Trigger Cost & Schedule

Similar documents
WBS Trigger. Wesley Smith, U. Wisconsin CMS Trigger Project Manager. DOE/NSF Review April 11, 2000

Trigger Report. Wesley H. Smith CMS Trigger Project Manager Report to Steering Committee February 23, 2004

WBS Calorimeter Trigger. Wesley Smith, U. Wisconsin CMS Trigger Project Manager. DOE/NSF Review April 12, 2000

WBS Trigger. Wesley Smith, U. Wisconsin CMS Trigger Project Manager. DOE/NSF Review February 17, 1999

US CMS Endcap Muon. Regional CSC Trigger System WBS 3.1.1

CSC Muon Trigger. Jay Hauser. Director s Review Fermilab, Apr 30, Outline

Status of the CSC Track-Finder

ADF-2 Production Readiness Review

Global Trigger Trigger meeting 27.Sept 00 A.Taurok

CMS Conference Report

Test Beam Wrap-Up. Darin Acosta

Risk Risk Title Severity (1-10) Probability (0-100%) I FPGA Area II Timing III Input Distortion IV Synchronization 9 60

SPS BPM system renovation. Roadmap & Milestones

Local Trigger Electronics for the CMS Drift Tubes Muon Detector

KPI and SLA regime: September 2015 performance summary

Mosaic 1.1 Progress Report April, 2010

Installation of a DAQ System in Hall C

Tests of the boards generating the CMS ECAL Trigger Primitives: from the On-Detector electronics to the Off-Detector electronics system

LSD Review December 2012 Schedule, Re-Baseline, & Resource Analysis

Design, Realization and Test of a DAQ chain for ALICE ITS Experiment. S. Antinori, D. Falchieri, A. Gabrielli, E. Gandolfi

LHCb and its electronics. J. Christiansen On behalf of the LHCb collaboration

RELIABILITY REASON FOR A COMMERCIAL INADVERTENT-INTERCHANGE SETTLEMENT STANDARD.

LHCb and its electronics.

Paul Dauncey For the CALICE-UK electronics group. A. Baird, D. Bowerman, P. Dauncey, R. Halsall, M. Postranecky, M.Warren, O.

KEK. Belle2Link. Belle2Link 1. S. Nishida. S. Nishida (KEK) Nov.. 26, Aerogel RICH Readout

Design of the Level-1 Global Calorimeter Trigger

ALA Webinar August 21, 2013

OB35 Paper 06 KPI Report

CGEM-IT project update

ALICE Muon Trigger upgrade

Development of beam-collision feedback systems for future lepton colliders. John Adams Institute for Accelerator Science, Oxford University

Sector Processor to Detector Dependent Unit Interface

GLAST Large Area Telescope:

DT Trigger Server: Milestone D324 : Sep99 TSM (ASIC) 1st prototype

Status of the LHCb Experiment

CERN-RRB April 2005 Status of the LHCb Experiment Report to April 2005 RRB By the LHCb Collaboration

Solutions to Embedded System Design Challenges Part II

PEP-II longitudinal feedback and the low groupdelay. Dmitry Teytelman

Monthly Progress Report Stanford Synchrotron Radiation Laboratory

Laboratory Exercise 4

Dick Loveless. 20 November 2008 SLHC Workshop. Dick Loveless SLHC Workshop 20 Nov

Synchronization of the CMS Cathode Strip Chambers

12 Cathode Strip Chamber Track-Finder

The ATLAS Tile Calorimeter, its performance with pp collisions and its upgrades for high luminosity LHC

TTC Interface Module for ATLAS Read-Out Electronics: Final production version based on Xilinx FPGA devices

KPI and SLA regime: June 2015 performance summary Ref Apr 15 May 15 Jun 15 Target Description KPI A 100% 100% 100% 99% green

S.Cenk Yıldız on behalf of ATLAS Muon Collaboration. Topical Workshop on Electronics for Particle Physics, 28 September - 2 October 2015

Minutes of the ALICE Technical Board, November 14 th, The draft minutes of the October 2013 TF meeting were approved without any changes.

Objectives. Combinational logics Sequential logics Finite state machine Arithmetic circuits Datapath

Beam Test Results and ORCA validation for CMS EMU CSC front-end electronics N. Terentiev

THE DIAGNOSTICS BACK END SYSTEM BASED ON THE IN HOUSE DEVELOPED A DA AND A D O BOARDS

KPI and SLA regime: October 2014 performance summary Reference Outcome Result Target Description KPI A Green 100% 99% green

Large Area, High Speed Photo-detectors Readout

CSC Data Rates, Formats and Calibration Methods

CMS Tracker Synchronization

Trigger Menus and Rates

The Pixel Trigger System for the ALICE experiment

The LEP Superconducting RF System

Status of GEM-based Digital Hadron Calorimetry

Random Access Scan. Veeraraghavan Ramamurthy Dept. of Electrical and Computer Engineering Auburn University, Auburn, AL

Lecture #4: Clocking in Synchronous Circuits

Library. Summary Report

KPI and SLA regime: August 2015 performance summary Ref Jun 15 Jul 15 Aug 15 Target Description KPI A 100% 100% 99.87% 99% green

Update on DAQ for 12 GeV Hall C

Scintillation Tile Hodoscope for the PANDA Barrel Time-Of-Flight Detector

Copyright 2018 Lev S. Kurilenko

Sharif University of Technology. SoC: Introduction

CMS Upgrade Activities

Commissioning and Initial Performance of the Belle II itop PID Subdetector

Deliverable 2.17 Periodic WP2 Progress Report 3

Optical Link Evaluation Board for the CSC Muon Trigger at CMS

ECE532 Digital System Design Title: Stereoscopic Depth Detection Using Two Cameras. Final Design Report

Optical clock distribution for a more efficient use of DRAMs

THE DESIGN OF CSNS INSTRUMENT CONTROL

HPS Slow Controls Overview

Highly Accelerated Stress Screening of the Atlas Liquid Argon Calorimeter Front End Boards

Why FPGAs? FPGA Overview. Why FPGAs?

Electronics procurements

A Fast Constant Coefficient Multiplier for the XC6200

SuperFRS GEM-TPC Development Status Report

KPI and SLA regime: September 2014 performance summary Reference Outcome Result Target Description KPI A Green 100% 99% green

Innovative Fast Timing Design

IN DIGITAL transmission systems, there are always scramblers

Front End Electronics

Laboratory 1 - Introduction to Digital Electronics and Lab Equipment (Logic Analyzers, Digital Oscilloscope, and FPGA-based Labkit)

Compact Muon Solenoid Detector (CMS) & The Token Bit Manager (TBM) Alex Armstrong & Wyatt Behn Mentor: Dr. Andrew Ivanov

bug, although this was still not quite clear. The problem seems to occur when there is an interrupt during a read cycle. Changing interrupt vectors an

An extreme high resolution Timing Counter for the MEG Upgrade

An Efficient Reduction of Area in Multistandard Transform Core

Design for Testability

EECS150 - Digital Design Lecture 10 - Interfacing. Recap and Topics

Research on Precise Synchronization System for Triple Modular Redundancy (TMR) Computer

Front End Electronics

Design and Implementation of SOC VGA Controller Using Spartan-3E FPGA

Advanced Training Course on FPGA Design and VHDL for Hardware Simulation and Synthesis. 26 October - 20 November, 2009

A Serializer ASIC at 5 Gbps for Detector Front-end Electronics Readout

C8000. switch over & ducking

AIDA Advanced European Infrastructures for Detectors at Accelerators. Milestone Report. Pixel gas read-out progress

Upgrades of the Tracker and Trigger of the CMS experiment at the CERN LHC

Tools to Debug Dead Boards

Transcription:

Trigger Cost & Schedule Wesley Smith, U. Wisconsin CMS Trigger Project Manager DOE/NSF Review May 9, 2001 1

Baseline L4 Trigger Costs From April '00 Review -- 5.69 M 3.96 M 1.73 M 2

Calorimeter Trig. Costs at L5 WBS Item Base(k$) Cont(%) 3.1.2 Cal. Regional Trigger 3,956 44 3.1.2.1 Prototypes 377 43 3.1.2.2 Preproduction ASICs 473 50 3.1.2.3 Test Facilities 79 50 3.1.2.4 Power Supplies 82 30 3.1.2.5 Crates 36 30 3.1.2.6 Backplane 77 54 3.1.2.7 Clock & Control Card 101 40 3.1.2.8 Receiver Card 1,545 46 3.1.2.9 Electron ID Card 707 32 3.1.2.10 Jet Summary Card 174 50 3.1.2.11 Cables 7 30 3.1.2.12 DAQ Processor 3.1.2.13 Crate Monitor Card 3.1.2.14 Trigger Tests 298 50 3.1.2.15 Trigger Project Management (April 2000 numbers) $ 5694 540 709 119 107 47 119 141 2262 934 261 9 ger i n TOTAL (K$) Changes since April 2000 Review: Backplane parts costs properly included (+ $88K) Additional Prototype Cycle for Serial Link for new Vitesse chip (+ $110K) Extra manpower for delayed installation (+ $100K) K 447 3

Muon Trigger Costs at L5 WBS ITEM BASE(K$) Cont(%) 3.1.1 CSC Muon Trigger 1,733 52 3.1.1.1 Muon Port Cards (MPC) 475 49 3.1.1.2 Sector Receivers (SR) 328 50 3.1.1.3 Sector Proc. (SP-CSC) 232 65 3.1.1.4 Overlap SP (SP-OVR) 202 64 3.1.1.5 Clock&Control (CCC) 142 40 3.1.1.6 Crate Monitor Cards 10 50 3.1.1.7 Muon Backplanes 94 47 3.1.1.15 Muon Sorter 104 48 3.1.1.8 Crate Controllers 35 50 3.1.1.9 Muon Crates 6 50 3.1.1.10 Muon Power Supplies 23 50 3.1.1.11 Additional Cables 30 50 3.1.1.12 Trigger System Tests 52 50 3.1.1.13 Trigger Proj. Manage. 0 (April 2000 numbers) TOTAL (K$) 2636 707 491 i 383 n K 331 $ 199 15 137 154 53 9 35 45 78 Changes since April 2000 Review Add design/prototyping of new FPGAs, Optical Links, Backplane (+ $140K) Add new task for interface to DAQ (+ $31K) Extra manpower for delayed installation (+ $100K) 4

Cost & Schedule Performance Important revisions result in an improved system Muon Trigger Combination of Sector Receiver & Processor into one card Elimination of crate interconnects Reduction of 6 full crates to one full crate 3 high bandwidth compact links per three muons Faster Backplane technology (GTLP instead of Ch. Links) Calorimeter Trigger Use of more reliable & stable Vitesse link technology Consequences for schedule Developments at the expense of schedule for now Will speed schedule in future More compact muon trigger -- less to design, build & debug More stable links -- easier to integrate and test 5

Cost/Schedule Performance 4500000 4000000 3500000 TRIDAS WBS 3.0 TRIGGER WBS 3.1 October 1999 through March 2001 Cumulative Trends Budget, Performance, Actuals, and Obligations 3000000 2500000 2000000 1500000 1000000 500000 0 New Compact Muon track-finder design Will be built faster Cal Trig need for new Serial Link Design Replace Vitesse 7214 with 7216 -- Done Budgeted Cost of Work Schedule - BCWS - Budget Budgeted Cost of Work Performed - BCWP - % Complete Actual Cost for Work Performed - ACWP - Paid Invoices Obligations = ACWP + open Commitments Oct-99 Nov-99 Dec-99 Jan-00 Feb-00 Mar-00 Apr-00 May-00 Jun-00 Jul-00 Aug-00 Sep-00 Oct-00 Nov-00 Dec-00 Jan-01 Feb-01 Mar-01 BCWS (Budget) 2E+06 2E+06 2E+06 2E+06 2E+06 2E+06 2E+06 3E+06 3E+06 3E+06 3E+06 3E+06 3E+06 3E+06 3E+06 3E+06 3E+06 4E+06 BCWP (Performance) 1E+06 2E+06 2E+06 2E+06 2E+06 2E+06 2E+06 2E+06 2E+06 3E+06 3E+06 3E+06 3E+06 3E+06 3E+06 3E+06 3E+06 3E+06 OBLIGATIONS 2E+06 2E+06 3E+06 3E+06 3E+06 3E+06 2E+06 2E+06 2E+06 3E+06 3E+06 3E+06 3E+06 3E+06 3E+06 3E+06 4E+06 4E+06 ACWP (Paid Actuals) 2E+06 2E+06 2E+06 2E+06 2E+06 2E+06 1E+06 2E+06 2E+06 3E+06 3E+06 3E+06 3E+06 3E+06 3E+06 3E+06 3E+06 3E+06 6

Trigger Cost/Sched. Trends $800,000 $600,000 $400,000 TRIDAS WBS 3.0 Trigger WBS 3.1 October 1999 through March 2001 Cumulative Trends for Cost and Schedule and Obligations Variances $200,000 $0 ($200,000) ($400,000) ($600,000) ($800,000) ($1,000,000) ($1,200,000) Schedule Variance Cost Variance Obligation Variance SV = BCWP - BCWS CV = BCWP - ACWP OV = BCWP - Obligations Negative Cost or Schedule Variance is BEHIND schedule or OVER RUNNING Budget Positive Cost or Schedule Variance is AHEAD of schedule or UNDER RUNING Budget ($1,400,000) Oct-99 Nov-99 Dec-99 Jan-00 Feb-00 Mar-00 Apr-00 May-00 Jun-00 Jul-00 Aug-00 Sep-00 Oct-00 Nov-00 Dec-00 Jan-01 Feb-01 Mar-01 Schedule Variance -325042-229827 -246063-268131 -296892-338973 -322455-297138 -263010-202427 -228712-222120 -303027-303598 -337201-379831 -446452-495260 ACWP Variance -363114-258489 -246157-267477 -81515.4 183972 590876 58289.9 203035-111890 -53440.8-9681.17 7290.03 57758.6 70606.9 78190.2 123540 404605 Obligation Variance -550431-465684 -1048929-1100431 -915947-637436 -221466-92430.1 56449.2-243349 -390107-320349 -303378-252909 -240061-228381 -1116569-825077 7

US CMS Trigger (% Comp., Cont. Use) 0.500 0.400 0.300 0.200 0.100 BCWP/EAC (EAC-Base)/Base 0.000-0.100 Jan-00 Mar-00 May-00 Jul-00 Sep-00 Nov-00 Jan-01 Mar-01 Negligible contingency use thus far Some ASICs purchased early US CMS DOE/NSF Review: May 8-10, 2001 8

Trigger - Yearly BCWS Costs ramp up until production, the bulk of which happens in FY02. M&S costs dominate at 65% of the ETC. Trigger BCWS by Fiscal Year 3,000,000 2,500,000 2,000,000 1,500,000 1,000,000 500,000 0 FY96 FY97 FY98 FY99 FY00 FY01 FY02 FY03 FY04 FY05 US CMS DOE/NSF Review: May 8-10, 2001 9

Trigger Resource Usage Engineering and Technical resources are compared to the people called out in the annual SOW. This tracking ensures that the needed labor is deployed. Trigger - Resource Usage 5 4.5 4 3.5 3 2.5 2 1.5 1 0.5 0 FY97 FY98 FY99 FY00 FY01 FY02 FY03 FY04 T E US CMS DOE/NSF Review: May 8-10, 2001 10

Peak Engineering Level M Y 2.5 2 Calorimeter Trigger 2.5 2.5 2.2 WBS 3.1.2 1.5 1 0.5 1.4 1.4 1.3 1.3 0 FY98 FY99 FY00 FY01 FY02 FY03 FY04 Fiscal Year Wisconsin 11

M Y 3.2 2.8 2.4 2 1.6 1.2 0.8 0.4 0 2.2 1.5 0.6 Peak Engineering Level 1.6 1.1 Muon Trigger 2.9 1.7 0.2 0.3 2.3 1.3 0.5 1.9 1.1 0.8 0.9 0.6 0.6 0.3 0.2 0.3 FY98 FY99 FY00 FY01 FY02 FY03 FY04 Fiscal Year WBS 3.1.1 UCLA Florida Rice 12

US CMS Trigger L1, L2, L3 Milestone Performance Comments: Major L1 Milestone: Trigger TDR on Time! Milestone for SORT ASIC start compensated by faster finish Integration waiting for ECAL electronics Extra slack in schedule due to delayed installation US CMS DOE/NSF Review: May 8-10, 2001 13

Level 1 Milestones: 1998-2000 Nov. 1998 Complete Initial Trigger Design Algorithms finalized Functional blocks determined Numbers of ASICs, boards, cards and crates specified Interfaces specified Trigger geometry determined Nov. 1999 Complete Phase 1 Prototype Design Designs of boards, cards ASICs for prototype tests done Nov. 2000 Phase 1 Prototype Tests Finished All tests necessary to begin design of production electronics are complete Nov. 2000 Technical Design Report 14

CMS Level -1 Trigger TDR LABORATOIRE EUROPEEN POUR LA PHYSICQUE DES PARTICULES CERN EUROPEAN LABORATORY FOR PARTICLE PHYSICS CMS CERN/LHCC 00-xx CMS TDR 6.1 November 2000 CMS Level 1 Milestone Submitted to LHCC on Nov. 28, 2000: CERN/LHCC 2000-38 CMS TDR 6.1 Approved in March, 2001. The TriDAS project. Volume I The Trigger Systems http://cmsdoc.cern.ch/cms/ TDR/TRIGGER-public/trigger.html 15

Cal.Trig. - 3.1.2 Milestones 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 Oct Apr Oct Apr Oct Apr Oct Apr Oct Apr Oct Apr Oct Apr Oct Apr Oct Apr Oct Apr Start Prototype Boards 10/1/97 Begin ASIC Development 10/1/97 Internal Design Review 1 11/12/98 Prototype Design Finished 9/9/99 Internal Design Review 2 11/4/99 Begin ASIC Preproduction 9/30/99 Proto. Boards & Tests Finished 4/6/01 Review tests of Regional Trigger 4/6/01 Review of Integration of calorimeter trigger 5/25/01 Begin Backplane & Crate Production 8/31/01 ASIC Development Complete 9/25/01 Finish ASIC Preproduction 1/30/02 Begin Trigger Board Production 11/27/01 Begin ASIC Production 2/28/02 Crate & Backplane Complete 9/18/02 Begin Production Board Tests 9/18/02 Designs Finished 6/26/02 Finish ASIC Production 10/31/03 Finish Trigger Board Production 2/10/ Finish Production Board Tests 3/9/0 16

Muon Trig. - 3.1.1 Milestones 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 Oct Apr Oct Apr Oct Apr Oct Apr Oct Apr Oct Apr Oct Apr Oct Apr Oct Apr Oct Apr Begin Initial System Design 10/1/97 Finish Initial System Design 5/13/98 Begin Prototype Design 5/13/98 Finish Prototype Design 7/22/99 Begin Prototype Construction 5/13/99 Finish Prototype Construction 7/21/00 Begin Prototype Test 7/21/00 Finish Prototype Test 2/2/01 Begin Final Design 2/2/01 Finish Final Design 3/4/02 Begin Production 3/4/02 Finish Production 8/19/03 Begin Installation 8/19/03 Finish Installation 4/1/04 Begin Trigger System Tests 4/2/ Finish Trigger System Tests 17

Trigger R&D Program Summary Engineering evaluation & prototyping to evaluate design capability, feasibility, and cost. Goal is to provide the information required for the subsystem trigger designs and specifications of interfaces to the Front End, Trigger and DAQ systems. Phase 1 prototyping program designs were complete November 1999 and tests will be complete and fully reported on by November 2000. Final result of this program wasthe Level-1 Trigger Technical Design Report in 2000. Phase 2 prototyping program is concentrating on final or pre-production prototypes based on the design in the TDR. 18

Trigger Program Simulation Check detector changes effect on trigger performance Validate final algorithms as implemented in hardware Calorimeter Trigger Validate 160 MHz dataflow & processing Design & test prototype Boards Design & test prototype ASICs Design & test high speed Cu serial Link system Muon Trigger Design & test prototype Boards Design & test prototype FPGA circuits Design & test high speed optical serial link system Test interface with CSC FE electronics 19

Cal. Trigger Status & Plans Test Prototypes New Proto.160 MHz Backplane - manufactured New Proto. Receiver Card - in layout New Proto. Clock Card - being manufactured New Proto. Electron ID Card - in design Serial Data Tests New Serial Link Test Card - in design New Serial Link Mezzanine Card - in layout ASIC PrototypeTests All Prototype ASICs tested by Vitesse & Delivered Phase & BSCAN will test on Receiver Card SORT & Electron ID will test on Electron ID Card Integration Tests Serial Link Test Card & Mezzanine Card w/ ECAL 20

Muon Trigger Status & Plans Compact Muon Trigger Design Single Sector Processor FPGA Verified can be done with a single Xilinx 1600E New Backplane GTLP tested at 80 MHz Higher bandwidth and more compact optical links TI TLK 2501 tested at 80 MHz parallel I/O Technical Review on May 24 Outcome: plan & sched. for final design & protos. New Prototypes Muon Port Card proto. with new optical links Combined Sector Receiver/Sector Processor proto. Proto. Backplane based on GTLP 21

Trigger Project Management CMS TriDAS Reviews (besides this) April: TriDAS Status Progress, draft R&D plans & expenses for next year May: Electronics Systems Review September: CMS Annual Review With CMS & external referees October: LHCC Comprehensive Review LHCC subcommittee +external experts November: TriDAS Annual Review R&D Plans/Progress, Cost & Schedule, Milestones Finalize R&D plans & expenses for next year Internal Annual CMS Review w/external & CMS referees 22

Trigger Project Management US CMS Management US Reviews Monthly Video Conferences Florida, Rice, UCLA, Wisconsin Review Progress, milestones, simulation activities US Reporting Monthly progress reports: % complete activities narrative US Integration Meetings: Calorimeter Trigger: FNAL, Maryland, Wisconsin Muon Trigger: Ohio, Florida, Rice, UCLA, Wisconsin, others. US Trigger Site Visits: Florida, Rice, UCLA 23

Conclusions - Trigger Good Progress Since April 2000 Lehman Review Extensive prototyping & test program "Proof of principle" of all critical items Number of successes already CSC trigger integration test, New Optical Links, Backplane, FPGA Calorimeter trigger Receiver & Electron Cards, Backplane, ASICs Cost & Schedule Performance All Milestones made BWCP/BWCS at 85% In good shape Compact muon trigger simpler -- will improve Prototype Calorimeter ASICs all in hand ahead of original schedule Project Management Extensive system of reviews and monitoring in place TDR done, detailed documentation on WWW: http://cmsdoc.cern.ch/ftp/afscms/tridas/html/level1.html 24