US-ILC Waveguide Industrialization Study. Marc Ross, Chris Nantista and Chris Adolphsen

Similar documents
Next Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack

Overview of RF Distribution System and Cost Drivers

INFN School on Electron Accelerators. RF Power Sources and Distribution

WG2 Group Summary. Chris Adolphsen Terry Garvey Hitoshi Hayano

Detailed Design Report

XFEL High Power RF System Recent Developments

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

ILC-LNF TECHNICAL NOTE

45 MW, 22.8 GHz Second-Harmonic Multiplier for High-Gradient Tests*

5 Project Costs and Schedule

Nick Walker DESY MAC

RF Upgrades & Experience At JLab. Rick Nelson

A New 4MW LHCD System for EAST

Pulsed Klystrons for Next Generation Neutron Sources Edward L. Eisen - CPI, Inc. Palo Alto, CA, USA

DEVELOPMENT OF A 10 MW SHEET BEAM KLYSTRON FOR THE ILC*

L-Band RF R&D. SLAC DOE Review June 15 th, Chris Adolphsen SLAC

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

J/NLC Progress on R1 and R2 Issues. Chris Adolphsen

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems

The LEP Superconducting RF System

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

PEP-II Overview & Ramp Down Plan. J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007

Present Status and Future Upgrade of KEKB Injector Linac

Availability and Reliability Issues for the ILC

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

RF considerations for SwissFEL

TITLE PAGE. Title of paper: PUSH-PULL FEL, A NEW ERL CONCEPT Author: Andrew Hutton. Author Affiliation: Jefferson Lab. Requested Proceedings:

CLIC Feasibility Demonstration at CTF3

X-Band Klystron Development at

DELIVERY RECORD. Location: Ibaraki, Japan

!"!3

Spear3 RF System Sam Park 11/06/2003. Spear3 RF System. High Power Components Operation and Control. RF Requirement.

Development of Multiple Beam Guns for High Power RF Sources for Accelerators and Colliders

OF THIS DOCUMENT IS W8.MTO ^ SF6

SMTF Beta <1 Front End Linac Infrastructure and Plans

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

Evaluation of Performance, Reliability, and Risk for High Peak Power RF Sources from S-band through X-band for Advanced Accelerator Applications

ILC RF System R&D. Chris Adolphsen, SLAC. Section of 1.3 GHz SC Linac. June 29, 2007 PAC07 Talk FRYC01

Towards an X-Band Power Source at CERN and a European Structure Test Facility

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting

RF Power Upgrade at Jefferson Lab

DEPARTMENT OF ELECTRONICS AND COMMUNICATION ENGINEERING QUESTION BANK

SPS BPM system renovation. Roadmap & Milestones

STATUS OF THE INTERNATIONAL LINEAR COLLIDER

SUMMARY OF THE ILC R&D AND DESIGN

DEVELOPMENT OF X-BAND KLYSTRON TECHNOLOGY AT SLAC

Examples of Successful Collaboration Between CPI and DOE Labs. Todd Treado CPI December 2013

MPI Cable Selection Guide

Thoughts on Project Standard in Japan

North Damping Ring RF

ADE-R3GLH+ CONVERSION LOSS 50. ISOLATION (db) 10 LO= +7 dbm LO= +10 dbm LO=+13 dbm FREQUENCY (MHz) RF VSWR

ILC Damping Ring Lattice Status Report. Louis Emery and Aimin Xiao Argonne National Laboratory Presented at KEK workshop Dec 18th, 2007

White Paper. Performance analysis: DOCSIS 3.1 cable TV headend combining systems

SPINNER BROADCAST EXPLANATION OF THE MULTI CHANNEL COMBINER SPECIFICATIONS

PoS(EPS-HEP2015)525. The RF system for FCC-ee. A. Butterworth CERN 1211 Geneva 23, Switzerland

Suggested ILC Beam Parameter Range Rev. 2/28/05 Tor Raubenheimer

Pulses inside the pulse mode of operation at RF Gun

Karin Rathsman. Calculations on the RF Source and Distribution

STATUS OF THE SwissFEL C-BAND LINAC

High Brightness Injector Development and ERL Planning at Cornell. Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics

Features. = +25 C, IF = 1 GHz, LO = +13 dbm*

PEP II STATUS AND PLANS *

Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi)

A HIGH POWER LONG PULSE HIGH EFFICIENCY MULTI BEAM KLYSTRON

PEP II Status and Plans

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

DESIGN AND PERFORMANCE OF L-BAND AND S-BAND MULTI BEAM KLYSTRONS

Upgrade of CEBAF to 12 GeV

Design, Fabrication and Testing of Gun-Collector Test Module for 6 MW Peak, 24 kw Average Power, S-Band Klystron

Modulator Overview System Design vs. Tunnel Topologies. Snowmass Workshop August 16, 2005 Ray Larsen for the SLAC ILC Group

The FLASH objective: SASE between 60 and 13 nm

Status of CTF3. G.Geschonke CERN, AB

Features low conversion loss, 6.11 db typ. excellent L-R isolation, 44 db typ. CONVERSION LOSS (db) Mid-Band m. Range f L. Conversion Loss (db)

Accelerator Instrumentation RD. Monday, July 14, 2003 Marc Ross

Frequency Mixer wide band

MAMX Sub-Harmonic Pumped Mixer GHz Rev. V1. Functional Schematic. Features. Description. Pin Configuration 1

News from HZB / BESSY Wolfgang Anders at ESLS-RF Meeting September 2010 Trieste

Features low conversion loss, 5.94 db typ. aqueous washable J-leads for strain relief. CONVERSION LOSS (db) Mid-Band m. Range f L.

NSLS-II RF Systems James Rose, Radio Frequency Group Leader PAC 2011

Welcome and FRIB Project Status. FRIB Highlights and Plan Ahead

CEBAF 8 kw CW KLYSTRON SPECIFICATION EE0043, Rev. H January 15, 1998

RF Design of the LCLS Gun C.Limborg, Z.Li, L.Xiao, J.F. Schmerge, D.Dowell, S.Gierman, E.Bong, S.Gilevich February 9, 2005

Hitachi Kokusai Electric Comark LLC

A Cathode Development Cornell Cultera This scope includes all labor and purchases required produce photocathodes required by CBETA.

Summary of the 1 st Beam Line Review Meeting Injector ( )

Studies on an S-band bunching system with hybrid buncher

Axle Assembly Poke-Yoke

LAVI-U252VH+ Performance Charts. LO=+18dBm LO=+21dBm LO=+24dBm. LO=+18dBm LO=+21dBm LO=+24dBm. LO=+18dBm LO=+21dBm LO=+24dBm

Karin Rathsman, Håkan Danared and Rihua Zeng. Report from RF Power Source Workshop

TOSHIBA Industrial Magnetron E3328

The PEFP 20-MeV Proton Linear Accelerator

ANKA RF System - Upgrade Strategies

Features excellent conversion loss, 6.0 db typ. high L-R isolation, 40 db typ. L-I isolation, 55 db typ. rugged welded construction

ARES Status 2004(JFY)

Dark current and multipacting trajectories simulations for the RF Photo Gun at PITZ

Low Level RF for PIP-II. Jonathan Edelen LLRF 2017 Workshop (Barcelona) 16 Oct 2017

Operating Experience and Reliability Improvements on the 5 kw CW Klystron at Jefferson Lab

TEST RESULTS OF THE 84 GHZ / 200 KW / CW GYROTRON

Monthly Progress Report Stanford Synchrotron Radiation Laboratory

Mechanical aspects, FEA validation and geometry optimization

Transcription:

US-ILC Waveguide Industrialization Study Marc Ross, Chris Nantista and Chris Adolphsen

ILC Local Power Distribution System (LPDS) variable power divider, pressurizable, 0-100%, phase stable pressure window variable H-hybrid, non-press., limited range 5 MW load Original layout from 10 MW klystron 9 cavities 4 cavities quad 4 cavities 9 cavities 6 windows (assuming ~2 MW capability) RF UNIT: 3 cryomodules (26 cavities) New layout Beam current lowered, 1/3 of klystrons eliminated WR770 run For low power RDR-like option, one klystron powers 1 ½ rf units or 4 ½ cryomodules.

Detailed View of 13-Cavity LPDS Unit Power to each ½ cryomodule is fully adjustable via VPD s without affecting phases. Unused power can be dumped to the end load. cavity coupler bellows isolator w/ pickups phase shifter load WR650 waveguide loads variable power divider variable H-hybrids pressure window POWER FLOW Each cavity feed line has a phase shifter, isolator w/ bi-directional coupler, and flex guide

Tunnel End View

Feeding 3 Stations with 2 Klystrons WR770 used for long runs. Extra 2 3 port network needed at klystron.

Standard Waveguide and Waveguide Components Straight sections E-plane and H-plane bends T-splitters and magic T's Semi-flex waveguides folded magic T Need pressurizable and non-pressurizable versions, for stress relief in upper waveguide runs and at cavities.

Isolator and Loads S.P.A. Ferrite, Ltd. (Russia) Newer model includes forward and reflected pick-ups, eliminating the need for a separate bi-directional coupler (reflectometer)*. * But costed as separate components Water cooled (2 types) P pk P av 2 MW 10 kw 5 MW 100 kw

SLAC Air-to-Air Window Bi-Directional Couplers (Reflectometers) High power tested up to 3 MW, 1 ms. Ceramic Plug Pressure Window May be largely eliminated by use of isolators with built-in pick-ups.

Phase Shifters DESY/SPA Ferrite KEK/Toshiba

KEK Variable H-Hybrid (Power Divider) Sergey Kazakov Variable H-hybrid geometry, sample field pattern and in-line port design modification. Moving the two suspended conductors in and out perturbs the relative phase between the two modes supported in the interior section while retaining match, resulting in a varying power split at the output ports.

U-Bend Phase Shifter simulation field plot SLAC Variable Power Divider (VPD) = 2 U-bend phase shifters + 2 folded magic-t's C. Nantista

XFEL PDS: XFEL Mega: ~ 7K$ / cavity 12

ILC PDS: Three kinds of parts: 1. Catalog items (cost basis from Mega/Furukawa; LC=0.95) (modification may be required for pressurization) 2. Loads / Circulators (cost basis SPA Ferrite St. Petersburg; same LC) 3. SLAC / KEK in-house designs with integrated electromechanical actuator; based on WR650 hardware (cost basis from first article; same LC) TDR cost distribution for the above three kinds: 27% 29% 44% (including K-PDS) 13

ILC Industrialization Study Part Count -P = pressurizable -NP = non-pressurizable Assume all LPDS s like standard ML klystron feeding 39 cavities: Nc = # of cavities = 16,024 ITEM FORMULA QUANTITY Isolator -NP Nc 16,024 Semi-Flex guide -NP Nc 16,024 Semi-Flex guide -P 3*Nc/13 3,698 Reflectometer -NP Nc 16,024 Reflectometer -P 2*Nc/39 822 Phase Shifter -NP Nc 16,024 Phase Shifter -P Nc/39 411 Pressure window -P 3*Nc/13 3,698 1 MW load -P 3*Nc/13 3,698 5 MW load -P Nc/13 1,233 U-bend Phase Shifter -P 6*Nc/13 7,396 Folded magic-t -P 6*Nc/13 7,396 Variable hybrid -NP 10*Nc/13 12,326 3-dB Hybrid -P Nc/39 411 E-plane shunt T -P Nc/39 411 E-plane bend -P 15*Nc/39 6,163 H-plane bend -P 7*Nc/39 2,876 H-plane bend -NP Nc+3*Nc/13 19,722 E-plane U-bend -NP Nc 16,024 WR650-770 converter -P 2*Nc/39 822 WR770 straight 120 -P Nc/39 411 WR650 straight 4 -P 10*Nc/39 4,109 WR650 straight 8 -P 7*Nc/39 2,876 WR650 straight 12 -P 6*Nc/39 2,465 WR650 straight 3 -NP 9*Nc/39 3,698 WR650 straight 8 -NP 27*Nc/39 11,093 Nut/bolt/washers 10*(tot+Nc) 1,918,790

Post-TDR MEGA Cost Study Scope Twelve production schemes considered: deliver full, only standard waveguide, only circulators and loads, and only electromechanical devices at 3 varied production levels (25%, 50% and 100%) over a period of 6 years with up to 2 additional years for the following to be completed: a. Casting and extrusion tooling and process development / qualification b. Facility build-out c. Equipment and workstation installation and pre-production verification / release d. Production tooling and process development and qualification The results of this study include plant layouts, time planning for equipment and labor, work flow diagrams, and costs for the industrial components of plan estimated at 2013 prices and rates 15

Specific Report Items (1): Plant equipment requirements, including building, technical equipment, and layout of equipment in building. Costs, in 2013 dollars, to create such a facility, and time required to build, prepare, and prove the plant is ready for production. A production plan, including labor and machine hours required. Identification of the top 3 throughput bottlenecks in the plant, and the remedy for each. Analysis of alternatives for each production step, and identification of the top 3 alternatives which should be pursued with R&D to have the greatest economic effect on the production.

Specific Report items (2) Identification of components or subcomponents that are prime candidates for subcontracting, including description of existing companies that could fulfill such roles or a description of an industry where such subcontracting should be pursued. Identification of particularly economically burdensome production process requirements or component tolerances which are, and possible remedies for such. Identification of the hub Laboratory contributions, the reasoning for the choice, and a description of the technical criteria that would define such a handoff.

Fabrication Tasks Assembly Blending Brazing Manual Mills Clean / Mask Compression Convoluter Copper Plate Electrical Test EMMEGI Final Inspection Forming / Weld Heat Treat In-Process Insp 630 mm HMC 630 mm VMC 1,000 mm HMC Pack / Ship Paint Pressure Test Rinse Router Saws Silver Plate Solder 300 mm Lathe Autowelder TIG Welder

Example: TIG Welding

The Project Timeline captures the major milestones of the facility build out and ramp up to meet the production demand timeline.

Learning Curves The purely mechanical straights and sweeps will quickly hit a production plateau gaining potentially a 10% improvement over time as the workers become more comfortable with the serial production operations and techniques during the first year of production. The more complex components will take significantly more time to attain optimized throughput levels, but we believe a 20% or more improvement may be possible.

Top 3 Processes Machining (assumes 85% machinery utilization over two 8 hour shifts per day, five days per week) Welding Testing (to be shared with hub lab) These are also the three potential bottlenecks they identified in particular, in regard to Equipment up time (5% downtime in PY1 and 3% in years PY2 PY6) Employee availability Raw material supply

Hub Lab Tasks High power rf testing Electro-mechanical integration (final assembly of subassemblies with motorized drives) Final PDS integration and tuning

Possible Improvements Integration of special components Electromechanical devices, typ. SLAC / KEK designs Extrusion Casting Testing automation May provide 20 to 30% cost reduction

Summary Industrialization study of non-high-tech components (PDS) completed March 2014 US PDS industry is small-business based Substantial cost-reduction (~1% of ILC total) possible with nominal R&D investment