PEP-II Overview & Ramp Down Plan. J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007

Similar documents
PEP-II Disassembly Technical Systems

Status and Plans for PEP-II

Program Risks Risk Analysis Fallback Plans for the. John T. Seeman DOE PEP-II Operations Review April 26, 2006

PEP II Design Outline

PEP II STATUS AND PLANS *

PEP II Status and Plans

A Facility for Accelerator Physics and Test Beam Experiments

5 Project Costs and Schedule

SABER A Facility for Accelerator Physics and Test Beam Experiments Roger Erickson SABER Workshop March 15, 2006

AREAL- Phase 1. B. Grigoryan on behalf of AREAL team

ABORT DIAGNOSTICS AND ANALYSIS DURING KEKB OPERATION

RADIATION SAFETY SYSTEM OF THE B-FACTORY AT THE STANFORD LINEAR ACCELERATOR CENTER

PEP-II STATUS REPORT *

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

ANKA Status Report. N.Smale, A.-S. Müller, E. Huttel, M.Schuh Slides courtesy of A.-S. Müller and C.Heske.

Monthly Progress Report Stanford Synchrotron Radiation Laboratory

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

North Damping Ring RF

Detailed Design Report

PEP-I1 RF Feedback System Simulation

LCLS Injector Technical Review

Summary of CBETA Independent Cost Reviews. R. Michnoff January 19, 2017

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems

A Cathode Development Cornell Cultera This scope includes all labor and purchases required produce photocathodes required by CBETA.

Status of the FAIR Project. Jürgen Henschel FAIR Project Leader / Technical Director GSI & FAIR

Full IEFC workshop Feb.

Energy Upgrade Options for the LCLS-I Linac

ANKA RF System - Upgrade Strategies

PEP-II IR-2 Alignment

Availability and Reliability Issues for the ILC

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

OF THIS DOCUMENT IS W8.MTO ^ SF6

Upgrading LHC Luminosity

Present Status and Future Upgrade of KEKB Injector Linac

Upgrade of CEBAF to 12 GeV

What can be learned from HERA Experience for ILC Availability

PICS IN THE INJECTOR COMPLEX WHAT ARE WE TALKING ABOUT?

Accelerator Instrumentation RD. Monday, July 14, 2003 Marc Ross

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting

Next Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack

Operational Status of PF-Ring and PF-AR after the Earthquake

Workshop on Accelerator Operations August 6-10, 2012 Glen D. Johns Accelerator Operations Manager

Operating Experience and Reliability Improvements on the 5 kw CW Klystron at Jefferson Lab

Spear3 RF System Sam Park 11/06/2003. Spear3 RF System. High Power Components Operation and Control. RF Requirement.

RF Upgrades & Experience At JLab. Rick Nelson

!"!3

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

A Unique Power Supply for the PEP II Klystron at SLAC*

Status of RF Power and Acceleration of the MAX IV - LINAC

LHC Beam Instrumentation Further Discussion

DELIVERY RECORD. Location: Ibaraki, Japan

News from HZB / BESSY Wolfgang Anders at ESLS-RF Meeting September 2010 Trieste

Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi)

Status of the X-ray FEL control system at SPring-8

Radiation Safety System for Stanford Synchrotron Radiation Laboratory*

Proceedings of the 1997 Workshop on RF Superconductivity, Abano Terme (Padova), Italy

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

FIRST SIMULTANEOUS TOP-UP OPERATION OF THREE DIFFERENT RINGS IN KEK INJECTOR LINAC

SLAC ILC Accelerator R&D Program

LLRF at SSRF. Yubin Zhao

LEPTON COLLIDER OPERATION WITH CONSTANT CURRENTS Λ

RF Power Generation II

Digital BPMs and Orbit Feedback Systems

2008 JINST 3 S LHC Machine THE CERN LARGE HADRON COLLIDER: ACCELERATOR AND EXPERIMENTS. Lyndon Evans 1 and Philip Bryant (editors) 2

LSD Review December 2012 Schedule, Re-Baseline, & Resource Analysis

... A COMPUTER SYSTEM FOR MULTIPARAMETER PULSE HEIGHT ANALYSIS AND CONTROL*

The Elettra Storage Ring and Top-Up Operation

Preparations for Installation, Testing and Commissioning based on Experience at CERN, SNS and Siemens

INFN School on Electron Accelerators. RF Power Sources and Distribution

Current status of XFEL/SPring-8 project and SCSS test accelerator

KEKB INJECTOR LINAC AND UPGRADE FOR SUPERKEKB

Evaluation of Performance, Reliability, and Risk for High Peak Power RF Sources from S-band through X-band for Advanced Accelerator Applications

Linac 4 Instrumentation K.Hanke CERN

STATUS OF THE SwissFEL C-BAND LINAC

Bunch-by-bunch feedback and LLRF at ELSA

RF Power Klystrons & 20 Year Look. R. Nelson 7/15/15

CLIC Feasibility Demonstration at CTF3

Synchrotron Light Facility. Operation of ALBA RF. Angela Salom on behalf of RF team: Francis Perez, Bea Bravo and Jesus Ocampo

PRESENT STATUS OF J-PARC

Status of SOLARIS Arkadiusz Kisiel

Summer / Fall 2004 Downtime AEG Preparation Work

TWO BUNCHES WITH NS-SEPARATION WITH LCLS*

CBETA Quarterly Report 7

Equipment Installation, Planning, Layout, organisation and updates

PEP II Status. H. - Ulrich (UZi) Wienands PEP-II Run Coordinator. SLAGEPAC Meeting November 8,200O. Intro; 11/7/O 19:55

US-ILC Waveguide Industrialization Study. Marc Ross, Chris Nantista and Chris Adolphsen

The FAIR plinac RF Systems

High Brightness Injector Development and ERL Planning at Cornell. Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics

Development of Multiple Beam Guns for High Power RF Sources for Accelerators and Colliders

CERN S PROTON SYNCHROTRON COMPLEX OPERATION TEAMS AND DIAGNOSTICS APPLICATIONS

Andrei Seryi, Toshiaki Tauchi. December 15-18, 2008

Scavenger Extraction. Karen Goldsmith Shawn Alverson

P. Emma, et al. LCLS Operations Lectures

Linac3 experience for LHC ion runs

SUMMARY OF THE ILC R&D AND DESIGN

SLS RF operation report 2003

Report on the LCLS Injector Technical Review

SRS and ERLP developments. Andrew moss

1. General principles for injection of beam into the LHC

Transcription:

PEP-II Overview & Ramp Down Plan J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007

Topics Overview of the PEP-II Collider PEP-II turns off September 30, 2008. General list of components and buildings Categories of issues Overview of Ramp Down Plan Overview of Minimum Maintenance State (MMS)

PEP-II B Factory at SLAC + 9 GeV e 3.1 GeV e ϒ (4 S ) boost: βγ = 0.55 Head - on collisions Located at the Stanford Linear Accelerator Center

PEP-II e + e - Collider BaBarDetector HER RF 476 MHz Feedbacks Diagnostics LER RF 476 MHz C = 2200 m 3.1 GeV positrons x 9 GeV electrons

Beam Line Lengths HER = 2200 m LER = 2200 m HER injection line = 2300 m LER injection line = 2900 m Total length of beam line = 9600 m ( 6.0 miles)

Other components ~10 miles of cable trays ~200 miles of cable (typically 1 inch dia) ~7 miles of water distribution lines 15 klystron cavity systems ~900 electro-magnets per ring (~1800) ~6 miles of vacuum chambers Thousands of supports

PEP-II Arc Section LER HER

B-Factory RF Klystrons C. Pearson

PEP-II RF Cavities

Cable trays Sprinkler pipes Fire sensors Lights Utility pipes Supports Vacuum chambers Magnets

Document Items 1) The components in the tunnel should be technically documented and the data stored and correlated to the components. 2) Spare parts should be documented and collected. 3) The components should be offered to other DOE projects and/or facilities.

My list of valuable components RF systems Electro-magnets Power supplies Vacuum pumps and diagnostics Some beam instrumentation (e.g. streak camera at ~180 k$) Feedback amplifiers Water pumps, pump motors, heat exchangers

PEP-II Interaction Region (IR) Halls (six)

PEP-II IR Hall 12 (on tour today)

PEP-II IR2 with BaBar (on tour)

PEP-II RF High Voltage Pads and Water Pump Stations (three)

Support Buildings of PEP-II (six)

PEP-II Buildings Outside the Radiation Fence (two)

PEP-II Water Pump Pads (three)

PEP-II Power Distribution (~five)

PEP-II External Cable Trays

PEP-II Klystron High Voltage Power Supplies (15 total)

PEP-II Air Vents (seven)

Cut and Cover Region of PEP-II

PEP-II Klystron Building (three)

PEP-II Power Supply Buildings (nine)

PEP-II Cable Distribution

PEP-II injection line in Linac LER injection line Linac HER Injection Line

Injection Line (South)

PEP-II Injection Line

PEP-II Injection Septa (two)

PEP-II dipoles in 1994 ready for installation

PEP-II tunnel ceiling

PEP-II ground water wall leaks

PEP-II Sump Pumps

Wall Corrosion

PEP-II Utility work in late March 2007 (3 days) for LCLS Transite pipes PEP-II cooling water and air lines

Transition & DND planning Transition plan white paper: input to FY09 budget process Describes transition from fully operational state to a minimalmaintenance state in FY09-FY10 Outlines major tasks and timelines for this transition Extrapolations from existing PEP-II and BABAR operational experience Outlines scenarios for dismantle and disposal phase that emerged from discussions with OS/HEP in early May Input to FY09 budget development, FY10-FY11 planning Transition and D&D task force: in progress Established at beginning of May to review and refine transition plan and develop next level of planning for D&D in light of white paper scenarios Feedback from this review will be used to develop a more refined and detailed D&D plan in fall 2007

Transition planning assumptions FY09-FY10: Transition minimal maintenance state B Factory will immediately transition to minimal-maintenance state following end of operations FY10-FY14: Minimal maintenance state Kept in minimal-maintenance state to prevent deterioration of equipment Envision possibility for strategic re-use of components For example, potential interest in equipment as contribution to an off-shore Super B Factory. About FY15: Dismantle and dispose Equipment scheduled for removal, and storage or disposal Costs to be borne by DOE Scenarios for disposal depend on whether existing moratorium on recycling metals from accelerator housing remains in effect or not

Minimal Maintenance State (MMS) PEP-II Cooling systems of magnets and vacuum drained & dried Documentation of parts and spares Vacuum system vented and secured RF systems, including power supplies, klystrons, cavities, circulators, and dumps drained and secured Fire protection, tunnel lighting, water seepage system all maintained Estimate ~$1 million/year in manpower, M&S, and electricity costs for tunnel maintenance (not equipment) Security watches over the system Crane inspections Controls maintenance for safety issues (PPS/Fire)

Tasks and timelines: FY09-FY10

Manpower and budgets for transition FY09 FY10 FY11 FTE Budget [k$] FTE Budget [k$] FTE Budget [k$] Accelerator Systems Labor 2.2 330 1.7 270 0.6 100 Operations Directorate Labor 13.8 2070 6 940 1.9 280 M&S 600 400 200 Power 950 650 400 Total 3950 2260 980 Budget for MMS state is almost entirely building maintenance costs (sump pumps, lights, tunnel integrity) and not directly the cost of maintaining the equipment

Ramp Down Work Scheduling There are other items going on in October 2008: LCLS final construction SABER initial preparations Routine down maintenance repairs for next Linac run PEP-II ramp down will have lower priority during down! Is it best for many people to work for a short period (~ 1 month) or a few people for many months (~14)? It is likely that the PEP-II ramp down work will be delayed until the linac turns on later in the fiscal year, which avoids overlap with intense linac work period and allows leveling of man power loading. Thus, likely that a slower approach will be better.

Dismantling and disposal Major factor: DOE moratorium on removal for salvage of volumetrically contaminated metals from accelerator areas In effect since 2000, waiting for National Regulatory Commission to establish standards Possible to move equipment to other laboratories, but not to recycle commercially; options for disposal may be expensive and/or limited Scenario I: Provision for development of onsite storage of BABAR and/or PEP-II components removed from IR halls or tunnels Moratorium does not apply to service buildings and regions in IR halls outside controlled access area Scenario II Moratorium resolved, so that material with no residual activity can be removed and recycled

FFTB Metals Storage (FY2006)

FFTB Shielding Storage (FY2006)

SPEAR-II Metals Storage (~FY2001)

Conclusions The PEP-II ramp down scope has been identified. An initial transition plan has been made. Initial budget and manpower estimates have been made. A resolution of the Metals Moratorium would help this process.