Alberta Electric System Operator

Size: px
Start display at page:

Download "Alberta Electric System Operator"

Transcription

1 Decision D Downtown Calgary 138-kV Transmission System Reinforcement June 1, 2016

2 Alberta Utilities Commission Decision D Downtown Calgary 138-kV Transmission System Reinforcement Proceeding Application A001 June 1, 2016 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary, Alberta T2P 3L8 Telephone: Fax: Website:

3 Alberta Utilities Commission Calgary, Alberta Decision D Downtown Calgary 138-kV Proceeding Transmission System Reinforcement Application A001 1 Decision summary 1. In this decision, the Alberta Utilities Commission must decide whether to approve an application submitted by the (AESO) for the Downtown Calgary 138-kilovolt (kv) Transmission System Reinforcement. After consideration of the record of the proceeding, and for the reasons outlined in this decision, the Commission finds the AESO s assessment of the need to be correct and in the public interest and approves the AESO s needs identification document application. 2 Introduction and background 2. The AESO filed an application with the Commission seeking approval of a needs identification document (NID) for the Downtown Calgary 138-kV Transmission System Reinforcement (the transmission development). The transmission development includes a new 138-kV transmission line between the existing ENMAX No. 2 and ENMAX No. 8 substations. The application was registered on November 18, 2015 as Application A The Commission issued information requests to the AESO on December 14, The AESO responded to the information requests on January 21, On December 14, 2015, the Commission issued a notice of application for Proceeding Submissions to the Commission in response to the notice were due on January 11, The notice was sent through unaddressed mail via postal code to all occupants, residents, and landowners located in the area where the AESO had indicated that the transmission development may occur. The notice was also sent via addressed mail to government bodies, agencies and other stakeholders identified by the AESO. The notice was published in the Calgary Herald and the Calgary Sun on December 18, The notice was also published on the AUC website and notification was automatically ed to efiling System users that had chosen to be notified of notices of application issued by the Commission. 5. In response to the notice, the Commission received statements of intent to participate from ENMAX Power Corp. (ENMAX) and the following landowners: Mary Van Order Ray Chow Paul Featherstone Decision D (June 1, 2016) 1

4 Anca Medesan Fort Calgary Preservation Society 6. The Commission issued a ruling dated February 19, 2016, granting standing to all parties that had filed statements of intent to participate The Commission issued a notice of hearing on March 11, 2016 informing parties that it would consider the application through a written process. The notice provided details of the application and a schedule of the remaining process steps for consideration of the application. 8. On March 18, 2016, ENMAX requested that the Commission include an information request process in the schedule because doing so may eliminate the need for ENMAX to submit written evidence. In a letter dated March 23, 2016, the Commission granted ENMAX s request and provided a process schedule for interveners to ask the AESO information requests and for the AESO to respond. 9. On April 26, 2016, after the AESO responded to the interveners information requests, the City of Calgary filed a statement of intent to participate, in which it indicated that the AESO s response to ENMAX s information request had raised a new issue that had a direct bearing on the City of Calgary. The City of Calgary requested intervener status in the proceeding. In a ruling dated April 28, 2016, the Commission granted standing to the City of Calgary. 2.1 The process for new transmission development in Alberta 10. Except in the case of critical transmission infrastructure, two approvals from the Commission are required to build new transmission capacity in Alberta. First, an approval of the need for expansion or enhancement to the Alberta interconnected electric system pursuant to Section 34 of the Electric Utilities Act is required. Second, a permit to construct and a licence to operate a transmission facility pursuant to sections 14 and 15 of the Hydro and Electric Energy Act must be obtained. 11. The AESO, in its capacity as the independent system operator (ISO) established under the Electric Utilities Act, is responsible for preparing a NID and filing it with the Commission for approval pursuant to Section 34 of the Electric Utilities Act. As stated above, this NID application was filed on November 18, In Decision , the Commission s predecessor, the Alberta Energy and Utilities Board (Board), described the NID process as follows: It is the Board s view that section 34 contemplates a two-stage consideration of an NID. In the first stage, the Board must determine whether an expansion or enhancement of the capability of the transmission system is necessary to alleviate constraint, improve efficiency, or respond to a request for system access 1 Exhibit X0029, AUC Ruling on Standing, February 19, Decision D (June 1, 2016)

5 14 ST. SW BLACKFOOT TR. MACLEOD TR. CENTRE ST. Downtown Calgary 138-kV Transmission System Reinforcement If it is determined that expansion or enhancement of the system is required to address constraint, inefficiency, system access requests, or any combination thereof, the Board must then assess, in the second stage, whether enhancement or expansion measures proposed by AESO are reasonable and in the public interest. 13. Facility applications are prepared by the transmission facility owner assigned by the AESO. ENMAX is the transmission facility owner in the downtown Calgary area. No application for the facilities to meet the need identified by the AESO has been received. Should the Commission approve the AESO s application, the Commission anticipates that ENMAX will file a facility application to construct and operate the facilities for the transmission development. 3 Discussion 3.1 Views of the applicant 14. In its application, the AESO explained that the need for the transmission development is predominately driven by increasing demand in the downtown Calgary area. To ensure system reliability, additional reinforcement of the existing transmission system is required. The transmission development would reinforce the downtown Calgary transmission system by connecting the ENMAX No. 2 and ENMAX No. 8 substations with a 138-kV transmission line which may be routed within the shaded area as identified in the following map: DEERFOOT TR. ENMAX NO. 8 SUBSTATION 9 AVE. S BOW RIVER MEMORIAL DR. 17 AVE. SW CROWCHILD TR. 25 AVE. SE ENMAX NO. 2 SUBSTATION APPROXIMATE AREA WHERE TRANSMISSION LINE COULD BE LOCATED 15. The AESO also proposed to modify equipment at the substations, including adding a new 138-kV circuit breaker to the ENMAX No. 8 substation. 16. The AESO submitted that system studies indicated that the transmission system in the downtown Calgary area would be prone to overload under single contingency conditions. The studies showed that in the event of an outage of transmission line 2.83L, transmission line 2.82L would experience a thermal overload of nine per cent in 2017 under summer peak loading conditions. The severity of this thermal overload would increase as time progresses and would Decision D (June 1, 2016) 3

6 reach up to 42 per cent in the 20 year planning horizon as load in the area continues to grow. In addition, transmission line 2.83L would experience a thermal overload if there was an outage of transmission line 2.82L. 17. The AESO utilized a low-growth scenario because it determined that the 2014 Long-term Outlook overestimated the load growth potential for the downtown Calgary area. The AESO also utilized a sensitivity scenario that further decreased the expected load growth because of the recent historical peak load levels. The AESO stated that the constraints identified above would arise as early as the summer of 2017 using the low-growth scenario, but would not arise until the summer of 2021 when the sensitivity scenario is factored into the analysis. 18. In order to alleviate the identified constraint, the AESO considered two alternatives to expand and enhance the downtown Calgary transmission system. The AESO proposed one new 138-kV transmission circuit, with a minimum capacity in the order of 300 megavolt-ampere (MVA), between the ENMAX No. 2 and ENMAX No. 8 substations (the 138-kV option). The AESO also considered an alternative option of installing a 240-kV transmission circuit that would be initially energized at 138-kV but could be expanded to 240-kV in the future (the 240-kV option). 19. The AESO provided initial estimates that the 138-kV option would cost approximately $144 million (+/- 30 per cent, $2021) while the 240-kV option would cost approximately $148 million (+/- 30 per cent, $2021). These costs estimates included the cost to rebuild the ENMAX No. 8 substation to mitigate fault level issues within the substation. The AESO stated that the need to address rising fault levels was not part of this proceeding and that it was working with ENMAX to address this issue. The AESO filed a revised cost estimate of $101 million (+/- 30 per cent, $2021) for the 138-kV option and $106 million for the 240-kV option that did not include the cost to rebuild the ENMAX No. 8 substation. 20. To evaluate potential differences between the 138-kV option and the 240-kV option, the AESO directed ENMAX to prepare a report to consider the major aspects contemplated in Rule 007: Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments 2 (Rule 007) NID requirement 13. This report compared agricultural, environmental and residential impacts of the two transmission development options. In preparing its report, ENMAX assumed that the transmission development would be constructed underground. The report concluded that there was no factor that would preclude the development of either option and there would be no difference in impacts between the two options. 21. The AESO s analysis indicated that the 138-kV option would provide sufficient capacity for the 20 year planning horizon and that the 240-kV option did not provide any additional advantages in improving system performance. However, the 138-kV option had a lower cost and, therefore, the AESO identified it as its preferred alternative. 22. The AESO consulted with ENMAX regarding the in-service date of the transmission development and determined that the earliest estimated in-service date would be in the first 2 Rule 007 effective on April 1, 2015 and replaced by Rule 007 effective on February 1, Decision D (June 1, 2016)

7 quarter of This would fall within the required in-service dates identified by the low-growth scenario and the sensitivity scenario. Accordingly, the AESO stated that it might be necessary to implement operational measures until the transmission development becomes operational. 23. The AESO conducted a participant involvement program to notify and provide information to stakeholders in the area where the AESO determined that the transmission facilities could be installed. The participant involvement program included mailing newsletters through unaddressed mail via postal code to occupants, residents, and landowners in its notification area. The AESO also held four open houses between September 8 and September 18, Based on the results of its participant involvement program, the AESO submitted that it was not aware of any concerns or objections to the need for the transmission development. 3.2 Views of other parties 25. Mary Van Order is a resident of the East Village neighbourhood in Calgary. She submitted that above-ground transmission lines should not be located in the river valleys or parks so that they do not block views or impact the appearance and enjoyment of natural areas. 26. Ray Chow is a resident of the Ramsay neighbourhood in Calgary and requested that the Commission only consider underground solutions for the transmission development. He submitted that overhead transmission lines would have an unfavourable effect on residences, parks, and greenspaces, due to the visual impacts of the transmission line and structures. 27. Paul Featherstone submitted that the proposed development area is inappropriate to site a transmission line because it is predominantly residential neighbourhoods or river valleys. He added that the area indicated is broad in scope and quite vague as to the exact alignment. 28. Sara-Jane Gruetzner, on behalf of the Fort Calgary Preservation Society, submitted that the Commission should consider the importance of Fort Calgary to Calgary and the necessity to ensure the protection of the site, including the sub-surface artifacts and archaeology. The Fort Calgary Preservation Society argued that the Commission should consider the effects that the transmission line would have on Fort Calgary. It added that the AESO s application was very vague about the transmission line routing Anca Medesan is a resident of the Beltline area of Calgary. She stated that the air quality has degraded and the sulphur content in the air has increased since the time she began living in the neighbourhood 18 years ago. Further, the addition of a new 138-kV transmission line would be detrimental to the environment and to her health because it would result in additional coal generation which would cause an increase in air emissions including particulate matter, as well as mercury pollution. She also requested that the transmission line be constructed underground and shielded by an aluminum or copper mesh X0022 Statement of intent to Participate, January 5, Decision D (June 1, 2016) 5

8 30. ENMAX is the transmission facility operator in the service area. It requested that the Commission consider the application through a written process to allow parties the necessary time to file evidence and for the Commission to reach a decision in a reasonable amount of time. 31. ENMAX issued information requests to the AESO on March 30, 2016, regarding the potential for additional transmission development in the downtown Calgary area in the future and the costs and impacts of re-excavation in the downtown core. The AESO responded to ENMAX on April 13, By letter dated April 15, 2016, ENMAX stated that the information provided by the AESO had addressed its concerns. 32. The City of Calgary stated that the AESO did not consider any provisions, such as the installation of ducting, that would mitigate the impacts of future transmission development. Failure to consider future transmission development may result in further disturbance to roads and other public areas. The City of Calgary requested that the Commission direct the AESO to address the possibility of future capacity reinforcements in order to minimize disruption in the downtown Calgary area. 33. The AESO filed reply evidence to address the City of Calgary s evidence, where it submitted that: In exercising its legislated duty to plan the transmission system under sections 33 and 34 of the Electric Utilities Act, the AESO prepared and filed the NID, including engineering studies that assess the need for transmission capacity over the next 20 years. The NID demonstrates that there is currently no need for additional transmission capacity in the downtown Calgary area over and above the proposed transmission development for at least 20 years. In other words, the AESO s transmission system plans for the area do not require additional transmission capacity to be developed in the downtown Calgary area beyond what the AESO has already proposed The AESO added that even if future development is needed in the downtown Calgary area sometime after 2035, such future need may or may not benefit from the provision of ducts between the ENMAX No. 2 and ENMAX No. 8 substations. 35. The AESO submitted there was no evidence that the application is technically deficient or contrary to the public interest. 4 Findings 36. The Commission is satisfied that the NID application filed by the AESO contains all the information required by the Electric Utilities Act, the Transmission Regulation, and Rule The Commission finds that the participant involvement program undertaken by the AESO meets the requirements of Rule 007. The Commission has reviewed the AESO s participant involvement program materials and is also satisfied that they are sufficiently clear to 4 Exhibit X0045, May 11, Decision D (June 1, 2016)

9 communicate to parties the area where the transmission development infrastructure may be located. 38. Many of the parties concerns relate to the specific routing of the transmission line. Concerns such as visual impacts and site-specific impacts to properties are better considered at the facility application stage, when detailed routes have been determined. The Commission recognizes however, that in approving the application before it it is selecting a corridor within which future transmission line routes will be located and, in that sense, its decision will affect routing. Potential impacts that can be analyzed at a high level, such as environmental and residential impacts, must therefore be considered not only at the facility application stage, but also at this stage. 39. With respect to the transmission development s visual impacts, because ENMAX has stated that it anticipates that the transmission development would use underground infrastructure, the Commission considers that some of the site-specific concerns raised may be alleviated. 40. Based on the information filed, the Commission finds the NID to be acceptable from an environmental impact perspective. 41. The Commission finds that the 138-kV option provides an effective technical solution to satisfy the need for system enhancement. With respect to the 240-kV option, the Commission finds persuasive the AESO s submission that this alternative did not provide any additional advantage in improving system performance, compared to the 138-kV option. The Commission also considers the fact that the AESO s estimated cost of the 138-kV option is approximately $5 million less than the 240-kV option to be an important factor. 42. The Commission accepts the AESO s submission that for at least 20 years there is no need for additional transmission capacity in the downtown Calgary area beyond the transmission development. Consequently, the Commission finds that it is unnecessary to direct the AESO to address the possibility of future capacity requirements. 43. Based on the above considerations, no party has satisfied the Commission that the AESO s assessment of the need for the transmission development is technically deficient or that approval of the transmission development would not be in the public interest. 44. Therefore, the Commission considers the AESO s assessment of the need to be correct, in accordance with subsection 38(e) of the Transmission Regulation, and approves the AESO s NID application. Decision D (June 1, 2016) 7

10 5 Decision 45. Pursuant to Section 34 of the Electric Utilities Act, the Commission approves the NID for the transmission development and grants the AESO the approval set out in Appendix 1 Downtown Calgary 138-kV Transmission System Reinforcement Approval D June 1, 2016 (Appendix 1 will be distributed separately). Dated on June 1, Alberta Utilities Commission (original signed by) Anne Michaud Commission Member 8 Decision D (June 1, 2016)

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 21317-D01-2016 Central Alberta Underground Fibre Optic Build July 12, 2016 Alberta Utilities Commission Decision 21317-D01-2016 Central Alberta Underground Fibre Optic Build Proceeding 21317 Application

More information

PARTICIPANT INVOLVEMENT PROGRAM (PIP)

PARTICIPANT INVOLVEMENT PROGRAM (PIP) APPENDIX C PARTICIPANT INVOLVEMENT PROGRAM (PIP) Red Deer Region Participant Involvement Program From February to May 2011, the AESO conducted a participant involvement program (PIP) as part of preparing

More information

BEFORE THE NEW JERSEY BOARD OF PUBLIC UTILITIES

BEFORE THE NEW JERSEY BOARD OF PUBLIC UTILITIES EXHIBIT JC- BEFORE THE NEW JERSEY BOARD OF PUBLIC UTILITIES IN THE MATTER OF THE PETITION OF JERSEY CENTRAL POWER & LIGHT COMPANY PURSUANT TO N.J.S.A. 0:D-1 FOR A DETERMINATION THAT THE MONTVILLE - WHIPPANY

More information

SUMMARY REPORT. Consultation Summary Report. January 2016

SUMMARY REPORT. Consultation Summary Report. January 2016 SUMMARY REPORT BC Hydro Public Consultation: Transmission Line Relocation George Massey Tunnel November 2 20, 2015 Consultation Summary Report January 2016 Prepared by Kirk & Co. Consulting Ltd. About

More information

ORDER NO * * * * * * * * * On December 21, 2018, the Maryland Public Service Commission

ORDER NO * * * * * * * * * On December 21, 2018, the Maryland Public Service Commission ORDER NO. 88999 IN THE MATTER OF THE APPLICATION OF TRANSOURCE MARYLAND LLC FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT TWO NEW 230 KV TRANSMISSION LINES ASSOCIATED WITH THE INDEPENDENCE

More information

Toronto Hydro - Electric System

Toronto Hydro - Electric System Toronto Hydro - Electric System FIT Commissioning Requirements and Reports Comments and inquiries can be e-mailed to: FIT@torontohydro.com Customers without e-mail access can submit through regular mail

More information

Marc Richter Vice President Regulatory Services. June 3, 2015 CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION. By Electronic Delivery

Marc Richter Vice President Regulatory Services. June 3, 2015 CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION. By Electronic Delivery Marc Richter Vice President Regulatory Services CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION By Electronic Delivery Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888

More information

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements DRAFT 6 V4 Standard PRC-006- RFC-01 01/11/11 A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements Deleted: Deleted: 10 Deleted: 20 9 2. Number: PRC 006 RFC 01. Purpose: To establish

More information

FINAL REPORT LOAD SHEDDING IN TASMANIA ON 20 DECEMBER 2016 REVIEWABLE OPERATING INCIDENT REPORT FOR THE NATIONAL ELECTRICITY MARKET

FINAL REPORT LOAD SHEDDING IN TASMANIA ON 20 DECEMBER 2016 REVIEWABLE OPERATING INCIDENT REPORT FOR THE NATIONAL ELECTRICITY MARKET FINAL REPORT LOAD SHEDDING IN TASMANIA ON 20 DECEMBER 2016 REVIEWABLE OPERATING INCIDENT REPORT FOR THE NATIONAL ELECTRICITY MARKET Published: 6 April 2017 IMPORTANT NOTICE Purpose AEMO has prepared this

More information

VAR Generator Operation for Maintaining Network Voltage Schedules

VAR Generator Operation for Maintaining Network Voltage Schedules Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

FACILITIES STUDY MID AMERICAN TRANSMISSION SERVICE REQUESTS. OASIS Revision: 4

FACILITIES STUDY MID AMERICAN TRANSMISSION SERVICE REQUESTS. OASIS Revision: 4 TRANSMISSION / DISTRIBUTION PROJECTS COMPANY:EAI CUSTOMER: MID AMERICAN ENERGY. FACILITIES STUDY EJO # F4PPAR0422 MID AMERICAN TRANSMISSION SERVICE REQUESTS OASIS 1468288 Revision: 4 Rev Issue Date Description

More information

REFURBISHMENT OF SECONDARY SYSTEMS IN HIGH VOLTAGE SUBSTATIONS LESSONS LEARNED IN VENEZUELA

REFURBISHMENT OF SECONDARY SYSTEMS IN HIGH VOLTAGE SUBSTATIONS LESSONS LEARNED IN VENEZUELA 21, rue d'artois, F-75008 Paris http://www.cigre.org B3-110 Session 2004 CIGRÉ REFURBISHMENT OF SECONDARY SYSTEMS IN HIGH VOLTAGE SUBSTATIONS LESSONS LEARNED IN VENEZUELA by E. PADILLA * L. CEDEÑO E. PELAYO

More information

Definitions. Common Corridor:

Definitions. Common Corridor: Definitions Common Corridor: Contiguous right-of-way or two parallel right-of-ways with structure centerline separation less than the longest span length of the two transmission circuits at the point of

More information

ELIGIBLE INTERMITTENT RESOURCES PROTOCOL

ELIGIBLE INTERMITTENT RESOURCES PROTOCOL FIRST REPLACEMENT VOLUME NO. I Original Sheet No. 848 ELIGIBLE INTERMITTENT RESOURCES PROTOCOL FIRST REPLACEMENT VOLUME NO. I Original Sheet No. 850 ELIGIBLE INTERMITTENT RESOURCES PROTOCOL Table of Contents

More information

Notes Generator Verification SDT Project

Notes Generator Verification SDT Project Notes Generator Verification SDT Project 2007-09 FERC Office 888 First Street, NE Washington, DC 20426 1. Administration a. The following were in attendance: Bob Snow, Cynthia Pointer, Lim Hansen, Keith

More information

Licensing & Regulation #379

Licensing & Regulation #379 Licensing & Regulation #379 By Anita Gallucci I t is about three years before your local cable operator's franchise is to expire and your community, as the franchising authority, receives a letter from

More information

Joint submission by BBC, ITV, Channel 4, Channel 5, S4C, Arqiva 1 and SDN to Culture Media and Sport Committee inquiry into Spectrum

Joint submission by BBC, ITV, Channel 4, Channel 5, S4C, Arqiva 1 and SDN to Culture Media and Sport Committee inquiry into Spectrum Joint submission by BBC, ITV, Channel 4, Channel 5, S4C, Arqiva 1 and SDN to Culture Media and Sport Committee inquiry into Spectrum 1. Introduction and summary The above-named organisations welcome the

More information

10/13/2011 Planning Coordination Committee. Standards

10/13/2011 Planning Coordination Committee. Standards Document name Category System Performance Regional Criterion ( ) Regional Reliability Standard (X) Regional Criterion ( ) Policy ( ) Guideline ( ) Report or other Document date 12/01/2011 Adopted/approved

More information

BPA s Network Open Season

BPA s Network Open Season May 2009 Summary Welcome to the Twenty Second National Wind Coordinating Collaborative (NWCC) Transmission Update! Kevin Porter of Exeter Associates, Inc. led the April 21, 2009, Transmission Update conference

More information

Mitigation of Cascading Outages and Prevention of Blackouts:System-Wide Corrective Control

Mitigation of Cascading Outages and Prevention of Blackouts:System-Wide Corrective Control 10th Mediterranean Conference on Power Generation, Transmission, Distribution and Energy Conversion 6-9 November 2016 Belgrade, Serbia Mitigation of Cascading Outages and Prevention of Blackouts:System-Wide

More information

Preserving Digital Memory at the National Archives and Records Administration of the U.S.

Preserving Digital Memory at the National Archives and Records Administration of the U.S. Preserving Digital Memory at the National Archives and Records Administration of the U.S. Kenneth Thibodeau Workshop on Conservation of Digital Memories Second National Conference on Archives, Bologna,

More information

3 Resolution of the Board of Supervisors, acting as responsible agency with respect to

3 Resolution of the Board of Supervisors, acting as responsible agency with respect to FILE NO. 070314 RESOLUTION NO. Lf /3-01 1 [CEQA Findings in Connection with the Trans Bay Cable Project] 2 3 Resolution of the Board of Supervisors, acting as responsible agency with respect to 4 the Trans

More information

Digital Switchover Management of Transition Coverage Issues Statement

Digital Switchover Management of Transition Coverage Issues Statement Digital Switchover Management of Transition Coverage Issues Statement Statement Publication date: 16 May 2007 Contents Section Annex Page 1 Summary 1 2 Introduction 2 3 Comments received on the revised

More information

AES standard for audio connectors - Modified XLR-3 Connector for Digital Audio. Preview only

AES standard for audio connectors - Modified XLR-3 Connector for Digital Audio. Preview only Reaffirmed 2017 AES standard for audio connectors - Modified XLR-3 Connector for Digital Audio Published by Audio Engineering Society, Inc. Copyright 2011 by the Audio Engineering Society Abstract This

More information

This Chapter does not apply to applications and decisions on, development on land reserved in corridor maps.

This Chapter does not apply to applications and decisions on, development on land reserved in corridor maps. 1560 1561 1562 1563 1564 1565 1566 1567 1568 1569 1570 1571 1572 1573 1574 1575 1576 1577 1578 1579 1580 1581 1582 1583 1584 1585 1586 1587 1588 1589 1590 1591 1592 1593 1594 1595 1596 1597 1598 1599 1600

More information

FORENSIC CASEBOOK. By Bob Huddleston, Eastman Chemical Co. One of the most common. reasons for marriage failure

FORENSIC CASEBOOK. By Bob Huddleston, Eastman Chemical Co. One of the most common. reasons for marriage failure The Case of the Energized Cable Cutting Incident How miscommunication leads to an electrical helper slicing through live 13.8kV cable and miraculously walking away to tell about it By Bob Huddleston, Eastman

More information

COST SHARING POLICY FOR COMCAST CABLE SYSTEM CONSTRUCTION FOR STREETS WHICH DO NOT MEET MINIMUM DENSITY REQUIREMENTS

COST SHARING POLICY FOR COMCAST CABLE SYSTEM CONSTRUCTION FOR STREETS WHICH DO NOT MEET MINIMUM DENSITY REQUIREMENTS AGENDA ITEM #6.B TOWN OF LOS ALTOS HILLS Staff Report to the City Council August 18, 2016 SUBJECT: FROM: COST SHARING POLICY FOR COMCAST CABLE SYSTEM CONSTRUCTION FOR STREETS WHICH DO NOT MEET MINIMUM

More information

VERIZON MARYLAND INC.

VERIZON MARYLAND INC. VZ MD 271 Attachment 207 VERIZON MARYLAND INC. Methods and Procedures for Access To Poles, Ducts, Conduits and Rights-of-Way for Telecommunications Providers VERIZON MARYLAND INC. Methods and Procedures

More information

May 26 th, Lynelle Briggs AO Chair Planning and Assessment Commission

May 26 th, Lynelle Briggs AO Chair Planning and Assessment Commission May 26 th, 2017 Lynelle Briggs AO Chair Planning and Assessment Commission Open Letter to Chair of NSW Planning Assessment Commission re Apparent Serious Breaches of PAC s Code of Conduct by Commissioners

More information

Broadcasting Decision CRTC and Broadcasting Orders CRTC , , , , and

Broadcasting Decision CRTC and Broadcasting Orders CRTC , , , , and Broadcasting Decision CRTC 2018-468 and Broadcasting Orders CRTC 2018-469, 2018-470, 2018-471, 2018-472, 2018-473 and 2018-474 PDF version References: 2018-128 and 2018-128-1 Ottawa, 14 December 2018 La

More information

APPLICATION AND EFFECTIVENESS OF THE SEA DIRECTIVE (DIRECTIVE 2001/42/EC) 1. Legal framework CZECH REPUBLIC LEGAL AND ORGANISATIONAL ARRANGEMENTS 1

APPLICATION AND EFFECTIVENESS OF THE SEA DIRECTIVE (DIRECTIVE 2001/42/EC) 1. Legal framework CZECH REPUBLIC LEGAL AND ORGANISATIONAL ARRANGEMENTS 1 APPLICATION AND EFFECTIVENESS OF THE SEA DIRECTIVE (DIRECTIVE 2001/42/EC) CZECH REPUBLIC LEGAL AND ORGANISATIONAL ARRANGEMENTS 1 This summary provides basic information on the legal, administrative and

More information

City of Kingston Report to Committee of Adjustment Report Number COA

City of Kingston Report to Committee of Adjustment Report Number COA To: From: Date of Meeting: Application for: File Number: Address: Owner: Applicant: City of Kingston Chair and Members of Committee of Adjustment Sajid Sifat, Intermediate Planner Minor Variance D13-032-2018

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd Jemena Electricity Networks (Vic) Ltd Footscray West Zone Substation (FW) Switchgear and Relay Condition Risk RIT-D Stage 1: Non-Network Options Screening Report Public 18 September 2018 An appropriate

More information

SOUTHWESTERN BELL TELEPHONE COMPANY TARIFF F.C.C. NO. 73 1st Revised Page 9-1 Cancels Original Page 9-1

SOUTHWESTERN BELL TELEPHONE COMPANY TARIFF F.C.C. NO. 73 1st Revised Page 9-1 Cancels Original Page 9-1 1st Revised Page 9-1 Cancels Original Page 9-1 9. Directory Assistance Access Service 9-2 9.1 General Description 9-2 9.2 Service Description 9-3 9.3 Service Provisioning 9-4 Page 9.3.1 Manner of Provisioning

More information

Verizon NY Section 2 Network Services Issue C, December, 2001

Verizon NY Section 2 Network Services Issue C, December, 2001 Verizon NY Section 2 Evaluating Requests 2.01 While inquiries for information will be accepted in any form, requests for licensing agreements regarding Pole Attachments, Conduit Occupancy and/or (private

More information

Summary Project Specification Consultation Report

Summary Project Specification Consultation Report Project Specification Consultation Report: Maintaining reliability of supply at Townsville South Substation Powerlink Queensland Summary Project Specification Consultation Report 29 October 2018 Maintaining

More information

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona USA

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona USA ABSTRACT Unique Regulatory Approach for Licensing the Port Hope Remediation Project in Canada 13315 M. Kostova, D. Howard and P. Elder Directorate of Nuclear Cycle and Facilities Regulation Canadian Nuclear

More information

[MB Docket Nos , ; MM Docket Nos , ; CS Docket Nos ,

[MB Docket Nos , ; MM Docket Nos , ; CS Docket Nos , This document is scheduled to be published in the Federal Register on 11/27/2018 and available online at https://federalregister.gov/d/2018-25326, and on govinfo.gov 6712-01 FEDERAL COMMUNICATIONS COMMISSION

More information

Environmental Impact Statement (EIS)/ Section 106 Public Meeting Level 1 Concept Screening. May 16, 2017

Environmental Impact Statement (EIS)/ Section 106 Public Meeting Level 1 Concept Screening. May 16, 2017 Environmental Impact Statement (EIS)/ Section 106 Public Meeting Level 1 Concept Screening May 16, 2017 Today s Agenda Project Overview Project Schedule Purpose and Need Level 1 Concept Screening Results

More information

Block System Interface Requirements

Block System Interface Requirements Block System Interface Requirements Synopsis This document mandates the requirements for block systems interfaces between signalling infrastructure and railway operations. Copyright in the s is owned by

More information

0.1. Outage Management Process Summary

0.1. Outage Management Process Summary 0.1 Outage Management Process Summary Issue: 1.0 Issue Date: August 27, 2014 Table of Contents 1. Introduction... 4 1.1 Purpose... 4 1.2 Glossary... 4 State Transition Model... 8 2. Outage Management Processes...

More information

TRANSMISSION ENGINEERING STANDARD TES-P , Rev. 0 TABLE OF CONTENTS 1.0 SCOPE 2.0 CABLES SPLICES

TRANSMISSION ENGINEERING STANDARD TES-P , Rev. 0 TABLE OF CONTENTS 1.0 SCOPE 2.0 CABLES SPLICES 1.0 SCOPE TABLE OF CONTENTS 2.0 CABLES SPLICES 2.1 Definitions 2.2 Scope of Specifications and Drawings 2.3 General Requirements 2.4 Routing Cables 2.5 Connectors 2.6 Conductor Connections 2.7 Heat Shrinkable

More information

APPLICATION OF POWER SWITCHING FOR ALTERNATIVE LAND CABLE PROTECTION BETWEEN CABLE LANDING STATION AND BEACH MAN HOLE IN SUBMARINE NETWORKS

APPLICATION OF POWER SWITCHING FOR ALTERNATIVE LAND CABLE PROTECTION BETWEEN CABLE LANDING STATION AND BEACH MAN HOLE IN SUBMARINE NETWORKS APPLICATION OF POWER SWITCHING FOR ALTERNATIVE LAND PROTECTION BETWEEN LANDING STATION AND BEACH MAN HOLE IN SUBMARINE NETWORKS Liyuan Shi (Huawei Marine Networks) Email: Huawei

More information

Online Control System Migration of Industrial Centrifuge Project Description

Online Control System Migration of Industrial Centrifuge Project Description Canadian Consulting Engineering Awards 2017 Online Control System Migration of Industrial Centrifuge Project Description Category: Natural Resources, Mining, Industry & Energy Fort McMurray, AB Table of

More information

(1) These Regulations may be called PEMRA Standards for Cable Television Regulations 2003.

(1) These Regulations may be called PEMRA Standards for Cable Television Regulations 2003. PEMRA Cable Television (Operations) Regulations, 2002. Pakistan Electronic Media Regulatory Authority (PEMRA) The Pakistan Electronic Media Regulatory Authority (PEMRA) is pleased to make the Standards

More information

Before the FEDERAL COMMUNICATIONS COMMISSION Washington DC ) ) ) ) ) ) ) ) COMMENTS OF

Before the FEDERAL COMMUNICATIONS COMMISSION Washington DC ) ) ) ) ) ) ) ) COMMENTS OF Before the FEDERAL COMMUNICATIONS COMMISSION Washington DC 20554 In the Matter of Amendment of Part 101 of the Commission s Rules to Facilitate the Use of Microwave for Wireless Backhaul and Other Uses

More information

POLICY AND PROCEDURES FOR MEASUREMENT OF RESEARCH OUTPUT OF PUBLIC HIGHER EDUCATION INSTITUTIONS MINISTRY OF EDUCATION

POLICY AND PROCEDURES FOR MEASUREMENT OF RESEARCH OUTPUT OF PUBLIC HIGHER EDUCATION INSTITUTIONS MINISTRY OF EDUCATION HIGHER EDUCATION ACT 101, 1997 POLICY AND PROCEDURES FOR MEASUREMENT OF RESEARCH OUTPUT OF PUBLIC HIGHER EDUCATION INSTITUTIONS MINISTRY OF EDUCATION October 2003 Government Gazette Vol. 460 No. 25583

More information

Re: Broadcasting Public Notice CRTC Item 1 Application No , The Sports Network Inc.

Re: Broadcasting Public Notice CRTC Item 1 Application No , The Sports Network Inc. 27 July 2006 Ms. Diane Rhéaume Secretary-General Canadian Radio-Television & Telecommunications Commission Ottawa, Ontario K1A ON2 Re: Broadcasting Public Notice CRTC 2006-79 - Item 1 Application No. 2006-06942-9,

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. PRC-026-1 Relay Performance During Stable Power Swings Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the

More information

REPORT TO THE PLANNING COMMISSION

REPORT TO THE PLANNING COMMISSION REPORT TO THE PLANNING COMMISSION Meeting Date: May 13, 2015 Application: Design Review PDR15-0006 Location / APN: Near 19700 Prospect Road / 386-35-070 Owner / Applicant: Staff Planner: City of Saratoga

More information

Electrical Depth CAL IT 2. Brian Smith. Introduction

Electrical Depth CAL IT 2. Brian Smith. Introduction Electrical Depth Introduction The University of California, San Diego Cal IT 2 Building was electrically designed for a lot of future growth. With my changes in the lighting system and control zones, a

More information

LOW-BUDGET INDEPENDENT FEATURE FILM ASSISTANCE PROGRAM GUIDELINES FOR

LOW-BUDGET INDEPENDENT FEATURE FILM ASSISTANCE PROGRAM GUIDELINES FOR LOW-BUDGET INDEPENDENT FEATURE FILM ASSISTANCE PROGRAM GUIDELINES FOR 2002-2003 These Guidelines are specific to the terms and conditions of the program for the fiscal year of 2002-2003 (which ends on

More information

Notice Pursuant to Section 32H of the Telecommunications Ordinance (Chapter 106)

Notice Pursuant to Section 32H of the Telecommunications Ordinance (Chapter 106) Notice Pursuant to Section 32H of the Telecommunications Ordinance (Chapter 106) Interpretation In this Notice, unless the context otherwise requires, Authority means the Communications Authority; BO means

More information

Broadcasting Ordinance (Chapter 562)

Broadcasting Ordinance (Chapter 562) Broadcasting Ordinance (Chapter 562) Notice is hereby given that the Communications Authority ( CA ) has received an application from Phoenix Hong Kong Television Limited ( Phoenix HK ), a company duly

More information

FAR Part 150 Noise Exposure Map Checklist

FAR Part 150 Noise Exposure Map Checklist FAR Part 150 Noise Exposure Map Checklist I. IDENTIFICATION AND SUBMISSION OF MAP DOCUMENT: Page Number A. Is this submittal appropriately identified as one of the following, submitted under FAR Part 150:

More information

ESCORT & ESCORT AGENCY DOING BUSINESS IN WINNIPEG BY-LAW NO. 91/2008

ESCORT & ESCORT AGENCY DOING BUSINESS IN WINNIPEG BY-LAW NO. 91/2008 ESCORT & ESCORT AGENCY DOING BUSINESS IN WINNIPEG BY-LAW NO. 91/2008 By-law Extract of pertinent sections regarding the regulation of specific business activities as adopted by Council effective June 1,

More information

TO BE PUBLISHED IN THE GAZETTE OF INDIA EXTRAORDINARY, PART III SECTION 4 TELECOM REGULATORY AUTHORITY OF INDIA NOTIFICATION

TO BE PUBLISHED IN THE GAZETTE OF INDIA EXTRAORDINARY, PART III SECTION 4 TELECOM REGULATORY AUTHORITY OF INDIA NOTIFICATION TO BE PUBLISHED IN THE GAZETTE OF INDIA EXTRAORDINARY, PART III SECTION 4 TELECOM REGULATORY AUTHORITY OF INDIA NOTIFICATION New Delhi, the 14 th May, 2012 F. No. 16-3/2012-B&CS - In exercise of the powers

More information

Plan for Generic Information Collection Activity: Submission for. National Transportation Safety Board (NTSB).

Plan for Generic Information Collection Activity: Submission for. National Transportation Safety Board (NTSB). This document is scheduled to be published in the Federal Register on 10/10/2014 and available online at http://federalregister.gov/a/2014-24234, and on FDsys.gov 7533-01-M NATIONAL TRANSPORTATION SAFETY

More information

Broadcasting Decision CRTC

Broadcasting Decision CRTC Broadcasting Decision CRTC 2012-550 PDF version Route reference: 2012-224 Additional reference: 2012-224-1 Ottawa, 10 October 2012 Radio 710 AM Inc. Niagara Falls, Ontario Application 2011-0862-1, received

More information

1. EXPERT MEETING EXPERT MEETING EXPERT MEETING Feedback from the meeting attendees...

1. EXPERT MEETING EXPERT MEETING EXPERT MEETING Feedback from the meeting attendees... FEEDBACK REPORT STAKE HOLDER CONSULTATION PROCESS OFFSHORE GRID NL Type: Feedback report Work stream Technical Topics: P.01 Planning Filename ONL 15-149 P01_Planning_FBRe_v2 Version 2 public release Pages

More information

Director Corporate Services & Board Secretary

Director Corporate Services & Board Secretary \ I newfoundland labrador 11.h ydro a nalcor energy company Hydro Place. 500 Columbus Drive. P.O. Box 12400. St. John's. NI Canada A1B 4K7 t. 709.737.1400 1. 709.737.1800 www.n1h.rd.ca June 16, 2014 The

More information

Demand Side Engagement Document

Demand Side Engagement Document Demand Side Engagement Document Document UE PL 2202 Strategy This document details UE s demand side engagement plan as part of the National Distribution Planning & Expansion Framework This page has been

More information

December Spectrum Management and Telecommunications Policy

December Spectrum Management and Telecommunications Policy December 2003 Spectrum Management and Telecommunications Policy A Staff Study on the Potential Impact of Satellite Digital Audio Radio Services Terrestrial Repeaters on Wireless Communications Service

More information

Improving Lightning Protection of Power Systems with Externally Gapped Line Arresters (EGLA)

Improving Lightning Protection of Power Systems with Externally Gapped Line Arresters (EGLA) Improving Lightning Protection of Power Systems with Externally Gapped Line Arresters (EGLA) Jonathan Woodworth ArresterWorks 1 Today's Presentation 1. Real Value of Arresters 2. Improving Distribution

More information

47 USC 534. NB: This unofficial compilation of the U.S. Code is current as of Jan. 4, 2012 (see

47 USC 534. NB: This unofficial compilation of the U.S. Code is current as of Jan. 4, 2012 (see TITLE 47 - TELEGRAPHS, TELEPHONES, AND RADIOTELEGRAPHS CHAPTER 5 - WIRE OR RADIO COMMUNICATION SUBCHAPTER V-A - CABLE COMMUNICATIONS Part II - Use of Cable Channels and Cable Ownership Restrictions 534.

More information

Elbert Theatre Rental Application

Elbert Theatre Rental Application Elbert Theatre Rental Application To submit a rental application, receive additional information on the venue, or to check availability, Please contact: The Elbert Theatre P. O. Box 70 100 South Oliver

More information

SUMMARY. Southwest Zone Transmission Planning Meeting. October 5, 2004

SUMMARY. Southwest Zone Transmission Planning Meeting. October 5, 2004 SUMMARY Southwest Zone Transmission Planning Meeting October 5, 2004 The Southwest Zone Transmission Planning Meeting was held on October 5, 2004 at 7:00 p.m. at the Americinn of Marshall, 1406 East Lyon

More information

THE BAHAMAS EXPERIENCE. Contents. In this brief presentation we will give you:

THE BAHAMAS EXPERIENCE. Contents. In this brief presentation we will give you: THE BAHAMAS EXPERIENCE Contents In this brief presentation we will give you: An overview of the demographics of The Bahamas An explanation of its Legal Framework A short discussion about the Guidelines

More information

Phase 2 of System Protection Coordination (Requirement revisions to PRC ) Hydro Québec TransÉnergie

Phase 2 of System Protection Coordination (Requirement revisions to PRC ) Hydro Québec TransÉnergie Project 2007-06.2 Phase 2 of System Protection Coordination (Requirement revisions to PRC-001-1.1) Industry Webinar March 24, 2015 Standard Drafting Team Member Mark Peterson, Chair Michael Cruz Montes,

More information

Code of Practice on Changes to Existing Transmission and Reception Arrangements

Code of Practice on Changes to Existing Transmission and Reception Arrangements Code of Practice on Changes to Existing Transmission and Reception Arrangements Publication date: 11 March 2016 Code of Practice on Changes to Existing Transmission and Reception Arrangements Contents

More information

Specification. NGTS Issue 1 October 1993

Specification. NGTS Issue 1 October 1993 The Electrical Standards for SHE Transmission s area are non-maintained versions of National Grid Technical Specifications that are applicable to the SHE Transmission System only. These specific versions

More information

LUPA Proposed Final Programmatic Agreement November 20, 2015

LUPA Proposed Final Programmatic Agreement November 20, 2015 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 PROPOSED FINAL PROGRAMMATIC AGREEMENT AMONG THE BUREAU OF LAND MANAGEMENT

More information

BERMUDA STATUTORY INSTRUMENT BR 25/1987 TELEVISION BROADCASTING SERVICE REGULATIONS 1987

BERMUDA STATUTORY INSTRUMENT BR 25/1987 TELEVISION BROADCASTING SERVICE REGULATIONS 1987 Laws of Bermuda Title 24 Item 11(a) BERMUDA STATUTORY INSTRUMENT BR 25/1987 TELEVISION BROADCASTING SERVICE REGULATIONS 1987 [made under section 11 of the Broadcasting Commissioners Act 1953 [title 24

More information

Before the Federal Communications Commission Washington, D.C

Before the Federal Communications Commission Washington, D.C Before the Federal Communications Commission Washington, D.C. 20554 In the Matter of ) ) Assessment and Collection of Regulatory ) MD Docket No. 13-140 Fees for Fiscal Year 2013 ) ) Procedure for Assessment

More information

Automatic Under-Frequency Load Shedding (AUFLS) Technical Report

Automatic Under-Frequency Load Shedding (AUFLS) Technical Report Automatic Under-uency Load Shedding (AUFLS) Technical Report August 2010 System Operator 6/08/2010 Page 1 of 124 System Operator Report: Automatic Under-uency Load Shedding (AUFLS) Technical Report Page

More information

SCTE OPERATIONAL PRACTICE

SCTE OPERATIONAL PRACTICE Energy Management Subcommittee SCTE OPERATIONAL PRACTICE SCTE 245 2018 Use Cases for Adaptive Power Using APSIS NOTICE The Society of Cable Telecommunications Engineers (SCTE) / International Society of

More information

PURCHASING DEPARTMENT. Project # Addendum # # of pages Original Issue Date Request Doc # April 15, see text below

PURCHASING DEPARTMENT. Project # Addendum # # of pages Original Issue Date Request Doc # April 15, see text below PURCHASING DEPARTMENT The bid listed below has had addenda issued. Documents are available over the Internet at http://www.norwalkct.org Adobe Acrobat reader is required to view this document. If you do

More information

South Australian Energy Transformation

South Australian Energy Transformation South Australian Energy Transformation PSCR Supplementary Information Paper ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box 7096, Hutt Street Post Office, Adelaide,

More information

Request for Proposal Questions and Responses. Request for Proposal: Software Based CMED Radio Console and Associated Equipment

Request for Proposal Questions and Responses. Request for Proposal: Software Based CMED Radio Console and Associated Equipment Request for Proposal Questions and Responses Request for Proposal: Software Based CMED Radio Console and Associated Equipment Proposal Due Date: Friday December 14, 2018 All Prospective Proposers: In reference

More information

Implementation of a High-Speed Distribution Network Reconfiguration Scheme by Greg Hataway, Ted Warren, and Chris Stephens.

Implementation of a High-Speed Distribution Network Reconfiguration Scheme by Greg Hataway, Ted Warren, and Chris Stephens. The following technical papers supporting this presentation are available at www.selinc.com: Trip and Restore Distribution Circuits at Transmission Speeds by Jeff Roberts and Karl Zimmerman International

More information

SECTION MEDIUM VOLTAGE CABLE INSTALLATION. 1. Section Underground Ducts and Manholes.

SECTION MEDIUM VOLTAGE CABLE INSTALLATION. 1. Section Underground Ducts and Manholes. SECTION 33 71 49.23 MEDIUM VOLTAGE CABLE INSTALLATION PART 1 GENERAL 1.1 SCOPE A. Work included in this Section: Medium Voltage Cable (4 kv and 12 kv) Installation and Termination. Removal and return of

More information

800 MHz Band Reconfiguration

800 MHz Band Reconfiguration 800 MHz Band Reconfiguration RPC Meeting February 13, 2009 1 Agenda Reconfiguration Status Update Implementation Planning Session Schedule Monitoring & Management Change Notice Regional Plans Licensing

More information

Based on our maintenance efforts, during the second quarter of 2018, Comcast s plant was 99.9% reliable.

Based on our maintenance efforts, during the second quarter of 2018, Comcast s plant was 99.9% reliable. December XX, 2018 Comcast Cable 253 Najoles Road Millersville,MD 21108 Terry Shannon County Administrator 175 Main Street Prince Frederick, MD 20678 Dear Mrs. Shannon, The purpose of this letter is to

More information

CHARLOTTE MECKLENBURG PUBLIC ACCESS CORPORATION

CHARLOTTE MECKLENBURG PUBLIC ACCESS CORPORATION CHARLOTTE MECKLENBURG PUBLIC ACCESS CORPORATION REGULATIONS & PROCEDURES A. MISSION STATEMENT Effective 12/19/18 1. Charlotte Mecklenburg Public Access Corporation (CMPAC) was created to manage and operate

More information

Selecting Cables for Power over Ethernet

Selecting Cables for Power over Ethernet Hitachi Cable America Inc. Selecting Cables for Power over Ethernet Factors to Consider when Selecting the Appropriate Cable 8/12/217 Ratio of Power Dissipated vs 1 Power over Ethernet Standards and applications

More information

GROWING VOICE COMPETITION SPOTLIGHTS URGENCY OF IP TRANSITION By Patrick Brogan, Vice President of Industry Analysis

GROWING VOICE COMPETITION SPOTLIGHTS URGENCY OF IP TRANSITION By Patrick Brogan, Vice President of Industry Analysis RESEARCH BRIEF NOVEMBER 22, 2013 GROWING VOICE COMPETITION SPOTLIGHTS URGENCY OF IP TRANSITION By Patrick Brogan, Vice President of Industry Analysis An updated USTelecom analysis of residential voice

More information

Dynatel Advanced Cable Locator 2250

Dynatel Advanced Cable Locator 2250 3 Dynatel Advanced Cable Locator 2250 Quickly and Accurately Identify Underground Assets Pinpoint exact cable path and depth quickly and easily with this lightweight, easy-to-handle unit The 3M Dynatel

More information

Town Hall Use Policy Established February 22, 1999 rev. June 22, 2007

Town Hall Use Policy Established February 22, 1999 rev. June 22, 2007 Town Hall Use Policy Established February 22, 1999 rev. June 22, 2007 Purpose: The Hudson Town Hall houses the various governmental departments and their employees, and elected and appointed boards. Space:

More information

16 th Annual PQSynergy International Conference and Exhibition 2016

16 th Annual PQSynergy International Conference and Exhibition 2016 16 th Annual PQSynergy International Conference and Exhibition 2016 Er. Muhammad Najmi Bin Bohari MSc(Power Eng), B.Eng (EEE) P.Eng, MIES, M-CIGRE najmi@powerquality.sg Professional Engineer (Singapore).

More information

Broadcasting and on-demand audiovisual services Regulations (No. 153 of 28 February 1997)

Broadcasting and on-demand audiovisual services Regulations (No. 153 of 28 February 1997) Broadcasting and on-demand audiovisual services Regulations (No. 153 of 28 February 1997) Unofficial translation (Not complete, certain Sections that are not relevant for the notification have not been

More information

Escorting / Supervision of service providers and contractors

Escorting / Supervision of service providers and contractors Escorting / Supervision of service providers and contractors PIN020 Operations Directorate 8 The Director of Operations 29/01/14 See Section 5 of this document - - 29/01/2016 29/01/2014 IPS Policy for

More information

Date Effected May 20, May 20, 2015

Date Effected May 20, May 20, 2015 1. Purpose of the The Niagara Falls Board (hereinafter the Board ) has approved the to support its mission to be an informational, educational, cultural and recreational resource valued by the Niagara

More information

CENELEC GUIDE 13. IEC - CENELEC Agreement on Common planning of new work and parallel voting. Edition 1,

CENELEC GUIDE 13. IEC - CENELEC Agreement on Common planning of new work and parallel voting. Edition 1, CENELEC GUIDE 13 IEC - CENELEC Agreement on Common planning of new work and parallel voting Edition 1, 2001-01 The first IEC/CENELEC Cooperation Agreement on common planning of new work and parallel voting

More information

Canada Gazette, Part I, December 18, 2014, Notice No. SLPB Consultation on Repurposing the 600 MHz Band Eastlink s reply comments

Canada Gazette, Part I, December 18, 2014, Notice No. SLPB Consultation on Repurposing the 600 MHz Band Eastlink s reply comments March 26, 2015 Senior Director Spectrum Licensing and Auction Operations Industry Canada 235 Queen Street Ottawa, Ontario K1A 0H5 spectrum.auctions@ic.gc.ca Dear Sir/Madam: Re: Canada Gazette, Part I,

More information

IOT. Internet of Transformation. Whitepaper.

IOT. Internet of Transformation. Whitepaper. IOT Internet of Transformation Whitepaper www.juniperresearch.com 1 1.2 Definition of the Internet of Things 1.1 An Internet in Evolution Over the past decade or so, concepts of what the Internet is, or

More information

Before the FEDERAL COMMUNICATIONS COMMISSION Washington, DC 20554

Before the FEDERAL COMMUNICATIONS COMMISSION Washington, DC 20554 Before the FEDERAL COMMUNICATIONS COMMISSION Washington, DC 20554 In the Matters of ) ) Local Number Portability Porting Interval ) WC Docket No. 07-244 And Validation Requirements ) REPLY COMMENTS The

More information

116 Albert Street, Suite 811 Phone: K1P 5G3 Fax: Web site:

116 Albert Street, Suite 811 Phone: K1P 5G3 Fax: Web site: Radio Advisory Board of Canada Conseil consultatif canadien de la radio April 17, 2009 Leonard St-Aubin Director General Telecommunications Policy Branch Industry Canada 300 Slater Street Ottawa, Ontario

More information

Note for Applicants on Coverage of Forth Valley Local Television

Note for Applicants on Coverage of Forth Valley Local Television Note for Applicants on Coverage of Forth Valley Local Television Publication date: May 2014 Contents Section Page 1 Transmitter location 2 2 Assumptions and Caveats 3 3 Indicative Household Coverage 7

More information

Expert Workgroup on Fast Fault Current Injection stage 1 Terms of Reference

Expert Workgroup on Fast Fault Current Injection stage 1 Terms of Reference Expert Workgroup on Fast Fault Current Injection stage 1 Terms of Reference Governance 1. The need case to establish a Next Steps Expert Technical Workgroup Supporting Fast Fault Current Injection (FFCI)

More information

Property No

Property No EXHIBIT 2 Property No. 7065101-1 Alyson M. Seigal Area Manager FiOS Franchise Assurance New York City 140 West Street New York, NY 10007 Phone: (888) 364-3467 NYCFiOS@verizon.com August 24, 2016 VIA CERTIFIED

More information