A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

Size: px
Start display at page:

Download "A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements"

Transcription

1 DRAFT 6 V4 Standard PRC-006- RFC-01 01/11/11 A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements Deleted: Deleted: 10 Deleted: Number: PRC 006 RFC 01. Purpose: To establish ReliabilityFirst requirements for automatic underfrequency Load shedding (UFLS) to support NERC Reliability Standard PRC Applicability: 4.1 Distribution Providers 4.2 Transmission Owners 4. Generator Owners 4.4 Planning Coordinators 5. (Proposed) Effective Date: Upon ReliabilityFirst Board Approval, the standard will be mandatory and enforceable (without monetary penalties for noncompliance) to applicable ReliabilityFirst members based on the PRC-006-RFC- 01 Implementation Plan and the enforcement mechanism will be as a Term Of Membership under the ReliabilityFirst By-Laws. B. Requirements R1 Upon regulatory approval, the standard will be mandatory and enforceable (with monetary penalties for non-compliance) to all applicable NERC registered entities within the ReliabilityFirst footprint based on the PRC-006-RFC-01 Implementation Plan Each Distribution Provider that has more than 50 feeders shall implement an automatic UFLS program for their facilities or each Distribution Provider (regardless of number of feeders) shall participate with one or more Distribution Providers to collectively implement by mutual agreement a single automatic UFLS program. Providers automatic UFLS program shall include the following: [Violation Risk Factor: High][Time Horizon: Long-term Planning] 1.1 Have the capability of shedding at least 25 percent of the Load. This shall be satisfied by implementing the load shedding capability based on the forecasted annual peak hour. 1.2 Shed Load in a minimum of three steps. 1. Size each step equally where the variance between steps shall be no more than two percent of forecasted annual peak hour Load (additional Load shedding required per Requirement R9 or Requirement R11 is excluded from this requirement). 1.4 The first frequency set point shall not be lower than 59. Hz and not be higher than 59.5 Hz. Deleted: (all generators with an individual nameplate rating or plants, including Wind Generating Stations, with an aggregate nameplate rating of 20 MVA or greater, connected at 69kV or above) Deleted: The first day of the first calendar quarter, one year after applicable regulatory approval Formatted: Font: Not Bold Deleted: ; or in those jurisdictions where no regulatory approval is required, the first day of the first calendar quarter one year after Board of Trustees adoption. Deleted: Formatted: Font: Not Bold Formatted: Indent: Left: 6 pt, Hanging: 6 pt, No bullets or numbering Deleted: Deleted: Upon Board Approval Deleted: Deleted: Deleted: include the following requirements Deleted: Deleted: at peak based on the forecasted annual peak hour. Deleted: sub-requirement Deleted: may Deleted: planning and Deleted: Check for definition Formatted: Highlight Deleted: ( Deleted:. Deleted: ) Deleted: Deleted: 4 Deleted: be Approved: XXXX XX, 201X Page 1 of 19 Effective Date: XX/XX/XX

2 Deleted: Standard PRC-006- RFC-... [1] DRAFT 6 V4 Standard PRC-006- RFC-01 01/11/11 Deleted: be ot be... [2] Deleted: or Requirement R11R4... [] R2 R 1.5 The last frequency set point shall not be lower than 58.5 Hz and not be higher than 58.7 Hz (additional Load shedding required per Requirement R9 or Requirement R11 is excluded from this requirement). 1.6 The difference between frequency set points shall be at least 0.2 Hz but no greater than 0.5 Hz (additional Load shedding required per Requirement R9 or Requirement R11 is excluded from this requirement). 1.7 Intentional relay time delay shall be no greater than 20 cycles. For installations where motor loads or distributed generation may be isolated, additional supervision (e.g. undercurrent) shall be used to avoid false operation during Fault isolation. 1.8 Undervoltage inhibit (where applicable) shall be set as low as practical, but shall not be greater than 75 percent of nominal primary voltage. Each Distribution Provider, that has less than or equal to 50 feeders and has not aggregated their Load with other Distribution Providers to implement a collective UFLS program, shall implement a modified UFLS program as defined below. Providers modified automatic UFLS program shall include the following: [Violation Risk Factor: High][Time Horizon: Long-term Planning] 2.1 Have the capability of shedding at least 25 percent of the Load. This shall be satisfied by implementing the load shedding capability based on the forecasted annual peak hour. 2.2 Intentional relay time delay shall be no greater than 20 cycles. For installations where motor loads or distributed generation may be isolated, additional supervision (e.g. undercurrent) shall be used to avoid false operation during Fault isolation. 2. Undervoltage inhibit (where applicable) shall be set as low as practical, but shall not be greater than 75 percent of nominal primary voltage. 2.4 Either of the following frequency set points: Single frequency set point at 59.0 Hz Two frequency set points, with approximately equal amounts of load, at 59.0 Hz and 58.7 Hz (the variance between steps shall be no more than five percent of forecasted annual peak hour Load) Each Transmission Owner shall provide automatic switching of its existing capacitor banks and reactors to control over-voltage as a result of an UFLS event in accordance with the assessment performed by the Planning Coordinator in Requirement R16. [Violation Risk Factor: Medium][Time Horizon: Long-term Planning] Deleted: or Requirement R [4] Deleted:... [5] Deleted: [Violation Risk Factor: High][Time... [8] Formatted... [6] Deleted: Each Transmission Owner owning... [7] Deleted: Formatted... [9] Formatted... [11] Formatted... [10] Formatted... [12] Formatted... [1] Formatted... [14] Formatted... [15] Formatted... [16] Deleted: does not comply with sub-requirements... [22] Formatted... [2] Deleted: Formatted... [21] Deleted: Deleted: 1 Deleted:.1 Deleted:. Deleted: 1 Deleted: Single frequency set point at Hz [24] Deleted: Deleted: 1 Formatted... [17] Formatted... [18] Deleted: 5 Deleted: 1.5 Deleted: Deleted: If a Deleted: Each Distribution Provider, that has... less [19] Deleted: R4 Each Planning Coordinator shall have a documented methodology to determine areas of credible islanding. The methodology shall include the following: [Violation Risk Factor: Medium][Time Horizon: Long-term Planning] Approved: XXXX XX, 201X Page 2 of 19 Effective Date: XX/XX/XX Deleted: their Load with other Distribution... [20] Deleted:.2 Deleted: 5 Deleted:. Deleted: 2 Deleted: Two frequency set points, with equal... [25] Formatted... [26] Formatted... [27] 1.6 The difference between frequency... [28] Deleted: 2 Deleted: and implement a Deleted: ed Comment [A1]: if you are not defining "area" -... [29]

3 Deleted: Standard PRC-006- RFC-... [2] DRAFT 6 V4 Standard PRC-006- RFC-01 01/11/11 Deleted: ]: Formatted... [] Formatted... [4] R5 R6 R7 R8 R9 4.1 Consideration of historical islanding scenarios 4.2 Consideration of areas with a limited number of connecting lines 4. Consideration of System Operating Limit interfaces which define importing areas 4.4 A process to involve stakeholders in the analysis and results Each Planning Coordinator shall make its credible island determination methodology available for inspection and technical review by those entities directly and materially affected by the reliability of ReliabilityFirst Bulk Electric System (BES), within 15 calendar days of the receipt of a request. [Violation Risk Factor: Lower][Time Horizon: Long-term Planning] Each Planning Coordinator shall provide a written response to that commenting entity that is materially affected by the reliability of ReliabilityFirst BES, within 45 calendar days of receipt of those comments. The response shall indicate whether a change will be made to the credible island determination methodology and, if no change will be made, the reason why. [Violation Risk Factor: Lower][Time Horizon: Long-term Planning] Each Planning Coordinator shall use the credible island determination methodology at least every five years to determine areas of credible islanding, which have a forecasted annual peak hour Load of greater than 1,000 MW, that are within or partially within their area of responsibility. [Violation Risk Factor: Medium][Time Horizon: Long-term Planning] Each Planning Coordinator shall supply the results of applying the island methodology within 0 calendar days of completion of the process to the Distribution Providers, Transmission Owners and Generator Owners in the identified areas of credible islanding. [Violation Risk Factor: Lower][Time Horizon: Long-term Planning] Each Planning Coordinator shall establish a mitigation plan that specifically addresses generation/load imbalances in the area of credible islanding (as determined in Requirement R7). The mitigation plan shall consist of one or both of the following: [Violation Risk Factor: Medium][Time Horizon: Long-term Planning] 9.1. Installation of additional UFLS capability of Distribution Providers in the island area so as to cover potential generation/load imbalances in excess of the 25 percent specified in R1.1 or R2.1where the amount of additional UFLS capability Load to be shed in the island area and the corresponding Load shedding step sizes, relay trip and time delay settings of the additional UFLS capability shall be determined by engineering assessments. Each Planning Coordinator shall exempt Distribution Providers from installing total UFLS capability greater than 50 percent of their forecasted annual peak hour Load in the island area. Approved: XXXX XX, 201X Page of 19 Effective Date: XX/XX/XX Formatted... [5] Deleted: H Formatted... [6] Deleted: A Deleted: Formatted... [7] Formatted... [8] Deleted: S Formatted... [9] Formatted... [40] Formatted... [41] Deleted: 2.1 Deleted: business Formatted... [42] Deleted: 2.2 If entities directly and materially... [4] Formatted... [44] Formatted... [45] 2. Deleted: ach Planning Coordinator shall... use [46] Deleted: Formatted... [47] Formatted... [48] Deleted: 7 Deleted: 2.4 Deleted: Deleted: s of the determination (... [49] Deleted: Deleted: ) eliabilityfirst footprint of Deleted: (or sub areas) Deleted: 8 Deleted: Deleted: Distribution Provider, Transmission... [50] Deleted: (or sub areas) Deleted: of credible islanding (as determined... in [51] Formatted... [52] Deleted: participate in the engineering assessment... [5] Formatted... [54] Deleted: 2. The mitigation plan must be... [55] Formatted... [56] Deleted: h of the following: [Violation Risk... [57].1 Distribution Providers shall... utilize [58] Deleted: Deleted: Deleted: 8 Deleted: [59] Deleted: Install nstallation of additional UFLS... [60] Deleted: ( Deleted: he island area and the corresponding... [61] Deleted: )

4 DRAFT 6 V4 Standard PRC-006- RFC-01 01/11/11 Deleted: Standard PRC-006- RFC-... [62] R10 R11 R12 R1 9.2 Apply other methods of balancing Load and resources. Each Distribution Provider, Transmission Owner and Generator Owner in an identified area of credible islanding (as determined in Requirement R7) shall participate in the establishment of the mitigation plan (as required in Requirement R9). [Violation Risk Factor: Lower][Time Horizon: Long-term Planning] Each Distribution Provider, Transmission Owner and Generator Owner shall implement the mitigation plan as determined in Requirement R9 within three years of the completion of the mitigation plan. [Violation Risk Factor: Medium][Time Horizon: Long-term Planning] Each Generator Owner that owns a unit(s) with automatic underfrequency protection installed, shall set such protection in accordance with the minimum tripping time delays in Table 1, or if automatic underfrequency protection is not installed, the Generator Owner s underfrequency tripping procedures shall conform to Table 1: [Violation Risk Factor: Medium][Time Horizon: Long-term Planning] Table 1 Frequency (Hz) Minimum Time Delay (Sec) 59.5 Automatic Frequency Dependent Tripping Not Permitted <59.5 to > , to > to > Owner s Discretion 12.1 It is the sole responsibility of each Generator Owner to ensure that the time vs. frequency requirement listed in Table 1 is met. In those cases where a generator must be tripped for its own underfrequency protection outside the specifications in the above Table 1, each Generator Owner may become compliant by arranging for Load shedding, to be installed by mutual agreement with Distribution Providers, in addition to that required in Requirement R This additional Load shedding shall be equal to or greater than the generator MW dispatch, instituted at the same frequency and time as the generator would be expected to trip If the generator is located within a credible island, arrangement for additional Load shedding shall be within the credible island. Each Planning Coordinator shall establish and maintain an UFLS database. [Violation Risk Factor: Lower][Time Horizon: Long-term Planning] 1.1 The database shall be updated every five calendar years or as required by changes in system conditions. Deleted: Formatted: Don't keep lines together Deleted: Identified areas (or sub areas) of credible islanding with a forecasted annual... [6] Deleted: Distribution Providers are not... [64].1.1. Upon determination of... a new [65] Deleted: Deleted:.1.2 Deleted: 8 Deleted:... [66] Deleted: Identified areas (or sub areas)... of [67] Formatted... [68] Formatted: Indent: Left: 0 pt, First line: 0 pt Deleted: Upon determination of a new... [69].2 Each Generator Owner in... [70] Formatted: Indent: Hanging: 6 pt Deleted: 9 Each Distribution Provider,... [71] Formatted: Not Highlight Deleted: of identification of a new credible... island [72] Deleted: 4 Deleted: High Deleted: 4 4 Deleted: 1 4 Deleted: 1 Deleted: 5 Deleted: 1 Each Planning Coordinator shall... [7] 5 1 The database shall be updated... [74] 1.2 The database shall include the areas of credible islanding determined in Requirement R The database shall include the... [75] Approved: XXXX XX, 201X Page 4 of 19 Effective Date: XX/XX/XX

5 Deleted: Standard PRC-006- RFC-... [76] DRAFT 6 V4 Standard PRC-006- RFC-01 01/11/11. R14 R15 R16 Each Distribution Provider and Transmission Owner required to comply with the relevant sections of Requirement R1, Requirement 2 or Requirement R11,shall provide their Planning Coordinator the following data in a pre-arranged format to populate the UFLS database within 45 calendar days of the Planning Coordinators request: [Violation Risk Factor: Lower][Time Horizon: Long-term Planning] 14.1 Frequency trip points Percent of forecasted peak hour Load dropped at each trip point. 14. Relay operating time delay, intentional and unintentional Circuit breaker operating time UFLS relay undervoltage inhibit voltage level Information describing non-fault clearing tie-tripping schemes, islanding schemes, automatic load-restoration schemes, additional Load shedding schemes or any other schemes that are part of or impact the UFLS programs in sufficient detail to allow modeling for dynamics simulations 14.7 Any underfrequency trip set points, all overvoltage trip set points and time delays of capacitor banks connected to the BES. Each Generator Owner required to comply with the relevant sections of Requirement R11 or Requirement R12 shall provide their Planning Coordinator the following data in the pre-arranged format to populate the UFLS database within 45 calendar days of the Planning Coordinators request: [Violation Risk Factor: Lower][Time Horizon: Long-term Planning] 15.1 Underfrequency trip set points and time delays of each generating unit Information describing any other schemes that are part of or impact the UFLS program. Each Planning Coordinator shall perform and document an assessment of the effectiveness of the design and implementation of the UFLS programs within its footprint. This assessment shall include effects of neighboring Planning Coordinator areas and may be performed jointly with other Planning Coordinators. This assessment shall be conducted periodically at least every five years or as required by changes in system conditions and shall include, but not be limited to the following: [Violation Risk Factor: Medium][Time Horizon: Longterm Planning] 16.1 A review of the current frequency set points and timing A review of automatic switching of existing capacitor banks and reactors to control over-voltage as a result of an UFLS event Approved: XXXX XX, 201X Page 5 of 19 Effective Date: XX/XX/XX Deleted: 2 Deleted: 6 Each Distribution Provider, nd... [77] Deleted:, Requirement R11 or R4... [78] Deleted: populate Deleted: needed Deleted: s FLS database ( ithin 45 calendar... [79] Deleted:, in the pre-arranged format Deleted:, as follows Deleted: : 6.1 Each Distribution Provider... and [80] Formatted... [81] Deleted:... [82] Deleted: 6 Deleted:.1 Formatted... [8] Deleted: 6 Deleted: 1.2 Deleted: T ip pp... [84] Formatted... [85] Deleted: 6 Deleted: 1. Formatted... [86] Deleted: 6 Deleted: 1.4 Formatted... [87] Deleted: 6 Deleted: 1.5 Formatted... [88] Deleted: 6 Deleted: 1.6 Formatted... [89] Deleted: 6 Deleted: 1. Formatted... [90] Deleted: 6 Deleted: Deleted:.2 Deleted: supply the following information... as [91] Deleted: 5R6.2 1 Underfrequency trip... set [92] Formatted... [9] 6.2 Deleted: 4 Deleted: 7 Each Planning Coordinator shall... [94] Deleted: Lower [Time Horizon: Long-term... [95] Formatted... [96] Deleted: 4 7 Deleted:. Formatted... [97]

6 DRAFT 6 V4 Standard PRC-006- RFC-01 01/11/11 Deleted: Standard PRC-006- RFC-... [100] R17 R Dynamic simulation of possible Disturbances that cause the Planning Coordinators systems or portions of the Planning Coordinators systems to experience imbalances between Load and generation sufficient to cause activation of one or more steps of UFLS. Each Distribution Provider, Transmission Owner and Generator Owner for which UFLS or other protection system changes are recommended by the Planning Coordinators assessment, (as determined in Requirement R16) shall complete the changes within three years of the completion date of the Planning Coordinators assessment (as determined in Requirement R16). [Violation Risk Factor: Medium][Time Horizon: Long-term Planning] Each Planning Coordinator shall coordinate UFLS programs with neighboring Planning Coordinators and entities responsible for UFLS assessment. Coordination of UFLS programs shall be accomplished by the following; [Violation Risk Factor: Lower][Time Horizon: Long-term Planning] 18.1 Each Planning Coordinator shall provide the data in the database required in Requirement R14 and Requirement R15 to neighboring Planning Coordinators within ReliabilityFirst Each Planning Coordinator shall provide the data in the database required in Requirement R14 and Requirement R15 and assessment results required in Requirement R16 to neighboring entities responsible for UFLS assessment external to ReliabilityFirst. 18. Each Planning Coordinator shall request UFLS data and assessment results from neighboring entities responsible for UFLS assessment external to ReliabilityFirst. C. Measures The following documentation will be used to determine compliance with the above requirements. M1 M2 Each Distribution Provider that has more than 50 feeders shall have dated evidence such as lists summarizing feeder load armed with UFLS relays, lists with UFLS relay settings, or other dated documentation showing they implemented an automatic UFLS program for their facilities or shall have shall have dated evidence such as a dated mutual agreement along with lists summarizing feeder load armed with UFLS relays, lists with UFLS relay settings, or other dated documentation showing they participated with one or more Distribution Providers to collectively implement a single automatic UFLS program per Requirement R1. Each Distribution Provider that has less than or equal to 50 feeders and has not aggregated their Load with other Distribution Providers shall have dated evidence such as lists summarizing feeder load armed with UFLS relays, lists with UFLS relay settings, or other dated documentation showing they implemented a modified automatic UFLS program for their facilities per Requirement R2. Deleted: [101] Deleted:. Dynamic simulation of possible... [102] Formatted: Highlight Formatted: Indent: Left: 0 pt, First line: 0 pt Formatted: Not Highlight Deleted: 14 7 Deleted:.4 Deleted: Formatted... [10] Deleted: If Formatted: Not Highlight Deleted: FLS or other protection system... [104] Formatted... [105] Deleted:, Formatted: Not Highlight Deleted: the responsible entity has Formatted... [106] Deleted: from he approval... [107] Formatted: Not Highlight Deleted: report Formatted... [108] Deleted: to complete the changes Deleted: Deleted: 5 Deleted: 8 Deleted:. oordination of UFLS programs... [109] shall 8 1 Each Planning Coordinator... [110] shall 8 2 Each Planning Coordinator... [111] shall 8 Formatted... [112] Deleted: Measures must include examples... [11] the Formatted: Deleted: and Transmission Owner Formatted... [114] Deleted: Formatted... [115] Deleted: they comply with all applicable... [116] Formatted... [117] Approved: XXXX XX, 201X Page 6 of 19 Effective Date: XX/XX/XX

7 DRAFT 6 V4 Standard PRC-006- RFC-01 01/11/11 M Each Transmission Owner shall have dated evidence such as relay settings, tripping logic or other dated documentation that it implemented automatic switching of its existing capacitor banks and reactors in order to control overvoltage as a result of underfrequency load shedding event per Requirement R. Deleted: Deleted: 10 Deleted: 20 9 Formatted: Formatted: M4 M5 M6 M7 M8 M9 M10 M11 M12 Each Planning Coordinator shall have evidence of a documented methodology to determine areas of credible islanding per Requirement R4. Each Planning Coordinator shall have dated evidence such as letters, memorandums, meeting minutes, s or other dated documentation that it made its credible island determination methodology available for inspection and technical review by those entities directly and materially affected by the reliability of ReliabilityFirst Bulk Electric System (BES), within 15 business days of the receipt of a request Requirement R5. Each Planning Coordinator shall have dated evidence such as letters, memorandums, s or other dated documentation that it provided a written response to the commenting entity, within 45 calendar days of receipt of those comments per Requirement R6. Each Planning Coordinator shall have dated evidence such as reports, memorandums, s, or other documentation that it used the credible island determination methodology at least every five years to determine areas of credible islanding within their area of responsibility per Requirement R7. Each Planning Coordinator shall have dated evidence such as letters, memorandums, s or other dated documentation that it supplied the results of applying the island methodology within 0 days of completion of the process to the Distribution Providers, Transmission Owners and Generator Owners in the identified areas of credible islanding per Requirement R8. Each Planning Coordinator shall have dated evidence such as reports or other documentation of a mitigation plan that specifically addresses generation/load imbalances in the area of credible islanding per Requirement R9. Each Distribution Provider, Transmission Owner and Generator Owner in an identified area of credible islanding shall have evidence such as letters, memorandums, meeting minutes, s, reports or other dated documentation that it participated in the establishment of the mitigation plan per Requirement R10. Each Distribution Provider, Transmission Owner and Generator Owner shall have dated evidence such as lists summarizing feeder load armed with UFLS relays, lists with UFLS relay settings, or other dated documentation that it implemented the mitigation plan within three years of the completion of the mitigation plan per Requirement R9. Each Generator Owner owns a unit(s) with automatic underfrequency protection installed, shall have evidence such as lists or other documentation that the frequency protection settings conforms to Table 1 or if automatic underfrequency protection is not installed, the Generator Owner shall have dated evidence such Deleted: 2 Formatted: Deleted: documentation detailing processes to assess areas of credible islanding giving consideration to the items listed in R2. Each Planning Coordinator shall have evidence that an assessment to determine if credible islands exist was performed within the past 5 years. Each Planning Coordinator shall have documentation that the results of the assessment were supplied to the applicable Distribution Providers, Transmission Owners and Generator Owners. Deleted: Formatted: Formatted: Formatted: Formatted: Formatted: Formatted: Formatted: Formatted: Formatted: Deleted: Each Distribution Provider, Transmission Owner and Generator Owner in the ReliabilityFirst footprint in identified areas (or sub areas) of credible islanding (as determined in R2) shall have documentation of participation in the engineering assessment and documentation of installed applicable UFLS capability as required in R. Formatted: Indent: Left: 0 pt, First line: 0 pt Deleted: 4 Formatted: Formatted: Formatted: Deleted: it complies with the frequency protection settings of generators Formatted: Approved: XXXX XX, 201X Page 7 of 19 Effective Date: XX/XX/XX

8 DRAFT 6 V4 Standard PRC-006- RFC-01 01/11/11 Deleted: Standard PRC-006- RFC-... [118] M1 M14 M15 as underfrequency tripping or other documentation that its underfrequency tripping procedures conforms to Table 1 per Requirement R12. Each Planning Coordinator shall have dated evidence such as a UFLS database, data requests, data input forms, or other dated documentation to show that it established and maintained an UFLS database per Requirement R1. Each Distribution Provider and Transmission Owner required to comply with the relevant sections of Requirement R1, Requirement 2 or Requirement R11 shall have dated evidence such as responses to data requests, lists, letters or other dated documentation that it provided data in the pre-arranged format to its Planning Coordinator to populate the UFSL database within 45 days of the Planning Coordinators request, per Requirement R14. Each Generator Owner, required to comply with the relevant sections of Requirement R11 or Requirement R12, shall have dated evidence such as responses to data requests, lists, letters or other dated documentation that it provided data in the pre-arranged format to its Planning Coordinator to populate the UFLS database within 45 days of the Planning Coordinators request, per Requirement R15. Formatted: Deleted: has made arrangements for additional Load shedding, if appropriate, as required in R4. Formatted: Indent: Left: 6 pt, Hanging: 6 pt Deleted: 5 Formatted... [119] Deleted: as required in R5. Deleted: 6 Each respective istribution... [120] Formatted... [121] Deleted: and Generator Owner Formatted... [122] Deleted: that the information as required in R6 was supplied to the Planning Coordinator to populate the UFLS Database. Formatted... [12] M16 M17 M18 Each Planning Coordinator shall have dated evidence such as reports or other documentation of an assessment of the effectiveness of the design and implementation of the UFLS programs within its footprint which includes effects of neighboring Planning Coordinator areas and is conducted periodically at least every five years or as required by changes in system conditions per Requirement R16. Each respective Distribution Provider, Transmission Owner and Generator Owner shall have dated evidence such as lists summarizing feeder load armed with UFLS relays, lists with UFLS relay settings, lists with other protection system settings or other dated documentation that it made the UFLS or other protection system changes, which were recommended by the Planning Coordinators assessment, within three years of the completion date of the Planning Coordinators assessment, per Requirement R17. Each Planning Coordinator shall have dated evidence such as letters, memorandums, meeting minutes, s or other dated documentation that it coordinated its UFLS programs with neighboring Planning Coordinators and entities responsible for UFLS assessment per Requirement R18. D. Compliance 1 Compliance Monitoring Process 1.1 Compliance Enforcement ity Compliance Monitor: ReliabilityFirst Corporation 1.2 Data Retention Applicable entities shall retain information for five years. Deleted: 7 Formatted: Deleted: evidence that the assessment of the design effectiveness and implementation of UFLS as required by R7 has been completed and documented. Formatted... [124] Deleted: 8 Formatted... [125] Deleted: that the data in the database and relevant study results have been exchanged with neighboring Planning Coordinators as required by R8. Formatted: Indent: First line: 6 pt, No bullets or numbering Deleted: Compliance Monitoring Responsibility Formatted: Indent: Left: 90 pt, First line: 18 pt Formatted: Font: Not Italic Deleted: Deleted: 1.2 Compliance Monitoring Period and Reset On request (within 45 calendar days) Deleted: Formatted: Font: Bold Deleted: F Approved: XXXX XX, 201X Page 8 of 19 Effective Date: XX/XX/XX

9 DRAFT 6 V4 Standard PRC-006- RFC-01 01/11/11 If an Applicable entity is found non-compliant, they shall keep information related to the non-compliance until found compliant. The Compliance Monitor shall retain any audit data for five years. Deleted: Deleted: 10 Deleted: 20 9 Formatted: Indent: Left: 108 pt Deleted: 1. Compliance Monitoring and Assessment Processes Compliance Audits Self-Certifications Spot Checking Compliance Violation Investigations Self-Reporting Complaints 1.4 Additional Compliance Information None 2 Violation Severity Levels Req. Number R1 Provider total UFLS is less than 25% but greater than or equal to 2% of the Load as Requirement 1, Part 1.1 VIOLATION SEVERITY LEVEL LOWER MODERATE HIGH SEVERE Provider total UFLS is Provider total UFLS is Provider total UFLS is less than 2% but less than 21% but less than 18% of the greater than or equal to greater than or equal to Load, as required in 21% of the Load as 18% of the Load, as Requirement 1, Part 1.1 required in Requirement required in Requirement 1, Part 1.1 1, Part 1.1 Provider intentional relay time delays are greater than 20 cycles, but less than or equal to 22 cycles, as required in Requirement 1, Part 1.7 Provider UFLS program steps are not equal to within 2% of the forecasted annual peak hour Load as required in Requirement R1, Part 1. Provider intentional relay time delays are greater than 22 cycles, but less than or equal to 24 cycles, as required in Requirement 1, Part 1.7 Provider difference between frequency set points is less than 0.2 Hz or greater than 0.5 Hz, as required in Requirement 1, Part 1.6 Provider undervoltage inhibit (where applicable) is set greater than 75 % of nominal primary voltage, as required in Requirement 1, Part 1.8 Provider UFLS program contains less than Deleted: three steps, as required in Requirement 1, Part 1.2 Provider first frequency R1.5; set point of the UFLS program is less than 59. Hz per Requirement 1, part 1.4, Provider last set point is Formatted: Indent: Left: 6 pt, No bullets or numbering Deleted: 4 Formatted: Indent: Left: 90 pt, First line: 18 pt Formatted: Indent: Left: 72 pt, First line: 6 pt Formatted: Indent: Left: 108 pt Formatted: Indent: Left: 90 pt, First line: 18 pt Formatted: Indent: Left: 72 pt, First line: 6 pt Formatted: Indent: Left: 6 pt, No bullets or numbering Deleted: Additional Compliance Information None Formatted: No bullets or numbering Formatted: Font: Bold Formatted: Font: Not Bold Deleted: as required in R1.1; Deleted: required in R1.1; Formatted: Font: Not Bold Formatted: Font: Not Bold 1.1; Deleted: as required in R1.1; Formatted: Font: Not Bold Formatted: Font: Not Bold Formatted: Font: Not Bold Deleted: as required in R1.2, except as allowed by Formatted: Font: Not Bold 1.7 Deleted: as required in R1.6; Deleted: as required in R1., except as allowed by R1.5; Formatted: Font: Not Bold Formatted: Font: Not Bold Deleted: as required in R1.7 Approved: XXXX XX, 201X Page 9 of 19 Effective Date: XX/XX/XX

10 DRAFT 6 V4 Standard PRC-006- RFC-01 01/11/11 Provider intentional relay time delays are greater than 24 cycles, but less than or equal to 0 cycles, as required in Requirement 1, Part 1.7 Deleted: Deleted: 10 Deleted: 20 less than 58.5 Hz or greater than 58.7 Deleted: Hz, as 09 required in Requirement 1, Part 1.5 Provider intentional relay time delays are greater than 0 cycles, by R1.5; as required in Requirement 1, Part 1.7 Provider failed to implement an automatic UFLS program for their facilities Deleted: as required in R1.8; Transmission Owners capacitor banks connected to the BES are not tripped as specified in R1.9; Formatted: Font: Not Bold Formatted: Font: Not Bold Deleted: Provider first frequency set point of the UFLS program is less than 59. Hz, or the last set point is less than 58.5 Hz or greater than 58.7 Hz, as required in R1.4, except as allowed Formatted: Font: Not Bold Deleted: as required in R1.7 Deleted: as required in R1.7 R2 Provider total UFLS is less than 25% but greater than or equal to 2% of the Load as required in Requirement 2, Part 2.1 Provider total UFLS is less than 2% but greater than or equal to 21% of the Load as required in Requirement 2, Part 2.1 Provider total UFLS is less than 21% but greater than or equal to 18% of the Load, as required in Requirement 2, Part 2.1 Provider failed to participate with one or more Distribution Providers to collectively implement by mutual agreement a single automatic UFLS program Provider total UFLS is less than 18% of the Load, as required in Requirement 2, Part 2.1 Provider intentional relay time delays are greater than 20 cycles, but less than or equal to 22 cycles, as required in Requirement 2, Part 2.2 Provider intentional relay time delays are greater than 22 cycles, but less than or equal to 24 cycles, as required in Requirement 2, Part 2.2 Provider intentional relay time delays are greater than 24 cycles, but less than or equal to 0 cycles, as required in Requirement 2, Part 2.2 Provider intentional relay time delays are greater than 0 cycles, as required in Requirement 2, Part 2.2 Approved: XXXX XX, 201X Page 10 of 19 Effective Date: XX/XX/XX

11 DRAFT 6 V4 Standard PRC-006- RFC-01 01/11/11 Provider undervoltage inhibit (where applicable) is set greater than 75 % of nominal primary voltage, as required in Requirement 2, Part 2. Deleted: Deleted: 10 Deleted: 20 Provider failed to include either a Deleted: single 09 frequency set point at 59.0 Hz or two frequency set points, with equal amounts of load, at 59.0 Hz and 58.7 Hz, as required by Requirement 2, Part 2.4 R R4 The Transmission Owner failed to provide for 5% or less of the automatic switching of its existing capacitor banks and reactors to control over-voltage as a result of an UFLS event in accordance with the review performed by the Planning Coordinator in Requirement R16 Coordinator has a documented methodology to determine areas of credible islanding but failed to include one (1) of the Parts as specified in Requirement R4, Parts 4.1, 4.2, 4. or 4.4 The Transmission Owner failed to provide for more than 5% but less than or equal to 10% of the automatic switching of its existing capacitor banks and reactors to control overvoltage as a result of an UFLS event in accordance with the review performed by the Planning Coordinator in Requirement R16 Coordinator has a documented methodology to determine areas of credible islanding but failed to include two (2) of the Parts as specified in Requirement R4, Parts 4.1, 4.2, 4. or 4.4 The Transmission Owner failed to provide for more than 10% but less than or equal to 15% of the automatic switching of its existing capacitor banks and reactors to control overvoltage as a result of an UFLS event in accordance with the review performed by the Planning Coordinator in Requirement R16 Coordinator has a documented methodology to determine areas of credible islanding but failed to include more than three () of the Parts as specified in Requirement R4, Parts 4.1, 4.2, 4. or 4.4 Provider failed to implement an automatic UFLS program for their facilities The Transmission Owner failed to provide more than 15% of the automatic switching of its existing capacitor banks and reactors to control over-voltage as a result of an UFLS event in accordance with the review performed by the Planning Coordinator in Requirement R16 Coordinator has a documented methodology to determine areas of credible islanding but failed to include all four (4) of the Parts as specified in Requirement R4, Parts 4.1, 4.2, 4. and 4.4 Deleted: 2 Deleted: Coordinator did not make its credible islanding determination methodology available within 15 business days of the receipt of a request, as required in R2.1; Coordinator did not respond to comments on its credible islanding determination methodology within 45 calendar days of receipt of a written comment, as required in R2.2 Deleted: Coordinator performed the assessment required in R2 but did not report the results to the Distribution Provider and Transmission Owner and Generator Owner in the ReliabilityFirst footprint affected by the credible islanding, as required in R2.4; Coordinator did not perform the assessment within five years of the previous determination, as required in R2. Coordinator failed to have a documented methodology to Deleted: Coordinator failed to address one or more of the bullet point per R2 to identify areas (or sub areas) of credible islanding in the methodology Approved: XXXX XX, 201X Page 11 of 19 Effective Date: XX/XX/XX

12 DRAFT 6 V4 Standard PRC-006- RFC-01 01/11/11 R5 Coordinator made its credible island determination methodology available for inspection and technical review by those entities directly and materially affected by the reliability of ReliabilityFirst Bulk Electric System (BES), but was more than 15 calendar days but less than or equal to 20 business days of the receipt of a request Coordinator made its credible island determination methodology available for inspection and technical review by those entities directly and materially affected by the reliability of ReliabilityFirst Bulk Electric System (BES), but was more than 20 calendar days but less than or equal to 25 business days of the receipt of a request Coordinator made its credible island determination methodology available for inspection and technical review by those entities directly and materially affected by the reliability of ReliabilityFirst Bulk Electric System (BES), but was more than 25 calendar days but less than or equal to 0 business days of the receipt of a request Deleted: Deleted: 10 Deleted: 20 determine areas of credible islanding Coordinator made its credible island determination methodology available for inspection and technical review by those entities directly and materially affected by the reliability of ReliabilityFirst Bulk Electric System (BES), more than 0 calendar days of the receipt of a request 9 Deleted: Coordinator did not perform the determination of credible islands as required in R2 R6 Coordinator provided a written response to that commenting entity that is materially affected by the reliability of ReliabilityFirst BES, but was more than 45 calendar days but less than or equal to 50 calendar days of the receipt of the comments. Coordinator provided a written response to that commenting entity that is materially affected by the reliability of ReliabilityFirst BES, but was more than 50 calendar days but less than or equal to 55 calendar days of the receipt of the comments. Coordinator provided a written response to that commenting entity that is materially affected by the reliability of ReliabilityFirst BES, but was more than 55 calendar days but less than or equal to 60 calendar days of the receipt of the comments. Coordinator failed to make its credible island determination methodology available for inspection and technical review by those entities directly and materially affected by the reliability of ReliabilityFirst Bulk Electric System (BES) Coordinator provided a written response to that commenting entity that is materially affected by the reliability of ReliabilityFirst BES, but was more than 60 calendar days of the receipt of the comments. Coordinator provided a written response to that Coordinator failed to provide a written response to that commenting entity that Approved: XXXX XX, 201X Page 12 of 19 Effective Date: XX/XX/XX

13 DRAFT 6 V4 Standard PRC-006- RFC-01 01/11/11 R7 R8 Coordinator supplied the results of applying the island methodology but was more than 0 calendar days but less than or equal to 5 of completion of the process to the Distribution Providers, Transmission Owners and Generator Owners in the ReliabilityFirst footprint of identified areas of credible islanding Coordinator supplied the results of applying the island methodology but was more than 5 calendar days but less than or equal to 40 of completion of the process to the Distribution Providers, Transmission Owners and Generator Owners in the ReliabilityFirst footprint of identified areas of credible islanding commenting entity that is materially affected by the reliability of ReliabilityFirst BES, within 45 calendar days of receipt of those comments but the response failed to indicate whether a change was made to the credible island determination methodology and, if no change will be made, the reason why Coordinator supplied the results of applying the island methodology but was more than 40 calendar days but less than or equal to 45 of completion of the process to the Distribution Providers, Transmission Owners and Generator Owners in the ReliabilityFirst footprint of identified areas of credible islanding Deleted: Deleted: 10 Deleted: 20 is materially affected by the reliability of 9 ReliabilityFirst BES Coordinator failed to use the credible island determination methodology at least every five years to determine areas of credible islanding within their area of responsibility. Coordinator supplied the results of applying the island methodology but was more than 45 of completion of the process to the Distribution Providers, Transmission Owners and Generator Owners in the ReliabilityFirst footprint of identified areas of credible islanding Coordinator failed to supply the results of applying the island methodology to the Distribution Providers, Transmission Owners and Generator Owners in the ReliabilityFirst Deleted: Provider, Transmission Owner or Generator Owner did not participate in the engineering assessment and mitigation that specifically address generation/load imbalances in the area of credible islanding as required in R Deleted: Providers did not install UFLS capability or apply other methods of balancing Load and resources as required in R.1.1 or R.1.2. Approved: XXXX XX, 201X Page 1 of 19 Effective Date: XX/XX/XX

14 DRAFT 6 V4 Standard PRC-006- RFC-01 01/11/11 R9 R10 R11 R12 Coordinator established a mitigation plan that specifically addressed generation/load imbalances in the area of credible islanding but the mitigation plan failed to consist one or both of Requirement R9, Part 9.1 or 9.2 Deleted: Deleted: 10 Deleted: 20 footprint of identified areas of credible islanding Coordinator failed to establish a mitigation plan that specifically addresses generation/load imbalances in the area of credible islanding. 9 Provider, Transmission Owner and Generator Owner in an identified area of credible islanding failed to participate in the establishment of the mitigation plan. Provider, Transmission Owner and Generator Owner failed to implement the mitigation plan within three years of the completion of the mitigation plan. The Generator Deleted: Owner 4 that owns a unit(s) with automatic underfrequency protection installed, failed to set such protection in accordance with the minimum tripping time delays in Requirement 12, Table 1 without using the mitigation technique suggested in Requirement R12, Part 12.1 Deleted: The Generator Owner that owns a unit with automatic underfrequency protection installed, greater than 0% but less than or equal to 5% of a Generator Owner s total MWs is tripped by underfrequency protection sooner than the minimum time delays required in the Table 1 in R4 without using the mitigation technique suggested in R4.1; The Generator Owner that owns a unit with automatic underfrequency protection not installed, the Generator Owner has an underfrequency tripping procedure(s) but it does not conform to Table 1 Approved: XXXX XX, 201X Page 14 of 19 Effective Date: XX/XX/XX

15 DRAFT 6 V4 Standard PRC-006- RFC-01 01/11/11 R1 R14 Each Distribution Provider and Transmission Owner required to comply with the relevant sections of Requirement R1, Requirement R2 or Requirement R11 provided their Planning Coordinator the data in the pre-arranged format to populate the UFLS database but was more than 45 calendar days but less than or equal to 50 calendar days of the Planning Coordinators Each Distribution Provider and Transmission Owner required to comply with the relevant sections of Requirement R1, Requirement R2 or Requirement R11 provided their Planning Coordinator the data in the pre-arranged format to populate the UFLS database but was more than 50 calendar days but less than or equal to 55 calendar days of the Planning Coordinators Coordinator established an UFLS database but failed to update the database every five calendar years or as required by changes in system conditions per Requirement R1, Part 1.1 Coordinator established an UFLS database but failed to include the areas of credible islanding determined in Requirement R7 per Requirement R1, Part 1.2 Each Distribution Provider and Transmission Owner required to comply with the relevant sections of Requirement R1, Requirement R2 or Requirement R11 provided their Planning Coordinator the data in the pre-arranged format to populate the UFLS database but was more than 55 calendar days but less than or equal to 60 calendar days of the Planning Coordinators Deleted: Deleted: 10 Deleted: 20 The Generator Owner that owns a unit(s) Deleted: with 09 automatic underfrequency protection installed, failed to have underfrequency tripping procedures which conform to Requirement R12, Table 1 Coordinator failed to established an UFLS database as required by R1 Each Distribution Provider and Transmission Owner Deleted: 6 required to comply with the relevant sections of Requirement R1, Requirement R2 or Requirement R11 provided their Planning Coordinator the data in the pre-arranged format to populate the UFLS database but was more than 60 calendar days of the Planning Coordinators request Deleted: The Generator Owner that owns a unit with automatic underfrequency protection installed, greater than 5% of a Generator Owner s total MWs is tripped by underfrequency protection sooner than the minimum time delays required in the Table 1in R4 without using the mitigation technique suggested in R4.1; The Generator Owner that owns a unit with automatic underfrequency protection not installed, the Generator Owner does not have an underfrequency tripping procedure(s). Deleted: 5 Deleted: Coordinator has not established and maintained UFLS database as required by R5 Coordinator has established and maintained the UFLS database as required by R5 but has not been updated within the last five years or as required by changes in system conditions as required by R5.1 Deleted: Coordinator established and maintained the UFLS database required by R5 but areas of credible islanding were not included as required by R5.2 Approved: XXXX XX, 201X Page 15 of 19 Effective Date: XX/XX/XX

16 DRAFT 6 V4 Standard PRC-006- RFC-01 01/11/11 request request request Each Distribution Provider and Transmission Owner required to comply with the relevant sections of Requirement R1, Requirement R2 or Requirement R11 provided their Planning Coordinator the data in the pre-arranged format to populate the UFLS database within 45 calendar days of the Planning Coordinators request but failed to include one (1) of the Parts as specified in Requirement R14, Parts 14.4, 14.5, 14.6, or 14.7 Deleted: Deleted: 10 Deleted: 20 9 Each Distribution Provider and Transmission Owner required to comply with the relevant sections of Requirement R1, Requirement R2 or Requirement R11 provided their Planning Coordinator the data in the pre-arranged format to populate the UFLS database within 45 calendar days of the Planning Coordinators incomplete request but failed to include more than one (1) of the Parts as specified in Requirement R14, Parts 14.1, 14.2 or 14. Each Distribution incomplete Provider and Transmission Owner required to comply with the relevant sections of Requirement R1, Requirement R2 or Requirement R11 provided their Planning Coordinator the data in the pre-arranged format to populate the UFLS database within 45 calendar days of the Planning Coordinators request but failed to include two (2) or more of the Parts as specified in Requirement R14, Parts 14.4, 14.5, 14.6, or 14.7 Each Distribution Deleted: Providers or Transmission Owners supplied the information but between 1% and 2% of the information submitted for any of the individual applicable sub-requirements listed in R6.1 is incomplete Providers, Transmission Owners and Generator Owners failed to supply the information within 45 days but not longer than 90 days from the Planning Coordinators request Deleted: Providers or Transmission Owners supplied the information but greater than or equal to 2% but less than % of the information submitted for any of the individual applicable sub requirements listed in R6.1 is The Generator Owner supplied the information within 45 days from the Planning Coordinators request but failed to submit underfrequency trip set points and time delays for one (1) generator as required by R6.2 Deleted: Providers or Transmission Owners supplied the information and greater than or equal to % but less than 6% of the information submitted for any of the individual applicable sub requirements listed in R6.1 is The Generator Owner supplied the information within 45 days from the Planning Coordinators request but failed to submit underfrequency trip set points and time delays for more than one (1) generator as required by R6.2 Approved: XXXX XX, 201X Page 16 of 19 Effective Date: XX/XX/XX

NERC Reliability Standard PRC-024 Generator Frequency and Voltage Protective Relay Settings

NERC Reliability Standard PRC-024 Generator Frequency and Voltage Protective Relay Settings NERC Reliability Standard PRC-024 024-1 Generator Frequency and Voltage Protective Relay Settings Rick Terrill Luminant Power Generation Compliance NERC Standards Drafting Team Member Reliability Standard

More information

Standard IRO Reliability Coordination Responsibilities and Authorities

Standard IRO Reliability Coordination Responsibilities and Authorities A. Introduction 1. Title: Reliability Coordination Responsibilities and Authorities 2. Number: IRO-001-3 3. Purpose: To establish the authority of Reliability Coordinators to direct other entities to prevent

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. PRC-026-1 Relay Performance During Stable Power Swings Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the

More information

VAR Generator Operation for Maintaining Network Voltage Schedules

VAR Generator Operation for Maintaining Network Voltage Schedules Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Definitions. Common Corridor:

Definitions. Common Corridor: Definitions Common Corridor: Contiguous right-of-way or two parallel right-of-ways with structure centerline separation less than the longest span length of the two transmission circuits at the point of

More information

10/13/2011 Planning Coordination Committee. Standards

10/13/2011 Planning Coordination Committee. Standards Document name Category System Performance Regional Criterion ( ) Regional Reliability Standard (X) Regional Criterion ( ) Policy ( ) Guideline ( ) Report or other Document date 12/01/2011 Adopted/approved

More information

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications Reliability Guideline: Generating Unit Operations During Complete Loss of Communications Preamble It is in the public interest for the North American Electric Reliability Corporation (NERC) to develop

More information

Notes Generator Verification SDT Project

Notes Generator Verification SDT Project Notes Generator Verification SDT Project 2007-09 FERC Office 888 First Street, NE Washington, DC 20426 1. Administration a. The following were in attendance: Bob Snow, Cynthia Pointer, Lim Hansen, Keith

More information

Toronto Hydro - Electric System

Toronto Hydro - Electric System Toronto Hydro - Electric System FIT Commissioning Requirements and Reports Comments and inquiries can be e-mailed to: FIT@torontohydro.com Customers without e-mail access can submit through regular mail

More information

BE1-81O/U Frequency Protection. Washington State University Hands-On Relay School.

BE1-81O/U Frequency Protection. Washington State University Hands-On Relay School. Frequency Protection Washington State University Hands-On Relay School www.basler.com Relay Benefits As many as four independent, adjustable frequency setpoints and time delays Each setpoint has output

More information

FINAL REPORT LOAD SHEDDING IN TASMANIA ON 20 DECEMBER 2016 REVIEWABLE OPERATING INCIDENT REPORT FOR THE NATIONAL ELECTRICITY MARKET

FINAL REPORT LOAD SHEDDING IN TASMANIA ON 20 DECEMBER 2016 REVIEWABLE OPERATING INCIDENT REPORT FOR THE NATIONAL ELECTRICITY MARKET FINAL REPORT LOAD SHEDDING IN TASMANIA ON 20 DECEMBER 2016 REVIEWABLE OPERATING INCIDENT REPORT FOR THE NATIONAL ELECTRICITY MARKET Published: 6 April 2017 IMPORTANT NOTICE Purpose AEMO has prepared this

More information

0.1. Outage Management Process Summary

0.1. Outage Management Process Summary 0.1 Outage Management Process Summary Issue: 1.0 Issue Date: August 27, 2014 Table of Contents 1. Introduction... 4 1.1 Purpose... 4 1.2 Glossary... 4 State Transition Model... 8 2. Outage Management Processes...

More information

I. History of Time Error Correction and Reduced Reliance On Manual TEC Today

I. History of Time Error Correction and Reduced Reliance On Manual TEC Today Time Error Correction and Reliability White Paper Recommendation of the Balancing Authority Reliability-based Controls 2.2 Standard Drafting Team to Retire BAL-004-0 Time Error Correction The Balancing

More information

Phase 2 of System Protection Coordination (Requirement revisions to PRC ) Hydro Québec TransÉnergie

Phase 2 of System Protection Coordination (Requirement revisions to PRC ) Hydro Québec TransÉnergie Project 2007-06.2 Phase 2 of System Protection Coordination (Requirement revisions to PRC-001-1.1) Industry Webinar March 24, 2015 Standard Drafting Team Member Mark Peterson, Chair Michael Cruz Montes,

More information

Mitigation of Cascading Outages and Prevention of Blackouts:System-Wide Corrective Control

Mitigation of Cascading Outages and Prevention of Blackouts:System-Wide Corrective Control 10th Mediterranean Conference on Power Generation, Transmission, Distribution and Energy Conversion 6-9 November 2016 Belgrade, Serbia Mitigation of Cascading Outages and Prevention of Blackouts:System-Wide

More information

Unofficial Comment Form Project Establish and Communicate System Operating Limits (SOL and SOL Exceedance Definitions)

Unofficial Comment Form Project Establish and Communicate System Operating Limits (SOL and SOL Exceedance Definitions) Unofficial Comment Form Project 2015-09 Establish and Communicate System Operating Limits (SOL and SOL Exceedance Definitions) Do not use this form for submitting comments. Use the electronic form to submit

More information

GLI-12 V1.1 GLI 12 V2.0

GLI-12 V1.1 GLI 12 V2.0 1.41 Other Standards. These standards cover the actual requirements for various types of progressive gaming devices in casinos. The following other standards may apply: a) Technical Standards for Gaming

More information

BAL Real Power Balancing Control Performance Standard Background Document

BAL Real Power Balancing Control Performance Standard Background Document BAL-001-2 Real Power Balancing Control Performance Standard Background Document February 2013 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com Table of Contents

More information

Term Sheet Reflecting the Agreement of the ACCESS Committee Regarding In-Flight Entertainment November 21, 2016

Term Sheet Reflecting the Agreement of the ACCESS Committee Regarding In-Flight Entertainment November 21, 2016 Term Sheet Reflecting the Agreement of the ACCESS Committee Regarding In-Flight Entertainment November 21, 2016 1. Definitions: a. IFE System: a system provided by an airline that provides entertainment

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 21038-D01-2016 Downtown Calgary 138-kV Transmission System Reinforcement June 1, 2016 Alberta Utilities Commission Decision 21038-D01-2016 Downtown Calgary 138-kV Transmission System Reinforcement

More information

BAL Real Power Balancing Control Performance Standard Background Document

BAL Real Power Balancing Control Performance Standard Background Document BAL-001-2 Real Power Balancing Control Performance Standard Background Document July 2013 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 404-446-2560 www.nerc.com Table of Contents Table

More information

ELIGIBLE INTERMITTENT RESOURCES PROTOCOL

ELIGIBLE INTERMITTENT RESOURCES PROTOCOL FIRST REPLACEMENT VOLUME NO. I Original Sheet No. 848 ELIGIBLE INTERMITTENT RESOURCES PROTOCOL FIRST REPLACEMENT VOLUME NO. I Original Sheet No. 850 ELIGIBLE INTERMITTENT RESOURCES PROTOCOL Table of Contents

More information

Specification. NGTS Issue 1 October 1993

Specification. NGTS Issue 1 October 1993 The Electrical Standards for SHE Transmission s area are non-maintained versions of National Grid Technical Specifications that are applicable to the SHE Transmission System only. These specific versions

More information

PRINCIPLES AND APPLICATIONS

PRINCIPLES AND APPLICATIONS GENERATION & NETWORK Digital Automation Measuring and Control Devices AMS7000 PROCOM The optimum operation of an electrical network depends particularly on the reliability and the availability of the protection,

More information

ALTERNATIVE BROADCAST INSPECTION PROGRAM

ALTERNATIVE BROADCAST INSPECTION PROGRAM ALTERNATIVE BROADCAST INSPECTION PROGRAM A Cooperative Effort of the FCC and ABA A Three-Year Insurance Policy with Low Premiums! The ABIP Program provides you with A Full Compliance Inspection Immunity

More information

South Australian Energy Transformation

South Australian Energy Transformation South Australian Energy Transformation PSCR Supplementary Information Paper ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box 7096, Hutt Street Post Office, Adelaide,

More information

REFURBISHMENT OF SECONDARY SYSTEMS IN HIGH VOLTAGE SUBSTATIONS LESSONS LEARNED IN VENEZUELA

REFURBISHMENT OF SECONDARY SYSTEMS IN HIGH VOLTAGE SUBSTATIONS LESSONS LEARNED IN VENEZUELA 21, rue d'artois, F-75008 Paris http://www.cigre.org B3-110 Session 2004 CIGRÉ REFURBISHMENT OF SECONDARY SYSTEMS IN HIGH VOLTAGE SUBSTATIONS LESSONS LEARNED IN VENEZUELA by E. PADILLA * L. CEDEÑO E. PELAYO

More information

02/11/2015

02/11/2015 DIN Rail Mount 17.5 mm MUS/MUSF 80 AC/DC Part number 84872141 Control relays monitoring their own power supply - MUS : Over/undervoltage control Selectable latching (memory) function - MUSF : Over/undervoltage

More information

of New York, Inc. Original Sheet No. 81 SCHEDULE 3 Black Start Capability

of New York, Inc. Original Sheet No. 81 SCHEDULE 3 Black Start Capability SCHEDULE 3 Black Start Capability This service allows the transmission system to be restored from a blackout condition by repowering steam powered generators at various locations in Con Edison. These units

More information

Load Frequency Control Structure for Ireland and Northern Ireland

Load Frequency Control Structure for Ireland and Northern Ireland Load Frequency Control Structure for Ireland and Northern Ireland EirGrid TSO & TSO consultation on a proposal for the determination of LFC blocks in accordance with Article 141(2) of the Commission Regulation

More information

Form C: Type Test Verification Report

Form C: Type Test Verification Report Form C: Type Test Verification Report Type Approval and Manufacturer declaration of compliance with the requirements of G98. This form should be used when making a Type Test submission to the Energy Networks

More information

Form C: Type Test Verification Report

Form C: Type Test Verification Report Form C: Type Test Verification Report Type Approval and Manufacturer declaration of compliance with the requirements of G98. This form should be used when making a Type Test submission to the Energy Networks

More information

FAR Part 150 Noise Exposure Map Checklist

FAR Part 150 Noise Exposure Map Checklist FAR Part 150 Noise Exposure Map Checklist I. IDENTIFICATION AND SUBMISSION OF MAP DOCUMENT: Page Number A. Is this submittal appropriately identified as one of the following, submitted under FAR Part 150:

More information

Automatic Under-Frequency Load Shedding (AUFLS) Technical Report

Automatic Under-Frequency Load Shedding (AUFLS) Technical Report Automatic Under-uency Load Shedding (AUFLS) Technical Report August 2010 System Operator 6/08/2010 Page 1 of 124 System Operator Report: Automatic Under-uency Load Shedding (AUFLS) Technical Report Page

More information

Engineering Instruction

Engineering Instruction Engineering Instruction Electrical Distribution Unit Approved by: Paul Poynton, A/Professional Head Electrical Engineering, Sydney Trains Authorised by: Jonathon McKinnon, Engineering Technical Publications

More information

Table of Contents. Section E: Inspection and Acceptance

Table of Contents. Section E: Inspection and Acceptance Table of Contents Section E: Inspection and Acceptance Section Page E.1 52.252-2 Clauses Incorporated by reference (Feb 1998) 1 E.2 Cutover and Acceptance Testing of Services and Systems 1 E.2.1 Cutover

More information

Expert Workgroup on Fast Fault Current Injection stage 1 Terms of Reference

Expert Workgroup on Fast Fault Current Injection stage 1 Terms of Reference Expert Workgroup on Fast Fault Current Injection stage 1 Terms of Reference Governance 1. The need case to establish a Next Steps Expert Technical Workgroup Supporting Fast Fault Current Injection (FFCI)

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd Jemena Electricity Networks (Vic) Ltd Footscray West Zone Substation (FW) Switchgear and Relay Condition Risk RIT-D Stage 1: Non-Network Options Screening Report Public 18 September 2018 An appropriate

More information

SINAMICS G130 / G150. Line harmonics filter. Operating Instructions 05/2010 SINAMICS

SINAMICS G130 / G150. Line harmonics filter. Operating Instructions 05/2010 SINAMICS SINAMICS G130 / G150 Line harmonics filter Operating Instructions 05/2010 SINAMICS s Safety information 1 General 2 SINAMICS SINAMICS G130 / G150 Operating Instructions Mechanical installation 3 Electrical

More information

MAP110 AC-DC Series Data Sheet

MAP110 AC-DC Series Data Sheet Description Single-Output Model Selection VOLTAGE RANGE OUTPUT CURRENT OUTPUT CURRENT REGULATION REGULATION %p-p (NOTE 1) ACCURACY MAP110-1005 5V 4.95V to 5.50 16A 2 0.2% 1% 1% 5.09V to 5.11V MAP110-1012

More information

Hornsdale 2 Wind Farm. FCAS Capability Test Plan

Hornsdale 2 Wind Farm. FCAS Capability Test Plan Hornsdale 2 Wind Farm FCAS Capability Test Plan Prepared by Siemens Wind Power Pty Ltd 885 Mountain Highway Bayswater VIC 3153 tristan.raysonhill@siemens.com daniel.gallagher@siemens.com Revision History

More information

Improved Synchronization System for Thermal Power Station

Improved Synchronization System for Thermal Power Station Improved Synchronization System for Thermal Power Station Lokeshkumar.C 1, Logeshkumar.E 2, Harikrishnan.M 3, Margaret 4, Dr.K.Sathiyasekar 5 UG Students, Department of EEE, S.A.Engineering College, Chennai,

More information

RCOA Mandatory Contestability for Phase 1 Customers. 16 December 2016

RCOA Mandatory Contestability for Phase 1 Customers. 16 December 2016 RCOA Mandatory Contestability for Phase 1 Customers 16 December 2016 TOPICS 1 2 3 4 RCOA Updates RCOA Timeline General Procedures on Mandatory Migration Requirements RCOA Updates 420 Contestable Customers

More information

Date. James W. Davis, PhD James W. Davis Consultant Inc.

Date. James W. Davis, PhD James W. Davis Consultant Inc. Measurement Report W D C C (FM) Tower Site Sanford, rth Carolina Prepared for Central Carolina Community College Prepared by: James W. Davis, PhD July 30, 2003 I, James W. Davis, contract engineer for

More information

Siemens AG Safety along the complete line: SIRIUS 3SE7 cable-operated switches SIRIUS. Answers for industry.

Siemens AG Safety along the complete line: SIRIUS 3SE7 cable-operated switches SIRIUS. Answers for industry. Safety along the complete line: 3SE7 cable-operated switches Answers for industry. Everything well under control. 3SE7 cable-operated switches With cable-operated switches from our 3SE7 product range,

More information

Close supervision. Simplicity of use. Productivity gains. Control relay. C-Lynx. Instinctive control

Close supervision. Simplicity of use. Productivity gains. Control relay. C-Lynx. Instinctive control Close supervision Simplicity of use Productivity gains Control relay C-Lynx Instinctive control C-Lynx Control relay 1 Close-up protection for total availability of equipment! By installing a control relay,

More information

Report on Comments June 2013 NFPA 70

Report on Comments June 2013 NFPA 70 10-1 Log #1392 NEC-P10 Dennis Darling, Stantec Consulting Ltd. 10-5 Delete text to read as follows: Localization of an overcurrent condition to restrict outages to the circuit or equipment affected, accomplished

More information

Operating Instructions 07/2007 Edition. SINAMICS G130/G150 Line harmonics filter. sinamics

Operating Instructions 07/2007 Edition. SINAMICS G130/G150 Line harmonics filter. sinamics Operating Instructions 07/2007 Edition SINAMICS G130/G150 Line harmonics filter sinamics s Safety information 1 General 2 SINAMICS SINAMICS G130/G150 Operating Instructions Mechanical installation 3 Electrical

More information

GC0100/101/102 Code Administrator Consultation Responses. Rob Wilson. Grid Code Panel 8 th Feb 2018

GC0100/101/102 Code Administrator Consultation Responses. Rob Wilson. Grid Code Panel 8 th Feb 2018 GC0100/101/102 Code Administrator Consultation Responses Rob Wilson Grid Code Panel 8 th Feb 2018 GC0100 Respondent Original/ Alternative Support Implementation Summary of Points View of Proposer EDF Energy

More information

(1) These Regulations may be called PEMRA Standards for Cable Television Regulations 2003.

(1) These Regulations may be called PEMRA Standards for Cable Television Regulations 2003. PEMRA Cable Television (Operations) Regulations, 2002. Pakistan Electronic Media Regulatory Authority (PEMRA) The Pakistan Electronic Media Regulatory Authority (PEMRA) is pleased to make the Standards

More information

These restrictions, also called Network Constraints, are characterized by:

These restrictions, also called Network Constraints, are characterized by: Subject: Congestion management on the Belgian transmission grid Date: 1 September 2016 Contact: Steven Harlem Phone: 0032 2 500 85 89 Mail: steven.harlem@febeg.be Introduction To guarantee the security,

More information

MATE3 Owner s Manual Addendum

MATE3 Owner s Manual Addendum Purpose MATE3 Owner s Manual Addendum This document is an addendum to 900-0117-01-00, Revision C of the MATE3 System Display and Controller Owner s Manual. It provides descriptions of changes to the MATE3

More information

ORDERING Page 6 BASLER RELAY STANDARDS, DIMENSIONS, ACCESSORIES Request bulletin SDA

ORDERING Page 6 BASLER RELAY STANDARDS, DIMENSIONS, ACCESSORIES Request bulletin SDA BE1-59NC CAPACITOR NEUTRAL OVERVOLTAGE RELAY The BE1-59NC Capacitor Neutral Overvoltage Relay provides sensitive protection for capacitor banks. ADDITIONAL INFORMATION INSTRUCTION MANUAL ADVANTAGES Helps

More information

Frequency Response and Standard background Overview of BAL-003-1

Frequency Response and Standard background Overview of BAL-003-1 Industry Webinar BAL-003-1 Draft Frequency Response Standard and Supporting Process July 18, 2011 Agenda Frequency Response and Standard background Overview of BAL-003-1 What s changing Field Trial Frequency

More information

1C.5.1 Voltage Fluctuation and Flicker

1C.5.1 Voltage Fluctuation and Flicker 2 1 Ja n 1 4 2 1 J a n 1 4 Vo l.1 -Ge n e r a l;p a r tc-p o we r Qu a lity 1. Scope This document contains guidelines regarding maximum acceptable levels of voltage fluctuation and light flicker in the

More information

Australian and New Zealand Energy Performance and Marking Requirements for External Power Supplies

Australian and New Zealand Energy Performance and Marking Requirements for External Power Supplies FACT SHEET October 2008 Australian and New Zealand Energy Performance and Marking Requirements for External Power Supplies Minimum Energy Performance Standards (MEPS) Implementation dates Australia - 1

More information

Single output models feature wide-range output adjustability to meet a wide variety of standard and user-specific output voltage requirements.

Single output models feature wide-range output adjustability to meet a wide variety of standard and user-specific output voltage requirements. RoHS Lead-Solder-Exemption Compliant New 3.3 V and 5 V Output Models Universal Input 85-264 VAC Industry-Standard Footprint: 7.0" x 4.3" x 1.97" (177.8 x 109.2 x 50.0 mm) Input Transient & ESD Compliance

More information

Demand Side Engagement Document

Demand Side Engagement Document Demand Side Engagement Document Document UE PL 2202 Strategy This document details UE s demand side engagement plan as part of the National Distribution Planning & Expansion Framework This page has been

More information

Class B digital device part 15 of the FCC rules

Class B digital device part 15 of the FCC rules Class B digital device part 15 of the FCC rules The Federal Code Of Regulation (CFR) FCC Part 15 is a common testing standard for most electronic equipment. FCC Part 15 covers the regulations under which

More information

BATTERY ENERGY STORAGE SYSTEM REQUIREMENTS FOR CONTINGENCY FCAS REGISTRATION

BATTERY ENERGY STORAGE SYSTEM REQUIREMENTS FOR CONTINGENCY FCAS REGISTRATION BATTERY ENERGY STORAGE SYSTEM REQUIREMENTS FOR CONTINGENCY FCAS REGISTRATION PREPARED BY: AEMO Operations Department Systems Performance & Commercial VERSION: 1.0 EFFECTIVE DATE: 14 January 2019 STATUS:

More information

Summary Project Specification Consultation Report

Summary Project Specification Consultation Report Project Specification Consultation Report: Maintaining reliability of supply at Townsville South Substation Powerlink Queensland Summary Project Specification Consultation Report 29 October 2018 Maintaining

More information

ATTACHMENT 2: SPECIFICATION FOR SEWER CCTV VIDEO INSPECTION

ATTACHMENT 2: SPECIFICATION FOR SEWER CCTV VIDEO INSPECTION ATTACHMENT 2: SPECIFICATION FOR SEWER CCTV VIDEO INSPECTION 1.0 General 1.1 The work covered by this section consists of providing all labor, equipment, insurance, accessories, tools, transportation, supplies,

More information

ORDERING Page 6 STANDARDS, DIMENSIONS and ACCESSORIES Request bulletin SDA

ORDERING Page 6 STANDARDS, DIMENSIONS and ACCESSORIES Request bulletin SDA BE1-59NC CAPACITOR NEUTRAL OVERVOLTAGE RELAY The BE1-59NC Capacitor Neutral Overvoltage Relay provides sensitive protection for capacitor banks. ADVANTAGES Helps avoid cascading capacitor failures. Sensing

More information

American National Standard for Lamp Ballasts High Frequency Fluorescent Lamp Ballasts

American National Standard for Lamp Ballasts High Frequency Fluorescent Lamp Ballasts American National Standard for Lamp Ballasts High Frequency Fluorescent Lamp Ballasts Secretariat: National Electrical Manufacturers Association Approved: January 23, 2017 American National Standards Institute,

More information

Transient Stability Events & Actions

Transient Stability Events & Actions ETAP TIP No. 009 Transient Stability Events & Actions Applicable ETAP Versions: 5.5.0, 5.5.5, 5.5.6 (For lower versions, some of the descriptions and procedures below may differ in some ways) Event is

More information

VERIZON TELEPHONE COMPANIES TARIFF FCC NO.

VERIZON TELEPHONE COMPANIES TARIFF FCC NO. Vice President, Federal Regulatory 3rd Revised Page -1 1300 I Street, NW Cancels 2nd Revised Page -1 Washington, DC 20005 Issued: November 15, 2010 Effective: November 30, 2010 ADVANCED COMMUNICATIONS

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 21317-D01-2016 Central Alberta Underground Fibre Optic Build July 12, 2016 Alberta Utilities Commission Decision 21317-D01-2016 Central Alberta Underground Fibre Optic Build Proceeding 21317 Application

More information

VERIZON MARYLAND INC.

VERIZON MARYLAND INC. VZ MD 271 Attachment 207 VERIZON MARYLAND INC. Methods and Procedures for Access To Poles, Ducts, Conduits and Rights-of-Way for Telecommunications Providers VERIZON MARYLAND INC. Methods and Procedures

More information

AMERICAN NATIONAL STANDARD

AMERICAN NATIONAL STANDARD Digital Video Subcommittee AMERICAN NATIONAL STANDARD ANSI/SCTE 197 2018 Recommendations for Spot Check Loudness Measurements NOTICE The Society of Cable Telecommunications Engineers (SCTE) / International

More information

SMPTE STANDARD Gb/s Signal/Data Serial Interface. Proposed SMPTE Standard for Television SMPTE 424M Date: < > TP Rev 0

SMPTE STANDARD Gb/s Signal/Data Serial Interface. Proposed SMPTE Standard for Television SMPTE 424M Date: < > TP Rev 0 Proposed SMPTE Standard for Television Date: TP Rev 0 SMPTE 424M-2005 SMPTE Technology Committee N 26 on File Management and Networking Technology SMPTE STANDARD- --- 3 Gb/s Signal/Data Serial

More information

This Chapter does not apply to applications and decisions on, development on land reserved in corridor maps.

This Chapter does not apply to applications and decisions on, development on land reserved in corridor maps. 1560 1561 1562 1563 1564 1565 1566 1567 1568 1569 1570 1571 1572 1573 1574 1575 1576 1577 1578 1579 1580 1581 1582 1583 1584 1585 1586 1587 1588 1589 1590 1591 1592 1593 1594 1595 1596 1597 1598 1599 1600

More information

The University of Texas at Austin September 30, 2011

The University of Texas at Austin September 30, 2011 SECTION 27 08 20 COPPER TESTING PART 1 - GENERAL 1.1 SUMMARY A. Test measurements shall be taken for all balanced-twisted pair cabling, including horizontal and backbone copper cables and wall-to-rack

More information

Federal Communications Commission

Federal Communications Commission Application Filing Results http://fjallfoss.fcc.gov/cgi-bin/ws.exe/prod/cdbs/forms/prod/cdbsmenu.hts 1 of 1 7/7/2009 5:38 PM Federal Communications Commission FCC MB - CDBS Electronic Filing Account number:

More information

MANAGING POWER SYSTEM FAULTS. Xianyong Feng, PhD Center for Electromechanics The University of Texas at Austin November 14, 2017

MANAGING POWER SYSTEM FAULTS. Xianyong Feng, PhD Center for Electromechanics The University of Texas at Austin November 14, 2017 MANAGING POWER SYSTEM FAULTS Xianyong Feng, PhD Center for Electromechanics The University of Texas at Austin November 14, 2017 2 Outline 1. Overview 2. Methodology 3. Case Studies 4. Conclusion 3 Power

More information

APQ Series Type C Power Factor Correction Banks

APQ Series Type C Power Factor Correction Banks APQ Series Type C Power Factor Correction Banks N52 W13670 NORTHPARK DR. MENOMONEE FALLS, WI 53051 P. (262) 754-3883 F. (262) 754-3993 www.apqpower.com Regardless of the load size or type, APQ will work

More information

GCC Interconnection Grid: Operational Studies for the GCC Interconnection with United Arab Emirates (UAE) N. AL-SHAHRANI GCCIA Saudi Arabia

GCC Interconnection Grid: Operational Studies for the GCC Interconnection with United Arab Emirates (UAE) N. AL-SHAHRANI GCCIA Saudi Arabia 21, rue d Artois, F-75008 PARIS C4-107 CIGRE 2012 http : //www.cigre.org GCC Interconnection Grid: Operational Studies for the GCC Interconnection with United Arab Emirates (UAE) A. AL-EBRAHIM GCCIA Bahrain

More information

Definitions. General Principles. Reviewed 08 August 2002

Definitions. General Principles. Reviewed 08 August 2002 !" $#%&! Reviewed 08 August 2002 This document outlines the interference resolution procedures that NESMC and its members will follow when faced with interference. This document is primarily concerned

More information

Dimming actuators GDA-4K KNX GDA-8K KNX

Dimming actuators GDA-4K KNX GDA-8K KNX Dimming actuators GDA-4K KNX GDA-8K KNX GDA-4K KNX 108394 GDA-8K KNX 108395 Updated: May-17 (Subject to changes) Page 1 of 67 Contents 1 FUNCTIONAL CHARACTERISTICS... 4 1.1 OPERATION... 5 2 TECHNICAL DATA...

More information

ITU-T Y Functional framework and capabilities of the Internet of things

ITU-T Y Functional framework and capabilities of the Internet of things I n t e r n a t i o n a l T e l e c o m m u n i c a t i o n U n i o n ITU-T Y.2068 TELECOMMUNICATION STANDARDIZATION SECTOR OF ITU (03/2015) SERIES Y: GLOBAL INFORMATION INFRASTRUCTURE, INTERNET PROTOCOL

More information

Block System Interface Requirements

Block System Interface Requirements Block System Interface Requirements Synopsis This document mandates the requirements for block systems interfaces between signalling infrastructure and railway operations. Copyright in the s is owned by

More information

Journal of Food Health and Bioenvironmental Science. Book Review

Journal of Food Health and Bioenvironmental Science. Book Review (May - August 2018), 11(2): 67 Journal homepage : http://jfhb.dusit.ac.th/ Book Review Tita Foophow Book name: Food Proteins and Peptides: Chemistry, Functionality, Interactions and Commercialization Author:

More information

LXM23DU10M3X motion servo drive - Lexium 23 - single phase V - 1 kw - I/O

LXM23DU10M3X motion servo drive - Lexium 23 - single phase V - 1 kw - I/O Characteristics motion servo drive - Lexium 23 - single phase 200...255 V - 1 kw - I/O Main Range of product Product or component type Device short name Complementary Format of the drive Network number

More information

IEEE 100BASE-T1 Physical Coding Sublayer Test Suite

IEEE 100BASE-T1 Physical Coding Sublayer Test Suite IEEE 100BASE-T1 Physical Coding Sublayer Test Suite Version 1.1 Author & Company Curtis Donahue, UNH-IOL Stephen Johnson, UNH-IOL Title IEEE 100BASE-T1 Physical Coding Sublayer Test Suite Version 1.1 Date

More information

3 Resolution of the Board of Supervisors, acting as responsible agency with respect to

3 Resolution of the Board of Supervisors, acting as responsible agency with respect to FILE NO. 070314 RESOLUTION NO. Lf /3-01 1 [CEQA Findings in Connection with the Trans Bay Cable Project] 2 3 Resolution of the Board of Supervisors, acting as responsible agency with respect to 4 the Trans

More information

CALL FOR PAPERS. standards. To ensure this, the University has put in place an editorial board of repute made up of

CALL FOR PAPERS. standards. To ensure this, the University has put in place an editorial board of repute made up of CALL FOR PAPERS Introduction Daystar University is re-launching its academic journal Perspectives: An Interdisciplinary Academic Journal of Daystar University. This is an attempt to raise its profile to

More information

FACILITIES STUDY MID AMERICAN TRANSMISSION SERVICE REQUESTS. OASIS Revision: 4

FACILITIES STUDY MID AMERICAN TRANSMISSION SERVICE REQUESTS. OASIS Revision: 4 TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:EAI CUSTOMER: MID AMERICAN ENERGY. FACILITIES STUDY EJO # F4PPAR0422 MID AMERICAN TRANSMISSION SERVICE REQUESTS OASIS 1468288 Revision: 4 Rev Issue Date Description

More information

Broadcasting Decision CRTC and Broadcasting Orders CRTC , , , , and

Broadcasting Decision CRTC and Broadcasting Orders CRTC , , , , and Broadcasting Decision CRTC 2018-468 and Broadcasting Orders CRTC 2018-469, 2018-470, 2018-471, 2018-472, 2018-473 and 2018-474 PDF version References: 2018-128 and 2018-128-1 Ottawa, 14 December 2018 La

More information

Broadcasting Decision CRTC and Broadcasting Orders CRTC , and

Broadcasting Decision CRTC and Broadcasting Orders CRTC , and Broadcasting Decision CRTC 2016-421 and Broadcasting Orders CRTC 2016-422, 2016-423 and 2016-424 PDF version Reference: 2016-64-1 Ottawa, 20 October 2016 Sur Sagar Radio Inc. Surrey, British Columbia Reference

More information

GUIDELINES FOR THE PREPARATION OF A GRADUATE THESIS. Master of Science Program. (Updated March 2018)

GUIDELINES FOR THE PREPARATION OF A GRADUATE THESIS. Master of Science Program. (Updated March 2018) 1 GUIDELINES FOR THE PREPARATION OF A GRADUATE THESIS Master of Science Program Science Graduate Studies Committee July 2015 (Updated March 2018) 2 I. INTRODUCTION The Graduate Studies Committee has prepared

More information

THE BAHAMAS EXPERIENCE. Contents. In this brief presentation we will give you:

THE BAHAMAS EXPERIENCE. Contents. In this brief presentation we will give you: THE BAHAMAS EXPERIENCE Contents In this brief presentation we will give you: An overview of the demographics of The Bahamas An explanation of its Legal Framework A short discussion about the Guidelines

More information

Specific Concerns with draft ErP Display Regulation (reference WTO notice EU 433) >> indicates change suggestions.

Specific Concerns with draft ErP Display Regulation (reference WTO notice EU 433) >> indicates change suggestions. To: Internal Market, Industry, Entrepreneurship and SMEs Directorate General Avenue des Nerviens 105 Brussels Belgium, 1040 Email: GROW EU TBT@ec.europa.eu From: Mr. Lauren Crane Manager, Product Environmental

More information

Guest Editor Pack. Guest Editor Guidelines for Special Issues using the online submission system

Guest Editor Pack. Guest Editor Guidelines for Special Issues using the online submission system Guest Editor Pack Guest Editor Guidelines for Special Issues using the online submission system Online submission 1. Quality All papers must be submitted via the Inderscience online system. Guest Editors

More information

DEPARTMENTAL GENERAL ORDER DEPARTMENT OF PUBLIC SAFETY January 8, 2003 MERCER ISLAND POLICE

DEPARTMENTAL GENERAL ORDER DEPARTMENT OF PUBLIC SAFETY January 8, 2003 MERCER ISLAND POLICE DEPARTMENTAL GENERAL ORDER 91-2 R-9 (Revised) DEPARTMENT OF PUBLIC SAFETY January 8, 2003 MERCER ISLAND POLICE Index as: Audio and Video Recording Camera, Video Equipment Use Photography, Audio/Video Use

More information

Simulation of DFIG and FSIG wind farms in. MATLAB SimPowerSystems. Industrial Electrical Engineering and Automation.

Simulation of DFIG and FSIG wind farms in. MATLAB SimPowerSystems. Industrial Electrical Engineering and Automation. CODEN:LUTEDX/(TEIE-7235)/1-007/(2009) Industrial Electrical Engineering and Automation Simulation of DFIG and FSIG wind farms in MATLAB SimPowerSystems Francesco Sulla Division of Industrial Electrical

More information

ABB CM-UFD.M31 monitoring datasheet

ABB CM-UFD.M31 monitoring datasheet ABB CM-UFD.M31 monitoring datasheet http://www.manuallib.com/abb/cm-ufd-m31-monitoring-datasheet.html The CM-UFD.M31 is a multifunctional grid feeding monitoring relay. It provides different monitoring

More information

SINAMICS G130. dv/dt filter plus Voltage Peak Limiter. Operating Instructions 03/2013 SINAMICS

SINAMICS G130. dv/dt filter plus Voltage Peak Limiter. Operating Instructions 03/2013 SINAMICS SINAMICS G130 Operating Instructions 03/2013 SINAMICS s dv/dt filter plus Voltage Peak Limiter Safety information 1 General 2 SINAMICS SINAMICS G130 Operating Instructions Mechanical installation 3 Electrical

More information

Grid feeding monitoring according to VDE-AR-N 4105 and BDEW CM-UFD.M31

Grid feeding monitoring according to VDE-AR-N 4105 and BDEW CM-UFD.M31 Data sheet Grid feeding monitoring according to VDE-AR-N 4105 and BDEW CM-UFD.M31 The CM-UFD.M31 is a multifunctional grid feeding monitoring relay. It provides different monitoring functions in accordance

More information

Assembly. Front view. LEDs. Parametrization interface. Power Bus

Assembly. Front view. LEDs. Parametrization interface. Power Bus otation Speed Monitor Features Assembly 1-channel signal conditioner 2 V DC supply Input for 2- or -wire sensors Input frequency 10 mhz... 50 khz elay contact output Start-up override and restart inhibit

More information

Bahrain Medical Bulletin

Bahrain Medical Bulletin Bahrain Medical Bulletin Part 1. Transfer of Copyright Agreement Complete copyright to the article entitled: I hereby transfer to the Bahrain Medical Bulletin the Complete copyright, if and when the article

More information