ARIEL Buildings Construction and Electron Linac Photo-Fission Driver for the Rare Isotope Program at TRIUMF

Similar documents
Electron linac photo-fission driver for rare isotope program at TRIUMF

Status of Superconducting Electron Linac Driver for Rare Ion Beam Production at TRIUMF

High Brightness Injector Development and ERL Planning at Cornell. Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

SRS and ERLP developments. Andrew moss

Biennial Scientific Report

NSLS-II RF Systems James Rose, Radio Frequency Group Leader PAC 2011

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY

RF plans for ESS. Morten Jensen. ESLS-RF 2013 Berlin

Next Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack

RF Power Upgrade at Jefferson Lab

ILC-LNF TECHNICAL NOTE

Introduction: CW SRF linac types, requirements and challenges High power RF system architecture

Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi)

INFN School on Electron Accelerators. RF Power Sources and Distribution

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

Welcome and FRIB Project Status. FRIB Highlights and Plan Ahead

Status of CTF3. G.Geschonke CERN, AB

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

The ESS Accelerator. For Norwegian Industry and Research. Oslo, 24 Sept Håkan Danared Deputy Head Accelerator Division Group Leader Beam Physics

XFEL High Power RF System Recent Developments

SLS RF operation report 2003

!"!3

4.4 Injector Linear Accelerator

Upgrading LHC Luminosity

5 Project Costs and Schedule

Operating Experience and Reliability Improvements on the 5 kw CW Klystron at Jefferson Lab

IOT RF Power Sources for Pulsed and CW Linacs

L-Band RF R&D. SLAC DOE Review June 15 th, Chris Adolphsen SLAC

Upgrade of CEBAF to 12 GeV

Pulsed Klystrons for Next Generation Neutron Sources Edward L. Eisen - CPI, Inc. Palo Alto, CA, USA

RF Upgrades & Experience At JLab. Rick Nelson

Detailed Design Report

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

ESS: The Machine. Bucharest, 24 April Håkan Danared Deputy Head Accelerator Division. H. Danared Industry & Partner Days Bucharest Page 1

LLRF at SSRF. Yubin Zhao

North Damping Ring RF

Towards an X-Band Power Source at CERN and a European Structure Test Facility

News from HZB / BESSY Wolfgang Anders at ESLS-RF Meeting September 2010 Trieste

RF Solutions for Science.

Evaluation of Performance, Reliability, and Risk for High Peak Power RF Sources from S-band through X-band for Advanced Accelerator Applications

RF Power Klystrons & 20 Year Look. R. Nelson 7/15/15

The basic parameters of the pre-injector are listed in the Table below. 100 MeV

WG2 Group Summary. Chris Adolphsen Terry Garvey Hitoshi Hayano

Linac 4 Instrumentation K.Hanke CERN

High Rep Rate Guns: FZD Superconducting RF Photogun

The PEFP 20-MeV Proton Linear Accelerator

SUMMARY OF THE ILC R&D AND DESIGN

RF considerations for SwissFEL

Development of Multiple Beam Guns for High Power RF Sources for Accelerators and Colliders

Performance of a DC GaAs photocathode gun for the Jefferson lab FEL

Current status of XFEL/SPring-8 project and SCSS test accelerator

Conceptual Design for the New RPI 2020 Linac

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

Present Status and Future Upgrade of KEKB Injector Linac

The LEP Superconducting RF System

Status and Plans for PEP-II

The ALS RF systems, upgrades and ALS-U plans

STATUS OF THE EUROPEAN XFEL CONSTRUCTING THE 17.5 GEV SUPERCONDUCTING LINEAR ACCELERATOR

The GRIFFIN Facility for Decay Spectroscopy at TRIUMF-ISAC

PHIN. Report on the Development of a Radio-Frequency Photo Electron Source with Superconducting Niobium Cavity (SRF Gun Realization)

A Cathode Development Cornell Cultera This scope includes all labor and purchases required produce photocathodes required by CBETA.

ANKA RF System - Upgrade Strategies

Technology Challenges for SRF Guns as ERL Sources in View of Rossendorf work

Availability and Reliability Issues for the ILC

ESS Linac WP8 Radio Frequency Systems and Test Facilities

KEKB INJECTOR LINAC AND UPGRADE FOR SUPERKEKB

The Construction Status of CSNS Linac

TECHNICAL SPECIFICATION Multi-beam S-band Klystron type BT267

ARIEL e-linac Machine Protection System Requirements

The Elettra Storage Ring and Top-Up Operation

DEVELOPMENT OF A 10 MW SHEET BEAM KLYSTRON FOR THE ILC*

Accelerator Division Plans:

A New 4MW LHCD System for EAST

CLIC Feasibility Demonstration at CTF3

RF Power Generation II

ESS Linac WP8 Radio Frequency Systems and Test Facilities

Preparations for Installation, Testing and Commissioning based on Experience at CERN, SNS and Siemens

Status of the FAIR Project. Jürgen Henschel FAIR Project Leader / Technical Director GSI & FAIR

Linac upgrade plan using a C-band system for SuperKEKB

SRF-gun Development Overview. J. Sekutowicz 17 th September, 2015 SRF15, Whistler, Canada

The SPL at CERN. slhc. 1. Introduction 2. Description. 3. Status of the SPL study. - Stage 1: Linac4 - Stage 2: LP-SPL - Potential further stages

J/NLC Progress on R1 and R2 Issues. Chris Adolphsen

Beam Loss Detection for MPS at FRIB

Cyclotron Institute upgrade project. H. L. Clark, F. Abegglen, G. Chubarian, G. Derrig, G. Kim, D. May, B. Roeder and G. Tabacaru

STATUS AND COMMISSIONING RESULTS OF THE R&D ERL AT BNL*

DELIVERY RECORD. Location: Ibaraki, Japan

Beam Losses During LCLS Injector Phase-1 1 Operation

Proton Engineering Frontier Project

STATUS OF THE SwissFEL C-BAND LINAC

30 GHz Power Production / Beam Line

Solid State Modulators for X-Band Accelerators

THE JLAB 12 GEV ENERGY UPGRADE OF CEBAF *

Jefferson Lab Experience with Beam Halo, Beam Loss, etc.

Commissioning the TAMUTRAP RFQ cooler/buncher. E. Bennett, R. Burch, B. Fenker, M. Mehlman, D. Melconian, and P.D. Shidling

Concept and R&D Plans for Project X

PoS(EPS-HEP2015)525. The RF system for FCC-ee. A. Butterworth CERN 1211 Geneva 23, Switzerland

Transcription:

Canada s national laboratory for particle and nuclear physics Laboratoire national canadien pour la recherche en physique nucléaire et en physique des particules ARIEL Buildings Construction and Electron Linac Photo-Fission Driver for the Rare Isotope Program at TRIUMF IPAC 12, 2012 May 21 Yu-Chiu Chao for e-linac team Accelerating Science for Canada Un accélérateur de la démarche scientifique canadienne Owned and operated as a joint venture by a consortium of Canadian universities via a contribution through the National Research Council Canada Propriété d un consortium d universités canadiennes, géré en co-entreprise à partir d une contribution administrée par le Conseil national de recherches Canada

Outline Motivation RIB science at ISAC ARIEL Civil Construction Stores & Badge Buildings Compressor Building ARIEL Targets and RIB Building E-hall renovation E-linac (the machine) E-Gun ELBT at VECC test area Cryomodules Cryogenic System HPRF Conclusion ARIEL E-linac, IPAC 12, 2012 May 21 2

ARIEL triples RIB science at ISAC New Mass Separators New Targets e-linac New Accelerators New Front End Cyclotron ISAC I ISAC II ARIEL I ARIEL II Existing 10-Year Vision: expanded RIB program with: three simultaneous beams increased number of hours delivered per year new beam species increased beam development capabilities Implementation: Complementary electron linac driver for photo-fission New target stations and front end New proton beamline Staged installation ARIEL E-linac, IPAC 12, 2012 May 21 3

Site Preparation: demolition, relocation, construction 2011 October CONGESTED SITE Old Stores &RH Demolition Excavation and shoring Makes way for ARIEL building New GHe compressor building New Stores building New Badge building ARIEL E-linac, IPAC 12, 2012 May 21 4

New Stores Bldg Ground Breaking: 2011 March Completion: 2011 September ARIEL E-linac, IPAC 12, 2012 May 21 5

New Badge Building Construction started: 2011 August Occupancy: 2011 November ARIEL E-linac, IPAC 12, 2012 May 21 6

Helium Compressor Building Ground breaking: 2012 March Foundations: 2012 May Expect occupancy: 2012 December ARIEL E-linac, IPAC 12, 2012 May 21 7

ARIEL building design The culmination of an intensive study of what is needed to facilitate smooth and routine RIB delivery. ARIEL E-linac, IPAC 12, 2012 May 21 8

ARIEL Layout below ground RIB front end BL4N protons Target Hall Actinide Annex Cyclotron vault Tunnel Electron Hall ARIEL E-linac, IPAC 12, 2012 May 21 9

Excavation, Shoring, Construction Excavation started: 2011 November Tunnel Actinide Labs Target Hall RIB Annex RIB front end ARIEL site: 2012 Jan Building occupancy expected: 2013 April ARIEL site: 2012 May ARIEL E-linac, IPAC 12, 2012 May 21 10

Electron Hall Renovation: Cleanout Electron Hall 2010 Oct Cyclotron vault Services Annex Proton hall clean up complete 2012 Feb Construction underway 2012 March Expect occupancy 2012 October 2012 Feb ARIEL E-linac, IPAC 12, 2012 May 21 11

Electron Hall Renovation: South shield wall 1st concrete pour 2012/March Shielding upgrades South wall B2 up to ground for ERL/RLA operation. Final S. wall pour, 2012/April ARIEL E-linac, IPAC 12, 2012 May 21 12

Electron Hall Renovation: North shield wall Poured-in-place concrete N. Wall (shield e-hall from BL4N) Rebar for N shield wall, 2012/April 1 st pour cured 2012/May ARIEL E-linac, IPAC 12, 2012 May 21 13

E-Linac: Accelerator Overview 300 kev thermionic gun: 650 MHz modulated NC Buncher Injector: SC Capture Cavities ARIEL Phase I: 25 MeV, 200kW 10 ma, 5-10 MeV gain 100 kw beam power Solenoid Installed Cryoplant for Phase I & II Accelerator: Two cryomodules Two cavities/module, 10 ma, 40 MeV gain 400 kw beam power ARIEL Phase II: 50 MeV, 500kW ARIEL E-linac, IPAC 12, 2012 May 21 14

300 kv 10 ma Electron Gun Gun assembly Detail design mostly complete Procurements in progress Installation begins: 2012 Sept HVPS SF6 Vessel Many long lead items already delivered: Ceramic, HVPS, ITX, RF Cathodes, Steering coils HV cage ARIEL E-linac, IPAC 12, 2012 May 21 15

Gun Components Ceramic Insulator Steering Coil Cathode Solenoid BeCu Anode ARIEL E-linac, IPAC 12, 2012 May 21 16

SF6 vessel & Gun RF modulation RF horns and ceramic waveguide Successful dielectric waveguide R&D program with scale model & HFSS Eimac cathode rf matching network Transmission optimized at 650 MHz RF modulation on 100kV prototype makes bunched beam at 650MHz RF power on grid used to generate duty factors 0.1% to 99.9% at rep rates 100Hz to 1kHz 10µs ARIEL E-linac, IPAC 12, 2012 May 21 17 17

ELBT at VECC test stand BPM Buncher BPM BPM Diagnostic Box #1 Allison Scanner. ARIEL E-linac, IPAC 12, 2012 May 21 18

Test 1 Configuration screen 100kV e-gun & solenoid Slit University of Victoria View Screen Profile Monitor 300 W Faraday cup Buncher Camera Turbo ARIEL E-linac, IPAC 12, 2012 May 21 19

VECC ELBT Test1 2011 Dec/2012 Feb 0 100 120 140 160 180-0.2-0.4-0.6-0.8-1 0.95 A 0.9 A 1.0A 1.05A 1.1A Slit scanner profile for various solenoid settings Allison emittance scans performed 2012 Feb 09 onward up to to 660W beam power at ~20W/mm 2011 Dec 07: Image of gun electron beam ARIEL E-linac, IPAC 12, 2012 May 21 20

Accelerator Cryomodule Jlab style Scissor-Tuner prototype Single-cavity EINJ prototypes most features of two-cavity EACA design. 2011 June: focus narrowed to completion of EINJ design, and fabrication in 2012 ARIEL E-linac, IPAC 12, 2012 May 21 Warm/cold Transition Ends 21

Injector Cryomodule Heat exchanger 4K separator Cryomodule concept borrows significantly from ISAC-II strongback 2K separator Power coupler Top loading box concept with cavity mounted to strongback that is suspended from struts Box gives headroom for on-board 2K/4K heat exchanger & 4K separator tuner cavity All procurements in hand Fabrication underway Cavity, 4K/2K insert (75% done) ARIEL E-linac, IPAC 12, 2012 May 21 22

Detail design complete: Cold mass support (strongback, struts), lid, cold mu-metal, scissor tuner Detail design in progress: Tank, warm/cold transition, LN2 shield Injector Cryomodule Detailing Completion milestone: ARIEL 2012 E-linac, IPAC June 12, 2012 May 1st 21 23

Cavity Status Success: 7 out of 7 PAVAC/TRIUMF singlecells meet requirements 7 cell Cu cavity delivered from PAVAC Nine cell cavity design fixed and contract signed Tooling optimized Four Nb half cells formed and welded ARIEL E-linac, IPAC 12, 2012 May 21 24

Cryogenic System Design/Procurement Liquid He @ 2K produced in cryo-modules by SA pumping elinac Cryomodules Subatmospheric Pumping system Compressor Compressor Liquid He @ 4K closed re-liquefaction/ refrigeration loop AND 77K LN system for He pre-cool. He Dewar Cold box Box Purity monitoring Purity monitoring (control) System Clean Helium Storage Tank Dirty Helium Storage Tank OR/GMS OR/GMS, Dryer, Purifier RT gaseous He. Emphasis on He purity White boxes: TRIUMF responsibility Pale blue boxes: cryoplant ordered from Air Liquide Advanced Technology, 2011 Oct ARIEL E-linac, IPAC 12, 2012 May 21 25

Helial Cold Box Supplied by ALAT Main Compressor Oil removal & Gas Management System Recovery Compressor Schedule 2013 March: ALAT cryoplant at TRIUMF 2013 October: commissioned Successful Final Design Review concluded 2012 May15 ARIEL E-linac, IPAC 12, 2012 May 21 26

Cryo-plant specs The plant shall demonstrate 3 modes: Mixed Mode: >130W @ 4,6K and 242 L/h rising level Pure Liquefaction: 288 L/h at 4.6K in the Dewar rising level Pure Refrigeration: 600W at 4.6K in the Dewar (expected) Mixed mode point Required load line ALAT load line ARIEL E-linac, IPAC 12, 2012 May 21 27

Other major components He buffer tanks: delivery expected 2013 Jan Dewar in hand; will widen neck He Purifier in design stage Cold Helium Distribution System: tender mid 2012 2K sub-atmospheric components: Pumps: tendere mid 2012 He heaters: prototyping He cold distribution and sub-atmospheric line Cold Box Tanks rated 15 Bara Capacity ~113 m 3 each LHe Dewar Accelerator cryomodules ARIEL E-linac, IPAC 12, 2012 May 21 15 Ω Resistive heater prototype 28

High Power RF staging: 5mA, 25 MeV in 2014 ACCELERATOR CRYOMODULE #1 300keV e-gun 5mA, 5MeV 50 kw coupler * 50 kw Couplers 5mA, 25MeV 1.3GHz NC Buncher Cavity INJECTOR CROMODULE 50 kw coupler 50 kw coupler 50 kw 30 kw Inductive Output Tube 270 kw Klystron ARIEL E-linac, IPAC 12, 2012 May 21 29

30 kw IOT Transmitter IOT transmitter will be used for EINJ beam test 2013 Jan; RF input coupler conditioning (10kW) 2012 March onward Pout & Gain 35 30 25 20 15 10 5 70 60 50 40 30 20 10 Efficiency 0 0 0.00 0.10 0.20 0.30 P input, mw Power Output, kw Gain, db Efficiency, % 2011 June: Tube operated tube in excess of 30kW 2011July: Successful acceptance tests: ran cw at 30 kw for 24 hours, at 25kW for 40 hours and at 20 kw for 7 days without trip. Now running routinely ARIEL E-linac, IPAC 12, 2012 May 21 30

Coupler Conditioning Stand in VECC test area ARIEL E-linac, IPAC 12, 2012 May 21 31

1.3 GHz 290 kw klystron & HVPS procurement Require 200kW cw for EACA (2-cavity) cryomodule 2011 Aug: 290kW Klystron ordered from CPI, USA Coordinated purchase with Helmholtz Zentrum Berlin 2012 June: Final design review 2012 Nov: klystron factory test 600kW High Voltage Power Supply 2012 Feb: Tender issued 2012 March: Tender closed Vendors under consideration Klystron predicted CW Power Output vs. RF Input Drive ARIEL E-linac, IPAC 12, 2012 May 21 32

Conclusion Outstanding Progress Across All Areas Buildings Construction on schedule for 2013 April Injector Cryomodule beam test on schedule for 2013 March Accelerator Cryomodule beam test on schedule for 2014 June ARIEL E-linac, IPAC 12, 2012 May 21 33

Cavity & HOM Damping 9 cell cavity Inner 7 cells TTF geometry Modified end groups for larger coupler &HOM damping HOM frequency spectrum and shunt resistance for 9-cell cavity 78mm 96 mm Minimal damping goal Achieved damping Ideal damping goal damper damper Two 50 kw Cornell/ CPI coupler per cavity HOM damping target set by Regenerative BBU (2-pass) 39/35/48 mm iris geometry gives the lowest maximal (Rd/Q) Q L Damping by SS ring on coupler end, CESIC ring on tuner end All modes (Rd/Q) Q L < 2 10 6 ohm ARIEL E-linac, IPAC 12, 2012 May 21 34

EINJ: Injector Cryomodule Detailing ARIEL E-linac, IPAC 12, 2012 May 21 35