The LEP Superconducting RF System

Similar documents
LEP OPERATION AND PERFORMANCE WITH ELECTRON-POSITRON COLLISIONS AT 209 GEV

Proceedings of the 1997 Workshop on RF Superconductivity, Abano Terme (Padova), Italy

ILC-LNF TECHNICAL NOTE

!"!3

LEP Status and Performance in 2000

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

PoS(EPS-HEP2015)525. The RF system for FCC-ee. A. Butterworth CERN 1211 Geneva 23, Switzerland

A HIGH-POWER SUPERCONDUCTING H - LINAC (SPL) AT CERN

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

RF Upgrades & Experience At JLab. Rick Nelson

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

Detailed Design Report

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting

ANKA RF System - Upgrade Strategies

Upgrade of CEBAF to 12 GeV

5 Project Costs and Schedule

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY

Present Status and Future Upgrade of KEKB Injector Linac

KEKB INJECTOR LINAC AND UPGRADE FOR SUPERKEKB

What can be learned from HERA Experience for ILC Availability

SUMMARY OF THE ILC R&D AND DESIGN

J/NLC Progress on R1 and R2 Issues. Chris Adolphsen

ABORT DIAGNOSTICS AND ANALYSIS DURING KEKB OPERATION

RF plans for ESS. Morten Jensen. ESLS-RF 2013 Berlin

RF Power Generation II

RF Power Upgrade at Jefferson Lab

Karin Rathsman. Calculations on the RF Source and Distribution

A New 4MW LHCD System for EAST

Upgrading LHC Luminosity

1. General principles for injection of beam into the LHC

Operating Experience and Reliability Improvements on the 5 kw CW Klystron at Jefferson Lab

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

Synchrotron Light Facility. Operation of ALBA RF. Angela Salom on behalf of RF team: Francis Perez, Bea Bravo and Jesus Ocampo

The Elettra Storage Ring and Top-Up Operation

XFEL High Power RF System Recent Developments

Status and Plans for PEP-II

Program Risks Risk Analysis Fallback Plans for the. John T. Seeman DOE PEP-II Operations Review April 26, 2006

Spear3 RF System Sam Park 11/06/2003. Spear3 RF System. High Power Components Operation and Control. RF Requirement.

The ESS Accelerator. For Norwegian Industry and Research. Oslo, 24 Sept Håkan Danared Deputy Head Accelerator Division Group Leader Beam Physics

Suggested ILC Beam Parameter Range Rev. 2/28/05 Tor Raubenheimer

High Brightness Injector Development and ERL Planning at Cornell. Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics

The PEFP 20-MeV Proton Linear Accelerator

A HIGH POWER LONG PULSE HIGH EFFICIENCY MULTI BEAM KLYSTRON

Karin Rathsman, Håkan Danared and Rihua Zeng. Report from RF Power Source Workshop

RF considerations for SwissFEL

High Rep Rate Guns: FZD Superconducting RF Photogun

IOT RF Power Sources for Pulsed and CW Linacs

The SPL at CERN. slhc. 1. Introduction 2. Description. 3. Status of the SPL study. - Stage 1: Linac4 - Stage 2: LP-SPL - Potential further stages

RF PERFORMANCE AND OPERATIONAL ISSUES

RUNNING EXPERIENCE OF FZD SRF PHOTOINJECTOR

2008 JINST 3 S LHC Machine THE CERN LARGE HADRON COLLIDER: ACCELERATOR AND EXPERIMENTS. Lyndon Evans 1 and Philip Bryant (editors) 2

OF THIS DOCUMENT IS W8.MTO ^ SF6

Performance of a DC GaAs photocathode gun for the Jefferson lab FEL

WG2 Group Summary. Chris Adolphsen Terry Garvey Hitoshi Hayano

Linac upgrade plan using a C-band system for SuperKEKB

Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi)

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

Concept and R&D Plans for Project X

PEP-I1 RF Feedback System Simulation

The TESLA RF System. S. Choroba. for the TESLA Collaboration. DESY Notkestr. 85, D Hamburg, Germany

18 GHz, 2.2 kw KLYSTRON GENERATOR GKP 24KP 18GHz WR62 3x400V

Basic rules for the design of RF Controls in High Intensity Proton Linacs. Particularities of proton linacs wrt electron linacs

Low Level RF for PIP-II. Jonathan Edelen LLRF 2017 Workshop (Barcelona) 16 Oct 2017

ESS: The Machine. Bucharest, 24 April Håkan Danared Deputy Head Accelerator Division. H. Danared Industry & Partner Days Bucharest Page 1

North Damping Ring RF

Introduction: CW SRF linac types, requirements and challenges High power RF system architecture

Status of JRA-SRF in CARE

PEP II Design Outline

Availability and Reliability Issues for the ILC

THE NEXT LINEAR COLLIDER TEST ACCELERATOR: STATUS AND RESULTS * Abstract

Nick Walker DESY MAC

INFN School on Electron Accelerators. RF Power Sources and Distribution

Welcome and FRIB Project Status. FRIB Highlights and Plan Ahead

HIGH-INTENSITY PROTON BEAMS AT CERN AND THE SPL STUDY

The FLASH objective: SASE between 60 and 13 nm

Dark current and multipacting trajectories simulations for the RF Photo Gun at PITZ

STATUS AND COMMISSIONING RESULTS OF THE R&D ERL AT BNL*

Future Circular Collider Study

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

ESS Linac WP8 Radio Frequency Systems and Test Facilities

SPINNER BROADCAST EXPLANATION OF THE MULTI CHANNEL COMBINER SPECIFICATIONS

TOSHIBA Industrial Magnetron E3328

Pulses inside the pulse mode of operation at RF Gun

14 GHz, 2.2 kw KLYSTRON GENERATOR GKP 22KP 14GHz WR62 3x400V

NSLS-II RF Systems James Rose, Radio Frequency Group Leader PAC 2011

RF upgrade program in LHC injectors and LHC machine

SLS RF operation report 2003

Status of CTF3. G.Geschonke CERN, AB

ARES Status 2004(JFY)

Towards an X-Band Power Source at CERN and a European Structure Test Facility

Empirical Model For ESS Klystron Cathode Voltage

ALPI and PIAVE Status and perspectives. Anna Maria Porcellato Lab. Naz. INFN Legnaro (PD) Italy

CLIC Feasibility Demonstration at CTF3

The European Spallation Source

PHIN. Report on the Development of a Radio-Frequency Photo Electron Source with Superconducting Niobium Cavity (SRF Gun Realization)

Investigation of Radio Frequency Breakdown in Fusion Experiments

LLRF at SSRF. Yubin Zhao

The Construction Status of CSNS Linac

SRS and ERLP developments. Andrew moss

Transcription:

The LEP Superconducting RF System K. Hübner* for the LEP RF Group CERN The basic components and the layout of the LEP rf system for the year 2000 are presented. The superconducting system consisted of 288 four-cell cavities operating at 32 MHz powered by 36 klystrons providing on average of 0.6 MW of rf power. This system was complemented by 6 cavities of the original copper rf system. A total accelerating voltage of 3630 MV could be provided routinely allowing operation up to 104 GeV. The installation schedule of the superconducting cavities is shown and comments are made about the evolution of the system over the years. The performance and the reliability of the final system are described. 1. Description of the system The superconducting rf system [1,2,3,4] of LEP consisted of 288 four-cell standing wave cavities which operated at 32 MHz and had an active length of 1.7m (2 lambda rf). The first 16 cavities were constructed of solid Nb and had a nominal accelerating gradient of MV/m. All the other cavities were made of Cu with a thin film of Nb sputtered on the cavity walls, a technology developed at CERN [,6]. The nominal gradient for the latter cavities was 6 MV/m. The Cu substrate gives a high mechanical stability and makes the cavities virtually quench-free due to its high thermal conductivity. The cavities were mounted in groups of four in one cryostat, called a module. They were immersed in a liquid He bath at 4.K. The He was provided by four large cooling plants with a total of 3 kw installed power [7]. Fig. 1 shows a cavity in the cryomodule. FIG. 1: Superconducting cavity in module. Eight cavities were fed by one klystron which was rated for 1.1 or 1.3 MW cw operation. Two klystrons shared one common dc power supply. Circulators protected the klystrons against excessive reflected power. Initially, LEP started with only a copper rf system [8] which consisted of 128 five-cell standing wave cavities. Two klystrons powered 16 cavities. In order to make space for the sc rf cavities, a number of Cu cavities has been removed so that finally only 6 cavities remained powered by eight klystrons. They provided a total maximum voltage of 140 MV and typically 130 MV. The rf system was installed in the four even-numbered long straight-sections of LEP, symmetrically arranged around the mid-point where the large LEP detectors were located. Table I gives the layout of the cavities in LEP in the year 2000. The 16 solid Nb cavities were located on one side of straight section 2. *Kurt.Hubner@cern.ch

2 Table I. Layout of the LEP acceleration system. Straight section sc cavities Cu cavities 2 64 28 4 80 6 64 28 8 80 2. Installation schedule Fig. 2 shows the installation schedule of the modules. Production of the Nb cavities started in 1991 while the Nb-film cavities were produced from 1992 onwards. Systematic module installation started at the end of 1994 somewhat delayed due to problems with the rf power coupler which were solved in 1994. Installation continued during 199 and 1996 leading to frequent stops in operation. From the winter shutdown 96/97 onwards the installation only took place during the regular long winter shut downs of the CERN accelerators. The production of the sc cavities ended in the first half of 1998 and the last modules were installed in the winter shutdown 98/99. The last modification of the rf system configuration occurred in the winter shutdown 99/00 with the re-installation of eight additional Cu cavities in order to mobilise all possible reserves to increase the beam energy. 7 72 70 6 LEP 2 Installation of SC Modules 60 0 4 40 3 30 2 20 1 10 1994 199 1996 1997 FIG. 2: Installation history of rf modules each containing four sc cavities. 1998 1999 3. SC cavity performance The solid Nb cavities were conditioned up to their nominal gradient of MV/m and operated up to 4. MV/m. The Nb-film superconducting rf system reached an average gradient of 6.1 MV/m already in 1996 but was pushed to an average of 7. MV/m (6 MV/m nominal) by 2000 mainly by careful, but in the end aggressive, rf conditioning. Field emission was the hard limitation as it led to local heating of the cavity walls and, consequently, to an increase in the pressure of the He bath which triggered a safety interlock. The resulting distribution is shown in Fig. 3.

3 30 Number of cavities 2 20 1 10 96 GeV 100 GeV 104 GeV 0 4 4.2 4.4 4.6 4.8.2.4.6.8 6 6.2 6.4 6.6 6.8 7 7.2 7.4 7.6 7.8 Accelerating field [MV/m] 8 8.2 8.4 8.6 8.8 FIG. 3: Number of cavities operating at a given gradient for three different beam energies in 1999 and 2000 [3]. In situ He processing of installed modules had been applied but produced mixed results. It was used in isolated cases but was eventually abandoned due to the inherent risk of damage by the klystron delivering excessive power to the cavity via strongly overcoupled power couplers. A number of ancillary systems were improved and limitations were systematically removed whenever possible. All this required a sizeable and sustained effort often after installation. The following main improvements were made: The voltage control per klystron maintaining the sum of the eight cavity voltages independent of the beam loading was changed to be based on the vector sum instead of the scalar sum for some of the units; The accelerating voltage of the cavities powered by the same klystron was equalized by inserting lambda/4 plates into the waveguide at the appropriate distance before the couplers; this compensated for the spread in the external Q between the cavities; The directivity of the directional couplers upstream of the main coupler was adjusted to better than 30 db in order to avoid perturbation of the frequency tuning of the individual cavities; The electrical length of the waveguides feeding a group of eight cavities per klystron was adjusted to a precision of about 3 degrees; Electro-acoustic (ponderomotive) oscillations [9] were limited by an active damping system on all cavities making use of the existing tuning system [2]; The cables connecting the HOM couplers to the loads outside the cryostat were replaced by rigid coaxial lines in all Nb-film cavities and by new cables in the Nb cavities in order raise the limit on the beam current imposed by the insufficient power rating of the original cables; All the cables connecting the two antennas in each cavity with the outside control circuits had to be changed because many of them were found to be damaged by HOM in installed cavities; these changes had to be done in situ for 248 Nb-film cavities which was a monumental task; Continuous upgrading of the control system including a GPS timing based diagnostic system for analysis of trips. The result of this painstaking effort, which extended over many years, is given in Fig. 4 showing the evolution of the installed rf voltage over the years [10]. The installed voltage was constant between 1989 and 199 when LEP operated at the Z 0 resonance. It can be seen that the available voltage exceeded the nominal voltage after the upgrading of the cryogenics in the shutdown 98/99 because then the accelerating gradient of the Nb-film rf system could be pushed above its nominal value. The concurrent increases in beam energy are also shown in Fig. 4. 9 9.2 9.4

4 4000 300 Available RF voltage Beam energy 12 [GeV] RF voltage [MV] 3000 200 2000 100 1000 00 Nominal RF voltage Cryogenics upgrade Beam energy 11 10 9 8 7 0 Jul-9 Feb-96 Aug-96 Mar-97 Sep-97 Apr-98 Nov-98 Date May- 99 6 Dec-99 Jun-00 Jan-01 FIG. 4: The evolution of beam energy, available and nominal rf voltage [10]. 4. Reliability During operation only a few cavities degraded in performance. Six cavities were recovered by rinsing with ultra-pure water and one cavity was recoated with a new Nb-film. The mean time between trips (i.e. one klystron off) (MTBT) was rather independent of the accelerating gradient and the beam current as long as the nominal values (6 MV/m and 6 ma) were not exceeded. Under these conditions the MTBT reached about 2 h. Since the rf system was operated with a voltage margin corresponding to 2 klystrons, trips did rarely result in beam loss. By keeping 2 klystrons in reserve, beam loss by a trip of the common power supply was also avoided. Most of the beams were dumped at the end of the run by the operator. The situation changed drastically in 2000 when the cavities had to operate with 7. MV/m on average. The MTBT dropped to 14 min. This operation beyond the safe limits led to equipment damage: arcing in the waveguides led to destruction of several components and damaged three circulators. By the end of the year, 4 cavities were damaged and 3 partially damaged. Hence, they had to be completely, respectively partially detuned.. Conclusions The excellent performance of this very large superconducting rf system was decisive for the success of LEP at high energy. The capability of the rf system to operate above nominal values lead to an extension of the LEP run into 2000 in order to push the Higgs boson discovery limit to a maximum. Eventually, the beam reached a maximum 104. GeV with useful integrated luminosity up to 104 GeV. A wealth of physics results [11] was obtained providing a solid basis for the investigations at the Tevatron and LHC which will take over from LEP. Their results will end the speculation whether full exploitation of LEP by equipping it with the maximum number of cavities which could be supported by the existing infrastructure, would have lead to the discovery the Higgs particle. The rf system together with the rest of LEP has been dismantled in 2001 in order to make space for LHC. Acknowledgements The successful operation and the excellent performance of the large LEP rf system which was pushed far beyond the nominal performance would not have been possible without the competence, dedication and perseverance of all the members of the RF Group supported by a number of services in the Accelerator and Technical Sector of CERN. I would like to thank P. Brown

and G. Geschonke for reading the manuscript and for many useful comments. Thanks are also due to H. Gaillard who provided Fig. 2. References [1] D. Boussard, Proc. PAC, Vancouver (1997) p.2879. [2] P. Brown et al., Proc. 9 th Workshop on RF Superconductivity, Santa Fe (1999). Report LA- 13782-C, p.1. [3] P. Brown et al., to be published Proc. PAC, Chicago (2001), see report CERN-SL-2001-018 HRF. [4] P. Brown et al., The LEP Superconducting RF System, to be submitted to NIM. [] C. Benvenuti, S. Calatroni, and G. Orlandi, Physica B 197 (1994) p.72. [6] D. Boussard et al., Proc. PAC, New York City (1999) p.946. [7] Gayet et al., Proc. 8 th LEP Performance workshop, Chamonix (1998). Report CERN-SL-98-006- DI. [8] G. Geschonke and S. Hansen, Part. Accel.28 (1990) p.779. [9] D. Boussard, P. Brown and J. Tückmantel, Proc. EPAC, Sitges (1996) p.187. [10] R.A. Assmann, Proc. of the LHC Workshop, Chamonix (2001). Report CERN-SL-2001-003 DI, p.323. [11] W. Venus, LEP Summary, to be published proceedings of EPS HEP Conference, Budapest 2001