Status of the SNS Linac: An Overview N. Holtkamp for the SNS Collaboration ORNL, Oak Ridge, TN 37830, USA

Similar documents
Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

The Spallation Neutron Source Project Geneva December 8, 2006

Linac 4 Instrumentation K.Hanke CERN

SNS Target Imaging and Related Developments

The ESS Accelerator. For Norwegian Industry and Research. Oslo, 24 Sept Håkan Danared Deputy Head Accelerator Division Group Leader Beam Physics

A Fifteen Year Perspective on the Design and Performance of the SNS Accelerator

Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi)

Workshop on Accelerator Operations August 6-10, 2012 Glen D. Johns Accelerator Operations Manager

Beam Loss Detection for MPS at FRIB

The PEFP 20-MeV Proton Linear Accelerator

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

Upgrading LHC Luminosity

The Construction Status of CSNS Linac

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

Proton Engineering Frontier Project

Detailed Design Report

DESIGN OF 1.2-GEV SCL AS NEW INJECTOR FOR THE BNL AGS*

RF plans for ESS. Morten Jensen. ESLS-RF 2013 Berlin

L-Band RF R&D. SLAC DOE Review June 15 th, Chris Adolphsen SLAC

ESS: The Machine. Bucharest, 24 April Håkan Danared Deputy Head Accelerator Division. H. Danared Industry & Partner Days Bucharest Page 1

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

Upgrade of CEBAF to 12 GeV

OPERATIONAL EXPERIENCE AT J-PARC

Preparations for Installation, Testing and Commissioning based on Experience at CERN, SNS and Siemens

COMMISSIONING SCENARIOS FOR THE J-PARC ACCELERATOR COMPLEX

PRESENT STATUS OF J-PARC

High Brightness Injector Development and ERL Planning at Cornell. Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics

RF considerations for SwissFEL

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

RF Upgrades & Experience At JLab. Rick Nelson

A HIGH-POWER SUPERCONDUCTING H - LINAC (SPL) AT CERN

4.4 Injector Linear Accelerator

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

5 Project Costs and Schedule

HIGH-INTENSITY PROTON BEAMS AT CERN AND THE SPL STUDY

The Beam Test Facility at the SNS

Welcome and FRIB Project Status. FRIB Highlights and Plan Ahead

Summary of the 1 st Beam Line Review Meeting Injector ( )

HIGH POWER BEAM DUMP AND TARGET / ACCELERATOR INTERFACE PROCEDURES *

INFN School on Electron Accelerators. RF Power Sources and Distribution

The LEP Superconducting RF System

Current status of XFEL/SPring-8 project and SCSS test accelerator

SUMMARY OF THE ILC R&D AND DESIGN

P. Emma, et al. LCLS Operations Lectures

PEP II Design Outline

LSD Review December 2012 Schedule, Re-Baseline, & Resource Analysis

Jefferson Lab Experience with Beam Halo, Beam Loss, etc.

The SPL at CERN. slhc. 1. Introduction 2. Description. 3. Status of the SPL study. - Stage 1: Linac4 - Stage 2: LP-SPL - Potential further stages

EPJ Web of Conferences 95,

Status of SOLARIS Arkadiusz Kisiel

CEBAF Accelerator Update. Michael Tiefenback CASA Accelerator Physics Experimental Liaison June 14, 2017

Present Status and Future Upgrade of KEKB Injector Linac

Status of RF Power and Acceleration of the MAX IV - LINAC

30 GHz Power Production / Beam Line

A New High Intensity Proton Source. The SCRF Proton Driver. (and more!) at Fermilab. July 15, Bill Foster SRF2005

LHC Beam Instrumentation Further Discussion

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY

SPEAR 3: Operations Update and Impact of Top-Off Injection

XFEL High Power RF System Recent Developments

RUNNING EXPERIENCE OF FZD SRF PHOTOINJECTOR

DELIVERY RECORD. Location: Ibaraki, Japan

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting

Activities on FEL Development and Application at Kyoto University

Pulsed Klystrons for Next Generation Neutron Sources Edward L. Eisen - CPI, Inc. Palo Alto, CA, USA

Status of the FAIR Project. Jürgen Henschel FAIR Project Leader / Technical Director GSI & FAIR

SNS TR0001-R00. Conceptual Design Report for the Spallation Neutron Source Power Upgrade MIE Project

!"!3

Commissioning the TAMUTRAP RFQ cooler/buncher. E. Bennett, R. Burch, B. Fenker, M. Mehlman, D. Melconian, and P.D. Shidling

High Rep Rate Guns: FZD Superconducting RF Photogun

ESS Linac WP8 Radio Frequency Systems and Test Facilities

Next Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack

Digital BPMs and Orbit Feedback Systems

Photoinjector Laser Operation and Cathode Performance

A HIGH POWER LONG PULSE HIGH EFFICIENCY MULTI BEAM KLYSTRON

The Elettra Storage Ring and Top-Up Operation

THE OPERATION EXPERIENCE AT KOMAC*

Basic rules for the design of RF Controls in High Intensity Proton Linacs. Particularities of proton linacs wrt electron linacs

Design of the linear accelerator for the MYRRHA project

The European Spallation Source

PoS(EPS-HEP2015)525. The RF system for FCC-ee. A. Butterworth CERN 1211 Geneva 23, Switzerland

NSLS-II RF Systems James Rose, Radio Frequency Group Leader PAC 2011

Status of CTF3. G.Geschonke CERN, AB

Operating Experience and Reliability Improvements on the 5 kw CW Klystron at Jefferson Lab

Beam Losses During LCLS Injector Phase-1 1 Operation

Design Studies For The LCLS 120 Hz RF Gun Injector

Performance of a DC GaAs photocathode gun for the Jefferson lab FEL

WG2 Group Summary. Chris Adolphsen Terry Garvey Hitoshi Hayano

Photo cathode RF gun -

Introduction: CW SRF linac types, requirements and challenges High power RF system architecture

Particle Beam Production - A Synchrotron-Based System - Prof. Dr. Thomas Haberer Scientific-technical Director Heidelberg Iontherapy Center

RF Power Klystrons & 20 Year Look. R. Nelson 7/15/15

Towards an X-Band Power Source at CERN and a European Structure Test Facility

CERN S PROTON SYNCHROTRON COMPLEX OPERATION TEAMS AND DIAGNOSTICS APPLICATIONS

KEKB INJECTOR LINAC AND UPGRADE FOR SUPERKEKB

ESS Linac WP8 Radio Frequency Systems and Test Facilities

Evaluation of Performance, Reliability, and Risk for High Peak Power RF Sources from S-band through X-band for Advanced Accelerator Applications

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

DEVELOPMENT OF A 10 MW SHEET BEAM KLYSTRON FOR THE ILC*

Low Level RF for PIP-II. Jonathan Edelen LLRF 2017 Workshop (Barcelona) 16 Oct 2017

News from HZB / BESSY Wolfgang Anders at ESLS-RF Meeting September 2010 Trieste

Transcription:

Lübeck, August 20, 2004 Status of the SNS Linac: An Overview N. Holtkamp for the SNS Collaboration ORNL, Oak Ridge, TN 37830, USA

SNS is the Forefront Facility for Future High Beam Power Accelerators Highest Beam Power worldwide under construction Stepping stone to next generation Spallation Sources The SNS will begin operation in 2006 At 1.4 MW it will be ~8x ISIS, the world s leading pulsed spallation source The peak thermal neutron flux will be ~50-100x ILL 5000 hours per year at an availability of >90%!!!!!!!!!!! (~ in 2009)

The Spallation Neutron Source Partnership Description Accelerator Project Support 75.6 Front End Systems 20.8 20.8 Linac Systems 315.9 315.9 Ring & Transfer System 142.0 142.0 Target Systems 108.2 Instrument Systems 63.3 Conventional Facilities 378.9 Integrated Control Syst 59.7 59.7 BAC 1,164.4 Contingency 28.3 TEC 1,192.7 R&D 100.0 80.0 Pre-Operations 119.0 95.2 TPC 1,411.7 713.6 At peak : ~500 People worked on the construction of the SNS accelerator SNS-ORNL Accelerator systems: ~167 M$ ~177 M$ ~60 M$ ~20 M$ ~63 M$ ~106 M$ ~113 M$ Oak Ridge, TN 35 49' N, 83 59' W

SNS Multilab Organizational Chart The Multi Lab Organization of SNS has brought an enormous amount of expertise to the table. It has made it easier to transition the required workforce in and out of the project. SNS is just one of several models that I m sure will be used to built large science projects in the future. The Multi Lab Org Chart for SNS is in many ways is not different than a typical one, but it does add a few layers of management.

Project Status Total cost is $1.4 B (US accounting), peaked in 2002 with $290 M. Project has costed or/and awarded almost $1.2B out of $1.4B Overall project design is 94% complete Overall the project is >84% complete (as of July) Within budget and schedule constraints ($1.4B and June 2006 completion) ES&H performance outstanding >5 million hours with one lost workday injury (combined hours worked for construction site and SNS/ORNL)

16 Instruments Now Formally Approved Fundamental Physics to Engineering Chemistry to Genomes to Life

Construction Nearing the End Target Front Building End Ring Building Tunnel Feb 2002 to Mai Linac 2002 Feb 2002

Major SNS Facility Parameters 402.5 MHz 805 MHz Proton beam energy on target 1.0 GeV HEBT Proton beam RFQ current DTL on target 1.4 CCL ma SRF, β=0.61 SC linac SRF, output β=0.81 energy To1.0 GeV Ring HEBT length 170 m Power on target 1.4 MW Pulse Injector repetition 2.5 rate MeV 86.8 MeV 186 60 MeV Accumulator Hz 387 MeV ring 1000 circ. MeV 248 m Ring fill time 1.0 ms Beam macropulse duty factor 6.0 % Ave. 1 RFQ Ring beam extraction gap 250 ns current in macro-pulse 11 26 Medium-β ma Cryomodules - 3 Nb cavities each 6 DTL Tanks RTBT length 150 m H - peak current front end > 12 38 High-β ma Cryomodules - 4 Nb cavities each 4 CCL Modules Protons per pulse on tgt 1.5x10 14 Chopper beam-on duty factor 68 % Proton pulse width on tgt 695 ns RFQ output energy 2.5 MeV Target material Liquid Hg FE + Linac length 335 m Weight of 1m 3 Hg 18 tons DTL output energy 87 MeV Energy per Pulse >17 kj CCL output energy 185 MeV Maximum # Instruments 24 AP Issue: Minimize losses along the accelerator chain!!!! 1 Watt per meter ( or 1 na) apart from collimators 1.0 GeV Ring Up to 1.3 GeV Lq Mercury Target

The SNS Ion Source Since Jan. 04 an SNS ion source is almost continuously in operation, 24/7, mostly unattended during nights and weekends. Since end of April 04 three runs have achieved a 6% and 5 runs a 7.4% duty cycle. All 8 runs were terminated after 1-2 weeks. No antenna failures have been detected. An operational run is typically terminated when the source output drops below 20-25 ma. Front-End Temporary control room Hot Spare Stand Front-End Building

The SNS Ion Source Typically the initial peak current exceeds the average current by ~30%. Average Beam Current (ma) 50 45 40 35 30 25 20 15 10 5 1st Cesiation archiver down 36 kw LDF begin 2% oper 50 kw Source #3 begin 4% oper 2nd Cesiation 4th Cesiation 3rd Cesiation 60 kw 5th Cesiation 0 31-May 2-Jun 4-Jun 6-Jun 8-Jun 10-Jun 12-Jun 14-Jun Date

LBNL: Design And Built Front End 2.5 MeV RFQ Ion Source

Drift Tube Linac Components DTL 1 in the tunnel Here it goes See S. Aleksandrov s Talk: WE 201 DTL 3

All DTLs 402.5 MHz DTL designed at LANL Components built to spec in industry (plating at GSI) Assembled largely at ORNL All DTLs installed with 210 drift tubes in place. Operates at 1.3 x Kilpatrick max. Drift tubes have integrated permanent magnet quads 24 steering dipoles 10 beam position +phase monitors 12 beam loss monitors 6 beam current monitors 6 5 wire scanners 5 Faraday cups 12 neutron detectors

Tank 3 Conditioned to Full Field and 40% Duty Factor in 30 hr! Increase P peak Increase P ave rf Power (kw) P forward P reflected

DTL 1-3 Commissioning: 40 MeV Can only run very short pulse and little beam power from now on. Beam Commissioned DTL1-3 in April 2004: Had beam through DTL3 36 hours after approval for operation: Achieved design 38 ma peak current 100% transmission

Coupled-Cavity Linac (CCL) Construction by LANL done in Industry Contract awarded to Industry Hot model operated at 130% of peak field and 190% average power Bridge Coupler 44 final machining Segment 1-6 fiducial machining Cooling tests Production Segments

Coupled-Cavity Linac Deliveries Support September 2004 Commissioning Start 55 m long linac divided into 4 modules Designed at LANL, build and tuned in industry. Operates at 1.3 x Kilpatrick max. 48 quadrupoles and 32 steering magnets between segments. 10 beam position and phase monitors 28 beam loss monitors 1 current monitors 7 wire scanners 1 Faraday cups 3 bunch shape monitors 8 neutron detectors In Germany and here.

CCL1 Module 1 Successfully RF Conditioned 100% Achieved: 2.5 MW (~120% of nominal power) @ 20Hz, 1ms after 5 x 12 hour shifts

HVCM Simplified Block Diagram RECTIFIER TRANSFORMER AND FILTERS SCR REGULATOR ENERGY STORAGE/SWITCHING BOOST TRANSFORMER HV RECTIFIER AND FILTER NETWORK 4mH 400A X3 -HV -HV -HV 10ohm 20mH.03uF CØ BØ 3Ø (ON/OFF) 6 EACH AØ BØ CØ.03uF.05uF VMON RTN 13.8KV 3Ø 50mH 6 EACH HV OUTPUT INPUT LINE CHOKE 5 th HARMONIC TRAP 7 th HARMONIC TRAP AØ 4mH 400A C SHUNT-PEAK RECTIFIER TRANSFORMER AND FILTERS SCR REGULATOR HIGH VOLTAGE CONVERTER/MODULATOR EQUIPMENT CONTROL RACK

HVCM Descritpion 11 HVCM out of 14 for the linac are installed. All 11 have been operated/tested. Combination of built to spec/built to print contract in industry. They have operated a total of ~8000 h at a variety of η with approximately 1500 at full load (η=7.5%). Depending on the klystron the operate between 75 and 115kV driving up to 12 klystrons in parallel. Have a very compact IGBT driven high Frequency (20kHz) converter with a compact polyphase transformer. The power density in the modulator compared to ~20 y ago went up by ~ x50.. Which has its challenges!

High-Power RF Installation Progress All RFQ / DTL HPRF Systems complete and operational. 2.5 MW - 402.5MHz klystron with 2-3 per HVCM All four CCL systems are complete. 5 MW 805MHZ klystron with 1 per HVCM. 60 of 81 SCL klystrons installed. 550kW- 805MHz klystrons with typically 12 per HVCM. 2 SCL modulators tested All klystrons are made in industry in Europe and the US. 4 CCL 5 MW Klystron 60 klystrons out of 81 for sc linac in place 7 tubes turned over to operations

RF System / Modulator Configuration Screen Status of each Klystron, HVCM and transmitters displayed along with a description of its readiness.

DTL-CCL Commissioning And Cryomodule Testing In The Tunnel Sept. 04 The DTL CCL enclosure will include the whole linac as one PPS area Decided to install shielding wall between CCL and SCL to minimize interference with conditioning, commissioning and SCL installation and testing. SCL cryomodule testing in the tunnel will begin mid-august. FES DTL CCL Beamstop SCL Klystron Gallery

JLAB: The Superconducting Linac Superconducting RF Advantages: 1. Flexibility gradient and energy are not fixed 2. More power efficient lower operational cost 3. High cavity fields less real estate 4. Better vacuum less gas stripping 5. Large aperture less aperture restrictions reduced beam loss reduced activation 0.05 Medium β 0.04 ε rms (π cm-mrad) 0.03 0.02 0.01 DTL+CCL ~ No ε growth ε x ε y ε z 0.00 0 100 200 300 400 500 600 700 800 900 1000 W (MeV)

The Superconducting Linac All 81 + 25 cavities are built, chemically pre treated and initially tuned in industry Linac has a total of 23 CM s; 11 medium β (MB) and 12 high β (HB). 9 more slots available. Cavities over-perform by ~25 % compared to spec for MB and HB. So far tested at JLab only. Linac is 157 m long and has 32 warm sections between CM s and 67 quadrupoles with h+v steerer windings and a special laser diagnostics for emittance measurements Medium Beta 7 CM in tunnel tested 3 CM in tunnel untested 1 CM complete at JLab High Beta 0 CM in tunnel tested 1 CM in tunnel untested 3 CM complete at JLab 5 CM in progress 2 Cavities delivered

SNS Medium Beta Cryomodule 3 cavity / CM layout for Med β CM 4 cavity / CM layout for Med β CM 11 CM s in the SNS Tunnel

High β Cryomodule 5 + 6 at JLab Test of first 2 CM in the tunnel has started as of last week. Testing of crymodules at JLab includes the first 12. All results shown are from there. Test of the remaining eleven is done at SNS in the tunnel Assembly of CM 5+6 at JLab

Med. β CM Performance E acc @ Q o = 5*10 9 20 18 16 14 12 Eacc 10 8 6 4 2 MB1, 2, 3, 4, 6 MB5 Partial Conditioning MB8 Improved Procedures MB8, 11 Final Procedures Avg Spec Min Spec Max Spec 0 1-Nov- 02 1-Dec- 02 1-Jan- 03 31- Jan-03 3-Mar- 03 2-Apr- 03 3-May- 03 2-Jun- 03 3-Jul- 03 2-Aug- 03 2-Sep- 03 2-Oct- 03 2-Nov- 03 2-Dec- 03 2-Jan- 04

High β CM Performance E acc @ Q 0 =5*10 9 Eacc 26 24 22 20 18 16 14 12 10 8 6 4 2 A. Spec. Min. S. Max. S. CM 0 1-Apr- 03 1-May- 03 1-Jun- 03 1-Jul- 03 1-Aug- 03 31-Aug- 03 1-Oct- 03 31-Oct- 03 1-Dec- 03 31-Dec- 03 31-Jan- 04 1-Mar- 04 1-Apr- 04 1-May- 04 1-Jun- 04 1-Jul- 04 1-Aug- 04

Medium β CM Versus Vertical Test 20 15 MB1, 2, 3, 4, 6 MB5 Partial Conditioning MB8 Improved Procedures MB8, 11 Final Procedures CM MV/m 10 23% 5 0 0 2 4 6 8 10 12 14 16 18 20 VTA MV/m

High β CM Versus Vertical Test 25 HB1 Cavity #1,3,5 20 HB1 Cavity #7 CM MV/m 15 10 23% 5 0 0 5 10 15 20 25 VTA MV/m

Lorentz Force Detuning Dynamic Lorentz Force Detuning - SNS Cryomodules Lorentz Detuning (Hz 500 450 400 350 300 250 200 150 100 50 0 Specification Cavity #1 Cavity #2 Cavity #3 w/ active PZT compensation M01 M02 M03 M05 H01 If we could keep all cavities @ 100Hz, the presently installed rf system can support ~ twice the beam power. Cryomodule 1 HB had a resonance and was x4 out of spec. Not clear why yet.

Cryomodule Assembly 81 69 57 45 33 21 9 23 20 17 14 11 8 5 Cavity # 17-Oct-03 17-Nov-03 17-Dec-03 17-Jan-04 17-Feb-04 17-Mar-04 17-Apr-04 17-May-04 17-Jun-04 17-Jul-04 17-Aug-04 17-Sep-04 17-Oct-04 17-Nov-04 17-Dec-04 17-Jan-05 17-Feb-05 17-Mar-05 CM# NOW Cavity Plan Cavity Actual Strings Plan Strings Actual MB CM # CM Plan CM Actuals 3.2 wk / CM 4.0 wk / CM

The Low-level RF Control System Production systems 97% complete. Collaboration between LBNL, LANL and ORNL. Production is under way with 20 units delivered. LANL supporting ORNL with ECAD, EPICS vendor QA, acceptance testing, installation (consulting & change-of-station assignments) LBNL continues to do FPGA code development. Installation and Integration in the Tunnel is underway.

FCM Test On A Cryomodule 11.3 MV/m, 30 Hz, 1.2 ms, 2.1 K specification of ±1%, ±1deg ±0.1%, ±0.2deg achieved

SNS CHL Facility Cold box specifications are: 8300 Watts on the shield 2400 Watts @ 2.1Kelvin 15g/s Liquefaction

SNS/SRF Cryogenic Distribution System Transfer line is installed for 9 additional cryomodules to be ready for the linac energy upgrade Transfer line; tested and leak checked. Same for expansion cans and piping. Built in house at OR

SNS Warm Compressor Procured by JLab in industry To be Updated! Warm compressors are operating after initial issue with heat exchangers. Three streets with one being redundant.

SNS 4.5 K Cold Box Procured by JLab in industry 4K Coldbox has operated in 3 different runs and is considered commissioned. July: Reached 100% of spec with lowered interstage pressure and somewhat lower efficiency. Presently transferline and 2 CM are at 4.5 K for test.

The 2.1K Cold Box Procured by JLab in industry. Had several issue due to shipment damage of turbines. Have still an issue with electrical feedthroughs that drive the turbines. Run foreseen in October after 4.5 K cooldown of transferline and cavities for first systems check

SNS Diagnostics Deployment Operational FY04 New to 2004 New to FY04 ½ Laser in 04 FY2004/5 DTL 10 Position 5 Wire 12 Loss 5 Faraday Cup 6 Current 6 Thermal and 12 PMT Neutron MEBT 6 Position 2 Current 5 Wires [2 Thermal Neutron] 9/04 [3 PMT Neutron] 9/04 1 Emittance [1 fast faraday cup] 9/04 1 faraday/beam stop D-box video D-box emittance 9/04 D-box beam stop D-box aperture Differential BCM [laser prototype] 9/04 CCL/SCL Transition 2 Position 1 Wire 1 Loss 1 Current IDump 1 Position 1 Wire 1 Current 6 BLM CCL 10 Position 9 Wire 8 Neutron 48 Loss 3 Bunch 1 Faraday Cup 1 Current SCL 32 Position 86 Loss 8 Laser Wire 7 PMT Neutron RING 44 Position 2 Ionization Profile 70 Loss 1 Current 5 Electron Det. 12 FBLM 2 Wire 1 Beam in Gap 2 Video 1 Tune HEBT 29 Position 11 Wire 46 BLM, 3 FBLM 4 Current LDump 6 Loss 6 Position 1 Wire EDump 1 Current 4 Loss 1 Wire RTBT 17 Position 36 Loss 4 Current 5 Wire 1 Harp 3 FBLM

Diagnostics Is Online During Commissioning Position, phase Current (toroids) emittance Current (MEBT beam stop) Current (DTL Faraday cup) Profile (wires) Loss (neutron) Current (D-plate beam stop) Halo Bunch shape

SCL Laser Transport-line Installation:

Laser Profile Monitor Progress Verification of electron collector for SCL laser profile monitor Reliable measurements to about 3 sigma Anti-reflection coating has been applied to the final windows. We expect an order of magnitude improvement in signal to noise ratio. Horizontal Profile Gaussian fit plotted out to 2.5x Sigma Sigma = 1.07 mm Signal from electron collector Top: laser intercepting beam core Bottom: laser intercepting beam tail

BNL: The Accumulator Ring and Transfer Lines Nr of injected turns 1060 Ring revolution frequency MHz 1.058 Ring filling fraction % 68 Ring transverse emittance 99% πmm mrad 240 Ring transverse acceptance πmm mrad 480 Space charge Tune shift Q x,y 0.15 Peak Current 52 A HEBT / RTBT Length m 170 / 150 Ring Circumference m 248 RTBT transverse acceptance πmm mrad 480 Beam size on target (HxV) mm x mm 200x70 Totals: 235 Low Power Bipolar Supplies (< 5 kw) 24 Medium Power Bipolar Supplies (5-50 kw) 101 Medium Power Supplies (5-50 kw) 42 High Power Supplies (>50 kw) 22 Kicker Power Supplies Baseline: 1.0 GeV, 2 MW Designed and built for 1.3 GeV Several commissioning beam dumps

BNL: Ring/HEBT Installation Progress Beam line installation Linac to Ring complete. Ring installation ~ 80% complete. Beam line installation Ring to Target has not started. The ring has an aperture of 460 π*mm*mrad (~ 15 cm diameter) to allow a 25 A average circulating current. From Chaos. Energy per pulse is ~ 25 kj.. To order!

RTBT/Target Interface 15 6 Target Flightube Q29 Harp Q30 Section through RTBT/Target Flight-tube Interface

Expected Dose Rates Q26 Q27 & Q28 Q29 & Q30 HARP Potential Active Maintenance Work Areas Prompt dose levels during operation (2 MW) 1500 rem/hr@ working area (Franz Gallmeier) Residual levels 2 hours 1 week after shutdown, factor of ~1000 less 1.5 rem/hr Updated dose rate calculations underway with existing design (Irina Popova) Recent calculated dose rates for dumps & back streaming from target (DH13) are very high

September 02 People Instrument floor layout Status as of July 2004 with construction activity limited to Target & can be seen and target Status as of September 03 Central Laboratory building and Nano Science Center installation began

Target Monolith Region Monolith Installation - Sept 2003 Core Vessel and Shielding

Target Installation

The SNS Target: 2-MW Design Cavitation-induced pitting is an issue. Options for mitigation: Materials, Geometry Mitigation 25 kj/pulse at 7x15cm beam size sets of transverse and longitudinal shock wave. Peanuts compared the Muon target! Needs to be exchanged every 3 month 1 mm Pits on inner surface in this geometry

Primary Concern: Uncontrolled Beam Loss Hands-on maintenance: no more than 100 mrem/hour residual activation (4 h cool down, 30 cm from surface) 1 Watt/m uncontrolled beam loss for linac & ring Less than 10-6 fractional beam loss per tunnel meter at 1 GeV; 10-4 loss for ring Uncontrolled loss during normal operation High rad areas Beam loss [W/m] 3 2.5 2 1.5 1 0.5 0 FE DTL CCL SCL HEBT RING RTBT 0 100 200 300 400 500 600 700 800 Length [m]

A 20-Year Plan- The Long Term Future for SNS Doubling the number of Kinetic energy, E users by k [MeV] adding a 2 nd Beam power on target, P target station max [MW] Baseline Upgrade Ultimate 1000 1300 1400 1.4 3.0 5.0 Chopper beam-on duty factor [%] 68 70 70 Linac beam macro pulse duty factor [%] 6.0 6.0 6.0 Average Requires macropulse Energy H- current [ma] Peak upgrade Current from in front the end linac system Linac (ring average is beam already current ok [ma] for SRF 1.3-1.4 cryo-module GeV) number (med-beta) 26 38 1.6 11 42 59 2.5 11 65 92 3.9 11 SRF cryo-module number (high-beta) 12 12 + 8 (+1 reserve) 12 + 8 (+1 reserve) Number of SRF cavities 33+48 33+80 (+4 reserve) 33+80 (+4 reserve) Peak gradient, E p (β=0.61 cavity) [MV/m] 27.5 (+/- 2.5) 27.5 (+/- 2.5) 27.5 (+/- 2.5) Peak gradient, E p (β=0.81 cavity) [MV/m] 35 (+2.5/-7.5) 31 34 Ring injection time [ms] / turns 1.0 / 1060 1.0 / 1100 1.0 / 1110 Ring rf frequency [MHz] 1.058 1.098 1.107 Ring bunch intensity [10 14 ] 1.6 2.5 3.8 Ring space-charge tune spread, Q sc 0.15 0.15 0.2 Pulse length on target [ns] 695 691 683

P. Lapostolle,

Summary The SNS project is still on track for achieving a June 06 finish date within the appropriated 1.4 Billion $. The construction is more than 85% complete. The program has benefited from enormous support in Washington with funding appropriated every year as planned. Commissioning has progressed as installation continues with 40MeV achieved at full spec. The next major step is the commissioning of complete warm linac (DTL + CCL). The full linac should be in commissioning next spring during PAC 05. It has been and still is a very successful collaboration between six partnering DOE laboratories. Please come visit us next year during PAC or whenever you get a chance.

PAC05 PAC 05 will be in Knoxville, TN, 25 miles from the site. There will be a site tour on Saturday Please come to visit us..