TC production and installation for 2016 run

Size: px
Start display at page:

Download "TC production and installation for 2016 run"

Transcription

1 TC production and installation for 2016 run M. De Gerone on behalf of the TC group Feb. 1st, 2016

2 Summary Progress from last referees meeting: PCBs and BPs production (almost) completed TC structure machining Few results from 2015 pre-engineering run M. De Gerone, Referee MEG 01/02/16 2

3 PCBs and BPs production Individual SiPMs tests finished in PV Last batch of SiPMs (600 pcs = 100PCBs, 5cm) will be delivered to the company for soldering this week All other boards (4cm, L-shaped) are ready and tested in PSI Mass production of the last pixels is currently on going. Individual SiPM tests almost finished in PV; scintillators, PCB and connectors ready; Backplanes are ready and tested, thermal sensors are mounted. Production of PCBs and BPS for BOTH detectors is (almost) completed (fully completed in a couple of weeks from now). All the boards produced till now have been tested (I-V curve). M. De Gerone, Referee MEG 01/02/16 3

4 Status of TC production towards 2016 The machining of the new structure is currently on going in Genova. Reminder We restarted the machining from scratch using a different raw material (moulding). First of all, we tested the junction between the central and lateral part of the structure (it wasn t tested in 2015). Side part Central part junction New material is much more robust. We didn t see any appreciable deformation during machining. M. De Gerone, Referee MEG 01/02/16 4

5 Status of TC production towards 2016 La lavorazione principale delle strutture (3 x TC) è quasi completa (fresature gole lato esterno per sistema di raffreddamento) Completamento delle lavorazioni (forature, filettature etc) previsto per fine maggio come da schedule. M. De Gerone, Referee MEG 01/02/16 5

6 Status of TC production towards 2016 M. De Gerone, Referee MEG 01/02/16 6

7 Status of TC production towards 2016 Altre lavorazioni in corso: produzione della parte interna (COBRA step) x 2 Timing Counter produzione dei carrelli per movimentazione / inserimento TC blocchetti per termalizzazione pixel Termine lavori previsto in Giugno (alcune lavorazioni procedono poi in parallelo all assemblaggio del primo TC) M. De Gerone, Referee MEG 01/02/16 7

8 Alcuni risultati dal beam test (preliminare) Caveat: stato DAQ non ottimale, calibrazione DRS Risoluzione (a 2 pixel): sigma della distribuzione ΔT=(T1-T2)/2 Constant del segnale Taglio in carica e altezza segnale per escludere segnali saturati e noise. M. De Gerone, Referee MEG 01/02/16 8

9 Alcuni risultati dal beam test (preliminare) Confronto risoluzioni in funzione della soglia del constant fraction fra test in laboratorio e pre-engineering run (pixel sullo stesso chip DRS) Valore ottimale in beam test 35% vs 20% in laboratorio (noise?). 15% differenza in risoluzione rispetto alle attese. NB: reso a 2 pixel in lab estratta da misure su singolo pixel M. De Gerone, Referee MEG 01/02/16 9

10 Alcuni risultati dal beam test (preliminare) Risoluzioni di doppio hit (CF 35%) drs chip 1 drs chip 2 σ ~ 60-75ps σ > 70ps pixel id pixel id M. De Gerone, Referee MEG 01/02/16 10

11 Conclusions La produzione delle schede PCB e BP è completata al 90% (rimane da saldare l ultimo batch di SiPM nelle prossime settimane) La lavorazione delle strutture dei 2 TC è in corso. Prevediamo di poter iniziare l assemblaggio del primo rivelatore a fine giugno (dopo beam test 2016). L analisi dei dati raccolti nel beam test 2015 è in corso. Nonostante i problemi di DAQ sembra che almeno l ultimo set di dati raccolti sia utilizzabile. Risoluzioni per ora estrapolate da eventi 2-hit, 60-70ps contro ~55ps attesi. M. De Gerone, Referee MEG 01/02/16 11

12 Back up

13 Status of TC production towards 2016 JAN FEB MAR APR MAY JUN JUL SiPM soldering and test scintillator test pixel assembly / test Structure machining assembly TC install Michel run? M. De Gerone, Referee MEG 01/02/16 13

14 M. De Gerone, Referee MEG 01/02/16 14

15 From last referee meeting: TC production For the 2015 pre-engineering run half of TC downstream sector was built: it corresponds to 128 pixels (16BPs), 256 channels (same number of channels available from DAQ side) It allows testing all detectors features (mechanics, electronics, multi-hit time reso) Pixel, backplane, insertion system, temperature sensors are the final ones. Structure production was delayed by some issues during the machining (structure deformations We will use the current structure this year only: the TC structure will be re-built from scratch for 2016 run. M. De Gerone, Referee MEG 01/02/16 15

16 From last referee meeting: TC production For the 2015 pre-engineering run half of TC downstream sector was built: it corresponds to 128 pixels (16BPs), 256 channels (same number of channels available from DAQ side) It allows testing all detectors features (mechanics, electronics, multi-hit time reso) Pixel, backplane, insertion system, temperature sensors are the final ones. Structure production was delayed by some issues during the machining (structure deformations We will use the current structure this year only: the TC structure will be re-built from scratch for 2016 run. M. De Gerone, Referee MEG 01/02/16 16

17 2015 pre-engineering run: mass production 139 pixels were produced and tested for this year run (needed: 128) couple scintillator to array with optical cement wait 12 hours couple other side, wait wrap pixel with reflector light shield with tedlar film Production and test rate: 10pixels/day M. De Gerone, Referee MEG 01/02/16 17

18 2015 pre-engineering run: mass production Each pixel was individually tested with usual lab setup in thermal chamber (moving stage for position scan, 90 Sr source, reference counter for event selection / trigger): 3 positions measurement; 90 time resolution; Sr source collected charge. Moving stage 73.6ps 4cm 76.8ps 5cm Pixel under test RC counter M. De Gerone, Referee MEG 01/02/16 18

19 2015 pre-engineering run: TC assembly DS L shape Mixed 5 cm 4 cm for engineering run = equipped with optical fiber 128 pixels / 256 channels we tested all pixel configurations (40/50mm height, L-shaped, mixed) a small subset was equipped with optical fibers allows testing of laser calibration system cooling system was not installed tight schedule anyway, no DCH electronics this year thermal block installed only in the inner side for mechanical reasons Assembly procedure is the same as the final (full) detector. M. De Gerone, Referee MEG 01/02/16 19

20 2015 pre-engineering run: TC assembly Each step of TC assembly was tested: backplanes and pixels positioning, cabling (pixel-bp transition in the inner step), insertion system. Few minor issues arose during the operations - negligible for this year goal, will be fixed for the next one (see next slide) M. De Gerone, Referee MEG 01/02/16 20

21 2015 pre-engineering run: TC assembly Pixels are mounted on the inner structure using the thermal block as support for the pixel itself. Some pixels have 1 leg on the inner structure and the other on the central one ( mixed pixels). TC Status, MEG Coll. Meet. 10/30/15 21

22 2015 pre-engineering run: TC assembly A couple of minor issues: Because of the structure deformation, rails position does not exactly fit the grooves made on the structure. We arranged the rails on site - a small (few mm) disalignment of TC is possible (but negligible) Because of a mistake during the machining, the position of a couple of backplanes is not the nominal one wrong position right position Impact on this year run is negligible. Issues will be fixed by remachining the TC structure from scratch (see next) M. De Gerone, Referee MEG 01/02/16 22

23 2015 pre-engineering run: TC insertion Rails are mounted inside COBRA and fixed to the COBRA structure. TC is mounted on a chariot which lodges the same rails as in COBRA. Then the 2 systems are joined in such a way to slide TC inside COBRA (same as MEG TC). TC Status, MEG Coll. Meet. 10/30/15 23

24 2015 pre-engineering run: TC insertion Pixel height was adjusted adding 2.5mm spacers. We did not see any conflicts between TC structure and DCH mockup! TC integration has been fully achieved M. De Gerone, Referee MEG 01/02/16 24

25 2015 pre-engineering run: signal check We use the old DCHs cables for TC cabling. A quick signal check was done before run kick-off using cosmic ray signals and oscilloscope (no waveform studies). 100% working channels M. De Gerone, Referee MEG 01/02/16 25

26 2015 pre-engineering run: a short summary Official beam time started on Dec. 7th but we started to take (TRG) data on Dec. 14th. Laser system was turned on on Dec. 18th. Wave dream waveform readout was achieved on Dec. 19th, then we started to take 24h-shifts till the end of beam time (Dec. 23rd). We found several problems on wave dream side. The main ones: DRS stop cell record had been unavailable until the last evening of DAQ, thus it is not possible to apply DRS time calibration for previously taken data. Double read-out: even cell is a copy of the neighboring odd cell thus effective sampling speed become half. No sync among different boards Large noise on analog front-ends full list in backup slides. M. De Gerone, Referee MEG 01/02/16 26

27 2015 pre-engineering run: what do we achieved? Some of the listed issues will strongly affected data quality: we took meaningful data only on the last 10 hours of run (when DRS stop cell bug was fixed)! seems very difficult to extract reliable time resolutions. Nevertheless, we were able to: test detector integration; test all the HW devices (SiPM bias and current, signals from pixel, temperature readout, etc); make a beam intensity scan; test several trigger configurations; multiple hits, track like events, laser calibration, pedestal ; test laser calibration (on a small pixel subset); develop some analysis tools; partially debug DAQ system. M. De Gerone, Referee MEG 01/02/16 27

28 2015 pre-engineering run: some events M. De Gerone, Referee MEG 01/02/16 28

29 2015 pre-engineering run: some events M. De Gerone, Referee MEG 01/02/16 29

30 2015 pre-engineering run: some events M. De Gerone, Referee MEG 01/02/16 30

31 2015 pre-engineering run: some events M. De Gerone, Referee MEG 01/02/16 31

32 Laser calibration system 8 pixels were equipped with optical fibers. We were able to test the full chain: laser, light transport from cave to experimental hall, splitter, pixel injection The more robust way to inject light into the pixel is to frill a small (diam. 1.9mm, depth 1mm ) hole in the scintillator. Time resolution is not affected by hole making. M. De Gerone, Referee MEG 01/02/16 32

33 Laser calibration system Laser light is transmitted using a 10m optical fiber from the cavern to the experimental hall. Signal is divided by means of an optical splitter, then fed into pixels. Trigger using laser SYNC signal. Data analysis on going. safe box for splitter pulse from laser pulses to pixels M. De Gerone, Referee MEG 01/02/16 33

34 Temperature read-out We installed 3 sensors for each backplane, but this year we recorded only few of them. 3 days temperature history ΔT on TC surface ~1.5 C ΔT day/night ~ 0.5 C No cooling system, no power dissipation from external sourcesdch M. De Gerone, Referee MEG 01/02/16 34

35 Current increase? 2 days@meg II expected intensity SiPM current seems to increase during the run (~0.5uA / 2 days). Is this due to radiation damages? If so, it could be an issue for long term operations. Deeper studies are ongoing (I-V curve and BD comparison before and after run). M. De Gerone, Referee MEG 01/02/16 35

36 Pixel: final design 6 SiPMs (Advansid ASD-NUV3S-P) in series connection are soldered on a PCB. Scintillator (Saint Gobain BC422) is glued to SiPMs, PBCs act as a frame for the pixel. The pixel is electrically connected to the backplanes by means of MCX connectors. Thermal link is provided by means of a small Cu block. Light trapping is increased by wrapping the pixel with a reflector (3M mirror film). Light tightness is provided by wrapping the pixel with a thin black foil (Tedlar). 120mm 40/50mm MCX connector Cu thermal link All the items listed above are established. PCBs for all kind of pixels are in production now. First 100 hundred boards are expected to be ready by the first week of April. M. De Gerone, Referee MEG 01/02/16 36

37 Connectors issue All purchased connectors were sensitive to magnetic field (nickel in body plating) We immediately asked for replacement but not all the needed models were available: - - MCX PLUG, placed on backplane for pixels connection - All replaced, OK MCX edge mount, to be mounted on pixels - We asked for replacement but we got magnetic model again! We are provisionally mounting these connectors for this run (should not be an issue because we will not track any positron this year) waiting for the right ones (order placed). They will be replaced next year - - MCX JACK, mounted on backplane for cables connection - They are placed outside the spectrometer sensitive volume. In principle, we can use these connectors if the magnetic field distortion is negligible. Simulations ongoing. M. De Gerone, Referee MEG 01/02/16 37

38 Current status: Backplanes production 16 backplanes (final layout) has been produced for this year run. Tested in Genova electrical continuity signal and GND lines 1-wire temperature device readout (with stand alone readout system) Mechanics (mounting on TC structure) All tests were OK, just needed a couple of minor modification of the TC structure: A couple of BP are slightly wider than nominal value (+0.2mm), grooves on structure have to be enlarged (will be taken into account in the next detector design) Backplanes are ready to be used in 2015 run. M. De Gerone, Referee MEG 01/02/16 38

39 TC structure: insertion system A couple of rails will be mounted inside COBRA, in order to allow TC to slide in. The fine movement will be provided by means of an endless screw which will be fixed on the bottom side of the Timing Counter Step 1: rails fixed in the COBRA before TC insertion Step 2: TC rails connected to COBRA rails Step 3: TC slides inside COBRA. Endless screw fixed to COBRA Step 4: Final TC position Timing Counter bottom view M. De Gerone, Referee MEG 01/02/16 39

40 TC structure: insertion system binario e struttura portante in alluminio carrello per trasporto TC e inserimento in COBRA All the items are ready. Vite senza fine in ottone e attacco al COBRA Vite agganciata al COBRA e al TC M. De Gerone, Referee MEG 01/02/16 40

41 1 wire bus - Temperature monitor We put 3 temperature sensor and 1 humidity sensor on each backplanes, and we prepared a stand alone system able to readout them (in final configuration, WaveDream will be used to read out). Thermometers are placed also on the inner part (5 sensors) and then connected (and read out) through backplanes. TC Status, MEG Coll. Meet. 10/30/15 41

42 1 wire bus - Temperature monitor For this year we plan to readout sensors from 5 backplanes (3 devices each) TC Status, MEG Coll. Meet. 10/30/15 42

43 Temperature Sensor Extension accuracy ±0.5 3 CHF 1-16 sensors per WD2 board with only one coaxial cable 18 March 2015 MEG Collaboration Meeting, Tokyo M. De Gerone, Referee MEG 01/02/16 43

44 Full list of DAQ problems M. De Gerone, Referee MEG 01/02/16 44

An extreme high resolution Timing Counter for the MEG Upgrade

An extreme high resolution Timing Counter for the MEG Upgrade An extreme high resolution Timing Counter for the MEG Upgrade M. De Gerone INFN Genova on behalf of the MEG collaboration 13th Topical Seminar on Innovative Particle and Radiation Detectors Siena, Oct.

More information

Scintillation Tile Hodoscope for the PANDA Barrel Time-Of-Flight Detector

Scintillation Tile Hodoscope for the PANDA Barrel Time-Of-Flight Detector Scintillation Tile Hodoscope for the PANDA Barrel Time-Of-Flight Detector William Nalti, Ken Suzuki, Stefan-Meyer-Institut, ÖAW on behalf of the PANDA/Barrel-TOF(SciTil) group 12.06.2018, ICASiPM2018 1

More information

Results on 0.7% X0 thick Pixel Modules for the ATLAS Detector.

Results on 0.7% X0 thick Pixel Modules for the ATLAS Detector. Results on 0.7% X0 thick Pixel Modules for the ATLAS Detector. INFN Genova: R.Beccherle, G.Darbo, G.Gagliardi, C.Gemme, P.Netchaeva, P.Oppizzi, L.Rossi, E.Ruscino, F.Vernocchi Lawrence Berkeley National

More information

THE TIMING COUNTER OF THE MEG EXPERIMENT: DESIGN AND COMMISSIONING (OR HOW TO BUILD YOUR OWN HIGH TIMING RESOLUTION DETECTOR )

THE TIMING COUNTER OF THE MEG EXPERIMENT: DESIGN AND COMMISSIONING (OR HOW TO BUILD YOUR OWN HIGH TIMING RESOLUTION DETECTOR ) THE TIMING COUNTER OF THE MEG EXPERIMENT: DESIGN AND COMMISSIONING (OR HOW TO BUILD YOUR OWN HIGH TIMING RESOLUTION DETECTOR ) S. DUSSONI FRONTIER DETECTOR FOR FRONTIER PHYSICS - LA BIODOLA 2009 Fastest

More information

THE WaveDAQ SYSTEM FOR THE MEG II UPGRADE

THE WaveDAQ SYSTEM FOR THE MEG II UPGRADE Stefan Ritt, Paul Scherrer Institute, Switzerland Luca Galli, Fabio Morsani, Donato Nicolò, INFN Pisa, Italy THE WaveDAQ SYSTEM FOR THE MEG II UPGRADE DRS4 Chip 0.2-2 ns Inverter Domino ring chain IN Clock

More information

Pixelated Positron Timing Counter with SiPM-readout Scintillator for MEG II experiment

Pixelated Positron Timing Counter with SiPM-readout Scintillator for MEG II experiment Pixelated Positron Timing Counter with SiPM-readout Scintillator for MEG II experiment Miki Nishimura a, Gianluigi Boca bc, Paolo Walter Cattaneo b, Matteo De Gerone d, Flavio Gatti de, Wataru Ootani a,

More information

An extreme high resolution Timing Counter for the MEG experiment Upgrade

An extreme high resolution Timing Counter for the MEG experiment Upgrade Preprint typeset in JINST style - HYPER VERSION An extreme high resolution Timing Counter for the MEG experiment Upgrade M. De Gerone a, F. Gatti a,b, W. Ootani c, Y. Uchiyama c, M. Nishimura c, S. Shirabe

More information

Status of the Front Tracker GEM and INFN Electronics

Status of the Front Tracker GEM and INFN Electronics Status of the Front Tracker GEM and INFN Electronics 2013 Apr 10 SBS Weekly Meeting INFN Catania, Genova, Bari and Rome GEM Production First Tests on module 0 Improvements in design Electronics Continue

More information

The Alice Silicon Pixel Detector (SPD) Peter Chochula for the Alice Pixel Collaboration

The Alice Silicon Pixel Detector (SPD) Peter Chochula for the Alice Pixel Collaboration The Alice Silicon Pixel Detector (SPD) Peter Chochula for the Alice Pixel Collaboration The Alice Pixel Detector R 1 =3.9 cm R 2 =7.6 cm Main Physics Goal Heavy Flavour Physics D 0 K π+ 15 days Pb-Pb data

More information

TIMING COUNTER: status report. Flavio Gatti - Lecce, Sept 23, INFN Genova, Pavia, Roma1

TIMING COUNTER: status report. Flavio Gatti - Lecce, Sept 23, INFN Genova, Pavia, Roma1 TIMING COUNTER: status report Flavio Gatti - Lecce, Sept 23, 2003. INFN Genova, Pavia, Roma1 Timing counter Activities Preliminary results of May test (Ge-Pv-Rm1) Tests on PM characteristics (Pv) and Tests

More information

Highly Accelerated Stress Screening of the Atlas Liquid Argon Calorimeter Front End Boards

Highly Accelerated Stress Screening of the Atlas Liquid Argon Calorimeter Front End Boards Highly Accelerated Stress Screening of the Atlas Liquid Argon Calorimeter Front End Boards K. Benslama, G. Brooijmans, C.-Y. Chi, D. Dannheim, I. Katsanos, J. Parsons, S. Simion Nevis Labs, Columbia University

More information

Design and test of an extremely high resolution Timing Counter for the MEG II experiment: preliminary results

Design and test of an extremely high resolution Timing Counter for the MEG II experiment: preliminary results Preprint typeset in JINST style - HYPER VERSION Design and test of an extremely high resolution Timing Counter for the MEG II experiment: preliminary results arxiv:32.087v [physics.ins-det] 3 Dec 203 M.

More information

Beam test of the QMB6 calibration board and HBU0 prototype

Beam test of the QMB6 calibration board and HBU0 prototype Beam test of the QMB6 calibration board and HBU0 prototype J. Cvach 1, J. Kvasnička 1,2, I. Polák 1, J. Zálešák 1 May 23, 2011 Abstract We report about the performance of the HBU0 board and the optical

More information

PHOTOTUBE SCANNING SETUP AT THE UNIVERSITY OF MARYLAND. Doug Roberts U of Maryland, College Park

PHOTOTUBE SCANNING SETUP AT THE UNIVERSITY OF MARYLAND. Doug Roberts U of Maryland, College Park PHOTOTUBE SCANNING SETUP AT THE UNIVERSITY OF MARYLAND Doug Roberts U of Maryland, College Park Overview We have developed a system for measuring and scanning phototubes for the FDIRC Based primarily on

More information

Report from the 2015 AHCAL beam test at the SPS. Katja Krüger CALICE Collaboration Meeting MPP Munich 10 September 2015

Report from the 2015 AHCAL beam test at the SPS. Katja Krüger CALICE Collaboration Meeting MPP Munich 10 September 2015 Report from the 2015 AHCAL beam test at the SPS Katja Krüger CALICE Collaboration Meeting MPP Munich 10 September 2015 Goals and Preparation > first SPS test beam with 2nd generation electronics and DAQ

More information

with Low Cost and Low Material Budget

with Low Cost and Low Material Budget Gaseous Beam Position Detectors, with Low Cost and Low Material Budget Gyula Bencédi on behalf of the REGaRD group MTA KFKI RMKI, ELTE November 29, 2011, Outline Physics Motivation Newish MWPCs, the Close

More information

Liquid Xenon Scintillation Detector with UV-SiPM Readout for MEG Upgrade

Liquid Xenon Scintillation Detector with UV-SiPM Readout for MEG Upgrade Liquid Xenon Scintillation Detector with UV-SiPM Readout for MEG Upgrade W. Ootani on behalf of MEG collaboration (ICEPP, Univ. of Tokyo) 13th Topical Seminar on Innovative Particle and Radiation Detectors

More information

The Silicon Pixel Detector (SPD) for the ALICE Experiment

The Silicon Pixel Detector (SPD) for the ALICE Experiment The Silicon Pixel Detector (SPD) for the ALICE Experiment V. Manzari/INFN Bari, Italy for the SPD Project in the ALICE Experiment INFN and Università Bari, Comenius University Bratislava, INFN and Università

More information

Coincidence Detection using the Broadcom AFBR-S4N44P163 4 x 4 SiPM Array and the Vertilon SIB916 Sensor Interface Board Application Note

Coincidence Detection using the Broadcom AFBR-S4N44P163 4 x 4 SiPM Array and the Vertilon SIB916 Sensor Interface Board Application Note Overview The Broadcom AFBR-S4N44P163 4 x 4 element silicon photomultiplier array and Vertilon SIB916 sensor interface board are an ideal combination for use in coincidence detection applications such as

More information

Status of the CUORE Electronics and the LHCb RICH Upgrade photodetector chain

Status of the CUORE Electronics and the LHCb RICH Upgrade photodetector chain Status of the CUORE Electronics and the LHCb RICH Upgrade photodetector chain Lorenzo Cassina - XXIX cycle MiB - Midterm Graduate School Seminar Day Outline Activity on LHCb MaPTM qualification RICH Upgrade

More information

The ATLAS Tile Calorimeter, its performance with pp collisions and its upgrades for high luminosity LHC

The ATLAS Tile Calorimeter, its performance with pp collisions and its upgrades for high luminosity LHC The ATLAS Tile Calorimeter, its performance with pp collisions and its upgrades for high luminosity LHC Tomas Davidek (Charles University), on behalf of the ATLAS Collaboration Tile Calorimeter Sampling

More information

CGEM-IT project update

CGEM-IT project update BESIII Physics and Software Workshop Beihang University February 20-23, 2014 CGEM-IT project update Gianluigi Cibinetto (INFN Ferrara) on behalf of the CGEM group Outline Introduction Mechanical development

More information

AREAL- Phase 1. B. Grigoryan on behalf of AREAL team

AREAL- Phase 1. B. Grigoryan on behalf of AREAL team AREAL- Phase 1 Progress & Status B. Grigoryan on behalf of AREAL team Contents Machine Layout Building & Infrastructure Laser System RF System Vacuum System Cooling System Control System Beam Diagnostics

More information

Status of the Timing Detector Plastic+SiPM Readout Option

Status of the Timing Detector Plastic+SiPM Readout Option SHiP Timing Detector Status of the Timing Detector Plastic+SiPM Readout Option Ruth Bruendler, University of Zurich on behalf of the Timing Detector Group 11th SHIP Collaboration Meeting CERN 7-9 June

More information

Drift Tubes as Muon Detectors for ILC

Drift Tubes as Muon Detectors for ILC Drift Tubes as Muon Detectors for ILC Dmitri Denisov Fermilab Major specifications for muon detectors D0 muon system tracking detectors Advantages and disadvantages of drift chambers as muon detectors

More information

HAPD and Electronics Updates

HAPD and Electronics Updates S. Nishida KEK 3rd Open Meeting for Belle II Collaboration 1 Contents Frontend Electronics Neutron Irradiation News from Hamamtsu 2 144ch HAPD HAPD (Hybrid Avalanche Photo Detector) photon bi alkali photocathode

More information

DAQ Systems in Hall A

DAQ Systems in Hall A CODA Users Workshop Data Acquisition at Jefferson Lab Newport News June 7, 2004 DAQ Systems in Hall A Overview of Hall A Standard Equipment: HRS, Beamline,... Parity Experiments Third Arms: BigBite, RCS

More information

TORCH a large-area detector for high resolution time-of-flight

TORCH a large-area detector for high resolution time-of-flight TORCH a large-area detector for high resolution time-of-flight Roger Forty (CERN) on behalf of the TORCH collaboration 1. TORCH concept 2. Application in LHCb 3. R&D project 4. Test-beam studies TIPP 2017,

More information

CMS Upgrade Activities

CMS Upgrade Activities CMS Upgrade Activities G. Eckerlin DESY WA, 1. Feb. 2011 CMS @ LHC CMS Upgrade Phase I CMS Upgrade Phase II Infrastructure Conclusion DESY-WA, 1. Feb. 2011 G. Eckerlin 1 The CMS Experiments at the LHC

More information

The hybrid photon detectors for the LHCb-RICH counters

The hybrid photon detectors for the LHCb-RICH counters 7 th International Conference on Advanced Technology and Particle Physics The hybrid photon detectors for the LHCb-RICH counters Maria Girone, CERN and Imperial College on behalf of the LHCb-RICH group

More information

Commissioning and Initial Performance of the Belle II itop PID Subdetector

Commissioning and Initial Performance of the Belle II itop PID Subdetector Commissioning and Initial Performance of the Belle II itop PID Subdetector Gary Varner University of Hawaii TIPP 2017 Beijing Upgrading PID Performance - PID (π/κ) detectors - Inside current calorimeter

More information

Commissioning and Performance of the ATLAS Transition Radiation Tracker with High Energy Collisions at LHC

Commissioning and Performance of the ATLAS Transition Radiation Tracker with High Energy Collisions at LHC Commissioning and Performance of the ATLAS Transition Radiation Tracker with High Energy Collisions at LHC 1 A L E J A N D R O A L O N S O L U N D U N I V E R S I T Y O N B E H A L F O F T H E A T L A

More information

itop (barrel PID) and endcap KLM G. Varner Jan-2011 Trigger/DAQ in Beijing

itop (barrel PID) and endcap KLM G. Varner Jan-2011 Trigger/DAQ in Beijing itop (barrel PID) and endcap KLM DAQ Summary G. Varner Jan-2011 Trigger/DAQ in Beijing 1 Overview Update on B-PID (itop) DAQ Big issue is SCROD eklm prototyping: Prototyping status Use Belle2link directly?

More information

Rome group activity since last meeting (4)

Rome group activity since last meeting (4) OLYMPUS Collaboration DESY 30/August/2010 Rome group activity since last meeting (4) DESY 30/August/2010 Olympus Collaboration meeting Salvatore Frullani / INFN-Rome Sanità Group 1 GEM electronics: Outline

More information

Commissioning of the ATLAS Transition Radiation Tracker (TRT)

Commissioning of the ATLAS Transition Radiation Tracker (TRT) Commissioning of the ATLAS Transition Radiation Tracker (TRT) 11 th Topical Seminar on Innovative Particle and Radiation Detector (IPRD08) 3 October 2008 bocci@fnal.gov On behalf of the ATLAS TRT community

More information

Silicon PhotoMultiplier Kits

Silicon PhotoMultiplier Kits Silicon PhotoMultiplier Kits Silicon PhotoMultipliers (SiPM) consist of a high density (up to ~ 10 3 /mm 2 ) matrix of photodiodes with a common output. Each diode is operated in a limited Geiger- Müller

More information

Prospect and Plan for IRS3B Readout

Prospect and Plan for IRS3B Readout Prospect and Plan for IRS3B Readout 1. Progress on Key Performance Parameters 2. Understanding limitations during LEPS operation 3. Carrier02 Rev. C (with O-E-M improvements) 4. Pre-production tasks/schedule

More information

Sensors for the CMS High Granularity Calorimeter

Sensors for the CMS High Granularity Calorimeter Sensors for the CMS High Granularity Calorimeter Andreas Alexander Maier (CERN) on behalf of the CMS Collaboration Wed, March 1, 2017 The CMS HGCAL project ECAL Answer to HL-LHC challenges: Pile-up: up

More information

Front End Electronics

Front End Electronics CLAS12 Ring Imaging Cherenkov (RICH) Detector Mid-term Review Front End Electronics INFN - Ferrara Matteo Turisini 2015 October 13 th Overview Readout requirements Hardware design Electronics boards Integration

More information

A new Scintillating Fibre Tracker for LHCb experiment

A new Scintillating Fibre Tracker for LHCb experiment A new Scintillating Fibre Tracker for LHCb experiment Alexander Malinin, NRC Kurchatov Institute on behalf of the LHCb-SciFi-Collaboration Instrumentation for Colliding Beam Physics BINP, Novosibirsk,

More information

Single Photoelectron timing resolution of SiPM

Single Photoelectron timing resolution of SiPM Research & Study Detector Group Single Photoelectron timing resolution of SiPM XVII SuperB Workshop - Kick Off meeting May 29 th - June 1 st 2011 Isola d Elba Véronique Puill, IN2P3-LAL -GRED C. Bazin,

More information

First evaluation of the prototype 19-modules camera for the Large Size Telescope of the CTA

First evaluation of the prototype 19-modules camera for the Large Size Telescope of the CTA First evaluation of the prototype 19-modules camera for the Large Size Telescope of the CTA Tsutomu Nagayoshi for the CTA-Japan Consortium Saitama Univ, Max-Planck-Institute for Physics 1 Cherenkov Telescope

More information

Outline. GEM R&D and assembly facilities at UVa. Cosmic test results. Update on the cm 2 GEM prototype

Outline. GEM R&D and assembly facilities at UVa. Cosmic test results. Update on the cm 2 GEM prototype Uva GEM R&D Update Kondo Gnanvo, Nilanga Liyanage, Vladimir Nelyubin, Kiadtisak Saenboonruang, Taylor Scholz and Adarsh Ramakrishnan In Collaboration with Evaristo Cisbani and Paolo Musico Outline GEM

More information

TWO BUNCHES WITH NS-SEPARATION WITH LCLS*

TWO BUNCHES WITH NS-SEPARATION WITH LCLS* TWO BUNCHES WITH NS-SEPARATION WITH LCLS* F.-J. Decker, S. Gilevich, Z. Huang, H. Loos, A. Marinelli, C.A. Stan, J.L. Turner, Z. van Hoover, S. Vetter, SLAC, Menlo Park, CA 94025, USA Abstract The Linac

More information

Quick Report on Silicon G-APDs (a.k.a. Si-PM) studies. XIV SuperB General Meeting LNF - Frascati

Quick Report on Silicon G-APDs (a.k.a. Si-PM) studies. XIV SuperB General Meeting LNF - Frascati Quick Report on Silicon G-APDs (a.k.a. Si-PM) studies XIV SuperB General Meeting LNF - Frascati Report of the work done in Padova Dal Corso F., E.F., Simi G., Stroili R. University & INFN Padova Outline

More information

Progress Update FDC Prototype Test Stand Development Upcoming Work

Progress Update FDC Prototype Test Stand Development Upcoming Work Progress Update FDC Prototype Test Stand Development Upcoming Work Progress Update OU GlueX postdoc position filled. Simon Taylor joins our group July 1, 2004 Position funded jointly by Ohio University

More information

Diamond detectors in the CMS BCM1F

Diamond detectors in the CMS BCM1F Diamond detectors in the CMS BCM1F DESY (Zeuthen) CARAT 2010 GSI, 13-15 December 2010 On behalf of the DESY BCM and CMS BRM groups 1 Outline: 1. Introduction to the CMS BRM 2. BCM1F: - Back-End Hardware

More information

A prototype of fine granularity lead-scintillating fiber calorimeter with imaging read-out

A prototype of fine granularity lead-scintillating fiber calorimeter with imaging read-out A prototype of fine granularity lead-scintillating fiber calorimeter with imaging read-out P.Branchini, F.Ceradini, B.Di Micco, A. Passeri INFN Roma Tre and Dipartimento di Fisica Università Roma Tre and

More information

OPTICAL POWER METER WITH SMART DETECTOR HEAD

OPTICAL POWER METER WITH SMART DETECTOR HEAD OPTICAL POWER METER WITH SMART DETECTOR HEAD Features Fast response (over 1000 readouts/s) Wavelengths: 440 to 900 nm for visible (VIS) and 800 to 1700 nm for infrared (IR) NIST traceable Built-in attenuator

More information

MOST. Getting the. BMW Assist. Climate. Settings

MOST. Getting the. BMW Assist. Climate. Settings feature BMW Assist Commun Getting the MOST Climate Any technological advance adds a level of complexity, and when it breaks we re the ones who are going to have to fix it. This includes the sophisticated

More information

LED-Strip C12 MK2.6. Product Sheet

LED-Strip C12 MK2.6. Product Sheet LED-Strip C12 MK2.6 Product Sheet schnick-schnack-systems Introduction features Generation 3 compatible Automatic Addressing System (Smart-Link) no addressing at the board Compatible with other series

More information

New Filling Pattern for SLS-FEMTO

New Filling Pattern for SLS-FEMTO SLS-TME-TA-2009-0317 July 14, 2009 New Filling Pattern for SLS-FEMTO Natalia Prado de Abreu, Paul Beaud, Gerhard Ingold and Andreas Streun Paul Scherrer Institut, CH-5232 Villigen PSI, Switzerland A new

More information

LED-Strip C25 MK2.6. Product Sheet

LED-Strip C25 MK2.6. Product Sheet LED-Strip C25 MK2.6 Product Sheet schnick-schnack-systems Introduction features Generation 3 compatible Automatic Addressing System (Smart Link) no addressing at the board Compatible with other series

More information

Atlas Pixel Replacement/Upgrade. Measurements on 3D sensors

Atlas Pixel Replacement/Upgrade. Measurements on 3D sensors Atlas Pixel Replacement/Upgrade and Measurements on 3D sensors Forskerskole 2007 by E. Bolle erlend.bolle@fys.uio.no Outline Sensors for Atlas pixel b-layer replacement/upgrade UiO activities CERN 3D test

More information

A TARGET-based camera for CTA

A TARGET-based camera for CTA A TARGET-based camera for CTA TeV Array Readout with GSa/s sampling and Event Trigger (TARGET) chip: overview Custom-designed ASIC for CTA, developed in collaboration with Gary Varner (U Hawaii) Implementation:

More information

Test beam data analysis for the CMS CASTOR calorimeter at the LHC

Test beam data analysis for the CMS CASTOR calorimeter at the LHC 1/ 24 DESY Summerstudent programme 2008 - Course review Test beam data analysis for the CMS CASTOR calorimeter at the LHC Agni Bethani a, Andrea Knue b a Technical University of Athens b Georg-August University

More information

Hall-B Beamline Commissioning Plan for CLAS12

Hall-B Beamline Commissioning Plan for CLAS12 Hall-B Beamline Commissioning Plan for CLAS12 Version 1.5 S. Stepanyan December 19, 2017 1 Introduction The beamline for CLAS12 utilizes the existing Hall-B beamline setup with a few modifications and

More information

GEM-TPC development in Canada. Dean Karlen Technology recommendation panel meeting January 16, 2006 KEK

GEM-TPC development in Canada. Dean Karlen Technology recommendation panel meeting January 16, 2006 KEK GEM-TPC development in Canada Dean Karlen Technology recommendation panel meeting KEK Outline Brief summary of GEM-TPC R&D in Canada (1999-2005) X-ray studies with small test cell First GEM-TPC studies

More information

The LEP Superconducting RF System

The LEP Superconducting RF System The LEP Superconducting RF System K. Hübner* for the LEP RF Group CERN The basic components and the layout of the LEP rf system for the year 2000 are presented. The superconducting system consisted of

More information

In-process inspection: Inspector technology and concept

In-process inspection: Inspector technology and concept Inspector In-process inspection: Inspector technology and concept Need to inspect a part during production or the final result? The Inspector system provides a quick and efficient method to interface a

More information

On Figure of Merit in PAM4 Optical Transmitter Evaluation, Particularly TDECQ

On Figure of Merit in PAM4 Optical Transmitter Evaluation, Particularly TDECQ On Figure of Merit in PAM4 Optical Transmitter Evaluation, Particularly TDECQ Pavel Zivny, Tektronix V1.0 On Figure of Merit in PAM4 Optical Transmitter Evaluation, Particularly TDECQ A brief presentation

More information

ALICE Muon Trigger upgrade

ALICE Muon Trigger upgrade ALICE Muon Trigger upgrade Context RPC Detector Status Front-End Electronics Upgrade Readout Electronics Upgrade Conclusions and Perspectives Dr Pascal Dupieux, LPC Clermont, QGPF 2013 1 Context The Muon

More information

RST INSTRUMENTS LTD.

RST INSTRUMENTS LTD. RST INSTRUMENTS LTD. MEMS Tilt Beam Instruction Manual Copyright 2012 Ltd. All Rights Reserved. Ltd. 11545 Kingston St., Maple Ridge, B.C. Canada V2X 0Z5 Tel: (604) 540-1100 Fax: (604) 540-1005 Email:

More information

SuperFRS GEM-TPC Development Status Report

SuperFRS GEM-TPC Development Status Report SuperFRS GEM-TPC Development Status Report COLLABORATORS F. García, R. Turpeinen, J. Heino, A. Karadzhinova, E. Tuominen, R. Lauhakangas Helsinki Institute of Physics University of Helsinki - Finland R.

More information

Digital Delay / Pulse Generator DG535 Digital delay and pulse generator (4-channel)

Digital Delay / Pulse Generator DG535 Digital delay and pulse generator (4-channel) Digital Delay / Pulse Generator Digital delay and pulse generator (4-channel) Digital Delay/Pulse Generator Four independent delay channels Two fully defined pulse channels 5 ps delay resolution 50 ps

More information

The ATLAS Pixel Detector

The ATLAS Pixel Detector The ATLAS Pixel Detector Fabian Hügging arxiv:physics/0412138v2 [physics.ins-det] 5 Aug 5 Abstract The ATLAS Pixel Detector is the innermost layer of the ATLAS tracking system and will contribute significantly

More information

TG 3 Status Report. C. Cattadori on behalf of TG3

TG 3 Status Report. C. Cattadori on behalf of TG3 TG 3 Status Report C. Cattadori on behalf of TG3 Status of FE circuits T [ns] Range[MeV] ENC rms [e-] R with crystal [kev] Output F-CSA104 Fully integrated 20 ns 0-11 MeV 270 @ LN (20 µs) 310 @ 20 C 5.4

More information

HDCVI Camera User s Manual

HDCVI Camera User s Manual HDCVI Camera User s Manual Version 1.0.0 Table of Contents 1 General Introduction... 1 1.1 Overview... 1 1.2 Features... 1 2 Device Framework... 2 3 Device Cable Structure... 4 4 Device Installation...

More information

Installation / Set-up of Autoread Camera System to DS1000/DS1200 Inserters

Installation / Set-up of Autoread Camera System to DS1000/DS1200 Inserters Installation / Set-up of Autoread Camera System to DS1000/DS1200 Inserters Written By: Colin Langridge Issue: Draft Date: 03 rd July 2008 1 Date: 29 th July 2008 2 Date: 20 th August 2008 3 Date: 02 nd

More information

CAEN Tools for Discovery

CAEN Tools for Discovery Viareggio March 28, 2011 Introduction: what is the SiPM? The Silicon PhotoMultiplier (SiPM) consists of a high density (up to ~10 3 /mm 2 ) matrix of diodes connected in parallel on a common Si substrate.

More information

THE ATLAS Inner Detector [2] is designed for precision

THE ATLAS Inner Detector [2] is designed for precision The ATLAS Pixel Detector Fabian Hügging on behalf of the ATLAS Pixel Collaboration [1] arxiv:physics/412138v1 [physics.ins-det] 21 Dec 4 Abstract The ATLAS Pixel Detector is the innermost layer of the

More information

Testing and Characterization of the MPA Pixel Readout ASIC for the Upgrade of the CMS Outer Tracker at the High Luminosity LHC

Testing and Characterization of the MPA Pixel Readout ASIC for the Upgrade of the CMS Outer Tracker at the High Luminosity LHC Testing and Characterization of the MPA Pixel Readout ASIC for the Upgrade of the CMS Outer Tracker at the High Luminosity LHC Dena Giovinazzo University of California, Santa Cruz Supervisors: Davide Ceresa

More information

Front End Electronics

Front End Electronics CLAS12 Ring Imaging Cherenkov (RICH) Detector Mid-term Review Front End Electronics INFN - Ferrara Matteo Turisini 2015 October 13 th Overview Readout requirements Hardware design Electronics boards Integration

More information

Cryostat Instrumentation Cabling Grounding and Shielding. Eric Hazen Boston University 12/15/08 1

Cryostat Instrumentation Cabling Grounding and Shielding. Eric Hazen Boston University 12/15/08 1 Cryostat Instrumentation Cabling Grounding and Shielding Eric Hazen Boston University 12/15/08 1 Electromagnetic Compatibility We need to classify our instrumentation in terms of Emission and Susceptibility

More information

Tests of Timing Properties of Silicon Photomultipliers

Tests of Timing Properties of Silicon Photomultipliers FERMILAB-PUB-10-052-PPD SLAC-PUB-14599 Tests of Timing Properties of Silicon Photomultipliers A. Ronzhin a, M. Albrow a, K. Byrum b, M. Demarteau a, S. Los a, E. May b, E. Ramberg a, J. Va vra d, A. Zatserklyaniy

More information

NanoCom ADS-B. Datasheet An ADS-B receiver for space applications

NanoCom ADS-B. Datasheet An ADS-B receiver for space applications NanoCom ADS-B Datasheet An ADS-B receiver for space applications 1 Table of contents 1 TABLE OF CONTENTS... 2 2 CHANGELOG... 3 3 INTRODUCTION... 4 4 OVERVIEW... 4 4.1 HIGHLIGHTED FEATURES... 4 4.2 BLOCK

More information

Update on DAQ for 12 GeV Hall C

Update on DAQ for 12 GeV Hall C Update on DAQ for 12 GeV Hall C Brad Sawatzky Hall C Winter User Group Meeting Jan 20, 2017 SHMS/HMS Trigger/Electronics H. Fenker 2 SHMS / HMS Triggers SCIN = 3/4 hodoscope planes CER = Cerenkov(s) STOF

More information

Update on DAQ for 12 GeV Hall C. Brad Sawatzky

Update on DAQ for 12 GeV Hall C. Brad Sawatzky Update on DAQ for 12 GeV Hall C Brad Sawatzky SHMS/HMS Trigger/Electronics H. Fenker 2 SHMS / HMS Triggers SCIN = 3/4 hodoscope planes CER = Cerenkov(s) STOF = S1 + S2 EL-Hi = SCIN + PSh_Hi EL-Lo = 2/3{SCIN,

More information

Muon Forward Tracker. MFT Collaboration

Muon Forward Tracker. MFT Collaboration Muon Forward Tracker MFT Collaboration QGP France 2013 Introduction Summary of what «physically» MFT looks like: - Silicon detector - Data flow - Mechanical aspects - Power supplies - Cooling - Insertion/Extraction

More information

BABAR IFR TDC Board (ITB): system design

BABAR IFR TDC Board (ITB): system design BABAR IFR TDC Board (ITB): system design Version 1.1 12 december 1997 G. Crosetti, S. Minutoli, E. Robutti I.N.F.N. Genova 1. Introduction TDC readout of the IFR will be used during BABAR data taking to

More information

Performance of a double-metal n-on-n and a Czochralski silicon strip detector read out at LHC speeds

Performance of a double-metal n-on-n and a Czochralski silicon strip detector read out at LHC speeds Performance of a double-metal n-on-n and a Czochralski silicon strip detector read out at LHC speeds Juan Palacios, On behalf of the LHCb VELO group J.P. Palacios, Liverpool Outline LHCb and VELO performance

More information

LED-Strip C50 MK2.6. Product Sheet

LED-Strip C50 MK2.6. Product Sheet LED-Strip C50 MK2.6 Product Sheet schnick-schnack-systems Introduction features Generation 3 compatible Automatic Addressing System (Smart Link) no addressing at the board Compatible with other series

More information

Study of Timing and Efficiency Properties of Multi-Anode Photomultipliers

Study of Timing and Efficiency Properties of Multi-Anode Photomultipliers Study of Timing and Efficiency Properties of Multi-Anode Photomultipliers T. Hadig, C.R. Field, D.W.G.S. Leith, G. Mazaheri, B.N. Ratcliff, J. Schwiening, J. Uher, J. Va vra Stanford Linear Accelerator

More information

Monolithic Thin Pixel Upgrade Testing Update. Gary S. Varner, Marlon Barbero and Fang Fang UH Belle Meeting, April 16 th 2004

Monolithic Thin Pixel Upgrade Testing Update. Gary S. Varner, Marlon Barbero and Fang Fang UH Belle Meeting, April 16 th 2004 Monolithic Thin Pixel Upgrade Testing Update Gary S. Varner, Marlon Barbero and Fang Fang UH Belle Meeting, April 16 th 2004 Basic Technology: Standard CMOS CMOS Camera Because of large Capacitance, need

More information

Studies of large dynamic range silicon photomultipliers for the CMS HCAL upgrade

Studies of large dynamic range silicon photomultipliers for the CMS HCAL upgrade Studies of large dynamic range silicon photomultipliers for the CMS HCAL upgrade Yuri Musienko* FNAL(USA) Arjan Heering University of Notre Dame (USA) For the CMS HCAL group *On leave from INR(Moscow)

More information

Product information. Front-door station series with video for surface-mount

Product information. Front-door station series with video for surface-mount Product information Front-door station series with video for surface-mount series VPES series VPDS 2 05/2006 Table of contents Scope of delivery...3 Safety notices...3 General notes on the cabling in TCS

More information

Practical De-embedding for Gigabit fixture. Ben Chia Senior Signal Integrity Consultant 5/17/2011

Practical De-embedding for Gigabit fixture. Ben Chia Senior Signal Integrity Consultant 5/17/2011 Practical De-embedding for Gigabit fixture Ben Chia Senior Signal Integrity Consultant 5/17/2011 Topics Why De-Embedding/Embedding? De-embedding in Time Domain De-embedding in Frequency Domain De-embedding

More information

Realization and Test of the Engineering Prototype of the CALICE Tile Hadron Calorimeter

Realization and Test of the Engineering Prototype of the CALICE Tile Hadron Calorimeter Realization and Test of the Engineering Prototype of the CALICE Tile Hadron Calorimeter Mark Terwort on behalf of the CALICE collaboration arxiv:1011.4760v1 [physics.ins-det] 22 Nov 2010 Abstract The CALICE

More information

SciFi A Large Scintillating Fibre Tracker for LHCb

SciFi A Large Scintillating Fibre Tracker for LHCb SciFi A Large Scintillating Fibre Tracker for LHCb Roman Greim on behalf of the LHCb-SciFi-Collaboration 14th Topical Seminar on Innovative Particle Radiation Detectors, Siena 5th October 2016 I. Physikalisches

More information

First LHC Beams in ATLAS. Peter Krieger University of Toronto On behalf of the ATLAS Collaboration

First LHC Beams in ATLAS. Peter Krieger University of Toronto On behalf of the ATLAS Collaboration First LHC Beams in ATLAS Peter Krieger University of Toronto On behalf of the ATLAS Collaboration Cutaway View LHC/ATLAS (Graphic) P. Krieger, University of Toronto Aspen Winter Conference, Feb. 2009 2

More information

Laser Beam Analyser Laser Diagnos c System. If you can measure it, you can control it!

Laser Beam Analyser Laser Diagnos c System. If you can measure it, you can control it! Laser Beam Analyser Laser Diagnos c System If you can measure it, you can control it! Introduc on to Laser Beam Analysis In industrial -, medical - and laboratory applications using CO 2 and YAG lasers,

More information

Imaging TOP (itop), Cosmic Ray Test Stand & PID Readout Update

Imaging TOP (itop), Cosmic Ray Test Stand & PID Readout Update Imaging TOP (itop), Cosmic Ray Test Stand & PID Readout Update Tom Browder, Herbert Hoedlmoser, Bryce Jacobsen, Jim Kennedy, KurtisNishimura, Marc Rosen, Larry Ruckman, Gary Varner Kurtis Nishimura SuperKEKB

More information

CONDITIONER TERMINAL BLOCK 8 ISOLATED ANALOG INPUTS STB 582

CONDITIONER TERMINAL BLOCK 8 ISOLATED ANALOG INPUTS STB 582 CONDITIONER TERMINAL BLOCK 8 ISOLATED ANALOG INPUTS STB 582 Eight 3-port isolated analog inputs INPUTS / OUTPUTS / POWER SUPPLY Protected inputs Levels from ± 50mV FS to ± 40V FS Low-pass 2 nd order filter

More information

3M High-Speed Solutions

3M High-Speed Solutions 3M High-Speed Solutions 3M 2011. All Rights Reserved. Distance 3M Electronic Solutions Division 3M Twin Axial and AOC Solutions Addressing Physical Medium Dependent in the InifiniBand Fabric 100m 10m 1m

More information

li, o p a f th ed lv o v ti, N sca reb g s In tio, F, Z stitu e tests o e O v o d a eters sin u i P r th e d est sezio tefa ectro lity stem l su

li, o p a f th ed lv o v ti, N sca reb g s In tio, F, Z stitu e tests o e O v o d a eters sin u i P r th e d est sezio tefa ectro lity stem l su Design and prototype tests of the system for the OPERA spectrometers Stefano Dusini INFN sezione di Padova Outline OPERA Detector Inner Tracker Design Mechanical support Gas & HV Production and Quality

More information

HDMI Demystified April 2011

HDMI Demystified April 2011 HDMI Demystified April 2011 What is HDMI? High-Definition Multimedia Interface, or HDMI, is a digital audio, video and control signal format defined by seven of the largest consumer electronics manufacturers.

More information

Multi-Key v2.4 Multi-Function Amplifier Keying Interface

Multi-Key v2.4 Multi-Function Amplifier Keying Interface Multi-Key v2.4 Multi-Function Amplifier Keying Interface ASSEMBLY & OPERATION INSTRUCTIONS INTRODUCTION The Harbach Electronics, LLC Multi-Key is a multi-function external device designed for the safe

More information

Linac 4 Instrumentation K.Hanke CERN

Linac 4 Instrumentation K.Hanke CERN Linac 4 Instrumentation K.Hanke CERN CERN Linac 4 PS2 (2016?) SPL (2015?) Linac4 (2012) Linac4 will first inject into the PSB and then can be the first element of a new LHC injector chain. It will increase

More information