SABER A Facility for Accelerator Physics and Test Beam Experiments Roger Erickson SABER Workshop March 15, 2006

Similar documents
A Facility for Accelerator Physics and Test Beam Experiments

PEP-II Overview & Ramp Down Plan. J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007

P. Emma, et al. LCLS Operations Lectures

PEP II STATUS AND PLANS *

Requirements for the Beam Abort Magnet and Dump

5 Project Costs and Schedule

PEP II Design Outline

PEP II Status and Plans

LCLS Injector Technical Review

FINAL DESIGN OF ILC RTML EXTRACTION LINE FOR SINGLE STAGE BUNCH COMPRESSOR

Electron Bypass Line (EBL) Design Electrons to A-line bypassing LCLS T. Fieguth, R. Arnold

Hall-B Beamline Commissioning Plan for CLAS12

Focus of efforts. ILC 2010, Mar/27/10 A. Seryi, BDS: 2

Future Performance of the LCLS

An Operational Diagnostic Complement for Positrons at CEBAF/JLab

Present Status and Future Upgrade of KEKB Injector Linac

SPEAR 3: Operations Update and Impact of Top-Off Injection

Beam Losses During LCLS Injector Phase-1 1 Operation

TITLE PAGE. Title of paper: PUSH-PULL FEL, A NEW ERL CONCEPT Author: Andrew Hutton. Author Affiliation: Jefferson Lab. Requested Proceedings:

PEP-II Disassembly Technical Systems

Accelerator Instrumentation RD. Monday, July 14, 2003 Marc Ross

Program Risks Risk Analysis Fallback Plans for the. John T. Seeman DOE PEP-II Operations Review April 26, 2006

Energy Upgrade Options for the LCLS-I Linac

Report on the LCLS Injector Technical Review

RADIATION SAFETY SYSTEM OF THE B-FACTORY AT THE STANFORD LINEAR ACCELERATOR CENTER

SUMMARY OF THE ILC R&D AND DESIGN

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems

LCLS Linac Technical Design Review Diagnostics and Controls

Station-100. From its Definition to its Realization both in the Tunnel and Outside. 05/05/05 Catherine LeCocq STA

PROJECT DESCRIPTION. Longitudinal phase space monitors for the ILC injectors and bunch compressors

Linac 4 Instrumentation K.Hanke CERN

Simulations on Beam Monitor Systems for Longitudinal Feedback Schemes at FLASH.

Linac-Beam Characterizations at 600 MeV Using Optical Transition Radiation Diagnostics *

Recent APS Storage Ring Instrumentation Developments. Glenn Decker Advanced Photon Source Beam Diagnostics March 1, 2010

THE NEXT LINEAR COLLIDER TEST ACCELERATOR: STATUS AND RESULTS * Abstract

Availability and Reliability Issues for the ILC

Summary of the 1 st Beam Line Review Meeting Injector ( )

Status and Plans for PEP-II

Digital BPMs and Orbit Feedback Systems

LEP OPERATION AND PERFORMANCE WITH ELECTRON-POSITRON COLLISIONS AT 209 GEV

Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi)

COMMISSIONING SCENARIOS FOR THE J-PARC ACCELERATOR COMPLEX

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

SLAC ILC Accelerator R&D Program

. SLAC-P~ December 1995

TESLA FEL-Report

1. General principles for injection of beam into the LHC

Status of SOLARIS Arkadiusz Kisiel

TWO BUNCHES WITH NS-SEPARATION WITH LCLS*

FIRST SIMULTANEOUS TOP-UP OPERATION OF THREE DIFFERENT RINGS IN KEK INJECTOR LINAC

Suggested ILC Beam Parameter Range Rev. 2/28/05 Tor Raubenheimer

30 GHz Power Production / Beam Line

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

The Elettra Storage Ring and Top-Up Operation

PEP-II STATUS REPORT *

LEPTON COLLIDER OPERATION WITH CONSTANT CURRENTS Λ

Tutorial: Trak design of an electron injector for a coupled-cavity linear accelerator

Status of Elettra, top-up and other upgrades

November 5,1999. The NLC Injector UCRL-JC

Characterizing Transverse Beam Dynamics at the APS Storage Ring Using a Dual-Sweep Streak Camera

CLIC Feasibility Demonstration at CTF3

OPERATIONAL EXPERIENCE AT J-PARC

CERN S PROTON SYNCHROTRON COMPLEX OPERATION TEAMS AND DIAGNOSTICS APPLICATIONS

Status of CTF3. G.Geschonke CERN, AB

Soft x-ray optical diagnostics, concepts and issues for NGLS

Periodic Seasonal Variation of Magnets Level of the STB ring

Andrei Seryi, Toshiaki Tauchi. December 15-18, 2008

Summer / Fall 2004 Downtime AEG Preparation Work

PEP-II IR-2 Alignment

COMMISSIONING AND FIRST RESULTS OF THE ELECTRON BEAM PROFILER IN THE MAIN INJECTOR AT FERMILAB*

Detailed Design Report

Upgrading LHC Luminosity

RF considerations for SwissFEL

BUNCH-COMPRESSOR TRANSVERSE PROFILE MONITORS OF THE SwissFEL INJECTOR TEST FACILITY

Start to End Simulations

Beam Instrumentation for CTF3 and CLIC

Week 0: PPS Certification and Processing. Mon Feb 11 Tue Feb 12 Wed Feb 13 Thu Feb 14 Fri Feb 15 Sat Feb 16 Sun Feb 17

STATUS OF THE SwissFEL C-BAND LINAC

Preparations for Installation, Testing and Commissioning based on Experience at CERN, SNS and Siemens

Technical Document 1 attached to the European XFEL Convention

An Overview of Beam Diagnostic and Control Systems for AREAL Linac

4.4 Injector Linear Accelerator

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

Top-Up Experience at SPEAR3

STATUS OF THE INTERNATIONAL LINEAR COLLIDER

Radiation Safety System for Stanford Synchrotron Radiation Laboratory*

Overview of the X-band R&D Program

Studies on an S-band bunching system with hybrid buncher

Extraction/Separator Setup. Michael Spata Operations Stay Treat July 16, 2015

STATUS OF THE EUROPEAN XFEL

Beam Instrumentation for X-ray FELs

AREAL- Phase 1. B. Grigoryan on behalf of AREAL team

New Filling Pattern for SLS-FEMTO

SLAC ILC program, International BDS Design, ATF2 facility

ILC Damping Ring Lattice Status Report. Louis Emery and Aimin Xiao Argonne National Laboratory Presented at KEK workshop Dec 18th, 2007

AN OPTICAL AND TERAHERTZ INSTRUMENTATION SYSTEM AT THE FAST LINAC AT FERMILAB*

LHC Beam Instrumentation Further Discussion

Scavenger Extraction. Karen Goldsmith Shawn Alverson

Commissioning and Performance of the ATLAS Transition Radiation Tracker with High Energy Collisions at LHC

Transcription:

SABER A Facility for Accelerator Physics and Test Beam Experiments Roger Erickson SABER Workshop March 15, 2006

FFTB will soon be gone! The Problem: On April 10, 2006, the Final Focus Test Beam (FFTB) will be shut down to make room for the LCLS. What can be done to replace its functions? SABER: South Arc Beam Experiment Region A proposed facility for experiments requiring compressed, focused beams of electrons or positrons. To be built in the Instrument Section in the SLC South Arc tunnel.

SLAC Overview with SABER LCLS injector will be installed at Sector 21, downstream of existing positron source. LCLS transport system and undulator will displace the FFTB. SABER consists of three main components: Experimental area with final focus and beam dump in SLC South Arc tunnel. Linac Pulse Compressor upgrade to compress positron bunches. Bypass Line to deliver e - or e + beams to SABER, bypassing the LCLS.

Recent History of FFTB Final Focus Test Beam (FFTB) Preserves small emittance. Delivers and compresses ultrashort (< 100 fsec) bunches. Strong user demand: Plasma wakefield acceleration SPPS Laboratory Astrophysics Many other unusual physics and technology measurements

Research Yard Experimental Facilities ESA FFTB

Final Focus Test Beam Programs The FFTB was originally built to demonstrate technology for focusing and measuring sub-micron electron beams suitable for a future linear collider. Experiment E-166 A Proposal to Test Production of Polarized Positrons with the SLAC 50-GeV Beam in the FFTB. An undulator-based technique applicable to a future linear collider. Status: Data run completed. Positron polarization demonstrated. SPPS Ongoing program involving generation of extremely short x-ray pulses. Status: Currently running. E-167 Plasma Wakefield Acceleration Ongoing program to develop new methods for achieving very high accelerating gradients, strong plasma focusing, and related technology. Status: Next run scheduled to start March 20. Laboratory Astrophysics E-165 Fluorescence in Air from Showers (FLASH) A continuing program to quantitatively understand the production of light by cosmic rays in the upper atmosphere, using controlled laboratory conditions. Status: Next run not yet scheduled. Candidate for first SABER experiment.

Test Beam Experiments in FFTB T-447 Single Pulse Damage in Materials (Sept 2000) T-448 Magnified Optical Transition Radiation Test (Oct 2000) T-450 Damage Test in Diamond for LCLS (Oct 2000) T-451 High Energy Neutron Spectra Measurement (March 2001) T-452 STAR Endcap Calorimeter Detector Prototype Test (Jan 2001) T-453 Radiation Damage in Diamond for LCLS (April 2001) T-454 Measurement of Neutron Spectra (June 2001) T-455 Measurement of the Calorimeter for the Local Polarimeter at Phenix/RHIC (Aug 2001) T-456 Magnetization Dynamics in Magnetic Films (Sept 2001) T-457 Measurement of Neutron Energy Spectra Using Bonner Multi-Sphere Spectrometer (June 2002) T-460 Characterization of Askaryan Effect in Rock Salt (June 2002) T-461 High Atmosphere Air Fluorescence (June 2002) T-462 Magnetization Dynamics of Soft-Magnetic Films (June 2002) T-464 Correlation of Linac Transverse Deflection Cavity with FFTB Streak Camera (June 2002) T-465 Magnetization Dynamics in the Sub-picosecond Time Scale (May 2003) T-466 UCLA Electromagnetic Calorimeter (EMC) Prototype (May 2003) T-467 Measurement of FFTB Backgrounds for E166 (Jan 2004) T-468 Diamond Detector Response (July 2003) T-470 DASH: Diamond Detectors for FLASH (June 2004) T-471 Incoherent Radio Emission from Showers (July 2004) T-472 Neutron Energy Spectra Measurements (June 2004) T-473 Diamond Detector Response (July 2004) T-478 Magnetism with Ultrashort Magnetic Field Pulses (August 2005) T-481 Ultra-high Gradient Cerenkov Wakefield Acceleration (August 2005) T-482 XTR as an Electron Beam Diagnostic (August 2005) T-485 Magnetism with Ultrashort Magnetic Field Pulses (January 2006)

SABER in SLC South Arc Tunnel

Architectural Drawing of South Arc Area

South Arc Tunnel People can work safely in the South Arc tunnel, independent of PEP-II or LCLS operations. Easy access through upgraded SW Adit entrance. Convenient space for user building in existing paved area beside SW Adit ramp. Radiation safety issues are easier than in FFTB (SABER is deep underground).

South Arc Tunnel Upstream end of Instrument Section, SW Adit visible to the left. Southwest Adit tunnel, leading to removable shielding wall.

South Arc Tunnel User experiments could be set up in this area. Instrument Section, looking downstream. Floor slopes slightly downward. Instrument Section, looking upstream.

South Arc Tunnel Cross Section

Current Status of South Arc SLC ran until June 1998. South arc and Instrument Section have been well preserved. Plumbing and most magnets appear to be in good shape. LCW flow has been maintained, except for a few devices in the BSY. Some flexible hoses need preventive maintenance. Vacuum system integrity is good. System is being pumped down. Control system is functioning; arc magnet movers respond to control system commands. Evidence of radiation damage to dc cables in BSY area requires further investigation. PPS system has been decommissioned and requires work. Quadrupole magnets in the BSY zone and non-interlocked corrector magnets in the S ARC zone have been powered up.

Questions/Issues for Experimental Area How much space is needed to accommodate experiments? Current working design: Nominal beam position: 42 inches above the tunnel floor. 39 inches from south tunnel wall. Downward pitch 3.730 deg. Focal point is 2m downstream of face of last quadrupole. Drift following focal point is approximately 70 feet to the next arc AG magnet (where the tunnel starts to curve to the south).

Ease of Access SW Adit entrance: Ramp is approximately 10 ft wide. Would a 39 inch door (same as FFTB), followed by 4 ft wide PPS maze, be wide enough for equipment access? Two vertical cable penetrations, currently filled with conduits, can accommodate a few more cables. One is near the upstream end of the IS, and reaches the surface outside the west door of MCC. The other is near the proposed IP and reaches the surface outside the east door of MCC. A cable tray could be installed through the SW Adit (through the maze or above the shielding blocks) to a trailer or other building on the paved area near the SW Adit ramp. Expect total cable length approx 300 feet.

Beam Dump Issues What are experimenter requirements for dump line? Is beam deflection required after IP to separate charged particles from photons? By how large an angle or offset? Should the design include spectrometer features? Are additional focusing magnet needed downstream of the IP? What is maximum desired beam power? This will impact dump, shielding, and MPS designs. (FFTB was never more than about 1 KW.)

Positron Compressor Chicane Sector 10 compressor chicane has been used successfully for several years, but cannot be used with positrons (because electrons are required to make the positrons, and only one charge can pass through the present chicane). Chicane can be modified to be symmetric for electrons and positrons. Issues: Beam matching: beta x and beta y are interchanged between e+ and e- in the linac. Does this create a matching problem? Pole width of first and fourth dipole magnets may be marginal if used for both e+ and e -.

Proposed Symmetric Chicane e+ e-

Sector 10 Electron Compressor Chicane

First Dipole of Compressor Chicane Notice that straight-through beam is off center.

Bypass Line A Bypass Line from Sector 20 would allow delivery of 30 GeV electrons to BSY without passing through last third of linac. SABER would then be independent of LCLS operations. Optics design is compatible with connection to the South Arc, but trajectory and engineering details must be refined to minimize interference with existing equipment. Trajectory past Sector 30 and NIT/SIT breakout point passes through a congested area, but can be built with careful planning. Cost could be significantly reduced by converting one of the PEP-II injection transport lines for this purpose.

PEP-II Transport Lines in Linac Tunnel e- e+

Linac Tunnel Approaching BSY Bypass Line LINAC Bypass Line trajectory will pass over SIT Line through congested area. SIT Line to PEP-II

Bypass Trajectory near 51AGF Can we find a way to preserve the direct linac-to-sarc connection with the bypass?

Bypass Trajectory into 51B2

B2 Dipoles in 51- and 52-lines LCLS Trajectory 51-Line

Diverging Beam Lines in BSY

SABER Beam Parameters Energy: 28.5 GeV with PEP-II or LCLS with bypass line. Up to 50 GeV with full linac (but not with bypass line). Charge per pulse: 2 x 10 10 e - or e + /pulse with full compression. 3.5 x 10 10 e - or e + /pulse without compression. Pulse length: σ z = 30 μm with 4% momentum spread. σ z = 42 μm with 1.5% momentum spread. Spot size at IP: 10 μm nominal; σ x, y = 5.2 x 5.4 μm achieved in computer simulations. Momentum spread: 4% full width with full compression. < 0.5% full width without compression. Momentum dispersion at IP: η = 0. η = 0.

Focused Beam

Bunch length vs energy spread

Proposed Schedule Refurbishment work in BSY; tie in with PPS: August October 2006. First electrons to the SLC Instrument Section in December. First beam positrons or compressed electrons through the full linac, interleaved with PEP-II injection pulses, to a dump in the SLC Instrument Section in 2007. Installation of positron compressor chicane in linac: Sept Oct 2007. Positron beam, fully compressed and focused in 2008. Bypass line in 2009. SABER experimental programs can coexist with PEP-II and LCLS programs. This schedule depends on the availability of engineering manpower and other resources.

Summary We have seen a constant demand for electron and positron beams in the FFTB from a wide variety of users. The FFTB will be dismantled in a few weeks to make room for the Linac Coherent Light Source (LCLS). We have been exploring replacement options. A new facility to replace the FFTB can be constructed in the SLC South Arc tunnel. A proof-of-principle study shows that low emittance, compressed bunches can be delivered to users. The electron bunch compressor chicane in the linac can be modified to compress positron bunches, opening up new areas of physics. A Bypass Line from Sector 20 to the BSY can be built to deliver beams to SABER, independent of LCLS. A strong show of interest from the user community will ensure the success of this program!

Acknowledgements Special thanks to: Yuri Nosochkov, who has developed optical solutions for SABER. Karl Bane, who has been investigating wake field effects and demonstrated bunch compression in the South Arc. Lynn Bentson, who has done the preliminary engineering studies and cost estimates. Paul Emma, who did initial optics and tracking simulations for the FFTB and has helped in exploring other options. Mark Woodley, who has assisted with design and tracking studies. Patrick Krejcik, who revived our interest in the South Arc option and demonstrated its feasibility. Ted Fieguth, whose dedication to SLAC s test beam activities has kept these programs alive and who has provided invaluable advice and perspective. John Seeman, who has consistently supported and encouraged these studies. Al Baker, Martin Berndt, Alex Chao, Scott DeBarger, Rick Iverson, Paul Miller, Alyssa Prinz, Mike Saleski, and the MFD and CPE staff members who have been helping assess the feasibility of SABER.