Status and Plans for PEP-II

Similar documents
Program Risks Risk Analysis Fallback Plans for the. John T. Seeman DOE PEP-II Operations Review April 26, 2006

PEP II Design Outline

PEP II STATUS AND PLANS *

PEP-II Overview & Ramp Down Plan. J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007

PEP II Status and Plans

PEP-II Status and Outlook

PEP-II STATUS REPORT *

PEP II Status. H. - Ulrich (UZi) Wienands PEP-II Run Coordinator. SLAGEPAC Meeting November 8,200O. Intro; 11/7/O 19:55

PEP-II Status. U. Wienands, PEP-II Run Coordinator for the PEP-II team

ABORT DIAGNOSTICS AND ANALYSIS DURING KEKB OPERATION

SPEAR 3: Operations Update and Impact of Top-Off Injection

CONSTRUCTION AND COMMISSIONING OF BEPCII

KEKB Accelerator Physics Report

PEP-I1 RF Feedback System Simulation

North Damping Ring RF

Spear3 RF System Sam Park 11/06/2003. Spear3 RF System. High Power Components Operation and Control. RF Requirement.

!"!3

4.4 Injector Linear Accelerator

2008 JINST 3 S LHC Machine THE CERN LARGE HADRON COLLIDER: ACCELERATOR AND EXPERIMENTS. Lyndon Evans 1 and Philip Bryant (editors) 2

LEPTON COLLIDER OPERATION WITH CONSTANT CURRENTS Λ

KEKB INJECTOR LINAC AND UPGRADE FOR SUPERKEKB

LCLS RF Reference and Control R. Akre Last Update Sector 0 RF and Timing Systems

LHC Beam Instrumentation Further Discussion

Present Status and Future Upgrade of KEKB Injector Linac

SLAC ILC Accelerator R&D Program

Phase (deg) Phase (deg) Positive feedback, 317 ma. Negative feedback, 330 ma. jan2898/1638: beam pseudospectrum around 770*frev.

LEP Status and Performance in 2000

Design Studies For The LCLS 120 Hz RF Gun Injector

TWO BUNCHES WITH NS-SEPARATION WITH LCLS*

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting

ANKA RF System - Upgrade Strategies

The Elettra Storage Ring and Top-Up Operation

Detailed Design Report

A Facility for Accelerator Physics and Test Beam Experiments

LCLS Injector Technical Review

The LEP Superconducting RF System

Accelerator Instrumentation RD. Monday, July 14, 2003 Marc Ross

Synchrotron Light Facility. Operation of ALBA RF. Angela Salom on behalf of RF team: Francis Perez, Bea Bravo and Jesus Ocampo

SLAC R&D Program for a Polarized RF Gun

News from HZB / BESSY Wolfgang Anders at ESLS-RF Meeting September 2010 Trieste

30 GHz Power Production / Beam Line

MULTI-BUNCH INSTABILITY DIAGNOSTICS VIA DIGITAL FEEDBACK SYSTEMS AT PEP-II, DAæNE, ALS and SPEAR

J/NLC Progress on R1 and R2 Issues. Chris Adolphsen

SuperTRISTAN. A possibility of ring collider for Higgs factory. 13 Feb K. Oide (KEK)

FIRST SIMULTANEOUS TOP-UP OPERATION OF THREE DIFFERENT RINGS IN KEK INJECTOR LINAC

Status of CTF3. G.Geschonke CERN, AB

ANKA Status Report. N.Smale, A.-S. Müller, E. Huttel, M.Schuh Slides courtesy of A.-S. Müller and C.Heske.

PoS(EPS-HEP2015)525. The RF system for FCC-ee. A. Butterworth CERN 1211 Geneva 23, Switzerland

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

PEP-II IR-2 Alignment

SUMMARY OF THE ILC R&D AND DESIGN

Andrei Seryi, Toshiaki Tauchi. December 15-18, 2008

A Fifteen Year Perspective on the Design and Performance of the SNS Accelerator

CEBAF Accelerator Update. Michael Tiefenback CASA Accelerator Physics Experimental Liaison June 14, 2017

ARES Status 2004(JFY)

PEP-II Operation and Machine Development. U. Wienands PEP-II Run Coordinator for the PEP-II Team

First Simultaneous Top-up Operation of Three Different Rings in KEK Injector Linac

Status of Elettra, top-up and other upgrades

IOT OPERATIONAL EXPERIENCE ON ALICE AND EMMA AT DARESBURY LABORATORY

PEP-II longitudinal feedback and the low groupdelay. Dmitry Teytelman

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

CESR BPM System Calibration

beam dump from P2 losses this morning

A HIGH POWER LONG PULSE HIGH EFFICIENCY MULTI BEAM KLYSTRON

Operational Status of PF-Ring and PF-AR after the Earthquake

New Filling Pattern for SLS-FEMTO

Report on the LCLS Injector Technical Review

Diamond RF Status (RF Activities at Daresbury) Mike Dykes

CLIC Feasibility Demonstration at CTF3

What can be learned from HERA Experience for ILC Availability

OPERATIONAL EXPERIENCE AT J-PARC

P. Emma, et al. LCLS Operations Lectures

PEP-II Disassembly Technical Systems

Evaluation of Performance, Reliability, and Risk for High Peak Power RF Sources from S-band through X-band for Advanced Accelerator Applications

Next Linear Collider. The 8-Pack Project. 8-Pack Project. Four 50 MW XL4 X-band klystrons installed on the 8-Pack

Pulsed Klystrons for Next Generation Neutron Sources Edward L. Eisen - CPI, Inc. Palo Alto, CA, USA

High Brightness Injector Development and ERL Planning at Cornell. Charlie Sinclair Cornell University Laboratory for Elementary-Particle Physics

Beam systems without failures what can be done?

Photo cathode RF gun -

Status of SOLARIS. Paweł Borowiec On behalf of Solaris Team

June 2005 Advanced Electronics Group, ARDA

Production of quasi-monochromatic MeV photon in a synchrotron radiation facility

Focus of efforts. ILC 2010, Mar/27/10 A. Seryi, BDS: 2

SRS and ERLP developments. Andrew moss

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

RADIATION SAFETY SYSTEM OF THE B-FACTORY AT THE STANFORD LINEAR ACCELERATOR CENTER

Top-Up Experience at SPEAR3

STATUS OF THE INTERNATIONAL LINEAR COLLIDER

Feedback Control of SPS E-Cloud/TMCI Instabilities

Concept and R&D Plans for Project X

Challenges in Accelerator Beam Instrumentation

Linac upgrade plan using a C-band system for SuperKEKB

A New 4MW LHCD System for EAST

SLAC ILC program, International BDS Design, ATF2 facility

Upgrading LHC Luminosity

The basic parameters of the pre-injector are listed in the Table below. 100 MeV

Overview of the X-band R&D Program

ANKA Status Report. N.Smale, on behalf of all ANKA colleagues, Directors : A.-S. Müller, C Heske, T Baumbach.

DESIGN AND PERFORMANCE OF L-BAND AND S-BAND MULTI BEAM KLYSTRONS

Precision measurements of beam current, position and phase for an e+e- linear collider

Transcription:

Status and Plans for PEP-II John Seeman SLAC Particle and Particle-Astrophysics DOE HEPAP P5 Review April 21, 2006

Topics Luminosity records for PEP-II in October 2005 Fall shut-down upgrades Run 5b turn on Two vacuum issues arose and were solved. Status of upgrade efforts Future schedule PEP-II luminosity projections

The PEP-II Team Accelerator Systems Division SLAC Support Groups BaBar LBNL ILC Machine Advisory Committee 1x10 34

PEP-II Interaction Region Components near BaBar LER HER BaBar Collision point

Luminosity: Run 5 April 2005-2006 P5 10 34 Fall down Vacuum issues MAC Ecklund

Sullivan

PEP-II Progress since October 2005 Installation down (Oct 10-Nov 15). One new IR chamber Improved IR NEG pumps Position monitor upgrades Abort window spoiler Safety upgrades. IP dither feedback coils Turned on November 15. Luminosity rose quickly and reached 0.86 x 10 34 /cm 2 /s in mid-december. Successfully ran PEP-II through the year-end holidays Two vacuum issues came up in December 2005.

PEP-II Machine Advisory Committee Meeting: January 18-20, 2006 Members: D. Rice (chair), J. Corlett, K. Harkay, S. Henderson, I. Koop, J. Marriner, K. Oide, D. Rice, D. Rubin, L. Bertolini, F. Pedersen, P. Raimondi Report available. Words from report: Impressive progress in all areas since the last the review a year before. Congratulates achievement of 10 34 luminosity (3.3 x design). Trickle charge injection is very effective. Accelerator plan is sound for optimizing the collider productivity though FY2008 Vacuum burst studies are being intensely investigated. [Committee made several suggests what to look for.] Suggest re-examine increasing the specific luminosity.

Two Vacuum Issues in December 2005 Two major vacuum problems developed in the month of December limiting the peak luminosity to about ~0.5 x 10 34 /cm 2 /s: Gap ring (RF seal) problem near LER RF cavity caused e + beam instability Higher Order Mode absorbing bellows caused vacuum bursts in IR The first problem was quickly identified (~ 2 weeks) and solved in late January. The second problem was thoroughly investigated, replacement parts manufactured, and repaired in late March with elapsed time of about three months.

LER Current in Run 5 2.95 A Fall down Vacuum issues

Location of the First Vacuum Problem Vacuum spike area RF seal installation procedure problem

Second Vacuum Event: BaBar Background Trip Vacuum Spikes

December 25, 2005 High LER+HER Current Causes Radiation Trips Clear current threshold

PEP-II Task Force Structure addressed the issue April 2006

IP Vacuum Issue Resources Help from many groups: PEP-II, BaBar, Material Science Group, Klystron Dept., High Power RF Group, Vacuum Dept., Pulsed Kicker Group, and LBNL. Many studies done: Beam current thresholds Beam instability identification External leak checks Transient leak checks during spikes Gas pressure profiles Gas pressure flow rates Gas injections (puffs) (He, N2, Air) (various locations) Transient gas analysis during spikes NEG pump heating to make H2 gas Background timing with BaBar Borescoped 100 m of vacuum chamber (several times) Replaced RF seals and four vacuum chambers SiC-AlN HOM tile lab tests and thermal calculations This vacuum problem was the most subtle and hard to diagnose problem PEP-II has had. However, we solved it in a timely way over two months with a strong team. In the end as will be shown later, the chamber at fault was anticipated to be a long term problem and was scheduled to be replaced in Fall 2006 (AIP project). (The problem came 6 months too early!)

PEP- II Linac Accelerator Systems Department

LER Forward Q4 Location

PEP- II Linac Accelerator Systems Department

Discharge on Absorbing Tile SiC/AlN HOM Tile Arc site Cu heat sink RF seal fingers

New RF seal to correct problem: New seat on Cu base not tile N. Kurita

New HOM bellows design for Fall 2006 N. Kurita Novokhatski Weathersby April 2006 Tiles behind Fingers

Recent Run Results Vacuum work

Delivered luminosity matches prediction since March 1. Today FFTB removal delay Prediction start date Vacuum repair April 20, 2006

PEP-II Long Term Run Schedule Run 5b: November 2005-July 2006 Down: August-November 2006 (Major upgrades for PEP-II & BaBar + LCLS installation) Run 6: December 2006-August 2007 Down: September-November 2007 (PEP-II one month + LCLS installation) Run 7: December 2007-September 2008.

PEP-II Overall Parameters and Goals Parameter Units Design Present best 2007 goal I+ ma 2140 2940 4000 I- ma 750 1740 2200 Number bunches 1658 1732 1732 β y * mm 15-20 11 8-8.5 Bunch length mm 15 11-12 8.5-9 ξ y 0.03 0.044-0.065 0.054-0.07 Luminosity x10 33 3 10 20 Int lumi / day pb -1 130 727 1300 Over three times design Five times design

Integrated Luminosity Projection March 1, 2006 2006 down 2007 down Now

PEP-II Upgrades Goal: A factor of two in PEP-II luminosity (1 2 x10 34 /cm 2 /s) will come from: Increasing each beam current by 40%. Lowering β y * from 11 to 8.5 mm giving 30%. Increasing the beam-beam parameters by 10%. Keeping detector backgrounds at the predicted levels. Maintaining (and improving) accelerator reliability.

Upgrade Planning and Execution The items to upgrade PEP-II have been identified by the PEP-II Task Forces. Engineering has been done on most items and these items are in manufacturing. A few items are in final design review to start manufacturing in about one month. Funding is in place for all PEP-II items. Detailed time planning for the fall down has started with every task being identified with loading for the various shops. Interferences with BaBar and LCLS are being worked out months in advance to minimize problems.

Many of the new vacuum chambers for higher current are near the IP Dots show new vacuum chamber locations. Done March 2006 Recent problem bellows Done October 2005

Accelerator Improvement Projects on track for Fall 2006 X-Y BPM upgrades 2005-2006 New HER Q5 vacuum chambers 2005-2006 New HER/LER Q2 chambers 2006 HER-10 RF station 2006 HER-11 RF station 2006 HER power supply upgrade for higher tunes 2006 New HER Q4 vacuum chambers 2006 New IR2 Q2 bellows 2006 LER IR HOM absorber 2006 HER IR HOM absorber 2006 LER BPM monitor upgrade 2006 LER new high power bellows 2006 LER NEG vacuum chamber upgrade 2006 New Longitudinal feedback processor 2006 Cost of AIP projects is about 7 M$ spread over FY2006 and FY2007. PEP-II AIP expenditures from 1999-2005 averaged about 5 M$ each year.

B-Factory RF Klystrons (1.2 MW) under construction

Example: HER QF5R Chamber (Fall 2006) Specifications R. Pope Construction Design

LER/HER Q2 IR Vacuum Chamber (Fall 2006 March 2006) Thermal analysis of synchrotron radiation power (~100 W/cm) NEG Vacuum Pump S. Metcalfe High power separation chamber

PEP-II Accelerator Technology for Future Accelerators High beam currents World record e + current (2.95 A) World record e - current (1.75 A) High power vacuum chamber design Large number of bunches World record number of colliding bunches (1732) Very fast and strong bunch-by-bunch feedbacks (4 nsec) Electron Cloud Instability (ECI) cures (solenoids, antechambers) High power RF systems >1.2 MW CW klystrons 476 MHz High power Cu cavities (600 kw) Complex interaction region design with two rings PEP-II provides continued strong input into new accelerator designs: ILC damping rings, low emittance light sources (PETRA-3), Super-B Factories, LHC ECI, BEPC-II,

PEP-II Conclusions PEP-II achieved a new luminosity level (1x10 34 ) and set several integrated luminosity records. Run 5b started well but two serious vacuum problems occurred keeping the luminosity peak to about half the former peak. Both vacuum problems have been identified with the help of many people and experiments and have been solved in a timely way. Over past two weeks, the luminosity has risen steadily to >0.8x10 34 with many 500-600 pb -1 days. Planned upgrades towards ~2 10 34 are on track. Run plans are in place with a target of ~1 ab -1 in 2008. We strongly believe that the combined performance of PEP-II and BaBar will remain competitive through 2008.