REFURBISHMENT OF SECONDARY SYSTEMS IN HIGH VOLTAGE SUBSTATIONS LESSONS LEARNED IN VENEZUELA

Size: px
Start display at page:

Download "REFURBISHMENT OF SECONDARY SYSTEMS IN HIGH VOLTAGE SUBSTATIONS LESSONS LEARNED IN VENEZUELA"

Transcription

1 21, rue d'artois, F Paris B3-110 Session 2004 CIGRÉ REFURBISHMENT OF SECONDARY SYSTEMS IN HIGH VOLTAGE SUBSTATIONS LESSONS LEARNED IN VENEZUELA by E. PADILLA * L. CEDEÑO E. PELAYO A. DICTAMEN F. ANTOIMA C.V.G. EDELCA (Venezuela) The expected life time of secondary systems based on analogue technique is around 35 years. However, some circumstances such as extensions to the high voltage switchgear and reconfiguration of the substation lay-out, offer the opportunity to actualize the secondary system, in order to improve the capability and functionality of the whole substation using up to date technology. This paper deals with the refurbishment of secondary equipment at an existing 765 kv substation located in western Venezuela, where the wall mimic was replaced by a computer based HMI (Human Machine Interface) connected through optical fibre to RTIU (Remote Terminal Intelligent Units) located in relay rooms. In this particular case, some of the equipment, including the Event Recorders and the existing Remote Terminal had problems of obsolescence (e.g. Y2K compliance) and there were also difficulties in obtaining spare parts. Introducing the new RTIU and HMI connected through optical fibre cable solved these problems in a practical way, but a lot of preparatory work was necessary in order to reduce the problems during the actual refurbishment. As well as the new technologies incorporated into both the control system and the communication equipment, the paper discusses various critical technical, human and contractual factors which arose during the execution of the project, which should be clarified at an early stage of any future project of a similar nature in order to ensure maximum effectiveness both economically and in terms of project duration. Technical factors, such as lack of components on the market to expand some of the installed equipment, job execution at site, extended engineering time and coordination work to integrate elements coming from different providers, limitations in the modification of existing boards taking into account the permissible outage time, and unexpected details of existing internal wiring that influenced the scope of supply. During the engineering stage there were additional factors related to new requirements, especially in the communication services where network components such as routers and switches were necessary to achieve the new requirements; the quantity and quality of signals to be shared between the conventional existing wiring and the new supervisory and control system that had to be defined, and problems arose due to the as built drawings not reflecting the actual situation in the substation. Human factors, such as differences in concepts between maintenance and engineering personnel regarding the elimination of the wall mimic and its replacement by the PC based HMI; the definition of the sequence of the stages required when energizing the substation with the new supervisory and * C.V.G. EDELCA, Av. La Estancia, Edf. General, Piso 3, Chuao-Caracas, Venezuela; epadilla@edelca.com.ve 1

2 control system; difference of criteria between the utilities interconnected in the substation (C.V.G. EDELCA, CADAFE and ENELBAR). Contractual factors such as the convenience or not of desegregating the contract for the new supervisory and control system from the contract for the extensions to the remainder of the substation, and the timing between the signing of the different contracts. Actually, in the existing C.V.G. EDELCA network it is possible to improve the secondary system for substations for 765 kv, 400 kv and 230 kv, as much as twenty or thirty years old, by taking advantage of new technology based on computers and replacing existing wiring and obsolete equipment. Apart from describing each of the critical factors found during the execution of the project, the paper suggests the way to reduce the possibility of them to become obstacles in the development of new refurbishing projects on the secondary systems in other substations. Keywords: Refurbishment Updating Lifetime Secondary Systems Substation. 1. YARACUY SUBSTATION Yaracuy substation, to which this paper refers, is one of the most critical and important substations on the Venezuelan 765 kv system, due to its position as the interconnection between the centre and the west of the country. It is located close to Barquisimeto, Lara State, to the west of the country. From this substation, C.V.G. EDELCA supplies energy to CADAFE and ENELBAR, public utilities which own important distribution networks. The substation was first commissioned in 1990, and comprised two incomplete 765 kv bays and a bank of 765/400 kv transformers. In the year 2000, due to the increase in power demand in the western region of the country and the need to increase the reliability of the energy supply, it was necessary to undertake an extension to the Yaracuy substation. This extension consisted in completing a ring arrangement of four circuit breakers in the 765 kv bays in order to add a new bank of 1000 MVA, 765/230 kv transformers made up of three single phase units of 333 MVA each, and a spare unit. Figure 1 and Figure 2 show the initial and final configurations of the substation. Fig.1 Single line diagram of Yaracuy substation. Initial configuration Fig.2 Single line diagram of Yaracuy substation. Final configuration. Although the secondary system of the substation had not reached the end of its useful life in accordance with the statistics and considerations indicated in reference [1], some of the components had become prematurely obsolete. This was the case with the event recorder system which did not pass the Y2K verification tests, and the system of remote terminal units (RTU) for the transmission of signals to the C.V.G. EDELCA s Main Control Centre. Thus, the extensions needed to the high voltage switchgear and transformer capacity was seen as an opportunity to update the secondary system so as to incorporate new equipment based on a new Remote Terminal Intelligent Unit (RTIU) which would perform the functions of the existing remote terminal and at the same time those of the events recorder and the transducers. 2

3 2. SCOPE OF WORK ON THE SECONDARY SYSTEM In order to obtain an optimal solution for the secondary system, and minimize the problems which could arise during the modernization process, a review of the existing secondary system was carried out during the basic engineering stage (preparation of technical specifications), from which the following was determined: 1. The Events Recorder system did not comply with Y2K requirements. 2. It would be necessary to replace the existing remote terminal, as due to obsolescence, it was difficult to obtain spare parts. 3. There were also problems in obtaining spare parts for the existing mimic control panel. 4. It had been difficult to obtain spare parts for the transducers in the control panels, due to obsolescence. 5. There was a fibre optic cable between the Control Room and the Relay Room with sufficient pairs available for the transmission of information between the two buildings where the events recorder and remote terminal are installed. 6. There was a fibre optic cable between the Relay Room in C.V.G. EDELCA s 765 kv, switchyard and the Control Room in CADAFE s 230 kv switchyard with sufficient pairs available for the exchange of information between the two companies. Once this diagnostic had been completed, it was necessary to carry out an evaluation of the technical options available for the project, taking into account C.V.G. EDELCA s experience in the installation and operation of both conventional and digital control systems [2]. After analysing the possible options, it was decided to adopt a hybrid system based on the installation of Remote Terminal Intelligent Units (RTIU) in new interface panels (TI-R) located in the Relay Room. All the information related to control, signalling, metering, auxiliary services and the transformers fire protection system of bay 4 coming from the new high voltage equipment would be cabled to these panels together with the information from the existing bays 2 and 3. From these RTIU, all the signals would be transmitted via fibre optic cable to the substation control room where the human-machine interface (HMI) would be installed for the display and control of the information. From these same RTIU, the information would also be transmitted to the C.V.G. EDELCA s Regional Control Centre. In this way, the existing wall mimic would be replaced by the new HMI and the existing remote terminal unit replaced by the RTIU. It would also be possible to eliminate the existing transducers as the new RTIU could accept the signals directly from the switchyard equipment. The control schemes prior to the development of the project and as finally installed are shown in Figures 3 and 4 respectively. Fig.3. Actual supervision scheme of Yaracuy 765 kv substation Fig.4. New control scheme. Extension to Yaracuy substation The exchange of information with C.V.G. EDELCA s customer in the 230 kv, switchyard would be made using the existing fibre optic from the new RTIU to an interconnection panel (TIEC) located in 3

4 CADAFE s control room. The same route could be used to take the control and metering signals to and from the 230 kv and 765 kv switchyards, thus reducing the need to purchase energy meters for the 230 kv, switchyard as the signals would be taken by fibre optic. The protection of the interconnection between the two switchyards would also be cabled to this panel. The schematic distribution of the signals between the two switchyards could be seen in Figure 5. Fig.5. Schematic distribution of the signals between C.V.G. EDELCA and CADAFE. In order to define the scope described, which was part of the basic engineering, it was essential to include the active participation of the operation and maintenance departments together with the engineering staff, in order to reduce deviations in the scope and execution of the project and to consolidate the bid documents. CADAFE was also included in the project at this stage. For the execution of the work, two contracts were awarded: One contract for the supply, erection and testing of the new control system (RTIU and HMI) and the other for the supply, erection and testing of the high voltage equipment together with the integration of the rest of the components which made up the extension to the substation as a whole. 3. CRITICAL ISSUES WHICH AROSE DURING THE EXECUTION OF THE PROJECT As critical issues, in this paper were considered all those technical, human, or contractual situations which gave rise to a series of clarifications and agreements both internally within C.V.G. EDELCA and externally with customers and contractors. These critical issues consisted mainly in the following: 3.1. Technical Factors Among the critical technical issues that influenced into the project, the following could be mentioned: Premises for the expansion of existing equipment In accordance with the project specifications a set of electronic cards should be added to the existing communications equipment to permit the exchange of control signals, particularly indications and metering, to and from the CADAFE 230 kv switchyard. Due to the technological advances made by the manufacturer of these electronic cards, it was necessary to use the new teleprotection panels supplied under the project for this function. It is C.V.G. EDELCA s normal practice to separate the control signals from the teleprotection signals, but in this case, in order to adapt to the available technology, it was necessary to incorporate both functions in the teleprotection panel Additional engineering to realize the interface. In the scope of the integration contract it was foreseen that all the signals coming from the high 4

5 voltage equipment would meet at a series of terminal blocks located in the interface panel TI-R, which in turn would be connected to the control system supplied under another contract. In the detailed engineering stage it was found necessary, for the correct coordination of the two contracts, that these signals be previously identified, ordered and prioritized in order to generate the data base required by the RTIU of the new control system Problems with as-built drawings. During the development of the detailed engineering it was necessary to refer to the as-built drawings of the existing installations. It was found that these did not fully reflect the on-site situation, in regard to the control signals which should be generated. Additionally, there was no drawing of integration between the signals for a conventional type control system and those required by the new control system at the level of the interconnection panel (TI-R). These problems had to be resolved during the detailed engineering phase in order to correctly define the data base to be used by the new RTIU Use of new cables in place of the existing ones Taking into consideration the location of the panels and for economic reasons, during the basic engineering stage the most appropriate option was considered to be the re-routing of the cables connected to the existing events recorder into the new TI-R panels. Nonetheless, during the detailed engineering stage this option was reconsidered, and for operational reasons, it was decided to keep this recorder in operation until the new RTIU was available. This new option required the use of new cables for the signals which were to be taken from the existing panels to the TI-R panels, which also simplified the erection and testing of the equipment Restrictions on the wiring connections in existing panels. Yaracuy substation is of vital importance for the operation and supply of the transmission system in the west of Venezuela. For this reason, the C.V.G. EDELCA s Main Control Centre management considered it inconvenient to eliminate the information being provided by the existing events recorder, thus it was necessary to have the new RTIU ready for operation prior to the disconnection of the existing recorder. The same situation arose with the cabling from the existing control and protection panels to the new TI-R panels Sequence of the work associated with the energization of the bays. During the phase prior to the erection and testing it was considered necessary to form an on-site interdisciplinary working group. This group proposed that the commissioning should be carried out in stages and that the first priority would be bay number 4 as this would provide availability for the energization of the transformer bank, which in turn would supply energy to the CADAFE 230 kv busbar. This would be followed by the energization of bay number 3 and finally of bay number 2. It should be noted that this proposal took into account the normal time taken for the different activities associated with testing high and low voltage equipment in an energized substation, and the availability of the existing panels, particularly the events recorder. Among the reasons forming the basis for the adoption of this sequential scheme for the commissioning of the substation, the priority in providing service to the client, difficulties in obtaining permits for outages, and the need for minimizing operational risks were taken into account. This also permitted the commissioning of the new RTIU for the supervision and control of bay number 4 and then, depending on the operational restrictions of the substation, the incorporation of bays number 2 and 3, thus allowing the testing of the new supervision and control system for the substation with a minimum risk Communications between the RTIU and the HMI. In order to send the signals between the RTIU and the HMI via the existing fibre optics, it was necessary to acquire and install electro-optical converters both in the RTIU and the HMI. This equipment had not been included in either the integration contract or in the control system contract, but they were easily obtained and installed and did not cause any delay in the overall programme of work. 5

6 3.2. Human Issues Among the critical human issues that influenced into the project, the following could be mentioned: Re-evaluation of the retention of the wall mimic. From the basic engineering stage it had been contemplated that the existing wall mimic (Figure 6), would be deactivated and that the control at the substation level would be performed from the new computer based master station HMI (Figure 7). Along the development of the detailed engineering, some of the maintenance personnel proposed that this concept should be reconsidered and that the existing wall mimic should be retained and operated in parallel with the new HMI, based on the idea of having a back-up for the local control of the substation. This proposal was considered during a series of meetings and additional discussions to re-evaluate the decision taken during the basic engineering. The decision to dispose of the existing wall mimic was finally ratified and the control of the substation left to the new master station shown in Figure 4. Fig.6. Wall mimic to be removed. Fig.7. New main control centre Sequence in the development of on-site work. Due to its location in the national 765 kv grid, it is a requirement that Yaracuy substation be maintained in a state of reliable commercial operation, even while extension work is under way, as an outage or fault in the service would be extremely sensitive. For this reason, in addition to the precaution of carrying out the work in stages, extreme precautions were taken to guarantee electrical service by careful planning and executing each activity. For example, the local operation of the substation from the relay room was not allowed. Under other circumstances this would have permitted the acceleration of the commissioning of the substation extension CONTRACTUAL ISSUES The basic premise adopted for the performance of the project consisted on the separation of the contracts for the substation extension and the incorporation of the new remote intelligent terminal unit RTIU. As well as these two main contracts, the new power transformers and the communications equipment also had to be acquired. The works associated with the extensions to the 230 kv switchyard which were to be undertaken by C.V.G. EDELCA s customers CADAFE and ENELBAR was also a factor to be considered. The critical issues which arose were the following: The effect of separate contracts. The number of contracts mentioned above increased the complexity of coordination of the work by C.V.G. EDELCA. This complexity of coordination had consequences in time and costs and required meetings and agreements with different working groups belonging to separate organizational units, particularly with the contract related to the creation of the data base necessary for the processing of signals coming from the switchyard. 6

7 Different time scales for the contracts. The time scale for the main integration contract was 15 months, but for the supply and erection of the new RTIU was 6 months. In addition, these two contracts were managed by different organizational units within C.V.G. EDELCA. The difference in time scales and the proper planning of the contracting both internally and with customers CADAFE and ENELBAR, reduced the impact on the time of execution of the work, even taking into account problems of technical definitions, restrictions in the availability of existing panels and the sequence of energization adopted for the commissioning. 4. ANALYSIS OF THE CRITICAL ISSUES Within the framework of the philosophy of lessons learned which is now being applied in the electrical industry, the causes which gave rise to the critical issues reported in this paper were identified, together with the effects which they had on the development of the project. The results of this analysis are shown in Table I. Table I. Summary of Causes and Effects Issue Item Attributed Cause Effect Cost Time Other Technological advances in existing equipments Need of matching both new and old technologies Lack of previous verification of existing updated drawings TECHNICAL Need of simplifying operation, erection and commissioning HUMAN Need of keeping the availability of the substation Priority in providing service to customers and testing of the new bay Minor devices not defined during engineer stage Some maintenances people not convinced about removing the old wall mimic Maximum security criteria for commissioning CONTRACTUAL Different organizational units Different magnitude of works and organizational units 4. CONCLUSIONS The main experience reported in this paper arose substantially from the decision taken by C.V.G. EDELCA to contract the work in two separate contracts, one for the supply and installation of the control system and the other one for the works associated with the high voltage switchgear extensions and the integration of the works as a whole. In general, this case shows that this method of contracting for works of modernization or refurbishment implies a greater investment of time and energy on C.V.G. EDELCA s part in the coordination of the project to avoid delays in the supply of energy to the main customer. Not withstanding although it is certain that the work was developed in a segregated manner and with a high level of technical complexity, the harmonious way in which the working team operated, achieved success in the compliance within acceptable limits of the targets for time of execution, cost and quality, as well as the performance of the work without fault and with a high level of security taking into account the operational conditions of the Yaracuy substation. This teamwork was achieved starting from the conceptual and basic engineering stages, right through the detailed engineering, construction, erection testing and commissioning stages, both within C.V.G. EDELCA and jointly with customers CADAFE and ENELBAR. 7

8 As a contribution for future projects of this nature, from the lessons learned during this project, the following are suggested: Evaluate the optimal way for contracting the integration of the new control system and the extensions to the substation. At the outset of the project, define the list of signals and the interface such that the data base for the new control system can be defined at an early stage in the most precise manner possible. During the basic engineering should be defined which existing cables should be replaced in order to reduce the need to disconnect existing panels. From the outset of the project, the sequence of work required in order to avoid outages at both high and low voltage levels, should be defined. Verify, or include in the scope of the contract, the actualization of the As-Built drawings and keep this information up to date. 5. REFERENCES [1] L. Graines, Lifetime assessment and updating of substations, [Cigré 1994, , París] [2] E. Padilla, Experience on numerical substation protection and Control System in EDELCA Network, [Cigré 2000, , París] 8

Toronto Hydro - Electric System

Toronto Hydro - Electric System Toronto Hydro - Electric System FIT Commissioning Requirements and Reports Comments and inquiries can be e-mailed to: FIT@torontohydro.com Customers without e-mail access can submit through regular mail

More information

Specification. NGTS Issue 1 October 1993

Specification. NGTS Issue 1 October 1993 The Electrical Standards for SHE Transmission s area are non-maintained versions of National Grid Technical Specifications that are applicable to the SHE Transmission System only. These specific versions

More information

Definitions. Common Corridor:

Definitions. Common Corridor: Definitions Common Corridor: Contiguous right-of-way or two parallel right-of-ways with structure centerline separation less than the longest span length of the two transmission circuits at the point of

More information

FORENSIC CASEBOOK. By Bob Huddleston, Eastman Chemical Co. One of the most common. reasons for marriage failure

FORENSIC CASEBOOK. By Bob Huddleston, Eastman Chemical Co. One of the most common. reasons for marriage failure The Case of the Energized Cable Cutting Incident How miscommunication leads to an electrical helper slicing through live 13.8kV cable and miraculously walking away to tell about it By Bob Huddleston, Eastman

More information

10/13/2011 Planning Coordination Committee. Standards

10/13/2011 Planning Coordination Committee. Standards Document name Category System Performance Regional Criterion ( ) Regional Reliability Standard (X) Regional Criterion ( ) Policy ( ) Guideline ( ) Report or other Document date 12/01/2011 Adopted/approved

More information

Fieldbus Testing with Online Physical Layer Diagnostics

Fieldbus Testing with Online Physical Layer Diagnostics Technical White Paper Fieldbus Testing with Online Physical Layer Diagnostics The significant benefits realized by the latest fully automated fieldbus construction & pre-commissioning hardware, software

More information

PRINCIPLES AND APPLICATIONS

PRINCIPLES AND APPLICATIONS GENERATION & NETWORK Digital Automation Measuring and Control Devices AMS7000 PROCOM The optimum operation of an electrical network depends particularly on the reliability and the availability of the protection,

More information

HARMONIZATION OF SYNOPTIC BLOCK DIAGRAMS ON THE CONTROL PANELS OF MV SWITCHGEAR AND CONTROLGEAR

HARMONIZATION OF SYNOPTIC BLOCK DIAGRAMS ON THE CONTROL PANELS OF MV SWITCHGEAR AND CONTROLGEAR HARMONIZATION OF SYNOPTIC BLOCK DIAGRAMS ON THE CONTROL PANELS OF MV SWITCHGEAR AND CONTROLGEAR Yvan L. Tits ELECTRABEL 8, Boulevard du Régent, B-1000 Brussels (Belgium) Tel: +32 2 518 62 66 - Fax: +32

More information

Implementation of a High-Speed Distribution Network Reconfiguration Scheme by Greg Hataway, Ted Warren, and Chris Stephens.

Implementation of a High-Speed Distribution Network Reconfiguration Scheme by Greg Hataway, Ted Warren, and Chris Stephens. The following technical papers supporting this presentation are available at www.selinc.com: Trip and Restore Distribution Circuits at Transmission Speeds by Jeff Roberts and Karl Zimmerman International

More information

OFGEM REPORT ON SUPPORT INVESTIGATIONS INTO RECENT BLACKOUTS IN LONDON AND WEST MIDLANDS VOLUME 2 SUPPLEMENTARY REPORT

OFGEM REPORT ON SUPPORT INVESTIGATIONS INTO RECENT BLACKOUTS IN LONDON AND WEST MIDLANDS VOLUME 2 SUPPLEMENTARY REPORT OFGEM REPORT ON SUPPORT INVESTIGATIONS INTO RECENT BLACKOUTS IN LONDON AND WEST MIDLANDS VOLUME 2 SUPPLEMENTARY REPORT PROTECTION COMMISSIONING & PERFORMANCE FEBRUARY 2004 Page i of iv Pages CONTENTS Page

More information

This SOP is applicable to all WMATA personnel working on the Rail System, contractors performing the work and WMATA contractor escorts.

This SOP is applicable to all WMATA personnel working on the Rail System, contractors performing the work and WMATA contractor escorts. RFP: FQ13024/WJG CONTRACT NO. FQ13024 APPENDIX C STANDARD OPERATING PROCEDURES (SOP) SOP #33 REMOVAL AND RESTORATION OF THIRD RAIL POWER FOR WORK BY CONTRACTOR S FORCES MAINLINE, REVENUE SYSTEM PURPOSE

More information

SECTION MEDIUM VOLTAGE CABLE INSTALLATION. 1. Section Underground Ducts and Manholes.

SECTION MEDIUM VOLTAGE CABLE INSTALLATION. 1. Section Underground Ducts and Manholes. SECTION 33 71 49.23 MEDIUM VOLTAGE CABLE INSTALLATION PART 1 GENERAL 1.1 SCOPE A. Work included in this Section: Medium Voltage Cable (4 kv and 12 kv) Installation and Termination. Removal and return of

More information

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements DRAFT 6 V4 Standard PRC-006- RFC-01 01/11/11 A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements Deleted: Deleted: 10 Deleted: 20 9 2. Number: PRC 006 RFC 01. Purpose: To establish

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 21038-D01-2016 Downtown Calgary 138-kV Transmission System Reinforcement June 1, 2016 Alberta Utilities Commission Decision 21038-D01-2016 Downtown Calgary 138-kV Transmission System Reinforcement

More information

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 21317-D01-2016 Central Alberta Underground Fibre Optic Build July 12, 2016 Alberta Utilities Commission Decision 21317-D01-2016 Central Alberta Underground Fibre Optic Build Proceeding 21317 Application

More information

TRF STEP-DOWN TRANSFORMER USER MANUAL

TRF STEP-DOWN TRANSFORMER USER MANUAL TRF STEP-DOWN TRANSFORMER USER MANUA www.ventilation-system.com 2013 ! WARNING The present operation manual consisting of the technical details, operating instructions and technical specification applies

More information

The University of Texas at Austin September 30, 2011

The University of Texas at Austin September 30, 2011 SECTION 27 08 20 COPPER TESTING PART 1 - GENERAL 1.1 SUMMARY A. Test measurements shall be taken for all balanced-twisted pair cabling, including horizontal and backbone copper cables and wall-to-rack

More information

SURGE PROTECTIVE DEVICES

SURGE PROTECTIVE DEVICES SURGE PROTECTIVE DEVICES COMPANY INTRODUCTION Bridex Singapore Pte Ltd is founded in 1978 as a manufacturer of instruments transformer for the Asian market. We are the first local electrical switchgear

More information

Improved Synchronization System for Thermal Power Station

Improved Synchronization System for Thermal Power Station Improved Synchronization System for Thermal Power Station Lokeshkumar.C 1, Logeshkumar.E 2, Harikrishnan.M 3, Margaret 4, Dr.K.Sathiyasekar 5 UG Students, Department of EEE, S.A.Engineering College, Chennai,

More information

User Guide. Centrex Recording Interface

User Guide. Centrex Recording Interface User Guide Centrex Recording Interface Table of Contents Introduction... 2 The Meridian Business Set... 3 Key Numbering Plan (18 button add-on)... 4 Key Numbering Plan (36 button add-on)... 5 Key Numbering

More information

UCR 2008, Change 3, Section 5.3.7, Video Distribution System Requirements

UCR 2008, Change 3, Section 5.3.7, Video Distribution System Requirements DoD UCR 2008, Change 3 Errata Sheet UCR 2008, Change 3, Section 5.3.7, Video Distribution System Requirements SECTION 5.3.7.2.2 CORRECTION IPv6 Profile requirements were changed to a conditional clause

More information

IMS Brochure. Integrated Management System (IMS) of the ILF Group

IMS Brochure. Integrated Management System (IMS) of the ILF Group Br ochur e IMS Brochure Integrated Management System (IMS) of the ILF Group FOREWORD ILF Consulting Engineers always endeavours to precisely analyse the requests and needs of its customers and to subsequently

More information

Aqua Turf International, Inc.

Aqua Turf International, Inc. Satellite Versus Decoder Control System During the irrigation design process a decision must be made whether to chose a satellite or decoder style control system. The decision must be made soon after the

More information

INTERNATIONAL STANDARD

INTERNATIONAL STANDARD INTERNATIONAL STANDARD IEC 60958-3 Second edition 2003-01 Digital audio interface Part 3: Consumer applications Interface audionumérique Partie 3: Applications grand public Reference number IEC 60958-3:2003(E)

More information

Experiences of CESC in Smart Grid Initiatives LT Network Automation. Anjan Mitra / Arka Ghosh

Experiences of CESC in Smart Grid Initiatives LT Network Automation. Anjan Mitra / Arka Ghosh Experiences of CESC in Smart Grid Initiatives LT Network Automation Anjan Mitra / Arka Ghosh CESC An Overview About 120 year old fully Integrated Energy Utility Oldest private electricity utility in India

More information

New York MX700 Room. PWD-NY5-MX700-P60 List Price: $11, SLA Price: $1,100.00/year (Other options available See Appendix B)

New York MX700 Room. PWD-NY5-MX700-P60 List Price: $11, SLA Price: $1,100.00/year (Other options available See Appendix B) New York MX700 Room PWD-NY5-MX700-P60 List Price: $11,000.00 SLA Price: $1,100.00/year (Other options available See Appendix B) Statement of Work (SoW) Project Summary RoomReady will install the following

More information

POWER MONITORS ENERIUM RANGE. Minimize your energy consumption and optimize your installation

POWER MONITORS ENERIUM RANGE. Minimize your energy consumption and optimize your installation POWER MONITORS ENERIUM RANGE Minimize your energy consumption and optimize your installation From 0.2s critical electricity metering to the collection of metering data on all utilities Electrical feeder

More information

1. EXPERT MEETING EXPERT MEETING EXPERT MEETING Feedback from the meeting attendees...

1. EXPERT MEETING EXPERT MEETING EXPERT MEETING Feedback from the meeting attendees... FEEDBACK REPORT STAKE HOLDER CONSULTATION PROCESS OFFSHORE GRID NL Type: Feedback report Work stream Technical Topics: P.01 Planning Filename ONL 15-149 P01_Planning_FBRe_v2 Version 2 public release Pages

More information

Summary Project Specification Consultation Report

Summary Project Specification Consultation Report Project Specification Consultation Report: Maintaining reliability of supply at Townsville South Substation Powerlink Queensland Summary Project Specification Consultation Report 29 October 2018 Maintaining

More information

NERC Reliability Standard PRC-024 Generator Frequency and Voltage Protective Relay Settings

NERC Reliability Standard PRC-024 Generator Frequency and Voltage Protective Relay Settings NERC Reliability Standard PRC-024 024-1 Generator Frequency and Voltage Protective Relay Settings Rick Terrill Luminant Power Generation Compliance NERC Standards Drafting Team Member Reliability Standard

More information

INTERNATIONAL TELECOMMUNICATION UNION DIGITAL SECTIONS AND DIGITAL LINE SYSTEMS DEFINITION OF TERMS RELEVANT TO OPTICAL FIBRE SUBMARINE CABLE SYSTEMS

INTERNATIONAL TELECOMMUNICATION UNION DIGITAL SECTIONS AND DIGITAL LINE SYSTEMS DEFINITION OF TERMS RELEVANT TO OPTICAL FIBRE SUBMARINE CABLE SYSTEMS INTERNATIONAL TELECOMMUNICATION UNION ITU-T G.972 TELECOMMUNICATION (03/93) STANDARDIZATION SECTOR OF ITU DIGITAL SECTIONS AND DIGITAL LINE SYSTEMS DEFINITION OF TERMS RELEVANT TO OPTICAL FIBRE SUBMARINE

More information

Special Specification 6293 Adaptive Traffic Signal Control System

Special Specification 6293 Adaptive Traffic Signal Control System Special Specification Adaptive Traffic Signal Control System 1. DESCRIPTION 2. MATERIALS Furnish, install, relocate, or remove adaptive traffic signal control (ATSC) system software and equipment at locations

More information

OECD COMMUNICATIONS OUTLOOK 2001 Broadcasting Section

OECD COMMUNICATIONS OUTLOOK 2001 Broadcasting Section OECD COMMUNICATIONS OUTLOOK 2001 Broadcasting Section Country: HUNGAR Date completed: 13 June, 2000 1 BROADCASTING Broadcasting services available 1. Please provide details of the broadcasting and cable

More information

SPECIAL SPECIFICATION :1 Video (De) Mux with Data Channel

SPECIAL SPECIFICATION :1 Video (De) Mux with Data Channel 1993 Specifications CSJ 0924-06-223 SPECIAL SPECIFICATION 1160 8:1 Video (De) Mux with Data Channel 1. Description. This Item shall govern for furnishing and installing an 8 channel digital multiplexed

More information

Maintenance and upgrade of a BARCO video wall installed in the Crisis Room of the ECML

Maintenance and upgrade of a BARCO video wall installed in the Crisis Room of the ECML EUROPEAN COMMISSION JOINT RESEARCH CENTRE Institute for the Protection and Security of the Citizen (IPSC) Ref. Ares(2016)2988563-28/06/2016 ANNEX I TO CONTRACT. Maintenance and upgrade of a BARCO video

More information

Camera and Communication Systems for hazardous Areas. SAMCON Topical Booklet No. 0001

Camera and Communication Systems for hazardous Areas. SAMCON Topical Booklet No. 0001 Camera and Communication Systems for hazardous Areas SAMCON Topical Booklet No. 0001 See...what cannot be seen. Why use a camera when practically nothing can be seen through an inspection window with the

More information

db Broadcast reflect on their role in the largest broadcasting engineering project ever undertaken in the UK Digital Switchover

db Broadcast reflect on their role in the largest broadcasting engineering project ever undertaken in the UK Digital Switchover db Broadcast and Digital Switchover db Broadcast reflect on their role in the largest broadcasting engineering project ever undertaken in the UK Digital Switchover The digital switchover programme (DSO)

More information

Mitigation of Cascading Outages and Prevention of Blackouts:System-Wide Corrective Control

Mitigation of Cascading Outages and Prevention of Blackouts:System-Wide Corrective Control 10th Mediterranean Conference on Power Generation, Transmission, Distribution and Energy Conversion 6-9 November 2016 Belgrade, Serbia Mitigation of Cascading Outages and Prevention of Blackouts:System-Wide

More information

Online Control System Migration of Industrial Centrifuge Project Description

Online Control System Migration of Industrial Centrifuge Project Description Canadian Consulting Engineering Awards 2017 Online Control System Migration of Industrial Centrifuge Project Description Category: Natural Resources, Mining, Industry & Energy Fort McMurray, AB Table of

More information

INTERNATIONAL STANDARD

INTERNATIONAL STANDARD INTERNATIONAL STANDARD IEC 60958-1 Second edition 2004-03 Digital audio interface Part 1: General Reference number IEC 60958-1:2004(E) Publication numbering As from 1 January 1997 all IEC publications

More information

SITE All work shall be performed at Center Park Substation (1895 Kernan Blvd, Jacksonville, Fl ). DATE: 04/03/2018

SITE All work shall be performed at Center Park Substation (1895 Kernan Blvd, Jacksonville, Fl ). DATE: 04/03/2018 DATE: 04/03/2018 TO: The Contractor FROM: System Protection & Control Projects 20413 SUBJECT: Technical Specifications for Center Park APSTF Project PROJECT OVERVIEW This is a general specification that

More information

Generator protection relay

Generator protection relay Page 1 Issued: April 1999 Status: New Data subject to change without notice Features Off-the-shelf generator protection relay for small and medium sized power generators Three-phase time overcurrent and

More information

0.1. Outage Management Process Summary

0.1. Outage Management Process Summary 0.1 Outage Management Process Summary Issue: 1.0 Issue Date: August 27, 2014 Table of Contents 1. Introduction... 4 1.1 Purpose... 4 1.2 Glossary... 4 State Transition Model... 8 2. Outage Management Processes...

More information

Ground Frames and Shunters Releases

Ground Frames and Shunters Releases Ground Frames and Shunters Synopsis This document mandates the interface requirements for ground frames and shunters releases that may be operated by railway undertaking personnel. Copyright in the s is

More information

ACTIVE IF SPLITTER/COMBINER UHP-IFS

ACTIVE IF SPLITTER/COMBINER UHP-IFS ACTIVE IF SPLITTER/COMBINER UHP-IFS GENERAL DESCRIPTION AND INSTALLATION GUIDE DOCUMENT RELEASE 2 [UHP.IFS.2.EN] JUNE 2016 CONTENT Acronyms and Abbreviations... 4 Introduction... 5 Required level of qualification...

More information

Report on Comments June 2013 NFPA 70

Report on Comments June 2013 NFPA 70 10-1 Log #1392 NEC-P10 Dennis Darling, Stantec Consulting Ltd. 10-5 Delete text to read as follows: Localization of an overcurrent condition to restrict outages to the circuit or equipment affected, accomplished

More information

Signalling Cable Equivalent Sizes

Signalling Cable Equivalent Sizes Signalling Cable Equivalent Sizes Signatures removed from electronic version Submitted by... Jim Harper Nominated Responsible Manager Synopsis This Standard Authorises the use of cables to GS/ES 0872 as

More information

CHIEF BROADCAST ENGINEER

CHIEF BROADCAST ENGINEER PERSONNEL COMMISSION Class Code: 5150 Salary Range: 45 (M2) CHIEF BROADCAST ENGINEER JOB SUMMARY Under general direction, plan, organize, manage and participate in the on-air/technical operations and maintenance

More information

I 1 CASE STUDY. AccorHotels SAT. Kathrein Solutions for Hotels and Guest Houses

I 1 CASE STUDY. AccorHotels SAT. Kathrein Solutions for Hotels and Guest Houses I 1 CASE STUDY AccorHotels SAT Kathrein Solutions for Hotels and Guest Houses 2 I Kathrein I Company Portrait Who we are and what we stand for Kathrein is a leading international specialist for reliable,

More information

THE GARABI 2000 MW INTERCONNECTION BACK-TO-BACK HVDC TO CONNECT WEAK AC SYSTEMS

THE GARABI 2000 MW INTERCONNECTION BACK-TO-BACK HVDC TO CONNECT WEAK AC SYSTEMS THE GARABI 2000 MW INTERCONNECTION BACK-TO-BACK HVDC TO CONNECT WEAK AC SYSTEMS John Graham Birger Jonsson R.S. Moni Brazil Sweden India ABB Utilities AB, SE-771 80 Ludvika, Sweden SUMMARY The Argentina

More information

FINAL REPORT LOAD SHEDDING IN TASMANIA ON 20 DECEMBER 2016 REVIEWABLE OPERATING INCIDENT REPORT FOR THE NATIONAL ELECTRICITY MARKET

FINAL REPORT LOAD SHEDDING IN TASMANIA ON 20 DECEMBER 2016 REVIEWABLE OPERATING INCIDENT REPORT FOR THE NATIONAL ELECTRICITY MARKET FINAL REPORT LOAD SHEDDING IN TASMANIA ON 20 DECEMBER 2016 REVIEWABLE OPERATING INCIDENT REPORT FOR THE NATIONAL ELECTRICITY MARKET Published: 6 April 2017 IMPORTANT NOTICE Purpose AEMO has prepared this

More information

HONEYWELL VIDEO SYSTEMS HIGH-RESOLUTION COLOR DOME CAMERA

HONEYWELL VIDEO SYSTEMS HIGH-RESOLUTION COLOR DOME CAMERA Section 00000 SECURITY ACCESS AND SURVEILLANCE HONEYWELL VIDEO SYSTEMS HIGH-RESOLUTION COLOR DOME CAMERA PART 1 GENERAL 1.01 SUMMARY The intent of this document is to specify the minimum criteria for the

More information

CITY OF LOS ANGELES CIVIL SERVICE COMMISSION CLASS SPECIFICATION POSTED JUNE VIDEO TECHNICIAN, 6145

CITY OF LOS ANGELES CIVIL SERVICE COMMISSION CLASS SPECIFICATION POSTED JUNE VIDEO TECHNICIAN, 6145 CITY OF LOS ANGELES CIVIL SERVICE COMMISSION CLASS SPECIFICATION POSTED JUNE 1999 04-26-96 VIDEO TECHNICIAN, 6145 Summary of Duties: Operates municipal access equipment for City departments, City Council

More information

V9A01 Solution Specification V0.1

V9A01 Solution Specification V0.1 V9A01 Solution Specification V0.1 CONTENTS V9A01 Solution Specification Section 1 Document Descriptions... 4 1.1 Version Descriptions... 4 1.2 Nomenclature of this Document... 4 Section 2 Solution Overview...

More information

Request for Proposal Questions and Responses. Request for Proposal: Software Based CMED Radio Console and Associated Equipment

Request for Proposal Questions and Responses. Request for Proposal: Software Based CMED Radio Console and Associated Equipment Request for Proposal Questions and Responses Request for Proposal: Software Based CMED Radio Console and Associated Equipment Proposal Due Date: Friday December 14, 2018 All Prospective Proposers: In reference

More information

Design and Realization of the Guitar Tuner Using MyRIO

Design and Realization of the Guitar Tuner Using MyRIO Journal of Automation and Control, 2017, Vol. 5, No. 2, 41-45 Available online at http://pubs.sciepub.com/automation/5/2/2 Science and Education Publishing DOI:10.12691/automation-5-2-2 Design and Realization

More information

Recovering and Relaying Cables

Recovering and Relaying Cables Upgrades Edition 79 Recovering and Relaying Cables For Building New Subsea Systems Bertrand Clesca Why Cable Relay? With the prevalence of submarine cable systems in international communications, two trends

More information

AUTOMATIC VIDEO LOSS A/B SWITCH

AUTOMATIC VIDEO LOSS A/B SWITCH CG-X AUTOMATIC VIDEO LOSS A/B SWITCH INSTRUCTION BOOK IB647502 TABLE OF CONTENTS DESCRIPTION 2 MOUNTING INSTRUCTIONS 3 HOW TO CABLE THE CG-X 3 POWER SUPPLY INSTALLATION 3 OPERATION 3 CARE AND MAINTENANCE

More information

Intelligent solutions for Onshore Power Supply

Intelligent solutions for Onshore Power Supply Intelligent solutions for Onshore Power Supply Dipl. Ing. H.-E. Schmidt Account Manager OPS SIEMENS AG GER IC 20099 Hamburg September 2012 Siemens AG 2012 Ship to shore connection Nordlandkai Lübeck, Germany

More information

A. Almeida.do Vale M. J. Dias Gongalves Zita A. Vale Member,IEEE

A. Almeida.do Vale M. J. Dias Gongalves Zita A. Vale Member,IEEE IMPROVING MAN-MACHINE INTERACTION IN CONTROL CENTERS: THE IMPORTANCE OF A FULL-GRAPHICS INTERFACE A. Almeida.do Vale M. J. Dias Gongalves Zita A. Vale Member,IEEE University of Porto/Faculty of Engineering

More information

Guatemala Capital Area Digital Telephone Network Improvement and Expansion Project

Guatemala Capital Area Digital Telephone Network Improvement and Expansion Project Guatemala Capital Area Digital Telephone Network Improvement and Expansion Project 1. Project Profile and Japan s ODA Loan Report date: March 2001 Field survey: August 2000 Project site Site Map: Guatemala

More information

Dual Link DVI Receiver Implementation

Dual Link DVI Receiver Implementation Dual Link DVI Receiver Implementation This application note describes some features of single link receivers that must be considered when using 2 devices for a dual link application. Specific characteristics

More information

RECOGNITION OF PRIOR LEARNING CANDIDATE APPLICATION FORM UEE30811 CERTIFICATE III IN ELECTROTECHNOLOGY - ELECTRICIAN

RECOGNITION OF PRIOR LEARNING CANDIDATE APPLICATION FORM UEE30811 CERTIFICATE III IN ELECTROTECHNOLOGY - ELECTRICIAN RECOGNITION OF PRIOR LEARNING CANDIDATE APPLICATION FORM UEE30811 CERTIFICATE III IN ELECTROTECHNOLOGY - ELECTRICIAN APPLICATION FORM MUST BE FULLY D TO PROCEED WITH THE RPL PROCESS. PLEASE ENSURE THE

More information

Signalling Cable Equivalent Sizes (formerly RT/E/C/11213)

Signalling Cable Equivalent Sizes (formerly RT/E/C/11213) NR/GN/SIG/11213 Ref Date (formerly RT/E/C/11213) This temporary front sheet facilitates change to the new Network Rail Standards referencing nomenclature. The Ref above will be formally allocated to this

More information

AMERICAN NATIONAL STANDARD

AMERICAN NATIONAL STANDARD ENGINEERING COMMITTEE Interface Practices Subcommittee AMERICAN NATIONAL STANDARD ANSI/SCTE 76 2007 Antenna Selector Switches NOTICE The Society of Cable Telecommunications Engineers (SCTE) Standards are

More information

ITU-T Y Functional framework and capabilities of the Internet of things

ITU-T Y Functional framework and capabilities of the Internet of things I n t e r n a t i o n a l T e l e c o m m u n i c a t i o n U n i o n ITU-T Y.2068 TELECOMMUNICATION STANDARDIZATION SECTOR OF ITU (03/2015) SERIES Y: GLOBAL INFORMATION INFRASTRUCTURE, INTERNET PROTOCOL

More information

Sensor module. Safety instructions. Function Correct use. Product characteristics. Structure of the device. Operation. Ref.No.

Sensor module. Safety instructions. Function Correct use. Product characteristics. Structure of the device. Operation. Ref.No. Sensor module Ref.No.: SM 1608 V03 Safety instructions Caution! Electrical devices may only be installed and fitted by electrically skilled persons. Non-compliance with the installation information could

More information

MATE3 Owner s Manual Addendum

MATE3 Owner s Manual Addendum Purpose MATE3 Owner s Manual Addendum This document is an addendum to 900-0117-01-00, Revision C of the MATE3 System Display and Controller Owner s Manual. It provides descriptions of changes to the MATE3

More information

SINAMICS G130 / G150. Line harmonics filter. Operating Instructions 05/2010 SINAMICS

SINAMICS G130 / G150. Line harmonics filter. Operating Instructions 05/2010 SINAMICS SINAMICS G130 / G150 Line harmonics filter Operating Instructions 05/2010 SINAMICS s Safety information 1 General 2 SINAMICS SINAMICS G130 / G150 Operating Instructions Mechanical installation 3 Electrical

More information

This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents

This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents 2009R0642 EN 12.09.2013 001.001 1 This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents B COMMISSION REGULATION (EC) No 642/2009 of 22

More information

Emerging Subsea Networks

Emerging Subsea Networks THE CHALLENGES OF COMPLETING AN OIL & GAS CABLE SYSTEM ORDER Jerry Brown, Rendong Xu, Guilin Sun, Lei Zhang, Changji Hao, Xiong Wang, Hongli Qu, Di Wu, Fu Feng, Yin Jiang (Hengtong Marine Cable Systems)

More information

Designing Intelligence into Commutation Encoders

Designing Intelligence into Commutation Encoders I Designing Intelligence into Commutation Encoders By: Jeff Smoot, CUI Inc C U I NC Encoder users traditionally have been reluctant to change with good reason. Motor control on the factory floor or in

More information

3WS(Cape Town/Secretariat)1

3WS(Cape Town/Secretariat)1 For IEC use only 3WS(Cape Town/Secretariat)1 2005-10-04 INTERNATIONAL ELECTROTECHNICAL COMMISSION Technical Committee No. 3: Information structures, documentation and graphical symbols Occurrence-related

More information

DMX 512 Language Date: Venerdì, febbraio 12:15:08 CET Topic: Educational Lighting Site

DMX 512 Language Date: Venerdì, febbraio 12:15:08 CET Topic: Educational Lighting Site DMX 512 Language Date: Venerdì, febbraio 15 @ 12:15:08 CET Topic: Educational Lighting Site DMX512 Cable Connectors Principles of functioning Distaces Terminations Splitter & Buffer DMX 1990 Until a few

More information

Case analysis: An IoT energy monitoring system for a PV connected residence

Case analysis: An IoT energy monitoring system for a PV connected residence Case analysis: An IoT energy monitoring system for a PV connected residence Marcus André P. Oliveira, 1, Wendell E. Moura Costa 1, Maxwell Moura Costa 1, 1 IFTO Campus Palmas marcusandre@ifto.edu.br, wendell@ifto.edu.br,

More information

Improving Lightning Protection of Power Systems with Externally Gapped Line Arresters (EGLA)

Improving Lightning Protection of Power Systems with Externally Gapped Line Arresters (EGLA) Improving Lightning Protection of Power Systems with Externally Gapped Line Arresters (EGLA) Jonathan Woodworth ArresterWorks 1 Today's Presentation 1. Real Value of Arresters 2. Improving Distribution

More information

If you want to get an official version of this User Network Interface Specification, please order it by sending your request to:

If you want to get an official version of this User Network Interface Specification, please order it by sending your request to: This specification describes the situation of the Proximus network and services. It will be subject to modifications for corrections or when the network or the services will be modified. The reader is

More information

multi-function meters

multi-function meters multi-function meters eclipse 2 eclipse 7 installation and operating manual 1 GENERAL DESCRIPTION 2 INSTALLATION 3 WIRING INFORMATION 4 2 ECLIPSE 2 METERS 2.1 PROGRAMMING THE METER 5 2.2 INFORMATION 6

More information

-Technical Specifications-

-Technical Specifications- Annex I to Contract 108733 NL-Petten: the delivery, installation, warranty and maintenance of one (1) X-ray computed tomography system at the JRC-IET -Technical Specifications- INTRODUCTION In the 7th

More information

DIGITAL INSTRUMENTS S.R.L. SPM-ETH (Synchro Phasor Meter over ETH)

DIGITAL INSTRUMENTS S.R.L. SPM-ETH (Synchro Phasor Meter over ETH) DIGITAL INSTRUMENTS S.R.L. SPM-ETH (Synchro Phasor Meter over ETH) SPM-ETH (Synchro Phasor Meter over ETH) Digital Instruments 1 ver the years, an awareness of the criticality of the Power Grid and Orelated

More information

Study on Economic Partnership Projects. in Developing Countries in FY2008. Study on Digitalization of Terrestrial TV

Study on Economic Partnership Projects. in Developing Countries in FY2008. Study on Digitalization of Terrestrial TV Study on Economic Partnership Projects in Developing Countries in FY2008 Study on Digitalization of Terrestrial TV Broadcasting Systems in the Republic of the Philippines SUMMARY March 2009 Marubeni Corporation

More information

Research on Control Strategy of Complex Systems through VSC-HVDC Grid Parallel Device

Research on Control Strategy of Complex Systems through VSC-HVDC Grid Parallel Device Sensors & Transducers, Vol. 75, Issue 7, July, pp. 9-98 Sensors & Transducers by IFSA Publishing, S. L. http://www.sensorsportal.com Research on Control Strategy of Complex Systems through VSC-HVDC Grid

More information

Identification - electrical services

Identification - electrical services Identification - electrical services Aesthetic All live phase cable sheathing to be brown coloured and neutral phase cable sheathing to be blue coloured, all labelled L1, L2, L3 & N respectively in accordance

More information

COMMISSIONING AND ACCEPTANCE

COMMISSIONING AND ACCEPTANCE Tutorial COMMISSIONING AND ACCEPTANCE Corrado Rocca 1 Introduction TUTORIAL OUTLINE The Acceptance process within the contractual Plan of Work The Acceptance periods From Product Design acceptance to System

More information

White Paper. Power over Coax. HDCVI technology evolution, Simplify wiring and maintenance. White Paper by Dahua Technology. Release 1.

White Paper. Power over Coax. HDCVI technology evolution, Simplify wiring and maintenance. White Paper by Dahua Technology. Release 1. Power over Coax HDCVI technology evolution, Simplify wiring and maintenance White Paper by Dahua Technology Release 1.0 Table of contents 1 What is PoC... 2 2 Development of PoC... 2 2.1 Technology development...

More information

March 14, Gentlemen;

March 14, Gentlemen; March 14, 2012 Gentlemen; My name is James Kelley and I am a resident of the City of Charlottesville. First, allow me to thank you for the opportunity to address with you a cable television system change

More information

Form C: Type Test Verification Report

Form C: Type Test Verification Report Form C: Type Test Verification Report Type Approval and Manufacturer declaration of compliance with the requirements of G98. This form should be used when making a Type Test submission to the Energy Networks

More information

Form C: Type Test Verification Report

Form C: Type Test Verification Report Form C: Type Test Verification Report Type Approval and Manufacturer declaration of compliance with the requirements of G98. This form should be used when making a Type Test submission to the Energy Networks

More information

Review of the Comcast. Fort Collins Cable System. Technical Characteristics

Review of the Comcast. Fort Collins Cable System. Technical Characteristics Review of the Comcast Fort Collins Cable System Technical Characteristics Prepared by: January 30, 2004 Dick Nielsen Senior Engineer CBG Communications, Inc. Introduction and Background CBG Communications,

More information

AMERICAN NATIONAL STANDARD

AMERICAN NATIONAL STANDARD Interface Practices Subcommittee AMERICAN NATIONAL STANDARD ANSI/SCTE 108 2018 Test Method for Dielectric Withstand of Coaxial Cable NOTICE The Society of Cable Telecommunications Engineers (SCTE) / International

More information

Laying of cables and lines in electrical installations and data networks

Laying of cables and lines in electrical installations and data networks Technical bulletin Laying of cables and lines in electrical installations and data networks Date: 08/2006 This technical bulletin provides you with information on specific technical subjects. It is based

More information

HIGH COURT OF BOMBAY AT GOA

HIGH COURT OF BOMBAY AT GOA HIGH COURT OF BOMBAY AT GOA Calling Quotations for Supply and Installation of Wireless Synchronized Digital Clocks Quotations are invited from the Manufacturers/Suppliers of Wireless Synchronized Digital

More information

Henkel Installation Handbook LINEGUARD 2001

Henkel Installation Handbook LINEGUARD 2001 Henkel Installation Handbook LINEGUARD 2001 HENKEL ITALIA S.r.l. Microprocessor instruments Henkel Installation Handbook Lineguard 2001 Page 2 Summary 1. The Microprocessor Instruments... 4 1.1. Norms

More information

ADS Basic Automation solutions for the lighting industry

ADS Basic Automation solutions for the lighting industry ADS Basic Automation solutions for the lighting industry Rethinking productivity means continuously making full use of all opportunities. The increasing intensity of the competition, saturated markets,

More information

220KV EHV NETWORK AT RELIANCE JAMNAGAR REFINERY COMPLEX

220KV EHV NETWORK AT RELIANCE JAMNAGAR REFINERY COMPLEX 220KV EHV NETWORK AT RELIANCE JAMNAGAR REFINERY COMPLEX JAMNAGAR 220KV CABLE NETWORK: 2 2. DESIGN 2A. NETWORK: 220 KV NETWORK DESIGN IS DESIGNED WITH 100% REDUNDANCY FROM 220 KV BUS TO LOAD. THIS IS ACHIEVED

More information

Automatic Transfer Switch Control PLC Operator s Manual

Automatic Transfer Switch Control PLC Operator s Manual MTS Power Products MIAMI FL 33142 ATS-22AG Automatic Transfer Switch Control PLC Operator s Manual Dedicated Single Phase Transfer Switch ATS-22AG Automatic Transfer Switch INTRODUCTION 1.1 Preliminary

More information

3M Sensored Termination (15 kv) QX-T15I-vi1-E

3M Sensored Termination (15 kv) QX-T15I-vi1-E 3M Sensored Termination () QX-T15I-vi1-E Data Sheet May 2016 Kit Contents: Each kit contains sufficient quantities of the following materials to make three single-phase terminations. 31" (REF) One piece

More information

A Versatile New Intercom System

A Versatile New Intercom System Key, or push-button, telephones have made the telephone station an almost universal tool for everyday communications. The 6A Key Telephone System, recently developed at Bell Laboratories, adds significantly

More information

Notes Generator Verification SDT Project

Notes Generator Verification SDT Project Notes Generator Verification SDT Project 2007-09 FERC Office 888 First Street, NE Washington, DC 20426 1. Administration a. The following were in attendance: Bob Snow, Cynthia Pointer, Lim Hansen, Keith

More information

All-digital planning and digital switch-over

All-digital planning and digital switch-over All-digital planning and digital switch-over Chris Nokes, Nigel Laflin, Dave Darlington 10th September 2000 1 This presentation gives the results of some of the work that is being done by BBC R&D to investigate

More information