WHAT IS NEW AT CERN?

Size: px
Start display at page:

Download "WHAT IS NEW AT CERN?"

Transcription

1 WHAT IS NEW AT CERN? Dominique Missiaen, Antje Behrens, Patrick Bestmann, Jean-Frédéric Fuchs, Jean- Christophe Gayde, Mark Jones, Hélène Mainaud Durand, Antonio Marin, Dirk Mergelkuhl, Mateusz Sosin, CERN, Geneva, Switzerland Abstract Since 2009, the LHC has running very well and this year reached an energy of 4TEV, producing more luminosity than expected. At the end of 2011 the LHC experiments Atlas and CMS had both accumulated 5 fb-1. This has left very little time to access the tunnels and accomplish survey campaigns, except for some repositioning of the low beta quadrupoles and a measurement of sector 78 which has been a very unstable area since the era of LEP. From the end of 2012 up to November 2014, a long shut down will take place in order to repair the splices in the LHC interconnections, allowing in the future an energy of 7 TEV. This period will be used by the survey team to remeasure all the components of the LHC in the vertical and horizontal directions. The LHC collimator train also completed its first measurements during the last winter technical stop and studies for a new LHC survey train have been started. The Linac4 project, future proton source for the LHC injectors, is progressing slowly but work has been done for the fiducialisation of components and the determination of the geodetic network necessary for the installation of the infrastructure in the tunnel. The HIE-Isolde project has provided the opportunity to study a permanent monitoring system using the BCAM technology. This paper will present the status of all these activities and studies as well as the strategy for the survey activities during the next long shut-down. INTRODUCTION While the LHC and the injectors are running, the survey team is working on the alignment of new projects such as linac4, HIE-Isolde and the preparatory work for the LHC experiments upgrades planned for the next long shut-down and the non-lhc experiments. Studies have also started concerning the possibility of realising the automatic survey of LHC arcs and several sensors have been tested. During the technical stops of 2 months at the end of each year, an access is possible in the tunnels allowing preventative survey in the unstable areas and the first measurements with the train for the survey of the LHC collimators. A long shut-down of almost two years, called Long shut down 1 (LS1), has been scheduled to repair the splices in the LHC interconnects and this period will be used by the survey team to maintain the vertical and horizontal alignment of the whole LHC components and its injectors chain and to consolidate the low β quadrupoles permanent monitoring system. The survey team will also be deeply involved in important upgrades of the LHC Experiments such as the change of beam pipes for ATLAS, CMS and LHCb or new detector parts installations in ALICE and others. This will lead to a full opening of the detectors and a huge demand of survey measurements. LHC ACTIVITIES Survey and realignment Since 2009, the LHC runs very well with a maximum of time dedicated to physics. The schedule only allows some access in the tunnel during a winter technical stop which takes place at the end of each year and lasts about two months. Figure 1 : vertical smoothing in The sector 78 of the LHC, which has been detected very unstable since the era of the LEP has been remeasured in the vertical plane during the technical stop of and the well known hole of the LHC has been realigned as show on figure 1. The same measurement has been done during the last technical stop in in vertical and in horizontal as the LHC is critical in both planes and has not been measured in H since In the vertical direction, the hole was not observed with the direct levelling done with the DNA03 and Na2 and no re-alignment was done. But a deep analysis of the data taken with the AT401 [1] showed that the hole reappeared this year as well. In the horizontal plane, despite the fact that the magnets were re-aligned many times in vertical since 2009, there was no major displacement of the magnets. A total of 38 magnets that were far away from the smooth curve by more than 0.25

2 mm were realigned, among those only two were at almost 1 mm [1]. The LHC collimators survey train For the first time during the technical stop , the train for the remote survey of collimators [2] was tested in the Long Straight Section 7 measuring 200 m of collimators on each part of the IP7. The same measurements using standard techniques such as direct levelling and ecartometry were also realized allowing a comparison between both methods. In the horizontal plane, the remote measurements taken with the train are very similar with the standard ones as shown on Figure 2. In the vertical plane, some geoid corrections have still to be implemented in the final calculation. The main movements observed on these magnets are in the vertical plane where the Q1s are sinking while the Q3s are going in the opposite direction. This is particularly visible in points 1 and 5 where a new cavern has been built for the LHC experiments as shown on Figure 3. There were no real request from the Physics and Operation for realignments but the main goal for the survey team was to have these magnets in a smooth position with respect to the experiments on one hand and the magnets located in the Long Straight Sections on the other hand. During the realignment of the Q2 located on the right side of point 5 where a radial displacement of 25 μm was requested, we had the surprise to observe, thanks to our permanent monitoring system, the displacement of this cryo-magnet by 0.8 mm in the horizontal direction and mm in the vertical. This phenomenon is due to the fact that there are too many constraints in the interconnections between the magnets mainly due to tie rods which prevent the cryostat to move longitudinally the ones w.r.t the others and to bumpers which prevent the triplet to move towards the experiment. Figure 2 : horizontal position of collimators This test was globally very promising while some improvements concerning communication and software have been decided and already undertaken. The next step will be the measurements of the same zone and the collimators around point 3 during the LS1. Repositioning of the low β quadrupoles Despite the fact that the repositioning of the low β quadrupoles can be done remotely and doesn t require an access in the tunnel, a repositioning of these critical magnets took place during the technical stop for the points 2 (Alice) and 8 (LHCb) and during the one of for the magnets located around points 1 (Atlas) and 5 (CMS). CRYOSTAT JACK SENSOR + HARDENED INTERFACE WASHERS ACTUATOR Figure 4 : load sensors - strain gauge (washer type) As a matter of fact the cryostats were not supported only by their jacks but also by the interconnections themselves. This problem triggered the decision to install load sensors (Figure 4) between the jacks and the cryostats. These sensors will measure the weight applied by the cryostat on each jack and will help the survey operator to take the right action during a realignment operation. The installation has started in 2012 and will be completed during the LS1 [3][4]. Figure 3 : vertical position of the low β quads around IP5

3 Train studies LHC STUDIES The pre-studies for a new train generation have already started based on the experiences with the collimator survey train. The most delicate and complicated part of the train is the stretched wire reference which is used also in the vertical plane. This requires a very precise knowledge about the wire parameters and a wellcontrolled environment. It is impossible to ensure this for larger parts of the LHC and a new concept for the vertical measurements has to be developed. First tests have shown that the Ultrasonic HLS gives very promising results for a mobile application on the train. This system can be used to determine the height difference between two mobile parts of the train. The link with the magnets is done again using digital close range photogrammetry which worked very well already on the collimator train. The mobile HLS application is a compromise between the micrometric precision which can be achieved by these systems and the rough train conditions in which it will be implemented. The temperature gradients inside the flexible water tubes and the stabilisation of the water surface are limiting the HLS performance but it is still possible to achieve the precision of an optical level. The concept for the radial measurements has slightly changed as well. Instead of using optical laser micrometers around the wire, the new concept is working with photogrammetry only. Technically it is possible to measure the wire position directly with photogrammetry but the environment must be well under control. First tests done on several types of wire (Figure 5) gave results better than 30 µm in the determination of position. Figure 5 : different types of wire (iron, fishing, carbon peek and vectran) detected by photogrammetry Depth of scene, background, contrast and illumination are parameters playing an essential role for the precision and reliability of such a system and not all parameters can be fully controlled in the LHC. Major developments have to be done in order to make this reliable and fully automatic. Mechanically the most important modification will be the use of modular robotic arms for the manipulation of the sensor heads and wire anchorage. This arm is manipulating already the existing sensors for tests with excellent precision and great results so far. LINAC4 LINAC4As first step of the LHC luminosity upgrade program CERN is building a new 160 MeV H linear accelerator (Figure 6), Linac4, to replace the 50 MeV Linac2 as injector to the PS Booster (PSB). PIMS CCDTL DTL chopper line 160 MeV 104 MeV 50 MeV 3 MeV 86 m Figure 6 : Linac4 layout Installation of the machine infrastructure has been progressing since the delivery by the civil engineering company of the Linac4 building and tunnel at end All equipment has been preliminarily integrated into an extensive 3-D computer model which allowed an early solution of interference problems. The infrastructure installation will be completed in September 2012, to leave place to the installation of machine components. The beam line and assembly reference points were marked on the ground tunnel and a scan of the installed infrastructure in both the surface building and the tunnel was undertaken. Network determination During the Xmas Break 2011/2012 a new determination of the underground geodetic reference network along the main LINAC tunnel and the transfer line tunnel has been accomplished using AT401 and Gyromat3000 measurements. The new coordinates in the CCS (CERN Coordinate System) of the survey reference targets in the tunnel floor of the L4 have been determined by a final calculation with constraints on the reference marks of the Booster. The removable survey pillars will be soon installed and added to the L4 network. Everything is ready for the jack installation that has started in September (source, LEBT, RFQ, MEBT) and should be completed for all the L4 machine components in the beginning of The 3 MeV test stand The section up to 3 MeV is being installed and commissioned in a dedicated test stand. The LEBT is in place and the RFQ, built entirely in the CERN Workshop, has been installed and will be aligned soon. The first diagnostic line should be installed in a few months. All the 3 MeV elements will be transferred and aligned in 2013 to their locations in the Linac4 tunnel. Fiducialisation A complete metrology measurement of the first CCDTL module (Figure 7) has been done in Russia (BINP, Novosibirsk) in June with an API laser tracker in order to check feasibility of the 6 ½ tanks assembly and the geometry of the axis composed by the 6 drift tubes. RFQ

4 Figure 7 : metrological check of the first CCDTL The first DTL and CCDTL modules should be delivered in few months at CERN and many metrology measurements will be necessary with laser tracker before tunnel alignment. Beam commissioning of the linac4 will take place in steps of increasing energy between 2013 and From end of 2014 Linac4 could deliver 50 MeV protons in case of Linac2 failure. HIE-ISOLDE The HIE ISOLDE project is a major upgrade of the ISOLDE REX facility. The goal is to increase the energy and quality of the radioactive ion beams delivered to the experiments. The beams will be accelerated in a superconducting linac made of 6 cryo-modules (Figure 8) containing superconductive RF cavities and solenoids. The cryo-modules will share the insulation vacuum with the beam vacuum. The system is mainly based on well-proved elements such as the Brandeis CCD Angle Monitor (BCAM) devices [7]. The key elements such as the viewports and the possible target types have been studied and tested in different environments, including the constraints due to vacuum or cryogenic conditions. A HBCAM camera which is an upgrade of the proved BCAM is under development. Implementation of a new CCD, mechanical adaptation changes, focal length upgrade to increase the field of view and integration of an illumination ring are foreseen. First steps are encouraging and no important problem is expected. The software development [8] is well advanced. The mathematical model and main software modules for the reference frame reconstruction are ready. The validation started successfully on a partial but almost full size mockup. The HIE-Isolde Alignment System technological options are now almost all fixed. The goal is to be ready to install the first alignment system once the first cryomodule will be assembled and ready for vacuum and cryogenic tests. In the meantime more standard survey is being prepared to cover the needs of the cryomodule assembly in a class 5 clean room on The survey infrastructure integration in the global layout is under study. Simultaneously, preparatory work for the linac prealignment, the transfer line installation and alignment is on-going. Beam commissioning at 5.5MeV/u is foreseen for the end of the 2014 run and physics for the start of Two additional high-beta cryomodules will be installed in The two low-beta cryomodules completing the linac are foreseen for a later stage after ACTIVITIES FORESEEN DURING LS1 The LHC and its injectors Figure 8 : The HIE-ISOLDE Linac To run the linac in the optimum conditions an integrated permanent alignment system [6], based on opto-electronic sensors, optics and precise mechanical elements, is being developed. It aims to guaranty positioning and monitoring of the cryo-module active elements with precisions of 0.3 mm for the RF cavities and 0.15 mm for the solenoids at one sigma level along directions perpendicular to the beam axis. The concept is to create a permanently controlled reference frame in which the fiducial marks of the active elements will be observed. Figure 9 : the LHC and the injectors chain Initially foreseen to repair the splices of the LHC interconnects in order to run the machine at 7 TEV, the LS1 has been scheduled for a period of 20 months starting at the end of Taking into account that the next long shut down (LS2) is scheduled in 2018, many services decided to organize a heavy maintenance of their

5 equipment not only in the LHC but also in the injectors chain (Figure 9). The survey team, in close collaboration with the Accelerator & Beam Physics and Operation groups decided to launch a huge campaign of survey and realignment which includes: - The PS Ring which was surveyed for the last time in The PS Booster, surveyed in 2008, which will be renovated to be a central link in the chain of the new injector system when the Linac4 will be connected - The FT16(TT2) and TT10 transfer lines providing particles to the SPS - The SPS, surveyed for the last time in the H plane in 2005 and where a hole of 4mm on a distance of 1 km has to be realigned in V - The TI2 and TI8 transfer lines linking the SPS to the LHC which are well known as unstable areas since their construction - The LHC, not measured since 2008, where some areas are very unstable like the sector 78 and where the degradation of the alignment in the H plane reaches 0.12 mm per year at 1σ, which means that, in a period of 10 years, 2 magnets per sector will be misaligned w.r.t their neighbors by more than a mm if no realignment is done during LS1. Maintenance of the low β quadrupoles alignment system Low beta quadrupoles in the LHC are equipped with Hydrostatic Levelling Sensors (HLS) and Wire Positioning Sensors (WPS) in order to monitor their position. The simplest solution to check that all the HLS sensors work well is to add or remove water to the hydraulic network through a filling/purging device and check that all the sensors see the same displacement. Concerning WPS sensors, the stretched wire is displaced radially and vertically at its extremities, and the sensors have to monitor displacements that are proportional to their longitudinal position along the wire. Till now, this operation could be carried out directly in the tunnel, but the area will become more and more radioactive. Devices that will allow performing remotely these tests are under development. Figure 10 : WPS filling-up system The remote filling/purging for HLS will consist of a mobile water tank connected to the water network (see Figure 10). The vertical displacement of the tank is performed along a worm by a DC motor coupled with a RVDT [9]. Speed reducers and ending contacts complement the system. Figure 4 presents the prototype that is under validation at CERN. For the WPS, the principle of this system is to push the wire thanks to a piston tilted at 45 w.r.t the local vertical so that the validation can be done for both vertical and horizontal readings of sensors. Figure 11 : WPS validation system The concept of pushing the wire was validated with the system shown on Figure 11: the wire has been pushed more than 4000 times by the piston, without breaking. A period of 10s after displacement was necessary to stabilize the wire before recording the readings of the sensors [5]. Two systems based on the concept of displacing the wire are under design. LHC Experiments During the next LS1 an important amount of work is planned in the four LHC experiments in order to consolidate the infrastructure, to repair or fix known problems, install detector part which have been staged and install components of the first upgrade. Among these activities the change of the central beam pipes of ATLAS and CMS will be done as well as the replacement of the long section of the LHCb beryllium pipe. Different detector installations will be done such as the ATLAS IBL inner detector insertion near to the IP, the installation of the YE4 yoke end cap disk in CMS and of new detector modules in ALICE. For that, the full opening of the detectors is foreseen. These activities lead to a strong participation of the survey team not only during the LS1 period but already now in the frame of the preparatory work which is done for months mainly during the LHC run periods. As an example, a 20m long scale one mock-up of the ATLAS central part has been built to test the tools and the procedures in this area. In parallel the CMS YE4 preassembly has been performed on surface. Another example is the preparation of the LHCb large dipole consolidation for which a control of the deformations and displacements of the coils in the yoke between the 0 and 1 Tesla conditions was demanded. After study and tests photogrammetric measurements have been successfully done in this unusual environment, the camera being exposed to magnetic field of about 200 mt.

6 In the meantime the integration of an automatic system based on BCAMs for opening/closing of ATLAS is being studied in collaboration with the ATLAS team. The radioprotection and the integration of the ALARA (As Low As Reasonably Achievable) rules is also one of the concerns leading to some methodology and hardware changes. For example the use of AT401 instead of total stations or the integration of alignment systems in shielding parts will help in this direction. Resources This very ambitious survey campaign will require, on top of the 21 staff members, 15 extra persons coming from the manpower contract to realize all the measurements and re-alignments. A large effort of the Experiment Collaborations and Physics Department is also done to support the survey for experiments. A very detailed planning is in the process of being established taking into account the general LHC planning and all the co-activities constraints. The preparation concerned also the hardware maintenance of the CERN home-made instruments- and the software field data acquisition, post-processing and database. [5] S. Mico, Déplacement du fil par électro-aimant, edms n , CERN, [6] J-C. Gayde, G. Kautzmann et al, HIE Isolde Alignment and Monitoring System Technical Design and Project Status, Fermilab, Batavia, September [7] BCAM Brandeis Camera Angle Monitor, [8] J-C. Gayde, G. Kautzmann et al, The HIE-ISOLDE Alignment and Monitoring System Software and Test Mock-up, Fermilab, Batavia, September [9] A. Bonnal, Pilotage d'un moteur à courant continu pour contrôler le fonctionnement d'un ensemble de capteurs hydrostatiques et pour le remplissage et la vidange d'un réservoir d'eau Rapport de stage, july 2012, EDMS CONCLUSIONS Despite the fact that the LHC and the injectors chain has run very well since the restarting in November 2009 and there were very few access in the tunnels, the activity of the survey team was rather important. It mainly focused on the alignment and fiducialisation of new projects such as Linac4 and on R & D studies dedicated to a survey train for the remote measurements in the LHC and the permanent monitoring of superconducting RF cavities and solenoids located in the tank modules of the HIE-Isolde using the BCAM technology. In the experiments, out of the intensive Technical Stops periods, the work was focused on LS1 preparatory work and Non- LHC experiment projects. The LS1, which has been carefully and heavily prepared, will be a more intense period in terms of survey activities in the tunnel and all the studies will be slowed down and restarted in In the meantime and almost independently of the LHC schedule, the survey work for Non-LHC experiments will have to be continued. REFERENCES [1] D. Missiaen, M. Duquenne, Could the laser tracker AT401 replace digital levelling and ecartometry for the smoothing and realignment of the LHC, IWAA12, Fermilab, Batavia, September [2] P. Bestmann and al, The LHC collimator survey train, IWAA10, DESY, Hamburg, September [3] M.Sosin, Installation of load sensors at Low quadrupoles supports, CERN EDMS , December 2011 [4] M.Sosin, J.Sandomierski, Installation of load sensors at P5 low-beta jacks, CERN EDMS , June 2012

Upgrading LHC Luminosity

Upgrading LHC Luminosity 1 Upgrading LHC Luminosity 2 Luminosity (cm -2 s -1 ) Present (2011) ~2 x10 33 Beam intensity @ injection (*) Nominal (2015?) 1 x 10 34 1.1 x10 11 Upgraded (2021?) ~5 x10 34 ~2.4 x10 11 (*) protons per

More information

Linac 4 Instrumentation K.Hanke CERN

Linac 4 Instrumentation K.Hanke CERN Linac 4 Instrumentation K.Hanke CERN CERN Linac 4 PS2 (2016?) SPL (2015?) Linac4 (2012) Linac4 will first inject into the PSB and then can be the first element of a new LHC injector chain. It will increase

More information

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala)

2 Work Package and Work Unit descriptions. 2.8 WP8: RF Systems (R. Ruber, Uppsala) 2 Work Package and Work Unit descriptions 2.8 WP8: RF Systems (R. Ruber, Uppsala) The RF systems work package (WP) addresses the design and development of the RF power generation, control and distribution

More information

CERN S PROTON SYNCHROTRON COMPLEX OPERATION TEAMS AND DIAGNOSTICS APPLICATIONS

CERN S PROTON SYNCHROTRON COMPLEX OPERATION TEAMS AND DIAGNOSTICS APPLICATIONS Marc Delrieux, CERN, BE/OP/PS CERN S PROTON SYNCHROTRON COMPLEX OPERATION TEAMS AND DIAGNOSTICS APPLICATIONS CERN s Proton Synchrotron (PS) complex How are we involved? Review of some diagnostics applications

More information

Assembly of the HIE-ISOLDE accelerator cavities in a clean room.

Assembly of the HIE-ISOLDE accelerator cavities in a clean room. Final adjustments being made in the LHC tunnel before the return of beams. On 5 April, particles began circulating in the accelerator for the first time following the Long Shutdown. (CERN-PHOTO-201503-058-1)

More information

2008 JINST 3 S LHC Machine THE CERN LARGE HADRON COLLIDER: ACCELERATOR AND EXPERIMENTS. Lyndon Evans 1 and Philip Bryant (editors) 2

2008 JINST 3 S LHC Machine THE CERN LARGE HADRON COLLIDER: ACCELERATOR AND EXPERIMENTS. Lyndon Evans 1 and Philip Bryant (editors) 2 PUBLISHED BY INSTITUTE OF PHYSICS PUBLISHING AND SISSA RECEIVED: January 14, 2007 REVISED: June 3, 2008 ACCEPTED: June 23, 2008 PUBLISHED: August 14, 2008 THE CERN LARGE HADRON COLLIDER: ACCELERATOR AND

More information

HIGH-INTENSITY PROTON BEAMS AT CERN AND THE SPL STUDY

HIGH-INTENSITY PROTON BEAMS AT CERN AND THE SPL STUDY HIGH-INTENSITY PROTON BEAMS AT CERN AND THE STUDY E. Métral, M. Benedikt, K. Cornelis, R. Garoby, K. Hanke, A. Lombardi, C. Rossi, F. Ruggiero, M. Vretenar, CERN, Geneva, Switzerland Abstract The construction

More information

EPJ Web of Conferences 95,

EPJ Web of Conferences 95, EPJ Web of Conferences 95, 04012 (2015) DOI: 10.1051/ epjconf/ 20159504012 C Owned by the authors, published by EDP Sciences, 2015 The ELENA (Extra Low Energy Antiproton) project is a small size (30.4

More information

Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi)

Commissioning of Accelerators. Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi) Commissioning of Accelerators Dr. Marc Munoz (with the help of R. Miyamoto, C. Plostinar and M. Eshraqi) www.europeanspallationsource.se 6 July, 2017 Contents General points Definition of Commissioning

More information

Linac3 experience for LHC ion runs

Linac3 experience for LHC ion runs Linac3 experience for LHC ion runs G Bellodi for the Linac3 team Keywords: beam performance reliability set up time results of MDs remaining unknowns 1 A year in perspective Source removed: change of main

More information

LHC Beam Instrumentation Further Discussion

LHC Beam Instrumentation Further Discussion LHC Beam Instrumentation Further Discussion LHC Machine Advisory Committee 9 th December 2005 Rhodri Jones (CERN AB/BDI) Possible Discussion Topics Open Questions Tune measurement base band tune & 50Hz

More information

The SPL at CERN. slhc. 1. Introduction 2. Description. 3. Status of the SPL study. - Stage 1: Linac4 - Stage 2: LP-SPL - Potential further stages

The SPL at CERN. slhc. 1. Introduction 2. Description. 3. Status of the SPL study. - Stage 1: Linac4 - Stage 2: LP-SPL - Potential further stages The SPL at CERN 1. Introduction 2. Description - Stage 1: Linac4 - Stage 2: LP-SPL - Potential further stages 3. Status of the SPL study slhc Roa Garoby for the SPL team 1. Introduction Motivation for

More information

PEP II Design Outline

PEP II Design Outline PEP II Design Outline Balša Terzić Jefferson Lab Collider Review Retreat, February 24, 2010 Outline General Information Parameter list (and evolution), initial design, upgrades Collider Ring Layout, insertions,

More information

arxiv:hep-ex/ v1 27 Nov 2003

arxiv:hep-ex/ v1 27 Nov 2003 arxiv:hep-ex/0311058v1 27 Nov 2003 THE ATLAS TRANSITION RADIATION TRACKER V. A. MITSOU European Laboratory for Particle Physics (CERN), EP Division, CH-1211 Geneva 23, Switzerland E-mail: Vasiliki.Mitsou@cern.ch

More information

A HIGH-POWER SUPERCONDUCTING H - LINAC (SPL) AT CERN

A HIGH-POWER SUPERCONDUCTING H - LINAC (SPL) AT CERN A HIGH-POWER SUPERCONDUCTING H - LINAC (SPL) AT CERN E. Chiaveri, CERN, Geneva, Switzerland Abstract The conceptual design of a superconducting H - linear accelerator at CERN for a beam energy of 2.2 GeV

More information

PEP-II IR-2 Alignment

PEP-II IR-2 Alignment SLAC-PUB-10328 January 2004 PEP-II IR-2 Alignment A. Seryi, S. Ecklund, C. Le Cocq, R. Pushor, R. Ruland, Z. Wolf SLAC, Stanford, CA 94025, USA This paper describes the first results and preliminary analysis

More information

The PEFP 20-MeV Proton Linear Accelerator

The PEFP 20-MeV Proton Linear Accelerator Journal of the Korean Physical Society, Vol. 52, No. 3, March 2008, pp. 721726 Review Articles The PEFP 20-MeV Proton Linear Accelerator Y. S. Cho, H. J. Kwon, J. H. Jang, H. S. Kim, K. T. Seol, D. I.

More information

Equipment Installation, Planning, Layout, organisation and updates

Equipment Installation, Planning, Layout, organisation and updates Equipment Installation, Planning, Layout, organisation and updates Simon Mataguez, Julie Coupard with contributions of the LIU-PLI team Table of contents: LIU installation activities Organisation of the

More information

Focus of efforts. ILC 2010, Mar/27/10 A. Seryi, BDS: 2

Focus of efforts. ILC 2010, Mar/27/10 A. Seryi, BDS: 2 Beam Delivery System Updates Andrei Seryi for BDS design and ATF2 commissioning teams LCWS 2010 / ILC 2010 March 28, 2010 Plan of the program at ILC2010 Focus of efforts Work on parameter set for a possible

More information

Digital BPMs and Orbit Feedback Systems

Digital BPMs and Orbit Feedback Systems Digital BPMs and Orbit Feedback Systems, M. Böge, M. Dehler, B. Keil, P. Pollet, V. Schlott Outline stability requirements at SLS storage ring digital beam position monitors (DBPM) SLS global fast orbit

More information

5 Project Costs and Schedule

5 Project Costs and Schedule 93 5 Project Costs and Schedule 5.1 Overview The cost evaluation for the integrated version of the XFEL with 30 experiments and 35 GeV beam energy as described in the TDR-2001 yielded 673 million EUR for

More information

Mechanical aspects, FEA validation and geometry optimization

Mechanical aspects, FEA validation and geometry optimization RF Fingers for the new ESRF-EBS EBS storage ring The ESRF-EBS storage ring features new vacuum chamber profiles with reduced aperture. RF fingers are a key component to ensure good vacuum conditions and

More information

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project

Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project Workshop on the future and next generation capabilities of accelerator driven neutron and muon sources

More information

SUMMARY OF SESSION 4 - UPGRADE SCENARIO 2

SUMMARY OF SESSION 4 - UPGRADE SCENARIO 2 Published by CERN in the Proceedings of RLIUP: Review of LHC and Injector Upgrade Plans, Centre de Convention, Archamps, France, 29 31 October 2013, edited by B. Goddard and F. Zimmermann, CERN 2014 006

More information

SPEAR 3: Operations Update and Impact of Top-Off Injection

SPEAR 3: Operations Update and Impact of Top-Off Injection SPEAR 3: Operations Update and Impact of Top-Off Injection R. Hettel for the SSRL ASD 2005 SSRL Users Meeting October 18, 2005 SPEAR 3 Operations Update and Development Plans Highlights of 2005 SPEAR 3

More information

Future Circular Collider Study

Future Circular Collider Study Status and Progress M. Benedikt, F. Zimmermann gratefully acknowledging input from FCC coordination group global design study team and all other contributors LHC SPS PS FCC http://cern.ch/fcc Work supported

More information

Beam Loss Detection for MPS at FRIB

Beam Loss Detection for MPS at FRIB Beam Loss Detection for MPS at FRIB Zhengzheng Liu Beam Diagnostics Physicist This material is based upon work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC0000661.

More information

PRESENT STATUS OF J-PARC

PRESENT STATUS OF J-PARC PRESENT STATUS OF J-PARC # F. Naito, KEK, Tsukuba, Japan Abstract Japan Proton Accelerator Research Complex (J-PARC) is the scientific facility with the high-intensity proton accelerator aiming to realize

More information

The ESS Accelerator. For Norwegian Industry and Research. Oslo, 24 Sept Håkan Danared Deputy Head Accelerator Division Group Leader Beam Physics

The ESS Accelerator. For Norwegian Industry and Research. Oslo, 24 Sept Håkan Danared Deputy Head Accelerator Division Group Leader Beam Physics The ESS Accelerator For Norwegian Industry and Research Oslo, 24 Sept 2013 Håkan Danared Deputy Head Accelerator Division Group Leader Beam Physics The Hadron Intensity Frontier Courtesy of M. Seidel (PSI)

More information

Status of the FAIR Project. Jürgen Henschel FAIR Project Leader / Technical Director GSI & FAIR

Status of the FAIR Project. Jürgen Henschel FAIR Project Leader / Technical Director GSI & FAIR Status of the FAIR Project Jürgen Henschel FAIR Project Leader / Technical Director GSI & FAIR Finland France Germany India Poland Romania Russia Slovenia Sweden UK FAIR Strategic objectives FAIR phase

More information

Precision measurements of beam current, position and phase for an e+e- linear collider

Precision measurements of beam current, position and phase for an e+e- linear collider Precision measurements of beam current, position and phase for an e+e- linear collider R. Corsini on behalf of H. Braun, M. Gasior, S. Livesley, P. Odier, J. Sladen, L. Soby INTRODUCTION Commissioning

More information

ESS: The Machine. Bucharest, 24 April Håkan Danared Deputy Head Accelerator Division. H. Danared Industry & Partner Days Bucharest Page 1

ESS: The Machine. Bucharest, 24 April Håkan Danared Deputy Head Accelerator Division. H. Danared Industry & Partner Days Bucharest Page 1 ESS: The Machine Bucharest, 24 April 2014 Håkan Danared Deputy Head Accelerator Division H. Danared Industry & Partner Days Bucharest Page 1 2025 ESS construction complete 2009 Decision: ESS will be built

More information

Proceedings of the 1997 Workshop on RF Superconductivity, Abano Terme (Padova), Italy

Proceedings of the 1997 Workshop on RF Superconductivity, Abano Terme (Padova), Italy BEAM RELATED THERMAL LOSSES ON THE CRYOGENIC AND VACUUM SYSTEMS OF LEP G. Cavallari, Ph. Gayet, G. Geschonke, D. Kaiser, J.M. Jimenez CERN, 111 GENEVA 3 (Switzerland) Abstract The LEP Collider was operated

More information

LHC COMMISSIONING PLANS

LHC COMMISSIONING PLANS LHC COMMISSIONING PLANS R. Alemany Fernández, CERN, Geneva, Switzerland Abstract Operating the Large Hadron Collider (LHC) at design performance is not going to be easy. The machine is complex and with

More information

Simulations on Beam Monitor Systems for Longitudinal Feedback Schemes at FLASH.

Simulations on Beam Monitor Systems for Longitudinal Feedback Schemes at FLASH. Simulations on Beam Monitor Systems for Longitudinal Feedback Schemes at FLASH. Christopher Behrens for the FLASH team Deutsches Elektronen-Synchrotron (DESY) FLS-2010 Workshop at SLAC, 4. March 2010 C.

More information

Full IEFC workshop Feb.

Full IEFC workshop Feb. How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix How does one keep a 50 51 year old running for another 25 years? accelerator How

More information

CMS Upgrade Activities

CMS Upgrade Activities CMS Upgrade Activities G. Eckerlin DESY WA, 1. Feb. 2011 CMS @ LHC CMS Upgrade Phase I CMS Upgrade Phase II Infrastructure Conclusion DESY-WA, 1. Feb. 2011 G. Eckerlin 1 The CMS Experiments at the LHC

More information

What can be learned from HERA Experience for ILC Availability

What can be learned from HERA Experience for ILC Availability What can be learned from HERA Experience for ILC Availability August 17, 2005 F. Willeke, DESY HERA Performance Critical Design Decisions What could be avoided if HERA would have to be built again? HERA

More information

Effects of the cryogenics operational conditions on the mechanical stability of the FLASH linac modules

Effects of the cryogenics operational conditions on the mechanical stability of the FLASH linac modules Effects of the cryogenics operational conditions on the mechanical stability of the FLASH linac modules Ramila Amirikas, Alessandro Bertolini, Jürgen Eschke, Mark Lomperski XFEL Module Meeting, January

More information

Availability and Reliability Issues for the ILC

Availability and Reliability Issues for the ILC Availability and Reliability Issues for the ILC SLAC Presented at PAC07 26 June 07 Contents Introduction and purpose of studies The availability simulation What was modeled (important assumptions) Some

More information

Hall-B Beamline Commissioning Plan for CLAS12

Hall-B Beamline Commissioning Plan for CLAS12 Hall-B Beamline Commissioning Plan for CLAS12 Version 1.5 S. Stepanyan December 19, 2017 1 Introduction The beamline for CLAS12 utilizes the existing Hall-B beamline setup with a few modifications and

More information

The European Spallation Source

The European Spallation Source The European Spallation Source Roger Ruber Uppsala University NIKHEF industriemiddag 21 september 2011 The European Spallation Source Roger Ruber - The European Spallation Source NIKHEF, 21-Sep-2011 page

More information

P. Emma, et al. LCLS Operations Lectures

P. Emma, et al. LCLS Operations Lectures P. Emma, et al. LCLS Operations Lectures LCLS 1 LCLS Accelerator Schematic 6 MeV 135 MeV 250 MeV σ z 0.83 mm σ z 0.83 mm σ z 0.19 mm σ δ 0.05 % σ δ 0.10 % σ δ 1.6 % Linac-0 L =6 m rf gun L0-a,b Linac-1

More information

New Filling Pattern for SLS-FEMTO

New Filling Pattern for SLS-FEMTO SLS-TME-TA-2009-0317 July 14, 2009 New Filling Pattern for SLS-FEMTO Natalia Prado de Abreu, Paul Beaud, Gerhard Ingold and Andreas Streun Paul Scherrer Institut, CH-5232 Villigen PSI, Switzerland A new

More information

Status of CTF3. G.Geschonke CERN, AB

Status of CTF3. G.Geschonke CERN, AB Status of CTF3 G.Geschonke CERN, AB CTF3 layout CTF3 - Test of Drive Beam Generation, Acceleration & RF Multiplication by a factor 10 Drive Beam Injector ~ 50 m 3.5 A - 2100 b of 2.33 nc 150 MeV - 1.4

More information

PoS(EPS-HEP2015)525. The RF system for FCC-ee. A. Butterworth CERN 1211 Geneva 23, Switzerland

PoS(EPS-HEP2015)525. The RF system for FCC-ee. A. Butterworth CERN 1211 Geneva 23, Switzerland CERN 1211 Geneva 23, Switzerland E-mail: andrew.butterworth@cern.ch O. Brunner CERN 1211 Geneva 23, Switzerland E-mail: olivier.brunner@cern.ch R. Calaga CERN 1211 Geneva 23, Switzerland E-mail: rama.calaga@cern.ch

More information

RF considerations for SwissFEL

RF considerations for SwissFEL RF considerations for H. Fitze in behalf of the PSI RF group Workshop on Compact X-Ray Free Electron Lasers 19.-21. July 2010, Shanghai Agenda Introduction RF-Gun Development C-band development Summary

More information

30 GHz Power Production / Beam Line

30 GHz Power Production / Beam Line 30 GHz Power Production / Beam Line Motivation & Requirements Layout Power mode operation vs. nominal parameters Beam optics Achieved performance Problems Beam phase switch for 30 GHz pulse compression

More information

An Overview of Beam Diagnostic and Control Systems for AREAL Linac

An Overview of Beam Diagnostic and Control Systems for AREAL Linac An Overview of Beam Diagnostic and Control Systems for AREAL Linac Presenter G. Amatuni Ultrafast Beams and Applications 04-07 July 2017, CANDLE, Armenia Contents: 1. Current status of existing diagnostic

More information

Detailed Design Report

Detailed Design Report Detailed Design Report Chapter 4 MAX IV Injector 4.6. Acceleration MAX IV Facility CHAPTER 4.6. ACCELERATION 1(10) 4.6. Acceleration 4.6. Acceleration...2 4.6.1. RF Units... 2 4.6.2. Accelerator Units...

More information

The FAIR plinac RF Systems

The FAIR plinac RF Systems The FAIR plinac RF Systems Libera Workshop Sep. 2011 Gerald Schreiber Gerald Schreiber, GSI RF Department 2 (1) Overview GSI / FAIR (2) FAIR Proton Linear Accelerator "plinac" (3) plinac RF Systems (4)

More information

PICS IN THE INJECTOR COMPLEX WHAT ARE WE TALKING ABOUT?

PICS IN THE INJECTOR COMPLEX WHAT ARE WE TALKING ABOUT? Published by CERN in the Proceedings of RLIUP: Review of LHC and Injector Upgrade Plans, Centre de Convention, Archamps, France, 29 31 October 2013, edited by B. Goddard and F. Zimmermann, CERN 2014 006

More information

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation

Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation Experience with the Cornell ERL Injector SRF Cryomodule during High Beam Current Operation Matthias Liepe Assistant Professor of Physics Cornell University Experience with the Cornell ERL Injector SRF

More information

A new Scintillating Fibre Tracker for LHCb experiment

A new Scintillating Fibre Tracker for LHCb experiment A new Scintillating Fibre Tracker for LHCb experiment Alexander Malinin, NRC Kurchatov Institute on behalf of the LHCb-SciFi-Collaboration Instrumentation for Colliding Beam Physics BINP, Novosibirsk,

More information

RF upgrade program in LHC injectors and LHC machine

RF upgrade program in LHC injectors and LHC machine RF upgrade program in LHC injectors and LHC machine E r k J e n s e n, o n b e h a l f o f B E - RF Many thanks to M. E. Angoletta, O. Brunner, R. Calaga, E. Ciapala, H. Damerau, W. Höfle, E. Montesinos,

More information

The Construction Status of CSNS Linac

The Construction Status of CSNS Linac The Construction Status of CSNS Linac Sheng Wang Dongguan branch, Institute of High Energy Physics, CAS Sep.2, 2014, Geneva Outline The introduction to CSNS accelerators The commissoning of ion source

More information

CLIC Feasibility Demonstration at CTF3

CLIC Feasibility Demonstration at CTF3 CLIC Feasibility Demonstration at CTF3 Roger Ruber Uppsala University, Sweden, for the CLIC/CTF3 Collaboration http://cern.ch/clic-study LINAC 10 MO303 13 Sep 2010 The Key to CLIC Efficiency NC Linac for

More information

Nick Walker DESY MAC

Nick Walker DESY MAC Nick Walker DESY MAC 4.5.2006 XFEL X-Ray Free-Electron Laser DESY ILC Project Group Accelerator Experimentation Behnke, Elsen, Walker (chair) WP 15, 16 WP 4-7 Accelerator Physics and Design WP 6 High Gradient

More information

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting

Status of BESSY II and berlinpro. Wolfgang Anders. Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting Status of BESSY II and berlinpro Wolfgang Anders Helmholtz-Zentrum Berlin for Materials and Energy (HZB) 20th ESLS-RF Meeting 16.-17.11.2016 at PSI Outline BESSY II Problems with circulators Landau cavity

More information

Summary of the 1 st Beam Line Review Meeting Injector ( )

Summary of the 1 st Beam Line Review Meeting Injector ( ) Summary of the 1 st Beam Line Review Meeting Injector (23.10.2006) 15.11.2006 Review the status of: beam dynamics understanding and simulations completeness of beam line description conceptual design of

More information

Proton Engineering Frontier Project

Proton Engineering Frontier Project Proton Engineering Frontier Project OECD Nuclear Energy Agency Fifth International Workshop on the Utilisation and Reliability of High Power Proton Accelerators (HPPA5) (6-9 May 2007, Mol, Belgium) Yong-Sub

More information

DELIVERY RECORD. Location: Ibaraki, Japan

DELIVERY RECORD. Location: Ibaraki, Japan DELIVERY RECORD Client: Japan Atomic Energy Agency (JAEA) High Energy Accelerator Research Organization (KEK) Facility: J-PARC (Japan Proton Accelerator Research Complex) Location: Ibaraki, Japan 1 October

More information

Welcome and FRIB Project Status. FRIB Highlights and Plan Ahead

Welcome and FRIB Project Status. FRIB Highlights and Plan Ahead Welcome and FRIB Project Status Thomas Glasmacher Project Manager This material is based upon work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC0000661.

More information

BEAM DYNAMICS AND EXPERIMENT OF CPHS LINAC *

BEAM DYNAMICS AND EXPERIMENT OF CPHS LINAC * BEAM DYNAMICS AND EXPERIMENT OF CPHS LINAC * L. Du #, C.T. Du, X.L. Guan, C.X. Tang, R. Tang, X.W. Wang, Q.Z. Xing, S.X. Zheng, Key Laboratory of Particle & Radiation Imaging (Tsinghua University), Ministry

More information

Hydrostatic Levelling Systems (HLS) on ILC - general aspects and possible realization -

Hydrostatic Levelling Systems (HLS) on ILC - general aspects and possible realization - Hydrostatic Levelling Systems () on - general aspects and possible realization - DESY- Peter Göttlicher Mathias Reinecke Markus Schlösser IWAA08, KEK, 11. 15.02.2008 IWAA2008 on Peter Göttlicher, Mathias

More information

The LEP Superconducting RF System

The LEP Superconducting RF System The LEP Superconducting RF System K. Hübner* for the LEP RF Group CERN The basic components and the layout of the LEP rf system for the year 2000 are presented. The superconducting system consisted of

More information

Commissioning of the ATLAS Transition Radiation Tracker (TRT)

Commissioning of the ATLAS Transition Radiation Tracker (TRT) Commissioning of the ATLAS Transition Radiation Tracker (TRT) 11 th Topical Seminar on Innovative Particle and Radiation Detector (IPRD08) 3 October 2008 bocci@fnal.gov On behalf of the ATLAS TRT community

More information

CLEX (CLIC Experimental Area)

CLEX (CLIC Experimental Area) CLEX (CLIC Experimental Area) Status and plans G.Geschonke for Hans Braun CERN CT3 coll meetg 2005 CLEX 1 CT3 objectives R1.1 CLIC accelerating structure, R1.2 rive beam scheme with a fully loaded linac

More information

Summer / Fall 2004 Downtime AEG Preparation Work

Summer / Fall 2004 Downtime AEG Preparation Work Summer / Fall 2004 Downtime AEG Preparation Work In general the Alignment Engineering Group consulted with individuals involved in many of the scheduled downtime activities. Equipment was checked, manpower

More information

THE IBA SUPERCONDUCTING SYNCHROCYCLOTRON PROJECT S2C2

THE IBA SUPERCONDUCTING SYNCHROCYCLOTRON PROJECT S2C2 THE IBA SUPERCONDUCTING SYNCHROCYCLOTRON PROJECT S2C2 W. Kleeven, M. Abs, E. Forton, S. Henrotin, Y. Jongen, V. Nuttens, Y. Paradis, E. Pearson, S. Quets, J. Van de Walle, P. Verbruggen, S. Zaremba, IBA,

More information

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR

STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR Proceedings of FEL213, New York, NY, USA STATUS OF THE SWISSFEL C-BAND LINEAR ACCELERATOR F. Loehl, J. Alex, H. Blumer, M. Bopp, H. Braun, A. Citterio, U. Ellenberger, H. Fitze, H. Joehri, T. Kleeb, L.

More information

Preparations for Installation, Testing and Commissioning based on Experience at CERN, SNS and Siemens

Preparations for Installation, Testing and Commissioning based on Experience at CERN, SNS and Siemens Preparations for Installation, Testing and Commissioning based on Experience at CERN, SNS and Siemens Eugène Tanke FRIB / MSU ESS Seminar, Lund, 6 March 2013 Outline Project Goal for the Accelerator Path

More information

ILC-LNF TECHNICAL NOTE

ILC-LNF TECHNICAL NOTE IL-LNF EHNIAL NOE Divisione Acceleratori Frascati, July 4, 2006 Note: IL-LNF-001 RF SYSEM FOR HE IL DAMPING RINGS R. Boni, INFN-LNF, Frascati, Italy G. avallari, ERN, Geneva, Switzerland Introduction For

More information

Advanced Photon Source - Upgrades and Improvements

Advanced Photon Source - Upgrades and Improvements Advanced Photon Source - Upgrades and Improvements Horst W. Friedsam, Jaromir M. Penicka Argonne National Laboratory, Argonne, Illinois, USA 1. INTRODUCTION The APS has been operational since 1995. Recently

More information

Commissioning the TAMUTRAP RFQ cooler/buncher. E. Bennett, R. Burch, B. Fenker, M. Mehlman, D. Melconian, and P.D. Shidling

Commissioning the TAMUTRAP RFQ cooler/buncher. E. Bennett, R. Burch, B. Fenker, M. Mehlman, D. Melconian, and P.D. Shidling Commissioning the TAMUTRAP RFQ cooler/buncher E. Bennett, R. Burch, B. Fenker, M. Mehlman, D. Melconian, and P.D. Shidling In order to efficiently load ions into a Penning trap, the ion beam should be

More information

PUBLICATION. Measurement setup at light source operational: Milestone M4.3

PUBLICATION. Measurement setup at light source operational: Milestone M4.3 CERN-ACC-2016-0110 Future Circular Collider PUBLICATION Measurement setup at light source operational: Milestone M4.3 Perez, Francis (ALBA) et al. 24 August 2016 The European Circular Energy-Frontier Collider

More information

A Fifteen Year Perspective on the Design and Performance of the SNS Accelerator

A Fifteen Year Perspective on the Design and Performance of the SNS Accelerator A Fifteen Year Perspective on the Design and Performance of the SNS Accelerator S. Cousineau (On behalf of the SNS project) HB2016, Sweden July 04, 2016 ORNL is managed by UT-Battelle for the US Department

More information

Periodic Seasonal Variation of Magnets Level of the STB ring

Periodic Seasonal Variation of Magnets Level of the STB ring Periodic Seasonal Variation of Magnets Level of the STB ring Shigenobu Takahashi Laboratory of Nuclear Science,Tohoku University, Mikamine 1-2-1, Taihaku-ku, Sendai 982-0826, Japan 1. Introduction The

More information

BEAM DIAGNOSTICS IN THE CNAO INJECTION LINES COMMISSIONING

BEAM DIAGNOSTICS IN THE CNAO INJECTION LINES COMMISSIONING BEAM DIAGNOSTICS IN THE CNAO INJECTION LINES COMMISSIONING A. Parravicini, G. Balbinot, J. Bosser, E. Bressi, M. Caldara, L. Lanzavecchia, M. Pullia, M. Spairani, CNAO Foundation, Pavia, Italy C. Biscari,

More information

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline

3 cerl. 3-1 cerl Overview. 3-2 High-brightness DC Photocathode Gun and Gun Test Beamline 3 cerl 3-1 cerl Overview As described before, the aim of the cerl in the R&D program includes the development of critical components for the ERL, as well as the construction of a test accelerator. The

More information

SRS and ERLP developments. Andrew moss

SRS and ERLP developments. Andrew moss SRS and ERLP developments Andrew moss Contents SRS Status Latest news Major faults Status Energy Recovery Linac Prototype Latest news Status of the RF system Status of the cryogenic system SRS Status Machine

More information

DESIGN OF 1.2-GEV SCL AS NEW INJECTOR FOR THE BNL AGS*

DESIGN OF 1.2-GEV SCL AS NEW INJECTOR FOR THE BNL AGS* DESIGN OF 1.2-GEV SCL AS NEW INJECTOR FOR THE BNL AGS* A. G. Ruggiero, J. Alessi, M. Harrison, M. Iarocci, T. Nehring, D. Raparia, T. Roser, J. Tuozzolo, W. Weng. Brookhaven National Laboratory, PO Box

More information

Quad-to-quad correlated motion in FLASH

Quad-to-quad correlated motion in FLASH Quad-to-quad correlated motion in FLASH Ramila Amirikas, Alessandro Bertolini DESY Hamburg Quad-to-quad correlated motion in FLASH Introduction- The experiment - continuous monitoring of vibrations in

More information

STATUS OF THE INTERNATIONAL LINEAR COLLIDER

STATUS OF THE INTERNATIONAL LINEAR COLLIDER STATUS OF THE INTERNATIONAL LINEAR COLLIDER K. Yokoya, KEK, Tsukuba, Japan Abstract The International Linear Collider (ILC) is the nextgeneration electron-positron collider. Since the publication of the

More information

OPERATIONAL EXPERIENCE WITH CIRCULATING BEAM

OPERATIONAL EXPERIENCE WITH CIRCULATING BEAM OPERATIONAL EXPERIENCE WITH CIRCULATING BEAM S. Redaelli on behalf of the LHC beam commissioning team CERN, Geneva, Switzerland Abstract Following various injection tests, the full LHC beam commissioning

More information

High QE Photocathodes lifetime and dark current investigation

High QE Photocathodes lifetime and dark current investigation High QE Photocathodes lifetime and dark current investigation Paolo Michelato INFN Milano - LASA Main Topics High QE photocathode lifetime QE vs. time (measurements on several cathodes, FLASH data) QE

More information

AREAL- Phase 1. B. Grigoryan on behalf of AREAL team

AREAL- Phase 1. B. Grigoryan on behalf of AREAL team AREAL- Phase 1 Progress & Status B. Grigoryan on behalf of AREAL team Contents Machine Layout Building & Infrastructure Laser System RF System Vacuum System Cooling System Control System Beam Diagnostics

More information

Workshop on Accelerator Operations August 6-10, 2012 Glen D. Johns Accelerator Operations Manager

Workshop on Accelerator Operations August 6-10, 2012 Glen D. Johns Accelerator Operations Manager HWDB: Operations at the Spallation Neutron Source Workshop on Accelerator Operations August 6-10, 2012 Glen D. Johns Accelerator Operations Manager Outline Facility overview Organization Shift schedule

More information

Suggested ILC Beam Parameter Range Rev. 2/28/05 Tor Raubenheimer

Suggested ILC Beam Parameter Range Rev. 2/28/05 Tor Raubenheimer The machine parameters and the luminosity goals of the ILC were discussed at the 1 st ILC Workshop. In particular, Nick Walker noted that the TESLA machine parameters had been chosen to achieve a high

More information

Characterizing Transverse Beam Dynamics at the APS Storage Ring Using a Dual-Sweep Streak Camera

Characterizing Transverse Beam Dynamics at the APS Storage Ring Using a Dual-Sweep Streak Camera Characterizing Transverse Beam Dynamics at the APS Storage Ring Using a Dual-Sweep Streak Camera Bingxin Yang, Alex H. Lumpkin, Katherine Harkay, Louis Emery, Michael Borland, and Frank Lenkszus Advanced

More information

Mechanical Considerations in the Outer Tracker and VXD. Bill Cooper Fermilab

Mechanical Considerations in the Outer Tracker and VXD. Bill Cooper Fermilab Mechanical Considerations in the Outer Tracker and VXD Fermilab August 23, 2005 1 Overview I ll describe developments since the SLAC workshop in mechanical design efforts at Fermilab related to SiD tracking.

More information

LCLS Injector Technical Review

LCLS Injector Technical Review LCLS Injector Technical Review Stanford Linear Accelerator Center November 3&4 2003 Review Committee Members: Prof. Patrick O Shea Chair University of Maryland Dr. E. Colby Stanford Linear Accelerator

More information

Particle Beam Production - A Synchrotron-Based System - Prof. Dr. Thomas Haberer Scientific-technical Director Heidelberg Iontherapy Center

Particle Beam Production - A Synchrotron-Based System - Prof. Dr. Thomas Haberer Scientific-technical Director Heidelberg Iontherapy Center Particle Beam Production - A Synchrotron-Based System - Prof. Dr. Thomas Haberer Scientific-technical Director Heidelberg Iontherapy Center Outline Situation/Rationale Requirements Synchrotron choice Functions

More information

COMMISSIONING SCENARIOS FOR THE J-PARC ACCELERATOR COMPLEX

COMMISSIONING SCENARIOS FOR THE J-PARC ACCELERATOR COMPLEX COMMISSIONING SCENARIOS FOR THE J-PARC ACCELERATOR COMPLEX T. Koseki, M. Ikegami, M. Tomizawa, Accelerator Laboratory, KEK, Tsukuba, Japan F. Noda, JAEA, Tokai, Japan Abstract The J-PARC (Japan Proton

More information

SUMMARY OF THE ILC R&D AND DESIGN

SUMMARY OF THE ILC R&D AND DESIGN SUMMARY OF THE ILC R&D AND DESIGN B. C. Barish, California Institute of Technology, USA Abstract The International Linear Collider (ILC) is a linear electron-positron collider based on 1.3 GHz superconducting

More information

The Silicon Pixel Detector (SPD) for the ALICE Experiment

The Silicon Pixel Detector (SPD) for the ALICE Experiment The Silicon Pixel Detector (SPD) for the ALICE Experiment V. Manzari/INFN Bari, Italy for the SPD Project in the ALICE Experiment INFN and Università Bari, Comenius University Bratislava, INFN and Università

More information

A HIGH POWER LONG PULSE HIGH EFFICIENCY MULTI BEAM KLYSTRON

A HIGH POWER LONG PULSE HIGH EFFICIENCY MULTI BEAM KLYSTRON A HIGH POWER LONG PULSE HIGH EFFICIENCY MULTI BEAM KLYSTRON A.Beunas and G. Faillon Thales Electron Devices, Vélizy, France S. Choroba DESY, Hamburg, Germany Abstract THALES ELECTRON DEVICES has developed

More information

CMS Note Mailing address: CMS CERN, CH-1211 GENEVA 23, Switzerland

CMS Note Mailing address: CMS CERN, CH-1211 GENEVA 23, Switzerland Available on CMS information server CMS NOTE 1999/012 The Compact Muon Solenoid Experiment CMS Note Mailing address: CMS CERN, CH-1211 GENEVA 23, Switzerland February 23, 1999 Assembly and operation of

More information

A Cathode Development Cornell Cultera This scope includes all labor and purchases required produce photocathodes required by CBETA.

A Cathode Development Cornell Cultera This scope includes all labor and purchases required produce photocathodes required by CBETA. A1.01 PROJECT MANAGEMENT BNL/Cornell Michnoff A1.01.01 Milestones BNL/Cornell Michnoff This scope is a placeholder for all project high level milestones for NYSERDA. There is no cost or labor related to

More information

Upgrade of CEBAF to 12 GeV

Upgrade of CEBAF to 12 GeV Upgrade of CEBAF to 12 GeV Leigh Harwood (for 12 GeV Accelerator team) Page 1 Outline Background High-level description Schedule Sub-system descriptions and status Summary Page 2 CEBAF Science Mission

More information