Linac upgrade plan using a C-band system for SuperKEKB

Similar documents
KEKB INJECTOR LINAC AND UPGRADE FOR SUPERKEKB

Present Status and Future Upgrade of KEKB Injector Linac

Trigger-timing signal distribution system for the KEK electron/positron injector linac

Detailed Design Report

FIRST SIMULTANEOUS TOP-UP OPERATION OF THREE DIFFERENT RINGS IN KEK INJECTOR LINAC

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

ABORT DIAGNOSTICS AND ANALYSIS DURING KEKB OPERATION

The PEFP 20-MeV Proton Linear Accelerator

ILC-LNF TECHNICAL NOTE

DELIVERY RECORD. Location: Ibaraki, Japan

THE NEXT LINEAR COLLIDER TEST ACCELERATOR: STATUS AND RESULTS * Abstract

Status of KEK X-band Test Facility and its future plans

First Simultaneous Top-up Operation of Three Different Rings in KEK Injector Linac

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

Next Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack

A HIGH POWER LONG PULSE HIGH EFFICIENCY MULTI BEAM KLYSTRON

XFEL High Power RF System Recent Developments

The LEP Superconducting RF System

The KEKB injector linac

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting

Development of high power gyrotron and EC technologies for ITER

Current status of XFEL/SPring-8 project and SCSS test accelerator

STATUS OF THE SwissFEL C-BAND LINAC

RF considerations for SwissFEL

PEP II Design Outline

Status of CTF3. G.Geschonke CERN, AB

45 MW, 22.8 GHz Second-Harmonic Multiplier for High-Gradient Tests*

Status of RF Power and Acceleration of the MAX IV - LINAC

Towards an X-Band Power Source at CERN and a European Structure Test Facility

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems

INFN School on Electron Accelerators. RF Power Sources and Distribution

RF Power Generation II

Upgrading LHC Luminosity

DESIGN AND PERFORMANCE OF L-BAND AND S-BAND MULTI BEAM KLYSTRONS

Jae-Young Choi On behalf of PLS-II Linac team

The Elettra Storage Ring and Top-Up Operation

4.4 Injector Linear Accelerator

OF THIS DOCUMENT IS W8.MTO ^ SF6

A New 4MW LHCD System for EAST

reported by T. Shintake KEK / RIKEN Japan Summary of C-band R&D for Linear Collider at KEK New soft-x-ray FEL Project at RIKEN/SPring-8

SRS and ERLP developments. Andrew moss

Pulsed Klystrons for Next Generation Neutron Sources Edward L. Eisen - CPI, Inc. Palo Alto, CA, USA

KARA and FLUTE RF Overview/status

Commissioning the TAMUTRAP RFQ cooler/buncher. E. Bennett, R. Burch, B. Fenker, M. Mehlman, D. Melconian, and P.D. Shidling

J/NLC Progress on R1 and R2 Issues. Chris Adolphsen

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

Design and Simulation of High Power RF Modulated Triode Electron Gun. A. Poursaleh

Dark current and multipacting trajectories simulations for the RF Photo Gun at PITZ

Introduction to CTF3. G.Geschonke CERN / PS

Status and Plans for PEP-II

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY

Spear3 RF System Sam Park 11/06/2003. Spear3 RF System. High Power Components Operation and Control. RF Requirement.

!"!3

RF plans for ESS. Morten Jensen. ESLS-RF 2013 Berlin

CLIC Feasibility Demonstration at CTF3

Chapter 4. Rf System Design. 4.1 Introduction Historical Perspective NLC Rf System Overview

Performance of a DC GaAs photocathode gun for the Jefferson lab FEL

A HIGH-POWER SUPERCONDUCTING H - LINAC (SPL) AT CERN

High Brightness Injector Development and ERL Planning at Cornell. Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics

TECHNICAL SPECIFICATION Multi-beam S-band Klystron type BT267

CERN EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH. A 50 Hz LOW-POWER SOLID-STATE KLYSTRON-MODULATOR

The basic parameters of the pre-injector are listed in the Table below. 100 MeV

9th ESLS RF Meeting September ALBA RF System. F. Perez. RF System 1/20

North Damping Ring RF

The Construction Status of CSNS Linac

RECENT PROGRESS IN UPGRADE OF THE HIGH INTENSITY THzzz zz-fel AT OzSAKzA UNIVERSITYzzzz

30 GHz Power Production / Beam Line

PoS(EPS-HEP2015)525. The RF system for FCC-ee. A. Butterworth CERN 1211 Geneva 23, Switzerland

The ALS RF systems, upgrades and ALS-U plans

RF Upgrades & Experience At JLab. Rick Nelson

PULSED POWER FOR FUTURE LINEAR ACCELERATORS

IOT RF Power Sources for Pulsed and CW Linacs

PRESENT STATUS OF J-PARC

Pulses inside the pulse mode of operation at RF Gun

Operational experience with the SOLEIL LINAC and Status of the ThomX LINAC project

NSLS-II RF Systems James Rose, Radio Frequency Group Leader PAC 2011

STATUS OF THE INTERNATIONAL LINEAR COLLIDER

TEST RESULTS OF THE 84 GHZ / 200 KW / CW GYROTRON

PULSED MODULATOR TECHNOLOGY

The TESLA RF System. S. Choroba. for the TESLA Collaboration. DESY Notkestr. 85, D Hamburg, Germany

5 Project Costs and Schedule

NEW METHOD FOR KLYSTRON MODELING

Studies on an S-band bunching system with hybrid buncher

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

The ESS Accelerator. For Norwegian Industry and Research. Oslo, 24 Sept Håkan Danared Deputy Head Accelerator Division Group Leader Beam Physics

NLC - The Next Linear Collider Project NLC R&D. D. L. Burke. DOE Annual Program Review SLAC April 9-11, 2003

Solid State Modulators for X-Band Accelerators

Overview of NLC/JLC Collaboration *

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

Introduction: CW SRF linac types, requirements and challenges High power RF system architecture

Design of a 50 MW Klystron at X-Band*

STATUS AND FUTURE PROSPECTS OF CLIC

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

Overview of the X-band R&D Program

GA A26497 SOLID-STATE HIGH-VOLTAGE CROWBAR UTILIZING SERIES-CONNECTED THYRISTORS

18 GHz, 2.2 kw KLYSTRON GENERATOR GKP 24KP 18GHz WR62 3x400V

Digital BPMs and Orbit Feedback Systems

SUMMARY OF THE ILC R&D AND DESIGN

ANKA RF System - Upgrade Strategies

Transcription:

Linac upgrade plan using a C-band system for SuperKEKB S. Fukuda, M. Akemono, M. Ikeda, T. Oogoe, T. Ohsawa, Y. Ogawa, K. Kakihara, H. Katagiri, T. Kamitani, M. Sato, T. Shidara, A. Shirakawa, T. Sugimura, T. Suwada, T. Takenaka, K. Nakao, H. Nakajima, K. Furukawa, H. Honma, T. Matsumoto, S. Michizono, Y. Yano and A. Enomoto KEK, 1-1 Oho, Tsukuba 305-0801, Japan We are developing a linac upgrade to increase the positron energy from the current 3.5 GeV to 8 GeV for SuperKEKB. For this project, we are considering replacement of the current S-band system for the last three sectors (24 subunits) by a C-band system with six sectors (48 subunits) utilizing the current infrastructure effectively. One unit of a high-power RF source and an accelerator system were newly introduced and processing of the C-band accelerator guide up to 43 MV/m was achieved. Thereafter, an accelerator was installed in the beamline of the KEKB linac to conduct a beam acceleration test. Beam acceleration was successfully performed and the 43 MV/m acceleration gradient was confirmed. The C-band accelerator guide is now in operation in the KEKB linac. A brief description of this project and the current status of R&D are presented in this paper. 1. INTRODUCTION The KEK B-factory (KEKB) has successfully achieved its targeted luminosity of 1x10 34 cm -2 s -1 and has been accumulating valuable data on B-meson physics. Recently, consideration of the SuperKEKB project, which aims to achieve a one order higher luminosity, has been progressing. There are several possible schemes for the injector linac in this project, as described in section 2, and the most likely plan requires a major switch in the beam energies, i.e., a change in the positron energy from 3.5 to 8.0 GeV and in the electron energy from 8 to 3.5 GeV, in order to suppress positron beam blow-up caused by the electron cloud in the ring. At the same time, the positron and electron currents are required to be increased to 1.2 nc and 5 nc, respectively. We are now preparing to upgrade the linac under the assumption of this energy-exchange scheme. In this scheme, it is presently being considered to replace the last three sectors (24 S-band klystron units) with the six sectors using the C-band system (48 C-band klystron units)[1]. Positrons after the conversion target are to be accelerated to 8 GeV using 48 SLEDs and klystrons with 50-MW output. In this paper, brief description of the entire system proposed for this scheme and recent progress results are presented. Figure 1 Proposed scheme using C-band system Figure 2 Simultaneous injection scheme using C-band system 2. SCHEME CONSIDERATION The present KEKB injector linac accelerates electrons to 8 GeV with 59 accelerator units, including a few stand-by units[2]. The electrons are injected directly into the High Energy Ring (HER) of KEKB. For positron injection, the electrons are accelerated to 4 GeV in the first four sectors (26 units), and then converted to positrons by the metal target. The generated positrons are accelerated to 3.5 GeV in the last four sectors (29 units), and injected into the Low Energy Ring (LER) of KEKB. For the SuperKEKB plan, which requires an energy change between the electrons and the positrons, the positrons are accelerated to 8 GeV. However the maximum energy gain achieved by all of the existing positron Figure 3 One of the possible schemes using a C-band system if there is no energy change acceleration units is not sufficient for 8 GeV injection. A simple way to achieve the positron energy increase is to use C-band accelerating structures, which have a higher acceleration gradient. The upgrade scheme presently being considered is shown in Fig. 1. In order not to degrade the beam quality as a result of the transition from S-band to C- 1

100m 100m 10kW AMP. e - 114 571 MHz MHz SHB1 SHB2 Electron Gun High Power ATT /Phase Shifter 1kW Amp. System Trigger System 20m MR Prebuncher ACC Guide Buncher CW 571 MHz SB-A 10 MHz 508 MHz 40m 5m Sector A Counter SB-B Sector B MAIN DRIVE LINE 2856MHz Ref. Signal Generator (FMD-30) 114 MHz Coaxial Lines 30m 5m 80m SB-C Sector C 571 MHz OpticalLines SB-1 30m 15m E/O 1kW Amp. System 5712MHz O/E Driver SUB-BOOSTER 2 60kW S-band SUB DRIVE LINE(39D) I A C-band Waveguide Driving Line 50MW S-band SLED I A SUB-BOOSTER 3-1 100kW C-band SUB DRIVE LINE(WG) 50MW C-band SLED Target e + ACC ACC Sector 1 e- Sector 2 Sector 3-1 Sector 3-2 Sector 4-1 Sector 4-2 Sector 5-1 Sector 5-2 Electron to LER Positron/Damping Ring SB3-2 SB4-1 SB4-2 SB5-1 SB5-2 Figure 4 Block diagram of C-band system for SuperKEKB upgrade Present Configuration of and Inverter 560 560 600 Control 600 600RF and Coil P/S 800 Proposed Configuration band structures, a 1.0 GeV damping ring and a buncher are also being considered. Figure 2 shows another scheme involving simultaneous injection of the positrons and electrons to raise the efficiency of injection to the KEKB ring. If the two-bunch operation currently performed in the present S-band system, is also possible in the scheme of Fig. 1, this will be useful for meeting the current increase requirement, which is another requirement of the injector linac for SuperKEKB. If the energy change between the positrons and the electrons is not needed, the C-band scheme is evitable, while there is difficulty in increasing the beam current and it is possible to introduce yet another scheme such as a recirculating beam scheme. Figure 3 shows one of the possible plans using a C-band system for the case of no energy change. 3. PROPOSED UPGRADE PLAN The plan currently in progress is based on the scheme schematically shown in Fig. 1. The expected RF system is Control Beam 40 MW Control Figure 5 Comparison between the old and new modulators (left) and RF feeding scheme (right) 40 MW considered to be a complex similar to the current S-band system, as shown in Fig. 4. In order to make use of the existing infrastructures, the modulator is changed so as to use a compact inverter power supply, which charges the existing discharging circuits. This enables us to decrease the modulator size to one-third that of the existing modulator, as shown in Fig. 5, and to install 48 modulators in the existing klystron gallery. In order to utilize the existing building, the development of this compact modulator is inevitable. High-power klystrons required to output 50MW power are commercially available. It is also planned to reuse klystron sockets, such as pulse transformers and oil tanks, since the operating voltage for 50MW output is almost the same condition as for the present S-band klystron operations. The currently designed RF system has a 100kW sub-booster (SB) klystron that drives eight 50MW klystrons to suppress the cost of the individual driver amplifiers. The accelerator guide is half the scale of that in the current S-band structures and has a 40MV/m acceleration gradient; reuse of the accelerator girders is also being considered. In order to obtain a 40MV/m acceleration gradient, the 40MW output power from the klystron is multiplied by a SLED (a power multiplication of 3.4 at a pulse width of 2 µs), and then fed to two 2 m- long C-band accelerators, which are halh-scale versions of those in the S-band structure. Assuming a filling time of 380 ns and an attenuation constant of 0.703, a peak power of about 59 MW at the entrance of the accelerator guide and an average acceleration gradient of 40 MV/m have been obtained. The SLED is considered to be a CERN-LIPS type[3], which uses the TE 038 mode having a reasonably high Q-value. This compressor is almost the same size as the current S-band SLED and is expected to effectively utilize the prior manufacturing experience. Table 1 shows a comparison between the S-band SLED and the proposed SLED. 2

4. C-BAND R&D STATUS C-band R&D started in the spring of 2002. The shortterm goal was to install an accelerator guide in the KEKB linac of #4-4 (where no accelerator was installed) during the shutdown period in the summer of 2003 and to conduct a beam test in the autumn of 2003. We started by purchasing C-band components, since we had no components of the C-band frequency. Several important items for this project were the design and manufacturing of the C-band accelerator, a SiC dummy load, and a waveguide vacuum flange, as well as the construction of an RF system including the development of an SB klystron, a high-power RF window, and a compact modulator. These components were successfully completed by the summer of 2003. A high-power test of the system and processing of the accelerator guide were also completed, and the guide was installed in the beamline of the KEKB linac on schedule. Table 1 Comparison between S-band SLED and proposed C-band SLED. KEKB-SLED LIPS-Type Resonant TE015 TE038 mode Diameter 20.51cm 22.19cm(scaled) Length 33.59cm 29.8cm(scaled) Frequency 2856MHz 5712MHz Cavity Q 107000 146970 (theory) Cavity Q (measured.) 97000 127800 (Expected) Coupling β 6.4 9-11 4.2. 50MW and Driving System A simple RF system was used in the test stand, which comprised a 2856MHz signal generator, a frequency doubler, a pulse modulator, an 8 W-transistor amplifier, and an SB klystron. The SB klystron was manufactured by retuning a weather-satellite klystron. From the SB klystron, an RF was fed through a WR-5 waveguide to a Toshiba 50MW klystron (E3746). The klystron socket was used in the same way as in the S-band system, which was possible up to 350 kv if the pulse transformer was rewound from 1:13.5 to 1:15. 4.3. High-Power RF Window It was necessary to use the RF window to separate the vacuum system between the klystron and the accelerator guide. Although the high-power klystron was equipped with two windows, because of the simplicity of the vacuum system we developed a high-power RF window that was capable of being used at the 50MW power level. This was a mixed-mode window (TE 11 +TM 11 ) proposed by Kazakov[4]. Using the mixed mode, the field decreased at the ceramic surface and on the edge, where brazing was conducted. 4.4. SiC Dummy Load It was necessary to develop a dry load, which absorbed the RF power at the exit of the accelerator guide. A SiC dummy load was developed by loading SiC cylindrical materials on the waveguide surface of the E-plane. Two SiC dummy loads set in parallel were successfully tested, as described below. 4.1. Compact A compact modulator was a key issue in order to install all of the required units in the existing klystron gallery. A prototype was manufactured using a DC inverter power supply, which charged the Pulse Forming Network (PFN). This inverter s maximum charging voltage was 50 kv, the peak charging current was 1.5 A, and the charging power was 30 kj. In the PFN, two circuits with 14 inductances (1.55 nh) and 14 capacitances (15.5 µf) each were placed in parallel. The designed flat top was 2 µs and the characteristic impedance of the PFN was 5 ohms. A pulse transformer having a 1:15 step-up ratio gave a 350 kv pulse at maximum to the high-power klystron. Although we faced many problems, which caused the IGBT to break down in the first stage, it has been stably operating for more than 1000 hours up to now. At the same time, R&D work to achieve more stable operation of the inverter power supply has been proceeding. Figure 6 Cutaway view of accelerator (top), disks and cylinders (bottom left), and coupler (bottom right) 4.5. Development of Accelerator Guide Although the basic design assumed the use of a 2 m- long accelerator guide, a 1 m-long C-band accelerator guide, which was half the scale of the current S-band guide, was manufactured as a prototype. This structure had the same electric property of the last half section of the 3

proposed 2 m-long guide, and 2a (inner bore diameter of accelerator guide) was varied from 12.44 to 10.41 mm. The filling time was 234 ns and the attenuation constant was 0.434. With the conditions of no SLED and 40 MW output power from the klystron, an acceleration gradient of about 39 MV/m was expected. The design was implemented using the HFSS and MAFIA-3D codes. Disks and cylinders were manufactured at KEK and Mitsubishi Heavy Industry (MHI), and electroplating of the regular cells and electron beam welding of the couplers were carried out at MHI. Fig. 6 shows a drawing and photos of the cell and coupler. The second model accelerator guide, which is also 1 m long, is currently being manufactured at the KEK machine factory. 4.6. Test Bench and Test Results A C-band test station was set in the accelerator assembly hall next to the S-band klystron test hall in the KEKB linac, in consideration of the short distance from the RF source to the shielding room. In this stand, a modulator test was performed in February 2003, and a C-band klystron test was conducted up to an Es (PFN voltage) of 42.5 kv with the program. Interlocks of the internal pressure and the VSWR were used to ensure that the accelerator guide was processed properly. Data such as the processing history, the generated dark current, and waveforms of the reflected power were automatically saved to memory to be used for analysis of this processing. A vibration sensor to detect the arcing position in the guide was set and its data were also saved. Conditioning up to 43.7 MW (corresponding to 42 MV/m) with 50 pps repetition and a 500 ns pulse width (this corresponds to the SLED output power width) was successfully achieved with a reasonable fault rate. Before installation in the beamline, phase shift measurements were performed to confirm no serious damage to the guide. Fig. 10 shows the processing history as a function of the pulse shot numbers. Figure 8 Waveforms: Voltage pulse (top), phase (second), current (third), and output RF (bottom). The horizontal scale is 1µs/div Figure 7 Birds-eye view of test hall a pulse repetition of 50 pps and a pulse width of 2 µs in March 2003. An output power of 43 MW was measured with two water-loads. Then the klystron output characteristics were measured. We also adjusted the pulse flat top by changing the PFN inductance. Tentatively, 1.3% flatness was obtained. Another adjustment led to a flatness corresponding to a phase variation of 2.6 degrees. Fig. 7 shows photos of the test hall and Fig. 8 shows various waveforms obtained. A resonant ring test of an RF window with a forward traveling wave of up to 160 MW was performed in March 2003, as shown in Fig. 9, which confirmed the high-power capability of a mixed-mode RF window. A high-power test of a SiC dummy load up to 43 MW was then successfully conducted in June 2003. High-power processing of the 1 m-long accelerator guide was conducted from July to August 2003. This processing was performed under a pattern determined by Figure 9 Resonant ring test and waveforms. The second waveform is that of the forward travelling wave 5. BEAM ACCELERATION After the successful processing and checking of the phase measurement at MHI, the accelerator guide was installed at the end of the summer shut-down period[5]. A second new compact modulator had been manufactured and was already set at #4-4 in summer and tested with a resistive load. The 50 MW high-power klystron assembly and associated driver system were moved from the test stand and installed at #4-4. Figures 11 and 12 show the accelerator guide and the klystron unit installed in the linac tunnel and klystron gallery, respectively. Processing of the accelerator guide was started from the end of 4

Es RFÁPower about 5 per hour, which is higher than the existing S-band cases. From the measurements of the acoustic sensor and analysis of the timing of reflected power during the processing, it was found that arcing occurs mainly at the input coupler section. It is therefore necessary to change the input coupler design for the next structure, and this is already under consideration. 6. SUMMARY Figure 10 Processing history of the accelerator guide as a function of the RF pulse shot numbers September 2003 and it was found that the reprocessing was performed quickly even though the structure was exposed to the atmosphere. After a week of processing, the final goal of the 42 MW level was achieved and a beam acceleration using the C-band structure was performed. This beam test was successfully conducted before the KEKB operation started, and the energy gain was analyzed by the analyzer at the linac end in the beam-switching yard. The preliminary data show that the installed 1 m C-band accelerator guide produced an energy of 40 MeV with an estimated measuring error of 5%. This corresponds to an average energy gradient of 40 MV/m at the output power of 42 MW from the klystron, thus we confirmed the design value. Figure 13 shows measuring data of the energy gain with the function of the RF phase and the sinusoidal fitting results. Since this accelerator guide has been kept operating as part of the KEKB injector linac, its long-term reliability has also been able to be investigated. So far it has been observed that the trip rate due to the VSWR is The first test of the C-band accelerator unit, including the RF driving system, klystron, waveguide components, and 1 m-long accelerator guide, was successfully performed for the linac upgrade of SuperKEKB. We installed the accelerator guide in the KEKB linac beamline, and also successfully performed beam acceleration up to 40 MV/m. This C-band system has been operating in the KEKB linac beamline as part of the routine machine operation, and operating data have been accumulated. At the same time, we will prepare a new test stand to test the next accelerator guide and an RF compressor. We plan to install two 2 m-long accelerator guides fed by a 50 MW klystron or four 2 m-long accelerator guides fed by two 50 MW klystrons in the #4-4 station of the klystron gallery This will give us important C-band operation experience as well as an energy contribution to the KEKB operation. 7. ACKNOWLEDGMENT The authors wish to express their deep gratitude to Mr. Y. Iino, who was an engineer of MHI, and Dr. S. Yamaguchi of KEK for their collaborative work and advice. We wish to thank engineers of Nagoya Aerospace Systems in MHI for manufacturing the accelerator and waveguide components. We also wish to thank engineers of KEK machine division for final-machining of the accelerator disks and cylinders. Figure 11 Accelerator guide installed at the #4-4 position Figure 12, 50 MW klystron assembly, and SB klystron installed in the klystron gallery 5

References [1] T. Kamitani et al., R&D Status of C-band Figure 13 Energy gain measured by changing the RF phase when the output power from the klystron was 42 MW Accelerator Unit for SuperKEKB, PAC2003, Portland, Oregon, USA, May 12-16, 2003 [2] I. Abe et al., The KEKB injector linac, Nuclear Instruments and Methods in Phys. Res. A, Vol. 499, Issue 1, 21, February, pp.167-190, 2003. [3] A. Fiebig et al., Design Consideration, Construction and Performance of a SLED-type Radiofrequency Pulse Compressor Using Very High Q Cylindrical Cavities, IEEE 1987 Particle Acc. Conf., March 16-19,Washington DC, pp.1931-1933, 1987. [4] S. Y. Kazakov, A New Travelling-wave mixed-mode RF Window with a Low Electric Field in Ceramicmetal Brazing Area, KEK Preprint 98-120, 1998. [5] S. Fukuda et al., R&D Status of the Linac Upgrade Plan Using a C-band System for SuperKEKB, Proc. of the14th Symposium on Accelerator Science and Technology, KEK, Tsukuba, Japan, November 11-13, pp.105-108, 2003. 6