CEBAF Accelerator Update. Michael Tiefenback CASA Accelerator Physics Experimental Liaison June 14, 2017

Similar documents
Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

The Elettra Storage Ring and Top-Up Operation

RF Upgrades & Experience At JLab. Rick Nelson

Jefferson Lab Experience with Beam Halo, Beam Loss, etc.

An Operational Diagnostic Complement for Positrons at CEBAF/JLab

Hall-B Beamline Commissioning Plan for CLAS12

SPEAR 3: Operations Update and Impact of Top-Off Injection

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY

Present Status and Future Upgrade of KEKB Injector Linac

SRS and ERLP developments. Andrew moss

Availability and Reliability Issues for the ILC

LSD Review December 2012 Schedule, Re-Baseline, & Resource Analysis

Upgrade of CEBAF to 12 GeV

JEFFERSON LAB, A STATUS REPORT*

12GeV CEBAF Commissioning

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

LLRF at SSRF. Yubin Zhao

CEBAF 12GeV Commissioning: Status and Plans

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

High Brightness Injector Development and ERL Planning at Cornell. Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics

Operating Experience and Reliability Improvements on the 5 kw CW Klystron at Jefferson Lab

News from HZB / BESSY Wolfgang Anders at ESLS-RF Meeting September 2010 Trieste

Suggested ILC Beam Parameter Range Rev. 2/28/05 Tor Raubenheimer

Status and Plans for PEP-II

A Cathode Development Cornell Cultera This scope includes all labor and purchases required produce photocathodes required by CBETA.

Digital BPMs and Orbit Feedback Systems

PEP II Design Outline

Detailed Design Report

Photo cathode RF gun -

Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi)

Jae-Young Choi On behalf of PLS-II Linac team

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

TITLE PAGE. Title of paper: PUSH-PULL FEL, A NEW ERL CONCEPT Author: Andrew Hutton. Author Affiliation: Jefferson Lab. Requested Proceedings:

5 Project Costs and Schedule

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems

Beam Loss Detection for MPS at FRIB

RF Power Klystrons & 20 Year Look. R. Nelson 7/15/15

Status of Elettra, top-up and other upgrades

OPERATIONAL EXPERIENCE AT J-PARC

Accelerator Instrumentation RD. Monday, July 14, 2003 Marc Ross

Performance of a DC GaAs photocathode gun for the Jefferson lab FEL

Status of SOLARIS Arkadiusz Kisiel

The LEP Superconducting RF System

The Construction Status of CSNS Linac

30 GHz Power Production / Beam Line

BBU threshold current study for 6 GeV beam in 12 GeV beamline setup

Current status of XFEL/SPring-8 project and SCSS test accelerator

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

RUNNING EXPERIENCE OF FZD SRF PHOTOINJECTOR

Operation of CEBAF photoguns at average beam current > 1 ma

Program Risks Risk Analysis Fallback Plans for the. John T. Seeman DOE PEP-II Operations Review April 26, 2006

LEP Status and Performance in 2000

Andrei Seryi, Toshiaki Tauchi. December 15-18, 2008

Next Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack

Status of RF Power and Acceleration of the MAX IV - LINAC

Effects of the cryogenics operational conditions on the mechanical stability of the FLASH linac modules

AARHUS UNIVERSITET November, ASTRID2 Status. Heine Dølrath Thomsen on behalf of the ASTRID2 Team

DESIGN OF 1.2-GEV SCL AS NEW INJECTOR FOR THE BNL AGS*

Status of the X-ray FEL control system at SPring-8

RF considerations for SwissFEL

Workshop on Accelerator Operations August 6-10, 2012 Glen D. Johns Accelerator Operations Manager

The ESS Accelerator. For Norwegian Industry and Research. Oslo, 24 Sept Håkan Danared Deputy Head Accelerator Division Group Leader Beam Physics

SRF-gun Development Overview. J. Sekutowicz 17 th September, 2015 SRF15, Whistler, Canada

Spear3 RF System Sam Park 11/06/2003. Spear3 RF System. High Power Components Operation and Control. RF Requirement.

P. Adamson, Fermi National Accelerator Laboratory, Batavia, IL 60510, USA. Abstract

New Filling Pattern for SLS-FEMTO

HAPD and Electronics Updates

Report on the LCLS Injector Technical Review

Linac3 experience for LHC ion runs

Screen investigations for low energetic electron beams at PITZ

Technology Challenges for SRF Guns as ERL Sources in View of Rossendorf work

Capability Improvements: Polarized Photoinjector*

CBETA Quarterly Report 7

The basic parameters of the pre-injector are listed in the Table below. 100 MeV

What can be learned from HERA Experience for ILC Availability

RF plans for ESS. Morten Jensen. ESLS-RF 2013 Berlin

Status of the Jefferson Lab Polarized Beam Physics Program and Preparations for Upcoming Parity Experiments

A Fifteen Year Perspective on the Design and Performance of the SNS Accelerator

The PEFP 20-MeV Proton Linear Accelerator

Proceedings of the 1997 Workshop on RF Superconductivity, Abano Terme (Padova), Italy

PQB Meeting. Caryn Palatchi 02/15/2018

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

Focus of efforts. ILC 2010, Mar/27/10 A. Seryi, BDS: 2

Extraction/Separator Setup. Michael Spata Operations Stay Treat July 16, 2015

!"!3

ANKA Status Report. N.Smale, A.-S. Müller, E. Huttel, M.Schuh Slides courtesy of A.-S. Müller and C.Heske.

Design Studies For The LCLS 120 Hz RF Gun Injector

P. Emma, et al. LCLS Operations Lectures

RF Power Upgrade at Jefferson Lab

Proton Engineering Frontier Project

HIGH POWER BEAM DUMP AND TARGET / ACCELERATOR INTERFACE PROCEDURES *

Introduction: CW SRF linac types, requirements and challenges High power RF system architecture

Technology Challenges for SRF Guns as ERL Source in View of BNL Work

Pulsed Klystrons for Next Generation Neutron Sources Edward L. Eisen - CPI, Inc. Palo Alto, CA, USA

An Overview of Beam Diagnostic and Control Systems for AREAL Linac

Linac 4 Instrumentation K.Hanke CERN

Summary of the 1 st Beam Line Review Meeting Injector ( )

LCLS Injector Technical Review

Transcription:

CEBAF Accelerator Update Michael Tiefenback CASA Accelerator Physics Experimental Liaison June 14, 2017 CLAS12 Collaboration Meeting, June 13-16, 2017 1

Accelerator Division Leadership On April 30 Andrew Hutton stepped down as the head Accelerator Division ~10 years as Associate Director Prior to his appointment as Associate Director, Andrew was Director of Accelerator Operations for ~15 years. Commissioning of 4 GeV CEBAF Ramp up to 6 GeV Recovery post-hurricane Isabel Fulvia Pilat has assumed the role of Acting Division leader until the completion of the search for the new Division leader Fulvia has also accepted the Director of the Research Accelerator Division at SNS and will assume this position in Fall 2017. CLAS12 2017-06-14 2 CEBAF Operations

The View from Inside Your Side "What area(s) do you most want covered in the Accelerator Update?" Beam availability ( reliability vs. funding) Beam energy (immediate and near-term) Trip rate (beam interruptions) Other parameters Stability Momentum spread Envelope (RMS and 10-3 halo) CLAS12 Collaboration Meeting, June 13-16, 2017 3

12 GeV Out-year Beam Requirements CLAS12 Collaboration Meeting 02 Nov 2016 4

Beam Parameters at 12 GeV (2.2 GeV/pass) Vertical Emittance Horizontal Emittance Energy Spread 12 GeV CEBAF Ops Beam parameters at 12 GeV meet out-year specification. Growth in emittance/energy spread due to synchrotron radiation effects agrees well with expectations. 5/24

Potential Hall B 11 GeV Beam Envelope E_x = 3 nm E_y = 0.8 nm Emittance-limited target spot Supported by existing hardware (will require experience to achieve) CLAS12 Collaboration Meeting 02 Nov 2016 6

CEBAF 4-Hall Operations Begins Fall 2017 4 Hall Operations (also called D+3) begins this Fall Condition Maximum number of halls receiving beam ABC Beam @ 5th pass (Hall D on) ABC Beam @ 5th pass (Hall D off) ABC Beam @ lower passes (D+2) 3 halls 499 MHz 499 MHz 499 MHz (D+3) 4 halls 249.5 MHz 499 MHz 499 MHz 4 Hall Preparations Completed.so far Rebuild laser table w/ 4th laser and 4-beam combination Two beams @ 249.5 MHz share one 499 MHz RF Chopping Bucket 750 MHz separators for 5th pass ABC / D separation 7

12 GeV Peak(best) Performance (to date) 94% CEBAF System Reliability Tight configuration control during this period; not one quadrupole magnet was manually adjusted. No tweaking, just monitoring. 12 GeV CEBAF Ops 8

Source Operation Spring/Fall 2016 SSL GaAs/GaAsP SVT #5756-4 (Polarization ~ 87%) No heat/activation over Summer 2016 / Winter 2017 SADS Jun 2016 Fall 2016 Gun2 operating at -130 kv without any problems Charge lifetime >100C with average current 70-80 ma Sep 2016 Spring 2017 Delivering up to 3 halls at a time (either 249.5 or 499 MHz) Hall A (Physics), Hall B (KPP), Hall C (KPP), Hall D (Physics) 9

PSS High Voltage Interface Upgrade Fall 2016 Historically Gun HV commensurate with PSS Beam Permit state => Off often! Gun HV power supply now remains ON when PSS = Power Permit Anticipate improved injector reliability and possibly increased charge lifetime First 5 weeks of Spring 2016 Run (before upgrade) First 5 weeks of Fall 2016 Run (after upgrade) 10

Injector Summary CEBAF Operations Source is operating well, providing high polarization at 11 GeV On track for 4-Beam operations in Fall 2017, time will tell how easy this is. Injector Upgrade Deliver and test 200 kv beam at CEBAF injector Summer 2017 SAD Test of 200 kv Wien filter, new QCM and higher voltage polarized gun at UITF Rebuild baked beamline with 2-Wien spin flipper Summer 2018 SAD Parity Quality Beam Readiness Required specifications have been demonstrated We are ready to return to setting up and delivering PQB beams 11

Linacs and Accelerator Systems Energy set to 4% below 12 GeV nominal value Expect to hold at this energy (A. Freyberger 3/28/17) Trip rate is acceptable 750 MHz separators are operational We are learning how to operate the hardware We are learning where the limits are Some things have broken Some are being fixed Some are being worked around Development of the accelerator continues Working at hardware limits eats clock time a Bad Idea CLAS12 Collaboration Meeting, June 13-16, 2017 12

Fall 2016 RF Performance One pass energy gain set to 2.1 GeV/pass 100 MeV/pass lower than 12 GeV design (-5%) Availability during Spring 2016 Operations at 2.2 GeV/pass suffered due to lack of gradient margin. ~50 MeV/linac of gradient margin in Oct. 2016 (at 2.1 GeV/pass) Program flexibility: by-passed troubled cavities in a few minutes and resume beam operations. By Dec. margin was reduced to 25 MeV/linac due to by-passed cavities and other gradient reductions. Most of this reduction was recovered during Jan. 2017 SAD CLAS12 2017-06-14 13/NN CEBAF Operations

Fall 2016 Accelerator Operations Hall A (1,3,4,5 passes, 70 ua) & Hall-D 5.5 passes Linac Energy: 1050 MeV/linac Commission 5th pass separator Validate improvements made over the Summer 2016 Compact Geometry (+9%) Increase RF power (+10%) Vacuum leak in one of the cavities immediately following commissioning rained on the parade CLAS12 2017-06-14 14 CEBAF Operations

750 MHz Separator Leak Leak in tuner bellows associated with some discoloration Root cause of the leak still not identified Bellows and near-by wall surface nominally at ground potential No associated discoloration found on cavity wall CLAS12 2017-06-14 15/NN CEBAF Operations

750 MHz Separators Vacuum issue repaired (bellows punch-through) Arc mark in thin bellows (multipacting?) Separator system re-commissioned Improved system layout adds power margin Thermal control issues identified System is capable of continuous operation This fault was not anticipated. While not fully understood, it is not considered likely to recur. CLAS12 Collaboration Meeting, June 13-16, 2017 16

Replace Cryomodule 1L13 with a C50 C25 replacement boosts 22 MeV to ~50 MeV (Note improvement over time through Spring 2017) CLAS12 Collaboration Meeting, June 13-16, 2017 17

Ops RF trip rate management works Adjacent C25 zones 1L14/1L15 more capable than 1L13 (Again note improvement over time through Spring 2017) CLAS12 Collaboration Meeting, June 13-16, 2017 18

Linac Systems Issues Summary RF Performance in Fall 2016 was very good RF trips < 5 trips/h C100 trips factor two less than Spring 2016 Up 80 ma, 700kW delivered to Hall-A on 4th pass. Support two-hall operations on the last week. Month of Dec. had 80% overall availability 750 MHz separation improvement demonstrated (vacuum leak prevented further operation). Root cause not as yet known Repairs successfully accomplished 750 MHz separators fully functional Unanticipated LCW pressure vulnerability to be fixed CLAS12 2017-06-14 19/NN CEBAF Operations

Cold Compressor Trip, fast spin-down Spring 2017 run was going well up to March 9th 2017 CHL1->SC1 tripped off in the evening Recovered and tripped in the early morning of March 10th Cold Compressor 5 (CC5) inoperable post 2nd trip. Not initiated by power failure as earlier event CLAS12 Collaboration Meeting, June 13-16, 2017 20

Cryo: CHL1->SC1->CC5 Update 2017-05-02: Broken wire on magnetic bearing connector was found. CLAS12 2017-06-14 21 CEBAF Operations

CHL Status Now Failed CC4 from 2 years ago rebuilt and returned a week ago preparing for reinstallation Warm spin testing expected week of June 19 identified new CC5 wiring issue "infant mortality" in low-time system Repaired; warm spin testing this week spare oil-based compressor (2500 hp) deleted from 12 GeV project to cut costs equivalent item purchased (UIM) available for use now CLAS12 Collaboration Meeting, June 13-16, 2017 22

Unscheduled Tuning: what is it? Something goes wrong during beam delivery No system shows a fault Beam doesn't go where/how we want Vacuum Focusing magnets Bending/Steering magnets Accelerating RF Bunch formation RF in injector Cathode drive laser Unrecognized drifts in other systems Use the beam for sub-system diagnosis Time-consuming, inefficient CLAS12 Collaboration Meeting, June 13-16, 2017 23

Example: MQA2R09 wiring error Resistance (barely) within range Use raytrace differential orbit data to diagnose Identified long-standing 15% focusing strength error CLAS12 Collaboration Meeting, June 13-16, 2017 24

Reported Resistance of QA/QK Quads CLAS12 Collaboration Meeting, June 13-16, 2017 25

Improved Calibration of DC Power Systematic measurement of magnet resistances Recalibration of voltage read-back in trim system Voltage historically secondary to amperage Improved resistance measurements Identification of difficult-to-diagnose errors Follow-on to previous system improvements Noise alarm (flicker in readback) Voltage tracking after establishing set point Target: detection of in-situ degradation Better system monitoring Early identification of installation errors CLAS12 Collaboration Meeting, June 13-16, 2017 26

CEBAF Performance Plan (Under Development) CLAS12 2017-06-14 27 CEBAF Operations

Performance Goals What Unit Goal Availability % > 80 Optimal Weeks weeks-per-year 37 Beam Tuning Hours h/week <8 Peak Hall Multiplicity Number of halls 4 12 GeV Program Expected years Duration 20 Performance Plan Duration years 5 Linac Design Energy MeV 1090 Required Linac Energy Margin at start of FY MeV > 110 Overall FSD Trip rate trips/h < 15 Overall FSD Trip Downtime min/h 5 RF Trip rate trips/h < 10 Beam Loss Trip rate trips/h <5 CLAS12 2017-06-14 28 CEBAF Operations

Short-term Outlook CHL configuration uncertain for a few more weeks Overhauled cold compressor tests imminent Linac (SRF and other systems) performance improving 750 MHz separators back on-line Operational issues being solved Energy gain per pass is improving Improving operations procedures Improving internal calibrations Budget and schedule? We should all find out soon CLAS12 Collaboration Meeting, June 13-16, 2017 29

Summary 12 GeV Experimental program established Hall-A: GMp completed (Hall-A), schedule portion of DVCS completed Hall-B: PRad completed, HPS engineering run Hall-D: First production run Spring 2017 12 GeV beam related activities completed Hall-B KPP Hall-C KPP Accelerator Operations continues to dial in 12 GeV performance Combined effort with CASA, SRF, Engineering, Facilities Availability Challenges Remain New systems issues: Box supplies, magnet buses End-of-life issues: SRF Window failures, SC1 2K cold-box Performance Plan in development Lack of critical spares End-of-life issues and obsolescence CLAS12 2017-06-14 30 CEBAF Operations