 MW at end of commissioning Only beam stop to accept the nominal parameters is the Target The straight ahead tuning dump can take a full 2.86 ms pulse but only every ~30 s Most of the (invasive) diagnostic could not cope with the long pulse Large percentage of In-Kind contribution Start using a Local Control Room 14

Systems should be fully tested and commissioned before start of Beam Commissioning (BC) Beam diagnostic, Low level RF, would need the beam Staged Commissioning, in parallel to installation Could require temporary dumps and diagnostic Temporary shielding wall for parallel installation Temporary beam stops (details under consideration) HBL cavities not installed, reduced power (0.57 GeV) at the end of commissioning 15

Staged Commissioning Warm Linac: Mostly at 1 Hz, 5/50 µs beam (limited by the shielding wall) SC to Dump Mostly at 1 Hz, 5/50 µs beam, some test with longer pulses at slow repetition rate (limited by tuning dump) Linac to Target Starting with 1 Hz, 5 µs beam, ramping up to 2.86 ms 16

Logic and Milestones (P6) 17

Linac Commissioning schedule Step Period Max Energy ISrc - LEBT February-March 2018 75 kev ISrc - MEBT September-October 2018 3.7 MeV ISrc - DTL4 January-March 2019 75 MeV ISrc - DMPL 3rd quarter 2019 571 MeV ISrc - Target End 2019-Early 2020 571 MeV/ 1.3 GeV * Dates as 19 January 2017, but they are only a first aproximation

Sequence for commissioning to Target (no HBL cavities) Staged commissioning, in parallel to installation! IS-LEBT IS-LEBT-RFQ-MEBT IS-LEBT-RFQ-MEBT-DTL1-DTL2-DTL3-DTL4 Beam stoped at FC cups IS-LEBT-RFQ-MEBT-DTL1-DTL2-DTL3-DTL4-DTL5-SC Linac HEBT-Dump IS-LEBT-RFQ-MEBT-DTL1-DTL2-DTL3-DTL4-DTL5-SC Linac HEBT-A2T-Target 19

Temporary tunnel configuration for warm linac staged commissioning Front End Building (FEB) Beam direction FC with extra shielding Installation operations Temporary Front-end equipment access (with removable shield blocks) Regular front end personnel access 2016-Jan-20 Stubs and cable penetrations with final shielding configuration Temporary shield wall separating warm and cold linac activities 20

Beam Modes (Operational Envelopes) used for early commissioning (NCL) Name Description Characteristics Notes B0 No Beam No beam No beam B1 Probe Beam 5 µs @ 1Hz Used for initial tune up B2 Fast Tuning 5 µs @ 14 Hz limited beam loading; used for fast scans (e.g. RF and Wire scanners) B3 Slow tuning 50 µs @ 1 Hz Beam loading studies, limit of invasive diagnostics B4 Long pulse 2.86 ms @ 1/30 Hz Only use when tunes up. Ion source verification is capable of ~ 90mA * 6ms @ 14Hz. RF feed forward, Beam loading, Lorenz Investigating hardware methods to limit rate and detuning pulse compensation. Beam loss length for commissioning. minimization B5 Production 2.86 ms @ 14 Hz Normal operation with high power The temporary shielding wall will set the limit of the B6 Mixed mode 2.86 ms @ 1/60 Hz, TBC. May want to keep low power pilot beam modes to use. IS limited to 1 Hz, 3 ms pulse interleaved with beam on between high power pulses if 50 µs @ 1 Hz running pulse on demand. 2016-Jan-20 Supporting document: ESS-0038258 21

Local Control Room MCR will not be ready in time for BC We will use the Local Control Room, located at the end of the Gallery, in the Cryo Control Room 22

Courtesy R. Mudingay 23

SC BC Summary 1. Beam on tuning dump (demonstration?) in late 2019 at 571 MeV 2. Beam on target in late 2020 at 1.3 GeV Still needs to be confirmed 24

Stage 2: SC Linac to Dump Beam: Probe, Fast and Slow tuning, Long pulse verification(?), hybrid(?) The tuning dump has a limited capability, it will mostly use in short (5 to 50 µs pulses) Max Energy: 571 MeV Beam destination: Tuning dump plus any beam stop in the Linac 25

Steps Step 1: NCL recommissioning and DTL5 commissioning: Verify that the NCL up to DTL4 recovers to the previous configuration Beam to the exit of DTL5 (measurements using the dump in the Spokes) Optimize transmission Corrected trajectory Matched optics Objectives: Energy at the end of DTL5: nominal 89.6 MeV, minimum required 89 MeV Transmission > 99±1% Current > 30 ma Step 2: Spokes Beam to the exit of Spokes (measurements using the dump in the MBL) Optimize transmission Corrected trajectory Matched optics Objectives: Energy at the end of spokes: nominal 226 MeV, minimum required 200 MeV Transmission > 98±1% Current > 30 ma Step 3: Medium beta linac, MBL, MBL and beam transport to Tuning Dump Beam to the exit of MBL Beam transported to the Tuning Dump Optimize transmission Corrected trajectory Matched optics Objectives: Energy at the end of MBL: nominal 570 MeV, minimum required 475 MeV Transmission > 98±1% Current > 30 ma Beam Power: Objective 1 kw, minimum accepted 0.7 kw Step 4: 1/30 Hz, 2.86 ms beam to Tuning Dump 26

Stage 3 : SC Linac to Target - 1 st neutrons Beam: Probe beam. First production of neutrons. Max Energy: 571 MeV or 1.3 GeV Two steps Step 1: A2T/Dogleg commissioning Step 2: ~570 MeV (or 1.3 GeV), <5 µs, <10mA, 1/10 Hz to Target, Raster system off, ~ 3 W of power on Target 27

Stage 4: Low Power in Target The objectives of this stage are to commission the beam instrumentation systems in the Target and the rastering system, as well as to set the DC optics of the A2T. All the steps will have a small power in the target, under 1 kw in all cases. Step 1: Probe beam (5 µs, 30 ma, 1 Hz, 570 MeV) on Target, ~ 85 W of Power on Target Step 2: Commissioning of Target Beam Instrumentation: using as short pulse as possible Step 3: Commissioning Slow Tuning (50 µs beam, 30 ma, 1 Hz), ~850 W of Power in Target Step 4: Commissioning of 14 Hz rep rate, using the Fast Tuning beam Step 6: Commissioning of Raster system (6 ma, 2.86 ms, 570 MeV, 1/10 Hz) ~ 1 kw of power on target 28

Stage 5: 2.86 ms beam commissionig The objectives of this stage are to commission the 2.86 ms beam, compare its parameters to the short pulse one and to verify the stability of the beam. Step 1: Increasing the pulse length to 2.86 ms, 1 Hz rep rate, <10 ma current, up to 16 kw of Power in Target Step 2: Verify parameters of the long pulse respect the short ones (trajectory, energy) Step 3: Medium term (8 h to 24 h) stability studies 29

Stage 6: SCL Power Ramp The objectives of this stage are to ramp the beam to the parameters required for NSS instrument commissioning and operation. Step 1: Optimization of the Accelerator for long pulse Objectives: Energy > 500 MeV Transmission: 99%±1 Rep Rate: 1 Hz Current: 30 ma Pulse length: 2.86 ma Power ~ 50 kw Step 2: Increase of the repetition rate to 14 Hz Step 3: Increase of the current to the nominal one Set the beam for instruments commissioning and operation 30