RF Upgrades & Experience At JLab. Rick Nelson

Similar documents
RF Power Upgrade at Jefferson Lab

Upgrade of CEBAF to 12 GeV

Operating Experience and Reliability Improvements on the 5 kw CW Klystron at Jefferson Lab

RF Power Klystrons & 20 Year Look. R. Nelson 7/15/15

Introduction: CW SRF linac types, requirements and challenges High power RF system architecture

RF considerations for SwissFEL

Detailed Design Report

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

INFN School on Electron Accelerators. RF Power Sources and Distribution

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY

Spear3 RF System Sam Park 11/06/2003. Spear3 RF System. High Power Components Operation and Control. RF Requirement.

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

Pulsed Klystrons for Next Generation Neutron Sources Edward L. Eisen - CPI, Inc. Palo Alto, CA, USA

The LEP Superconducting RF System

CEBAF 8 kw CW KLYSTRON SPECIFICATION EE0043, Rev. H January 15, 1998

18 GHz, 2.2 kw KLYSTRON GENERATOR GKP 24KP 18GHz WR62 3x400V

CEBAF Accelerator Update. Michael Tiefenback CASA Accelerator Physics Experimental Liaison June 14, 2017

14 GHz, 2.2 kw KLYSTRON GENERATOR GKP 22KP 14GHz WR62 3x400V

XFEL High Power RF System Recent Developments

Next Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack

RF plans for ESS. Morten Jensen. ESLS-RF 2013 Berlin

9th ESLS RF Meeting September ALBA RF System. F. Perez. RF System 1/20

Low Level RF for PIP-II. Jonathan Edelen LLRF 2017 Workshop (Barcelona) 16 Oct 2017

IOT RF Power Sources for Pulsed and CW Linacs

High Brightness Injector Development and ERL Planning at Cornell. Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics

LLRF at SSRF. Yubin Zhao

ANKA RF System - Upgrade Strategies

A New 4MW LHCD System for EAST

A HIGH POWER LONG PULSE HIGH EFFICIENCY MULTI BEAM KLYSTRON

ILC-LNF TECHNICAL NOTE

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

Program Risks Risk Analysis Fallback Plans for the. John T. Seeman DOE PEP-II Operations Review April 26, 2006

Empirical Model For ESS Klystron Cathode Voltage

Beam Loss Detection for MPS at FRIB

RF Solutions for Science.

SRS and ERLP developments. Andrew moss

The PEFP 20-MeV Proton Linear Accelerator

NSLS-II RF Systems James Rose, Radio Frequency Group Leader PAC 2011

KEKB INJECTOR LINAC AND UPGRADE FOR SUPERKEKB

Synchrotron Light Facility. Operation of ALBA RF. Angela Salom on behalf of RF team: Francis Perez, Bea Bravo and Jesus Ocampo

RF Power Generation II

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

ANKA Status Report. N.Smale, on behalf of all ANKA colleagues, Directors : A.-S. Müller, C Heske, T Baumbach.

TOSHIBA Industrial Magnetron E3328

AREAL- Phase 1. B. Grigoryan on behalf of AREAL team

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

SLS RF operation report 2003

Jefferson Lab Experience with Beam Halo, Beam Loss, etc.

North Damping Ring RF

CEPC Klystron Development

MAXTECH, Inc. BRC-1000 Series. C-Band Redundant LNB Systems. Technology for Communications. System Block Diagrams

Linac3 experience for LHC ion runs

ESS Linac WP8 Radio Frequency Systems and Test Facilities

L-Band RF R&D. SLAC DOE Review June 15 th, Chris Adolphsen SLAC

Karin Rathsman, Håkan Danared and Rihua Zeng. Report from RF Power Source Workshop

INTEGRATED ASSEMBLIES MICROWAVE SOLUTIONS FROM TELEDYNE COUGAR

!"!3

Welcome and FRIB Project Status. FRIB Highlights and Plan Ahead

Pulses inside the pulse mode of operation at RF Gun

Dark current and multipacting trajectories simulations for the RF Photo Gun at PITZ

Power Amplifier 0.5 W 2.4 GHz AM TR Features. Functional Schematic. Description. Pin Configuration 1. Ordering Information

ModuMAX SSPA Systems. C, X, and Ku Bands. Completely modular solid-state power amplifier systems for world-wide satellite communications

Towards an X-Band Power Source at CERN and a European Structure Test Facility

650MHz/800kW Klystron Development at IHEP

Status of RF Power and Acceleration of the MAX IV - LINAC

A Unique Power Supply for the PEP II Klystron at SLAC*

PEP-II Overview & Ramp Down Plan. J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007

J/NLC Progress on R1 and R2 Issues. Chris Adolphsen

5 Project Costs and Schedule

Current status of XFEL/SPring-8 project and SCSS test accelerator

RSSL1:1-KuXER. Outdoor Unit (ODU) Ku Ext Ref LNB Redundancy System with external 10 MHz Reference System. Mux/Tee. Coax cable

The Elettra Storage Ring and Top-Up Operation

Application Note 5098

An Operational Diagnostic Complement for Positrons at CEBAF/JLab

K800 RF AMPLIFIER TUBE UPGRADE

THE JLAB 12 GEV ENERGY UPGRADE OF CEBAF *

Key Features and functions. General Description

6MSD Weekly Scheduling Meeting. 1:30, MCC Conference Room

SPINNER BROADCAST EXPLANATION OF THE MULTI CHANNEL COMBINER SPECIFICATIONS

Digital BPMs and Orbit Feedback Systems

DA E: Series of Narrowband or Wideband Distribution Amplifiers

Review of Diamond SR RF Operation and Upgrades

Evaluation of Performance, Reliability, and Risk for High Peak Power RF Sources from S-band through X-band for Advanced Accelerator Applications

PoS(EPS-HEP2015)525. The RF system for FCC-ee. A. Butterworth CERN 1211 Geneva 23, Switzerland

SMTF Beta <1 Front End Linac Infrastructure and Plans

TECHNICAL SPECIFICATION Multi-beam S-band Klystron type BT267

Solid State Modulators for X-Band Accelerators

Ku-Band Redundant LNB Systems. 1:1 System RF IN (WR75) TEST IN -40 db OFFLINE IN CONTROLLER. 1:2 System POL 1 IN (WR75) TEST IN -40 db POL 2 IN

The ESRF Radio-frequency Data Logging System for Failure Analysis

ANKA Status Report. N.Smale, A.-S. Müller, E. Huttel, M.Schuh Slides courtesy of A.-S. Müller and C.Heske.

Basic rules for the design of RF Controls in High Intensity Proton Linacs. Particularities of proton linacs wrt electron linacs

The TESLA RF System. S. Choroba. for the TESLA Collaboration. DESY Notkestr. 85, D Hamburg, Germany

DEVELOPMENT OF A 10 MW SHEET BEAM KLYSTRON FOR THE ILC*

CLIC Feasibility Demonstration at CTF3

Jae-Young Choi On behalf of PLS-II Linac team

US-ILC Waveguide Industrialization Study. Marc Ross, Chris Nantista and Chris Adolphsen

Non-Invasive Energy Spread Monitoring for the JLAB Experimental Program via Synchrotron Light Interferometers

Transcription:

RF Upgrades & Experience At JLab Rick Nelson

Outline Background: CEBAF / Jefferson Lab History, upgrade requirements & decisions Progress & problems along the way Present status Future directions & concerns

CEBAF at Jefferson Lab Design 4 GeV, 200 ua 3 Experimental Halls Present (pre-upgrade) 6 GeV, 200 ua Upgrade 3 Experimental Halls 11 GeV, 200 ua 3 Experimental Halls 12 GeV, 200 ua 4 th Hall D only

From 6 to 12 GeV Upgrade magnets and power supplies CHL-2 Upgrade Existing Halls

RF Upgrades Original 42.5 cryomodules/338 SC cavities 340 klystrons: 5 to 6.5 kw CW, 1497 MHz Upgrade C25, C50 cryomodules 10 cryomodules, 80 SC cavities 80 klystrons: 13 kw CW, 1497 MHz New designs for klystrons, power supplies, circulators, controls

Energy Content (Norm.) Key RF Requirements 10 new zones of RF power for new accelerating structures: 1497 MHz Operating Gradients Required >17.5 MV/m RF Power per cavity 13 kw saturated Regulation requirements (table) Cavity Q L 2x10 7 1.0 0.9 0.8 0.7 0.6 0.5 0.4 0.3 Phase Stability (rms) Amplitude (rms) Master Oscillator EPICS IOC Ethernet LLRF Controls Fast ( <1sec) Ethernet High Voltage Power Supply Klystron Slow (>1sec) 0.5º 3.0º 4.5x10-4 NA 8 0.2 0.1-600 -500-400 -300-200 -100 0 Detuning (Hz) 0.0 Superconducting Cavity Cavity de-tuning curve

1 per cavity (existing configuration) Minimum impact of failures How Many RF Sources? 1 per zone or 1 per linac Larger impact on faults High power splitters High power amplitude and phase control required with high precision. Additional controls and high power modulators found to be more $$ than individual RF sources. Single LINAC upgrade shown

CEBAF Klystrons Compared Parameter Power Old Spec 5 to 8 New Spec Actual Units 13 13 KW Center frequency 1497 1497 1497 MHz Bandwidth, -1dB 5 5 5+ MHz Bandwidth, -3 db 6 6 6+ MHz 0.5 db incremental gain at 4 10 meets kw Efficiency (at rated power) 32 >50 50.9 % Gain 38 >42 >50 db Harmonics -20-20 meets dbc Beam voltage 11.6 <16 14.5 kv DC Heater voltage 7.3 7.3 7.0 typ V DC Modulating anode Yes Yes Yes Isolated collector Yes Yes Yes Cavities/Resonators 4 5 5 Focus PM EM ~900 Watts

Each system powers 8 klystrons (as before) Resonant mode switcher design (15-20 KHz) 4 separate supplies. Each feeds 2 klystrons Minimizes klystrons taken offline due to power supply failure Controlled as a unit Each adjustable to -15kV 15 A total Design adapted from electrostatic precipitator application (higher volts/lower amps & in oil) 1000+ units in the field at award Highly tolerant to load faults HV DC Power Supply Lower stored energy than T-R, fast turn off on fault, series resistor limits output current (no crowbar)

Additional Views HV Deck (4 per system, on rollers) Rear View

Typical RF Installation All zones installed and commissioned with beam

Tunnel Connections Waveguide installation

RF Commissioning Selected Data Commissioned w/ Beam Commissioned w/o Beam Zone/ Cavity Gradient Cryomodule Energy Gain Beam Current Zone/ Cryomodule Gradient Cavity Energy Gain Beam Current SL24 SL23 1 15 100 1 20.4 NA 2 13.9 100 2 18.4 NA 3 13.4 100 3 19.4 NA 4 15.4 100 4 18 NA 5 19 100 5 21.4 NA 6 20 100 6 20.6 NA 7 17.7 100 7 22.2 NA 8 14.7 100 8 15.8 NA Total 129.1 90.37 100 Total 156.2 109.34 SL25 SL22 1 19.5 465 1 12 NA 2 20.5 465 2 21.2 NA 3 18.7 465 3 18.5 NA 4 20.5 465 4 20.2 NA 5 19 465 5 18.7 NA 6 20.1 465 6 20.7 NA 7 17.5 465 7 20.2 NA 8 18.5 465 8 20 NA Total 154.3 108.01 Total 151.5 106.05

Good & Bad Results Not all according to plan usual problems Delivery delays on several key components Klystron & general WG close to schedule HOM filters, isolators, solenoid power delayed Revisions and rework One contract cancellation Multiple installation delays with starts & stops Budget problems Reassignment of workforce Rework and reinstallation

Waveguide Isolators 13 kw CW, full reflection 0.2 db insertion loss 21 db isolation (any phase & power) Water cooled PM only - no TCU Operates adjacent to others Awarded to Ferrite (who supplied 350+ units for CEBAF) Full power testing at JLab Vendor capabilities missing Several rounds of testing with sliding short Using FA klystron at L-3 At JLab using 2 x 6.5 kw and 13 kw klystron

Events Initial tests looked OK and first lots were installed Initial tests into WG shorts not as good Results not repeatable/consistent Performance different for distance to short Two rounds of measurements & adjustments to understand the fix Next production units still variable

Testing

Sensitive to Match & Phase Isolation affected by Ferrite temperature Magnetic field strength These may be adjusted to maintain good performance Less field needed at higher temperature Solutions include TCU, active field control (VSWR) Automatically handled in small units Reflected phase Match (all ports) 2 of 3 need to be good for high isolation Load OK, short bad, klystron needs to be good (but not easily measured)

Early Test Results 35 11.5" short iso 30 25 20 15 Iso-J1223 11.5" Iso-J1196 Iso-J1204 iso 1210 iso 1229 Iso-J1219 Iso-J1217-10" Iso-J1217-11.5" Iso-J1199-11.5" Iso-J1209-10" Iso-J1209-11.5" 10 0 2 4 6 8 10 12

Early Test Results

Isolation (db) Isolation vs. Short Position 40 35 30 25 20 Iso-J1612-11" Iso-8.5" Iso-10" 15 10 0 1 2 3 4 5 6 7 8 9 10 11 12 Forward Power (kw)

Temperature Initial measurements done steady-state Find position for lowest isolation Changes observed at turn-on Concerns for off-resonance conditions at turn-on Avoid tripping on high reflected power 8 units per RF zone; different distances to cavities

power (dbm) Isolation vs. Heating/Time 75 27 70 25 65 23 60 55 50 21 19 forward-0 reverse-0 isolation-0 45 17 40 15 00:00.0 00:08.6 00:17.3 00:25.9 00:34.6 00:43.2 00:51.8 01:00.5 01:09.1 Elapsed time (seconds) RF heating of ferrite resulted in significant changes over (short) time

Adjusting Magnetic Fields Isolation response at 10+ kw vs Magnet Count 30 29 28 27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 00:00.0 00:08.6 00:17.3 00:25.9 00:34.6 00:43.2 00:51.8 01:00.5 01:09.1 isolation-0 isolation-1 isolation-2 Isolation-3 isolation-4

Isolator

Tuning

Resolution Vendor reworked dome new domes & rebuilds Results were still inconsistent Something being missed during setup Ultimately all setup the same, but fine-tuned at Jlab 100% re-tested at high power Reflected power well below threshold for klystron damage or performance degradation Solution meets operational needs including credible fault conditions All 84 units modified, tested, reinstalled Extra work since all units were installed/removed/reinstalled.

Isolation (db) Isolation vs. Short Position Iso-J1612 35 30 25 20 15 Iso-J1612 10 5 0 7 8 9 10 11 12 13 Short Position (inches)

HOM Filters Uncertainty of need Originally not needed so not ordered Directions changed, but only 2 of 8 caviteis expected cavities (later testing confirmed) Normal procurement process Final filters essentially identical to what we had from multiple purchases Small tweaks to reduce fundamental absorption Manufacturing relied on external shops (as before) Vendor a small concern, limited resources & staff Fabrication subcontracted (metal fab, Iridite, dip brazing) Dummy spool pieces installed in other positions Had expected this to come in last

Klystron HV PS Performance has been good overall Switcher design and controls work well - good reliability DSP-based controls with hardware safety interlocks Code changes needed to address timing issues 1 unit tested OK, but all 4 might trip external breaker Extended step-start to deal with high inrush & breaker trips Possible race condition for contactor control vs. status reporting (several contactors changed but seem to be OK) Control transformers (480:120) shorted out Loose connections/loosening connections Contactors, IGBT Suggestion: check everything carefully! No similar problems with old supplies, but a lot less connections DC power guys regularly check transistor connections New doesn t mean perfect -- especially after x-country trips A couple noticeable events

Installation Challenges Funding shortages resulted in work reassignments & delays Techs reassigned to dismantle other systems Start/stop/start not efficient and required relearning

Maintenance Issues New systems to be learned and maintained New systems to be checked closely Old systems getting older and more frail Significant PM planned for summer

A Year for Water Brazing issues and water leaks Multiple new components, nuisance problems Both believed to be of similar origin but different suppliers Pressure tested (but not long enough) Trapped flux dissolved out resulted in small leaks on a few pieces Circulator load assemblies New loads built, and testing refined Solenoid leaks on plumbing Longer pressure testing with hot water HOM dip braze excesses Control transformers shorted (purchased by vendor)

Ongoing Circulator (old style) Reliable for a lot of years, but load failures becoming more frequent LC DI water 15 years+ erosion and leaching Self-rebuilding w/o retuning Same load back to its circulator New circulator loads won t experience this failure mode

Water Flows Downhill All LCW was turned off during extended down (~1 year) Circulator load seals lost their seal Water in select waveguides (not our selection) Water level horizontal run Bleed hole was for air

Summary All new LINAC RF has been installed and commissioned Operating requirements met, though staff are still learning differences from old systems Maintenance activities scheduled for summer down old and new systems Lobby to purchase spares with new equipment Costs more later and may be too late Monitor procurements closely, start early